CRONOGRAMA DE ADQUISICION DE MATERIALES MATERIALES

PROYECTO:"MEJORAMIENTO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA ZONA URBANA DE LA CIUDAD DE ASCENSION,


DISTRITO DE ASCENSION - HUANCAVELICA - HUANCAVELICA"
DEPARTAMENT
O :HUANCAVELICA FECHA: JULIO DEL 2017
PROVINCIA :HUANCAVELICA
DISTRITO :ASCENSION
LUGAR :ASCENSION
ITEM DECRIPCION UND CANT. C.U PARCIAL MES 01 MES 02 TOTAL
MANO DE OBRA
1 OPERARIO hh 1,210.72 10.77 13,039.47 6,519.74 6,519.74 13,039.47
2 OFICIAL hh 180.78 9.68 1,749.95 874.98 874.98 1,749.95
3 PEON hh 2,842.18 8.91 25,323.82 12,661.91 12,661.91 25,323.82

MATERIALES
1 CLAVOS PARA MADERA CON CABEZA DE 3" kg 2.70 4.50 12.15 12.15 12.15
2 CLAVOS PARA MADERA CON CABEZA DE 2" kg 2.16 4.50 9.72 9.72 9.72
3 CORDEL m 19.20 0.05 0.96 0.96 0.96
PERNOS DE ANCLAJE CON TUERCA Y HUACHA DE 3/4"x2-1/4" CABEZA par 48.00 6.00 288.00 288.00
4 EXAGONAL 288.00
PERNOS DE ANCLAJE CON TUERCA Y HUACHA DE 3/4"x 2-1/2" CABEZA par 24.00 10.00 240.00 240.00
5 EXAGONAL 240.00
6 GRAPA GALBANIZADA PARA CERCA DE 1 1/2 X8 kg 46.17 1.00 46.17 46.17 46.17
7 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 12,514.59 3.20 40,046.68 40,046.68 40,046.68
8 ARENA FINA m3 3.81 140.00 533.61 266.81 266.81 533.61
9 TIERRA ORGANICA m3 123.90 60.00 7,433.86 3,716.93 3,716.93 7,433.86
10 PIEDRA CHANCADA DE 3/4" m3 5.87 85.00 499.12 249.56 249.56 499.12
11 PIEDRA MEDIANA DE 4" - 6" m3 13.25 50.00 662.40 331.20 331.20 662.40
12 ARENA GRUESA m3 3.67 90.00 330.30 165.15 165.15 330.30
13 MATERIAL DE PRESTAMO PARA RELLENO m3 6.30 40.00 252.00 126.00 126.00 252.00
14 CONECTOR DESMONTABLE (CONECTOR PICO DE LORO 3/4") u 8.10 50.00 405.00 405.00 405.00
15 CONCRETO PARA REJILLA m 7.89 1.95 15.38 15.38 15.38
16 CONDUCTOR CABLEADO # 6 AWG, COLOR AMARILLO, VERDE m 8.10 100.00 810.00 810.00 810.00
17 SOLDADURA ELECTRICA kg 18.00 15.00 270.00 270.00 270.00
CRONOGRAMA DE ADQUISICION DE MATERIALES MATERIALES
PROYECTO:"MEJORAMIENTO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA ZONA URBANA DE LA CIUDAD DE ASCENSION,
DISTRITO DE ASCENSION - HUANCAVELICA - HUANCAVELICA"
DEPARTAMENT
O :HUANCAVELICA FECHA: JULIO DEL 2017
PROVINCIA :HUANCAVELICA
DISTRITO :ASCENSION
LUGAR :ASCENSION
ITEM DECRIPCION UND CANT. C.U PARCIAL MES 01 MES 02 TOTAL
TUBO ELECTROSOLDADO RECTANGULAR DE 0.25 x 0.22 m x 4mm L=6.00 m u 6.00 700.00 4,200.00 4,200.00
18 c/acople 4,200.00
TUBO ELECTROSOLDADO RECTANGULAR DE 0.25 x 0.22 m x 4mm L=1m u 6.00 150.00 900.00 900.00
19 c/acople 900.00
20 TUBO ELECTROSOLDADO RECTANGULAR DE 4" x 3" x 2.5mm m 124.80 25.00 3,120.00 3,120.00 3,120.00
SEMAFORO PEATONAL UNA CARA CON DOS LUCES, 1C 2L DE CUENTA u 12.00 1,300.00 15,600.00 15,600.00
21 REGRESIVA, EST. POLICARBONATO DE 12x12 220 Vlts 15,600.00
SEMAFORO VIAL DE UNA CARA CON TRES LUCES, ESTUCHE POLICARBONATO u 12.00 1,600.00 19,200.00 19,200.00
22 DE 12x12x12 220 Vlts 19,200.00
23 CONTROLADOR ELECTRICO DE SEMAFORO A2 TRANSICON u 3.00 1,650.00 4,950.00 4,950.00 4,950.00
24 INTERRUPTOR DE SEGURIDAD TRIFASICO pza 1.80 56.00 100.80 100.80 100.80
25 CEMENTO PORTLAND TIPO I (42.5 kg) bls 141.18 24.00 3,388.25 3,388.25 3,388.25
26 TAPA DE CONCRETO PREFABRICADO 0.66 X 0.66M u 17.00 130.00 2,210.00 2,210.00 2,210.00
27 TAPA DE CONCRETO PREFABRICADO 0.86 X 0.86M u 18.00 160.00 2,880.00 2,880.00 2,880.00
28 TAPA DE CONCRETO PREFABRICADO 0.75 X 0.90M u 1.00 140.00 140.00 140.00 140.00
29 YESO EN BOLSAS DE 25 kg bls 5.76 6.50 37.44 37.44 37.44
30 THINNER gal 0.12 17.00 1.96 1.96 1.96
31 ADITIVO IMPERMEABILIZANTE gal 9.45 22.00 207.90 207.90 207.90
CABLEADO, CONEXION A SEMAFOROS, CONTADORES PEATONALES Y u 3.00 950.00 2,850.00 2,850.00
CONTROLADOR ELECTRONICO Y PUESTA EN MARCHA
32 2,850.00
33 CINTA DE SEÑALIZACION m 200.00 0.35 70.00 70.00 70.00
34 BROCHA 6" DE NEYLON u 1.28 13.00 16.65 16.65 16.65
35 RODILLO 3" PINTOR u 2.56 8.00 20.50 20.50 20.50
36 CINTA MASKINTAPE DE 1" u 344.49 4.50 1,550.21 1,550.21 1,550.21
37 HORMIGON (PUESTO EN OBRA) m3 13.97 85.00 1,187.28 1,187.28 1,187.28
38 AGUA m3 10.39 5.00 51.95 51.95 51.95
CRONOGRAMA DE ADQUISICION DE MATERIALES MATERIALES
PROYECTO:"MEJORAMIENTO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA ZONA URBANA DE LA CIUDAD DE ASCENSION,
DISTRITO DE ASCENSION - HUANCAVELICA - HUANCAVELICA"
DEPARTAMENT
O :HUANCAVELICA FECHA: JULIO DEL 2017
PROVINCIA :HUANCAVELICA
DISTRITO :ASCENSION
LUGAR :ASCENSION
ITEM DECRIPCION UND CANT. C.U PARCIAL MES 01 MES 02 TOTAL
39 ESCOBILLA DE ACERO pza 67.36 7.00 471.53 471.53 471.53
40 REGLA METALICA DE 1"x3"x6M u 0.05 60.00 3.07 3.07 3.07
41 CARTEL INFORMATIVO Y CULTURAL u 18.00 25.00 450.00 450.00 450.00
CARTEL DE OBRA, SEGUN DISEÑO; INCL. PROVICION, TRASPORTE E u 1.00 400.00 400.00 400.00
42 INSTALACION 400.00
43 OFICINA PARA RESIDENCIA Y SUPERVISION glb 2.00 250.00 500.00 500.00 500.00
44 REGULADOR DE VOLTAGE DE 12 VOLT u 18.00 90.00 1,620.00 1,620.00 1,620.00
45 CAPACITACION EN SEGURIDAD Y SALUD glb 1.00 500.00 500.00 500.00 500.00
46 MADERA TORNILLO p2 46.80 4.20 196.56 196.56 196.56
47 MADERA DE 2"x3"x10' u 403.99 12.00 4,847.85 4,847.85 4,847.85
48 TREBOL ROJO kg 154.87 20.00 3,097.44 3,097.44 3,097.44
49 RAY GRASS INGLES kg 309.74 25.00 7,743.60 7,743.60 7,743.60
50 PLANTON DE ARBOL NATIVO DE 1.50 M u 30.00 15.00 450.00 450.00 450.00
51 CABLE VULCANIZADO DE 4x16 AWG rll 2.40 500.00 1,200.00 1,200.00 1,200.00
52 CABLE VULCANIZADO DE 3x16 AWG rll 3.00 450.00 1,350.00 1,350.00 1,350.00
53 MADERA DE MONTAÑA CORRIENTE p2 1.08 2.90 3.12 3.12 3.12
54 ESTACA DE MADERA p2 9.00 2.80 25.20 25.20 25.20
55 ALAMBRE DE PUAS # 12 m 3,635.89 2.50 9,089.72 9,089.72 9,089.72
56 ANGULO DE ACERO DE 3/4" X 3/4" X 1.2 MM u 60.03 15.00 900.48 900.48 900.48
57 PLATINA DE ACERO 1-1/2" X 1/8" X 6m var 21.12 25.00 528.00 528.00 528.00
58 DISOLVENTE XILOL gal 28.51 45.00 1,283.02 1,283.02 1,283.02
59 PINTURA ESMALTE SINTETICO gal 3.60 38.00 136.80 136.80 136.80
60 PINTURA ANTICORROSIVA gal 3.60 35.00 126.00 126.00 126.00
61 PINTURA TRAFICO COLOR NEGRO gal 2.56 52.00 133.22 133.22 133.22
62 PINTURA TRAFICO COLOR AMARILLO gal 2.56 52.00 133.22 133.22 133.22
CRONOGRAMA DE ADQUISICION DE MATERIALES MATERIALES
PROYECTO:"MEJORAMIENTO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA ZONA URBANA DE LA CIUDAD DE ASCENSION,
DISTRITO DE ASCENSION - HUANCAVELICA - HUANCAVELICA"
DEPARTAMENT
O :HUANCAVELICA FECHA: JULIO DEL 2017
PROVINCIA :HUANCAVELICA
DISTRITO :ASCENSION
LUGAR :ASCENSION
ITEM DECRIPCION UND CANT. C.U PARCIAL MES 01 MES 02 TOTAL
63 PINTURA ESMALTE gal 10.28 48.00 493.42 493.42 493.42
64 PINTURA DE TRAFICO DE COLOR BLANCO gal 9.87 55.00 542.85 542.85 542.85
65 PINTURA DE TRAFICO DE COLOR AMARILLO gal 144.45 85.00 12,278.25 12,278.25 12,278.25
66 TRANQUERA DE MADERA u 4.00 70.00 280.00 280.00 280.00
67 CONO DE FIBRA DE VIDRIO DE 0.67 M u 4.00 82.50 330.00 330.00 330.00
68 DISOLVENTE THINER gal 1.80 19.00 34.20 34.20 34.20
69 PLAN DE MITIGACION AMBIENTAL glb 1.00 500.00 500.00 500.00 500.00
70 PLANCHA METALICA ESTRIADA 1.2 X 2.4 X2.5MM u 3.41 180.00 613.87 613.87 613.87
71 HOJAS DE SIERRA u 15.00 7.00 105.00 105.00 105.00
EQUIPOS
1 HERRAMIENTAS MANUALES %MO 1937.13 1,937.13 1,937.13
2 MEZCLADORA DE CONCRETO DE 9 -11p3 hm 4.0304 25 100.76 50.38 50.38 100.76
3 SOLDADORA ELECTRICA MONOFASICA ALTERNA 225 A hm 103.62 15 1554.30 777.15 777.15 1,554.30
4 CAMION VOLQUETE 6 m3 hm 19.5672 100 1956.72 978.36 978.36 1,956.72
BATERIA ELECTROLITICO GELIFICADO DE CICLO PROFUNDO DE 12 VOLT DE u 18 500 9000.00 4,500.00 4,500.00
5 100 AH 9,000.00
GENERADOR FOTOVOLTAICO DE 100 WATTS, NORMA INTERNACIONAL IEC- u 18 500 9000.00 4,500.00 4,500.00
6 61215 Y IEEE-1262 9,000.00
7 COMPRESORA NEUMATICA 250-330 PCM, 87 HP hm 2.496 80 199.68 99.84 99.84 199.68
8 COMPACTADOR VIBRATORIO TIPO PLANCHA 4 HP hm 7.9998 15 120.00 60.00 60.00 120.00
9 CORTADORA DE CONCRETO 8HP hm 2.496 15 37.44 18.72 18.72 37.44
10 MARTILLO NEUMATICO DE 25 kg hm 4.992 8.5 42.43 21.22 21.22 42.43
11 CAMION GRUA hm 28.8 200 5760.00 2,880.00 2,880.00 5,760.00
12 ESTACION TOTAL he 1.8 25 45.00 22.50 22.50 45.00
13 NIVEL TOPOGRAFICO he 1.8 10 18.00 9.00 9.00 18.00
CRONOGRAMA DE ADQUISICION DE MATERIALES MATERIALES
PROYECTO:"MEJORAMIENTO DE TRANSITABILIDAD VEHICULAR Y PEATONAL EN LA ZONA URBANA DE LA CIUDAD DE ASCENSION,
DISTRITO DE ASCENSION - HUANCAVELICA - HUANCAVELICA"
DEPARTAMENT
O :HUANCAVELICA FECHA: JULIO DEL 2017
PROVINCIA :HUANCAVELICA
DISTRITO :ASCENSION
LUGAR :ASCENSION
ITEM DECRIPCION UND CANT. C.U PARCIAL MES 01 MES 02 TOTAL
14 TECNICO EN SEMAFOROS glb 18 400 7200.00 3,600.00 3,600.00 7,200.00

PRESUPUESTO MES 01 MES 02 TOTAL


COSTO DIRECTO 241,989.41 199,559.98 42,429.43 241,989.41
AVANCE % 82.47 % 17.53 % 100.00 %
TOTAL DE COSTO DIRECTO 241,989.41