COSTING OF ASPHALT CONCRETE TYPE 1 - (0-14)

RAW MATERIALS
COST PER TON FOR
NO DESCRIPTION PERCENTAGE COST AC

1 10/14 MM AGRREGATES 27 1,520.00 410.40

2 6/10 MM AGRREGATES 12 1,320.00 158.40


0/6 MM AGRREGATES
3 (JARIBUNI) 30 1,050.00 315.00

0/6 MM AGRREGATES
4 (MAZERAS) 33 1,150.00 379.50
BITUMEN AT % OF TOTAL
5 WEIGHT (TONS) 5.6 77,000.00 4,312.00
SUBTOTAL FOR RAW MATERIALS 5,575.30
6 WASTAGES 2.5 139.38
PRODUCTION COST
COST PER TON FOR
NO DESCRIPTION UNIT COST AC

6 HEATING BITUMEN 1.14 101.00 115.14

7 PRODUCTION COST OF PLANT 10 101.00 1,010.00

9 LABOUR FOR PRODUCTION 1 121.43 121.43


SUBTOTAL PRODUCTION COST 1,246.57
TRANSPORTATION AND LAYING COST

10 TIPPER TRANSPORT 1 850.00 850.00

11 LABOUR FOR LAYING 1 114.29 91.42

12 LAYING EQUIPMENT PER DAY


PAVER 1.00 35,000.00
TANDEM ROLLER 1.00 25,000.00
PNEUMATIC TYRED
ROLLER 1.00 25,000.00
AIR COMPRESSOR 1.00 10,000.00
HAND SPRAYER 1.00 6,000.00
OPERATORS 6 NO. AT
1500 PER DAY 6.00 9,000.00

SUBTOTAL TRANSPORT AND LAYING COST 1,571.43


SUBTOTAL 2 2,512.85
GRAND TOTAL 9,474.10
PROFIT AND OVERHEADS AT 30 % 2,368.53
COST PER TON 11,842.63
COST PER CUBIC 26,053.78

K 160
DESCRIPTION COST PER LITRE REMARKS
COST PER DRUM 18,000.00 90.00 18,000/ 200 LITRES
TRANSPORT 5.000 5 /= PER L
PROFITS AND OVERHEADS 25% 23.75
TOTAL 118.75

MC 30
DESCRIPTION COST PER LITRE REMARKS
COST PER DRUM 18,000.00 90.00 18,000/ 200 LITRES

MOBILIZATION OF DISTRIBUTOR 5.000 5 /= PER L

30,000/= PER DAY


FOR 4,500 LITRES IS
HIRE OF DISTRIBUTOR 7.000 15.60
PROFITS AND OVERHEADS 25% 23.75
TOTAL 125.75
YPE 1 - (0-14)

REMARKS
EX QUARRY - 600/=,TRANSPORT 800/=, CESS
120/=
EX QUARRY - 400/=,TRANSPORT 800/=, CESS
120/=
EX QUARRY - 200/=,TRANSPORT 800/=, CESS
50/=

EX QUARRY - 300/=,TRANSPORT 800/=, CESS


50/=

72/= PER KG+5 /= TRANSPORT

REMARKS

80 LTRS IS USED TO HEATUP BITUMEN THAT


CAN PRODUCE APPOX 70 TONS OF AC . GIVES
1.14 LITRES PER TON OF AC AT 101/=

10 LTRS PRODUCE 1 TON OF AC, AT 101/= PER


LITRE

OPERATORS AT 5,000/= PER DAY CASUAL


LABOURERS AT 3,500/= FOR 70 TONS OF AC
PRODUCED, GIVING 121.43 /= PER TON

ST
2 TRIPS A DAY AT 30,000/= A DAY HIRED GIVES
850/=

8 PERSONNEL AT 800/= PER DAY FOR THE 70


TONS IS 91.42/=

110,000/= FOR 70 TONS GIVES 1,171.43/= PER


TON