Professional Documents
Culture Documents
Publications
Current Transformer
Testing Guide
Introduction
This is Outdoor CT, it can work upto 15KV line,
frequency mention is 60Hz, it is multi ratio CT of
150:300:5; multi ratio CT is developed with the help of
tapping at CT’s Secondary, but you can use one ratio
at a time, means i can use it as 300:1 or as 150:1 CT at
a single event, and if i am using 150:1(X2 & X3), i do
not need to short rest of the CT section(X1 &X2), but
please remember this is not the practice of multi core
CT, if i have multi core CT of 300:1:1, and it is desig-
nated as protection (300:1) and measurment(300:1)
CT, i have to Test only protection core, then it is men-
datory to short the remaining measurment CT core.
2 3
Why?because multi core 300:1:1 CT is actaully rep- BIL is bulk impulse lightning voltage,this viltage is
resenting two CTs of 300:1 ratios with single primary definif insulation withstand capability of CT against
current of 300A, if any of secondary core remains defined voltage value.
open, it will act as a open circuit CT under excitation, Now we will observe a IEC coded CT,
and remember open circuit CT under excitation is the
most dangerous practice in protection engineering
field which will result in human casuality and equip-
ment damage.
VK=IZ
it will become, VK=ALF*ISN*(RCT+RB+RLead)
RB is burden resistance, we have 400-200-100/1-1-1-1,
5P10, 30VA CT, if lead resistance is not mention con-
sider it zero, RCT is 4 to 5 at 75 degree celcius
VK=10*1*(4+30+0)
VK=340V
8
CT Representation in Schematic Draw- Testing Practices
ings
Here CT is connected via Test block to OVERCURRENT De-Magnetizing of CT
Relay, these CTs are multi ratio CT, you can recognize them
from secondary core codes 1S1,1S2 and 1S3. Before any testing practice, we need to demagnetize
CT, WHY? may be there is residual flux/magnetiza-
tion flux in CT, this residual flux may be due to previ-
Test Switches ous CT Testing or may be subjected to high current.
Current switches consisting of a test jack and current short-
ing elements are placed in current circuits to facilitate check- Two methods are available for demagnetization of CT,
out, troubleshooting, calibration, and periodic testing of one is similar to knee point testing, 2nd method is us-
relays, meters, transducers, and instrumentation. These ing secondary loop resistance reduction.
switches permit testing to take place without de-energizing
the primary circuit and may be a separate unit or built into a 1st method
protective relay case.
Connect CT as shown below
Test Jacks
The test jack is used to allow current measurements to be
taken without opening the circuit by inserting a test plug into
the test jack. The test plug is a two-wire device connected to
an ammeter. Inserting the test plug into the test jack places
the ammeter in series with the current circuit. Before the test
plug is inserted into the jack, extreme care should be taken
to make sure that a complete low-impedance circuit exists
1.1st put off circuit breaker
through the ammeter.
2. Confirm supply zero by short and ground method
9 10
3. Remove Test block of CT
4. Insert Test plugs of your power source, as per circuit
the ammeter must be in series with AC source and CT,
Voltmeter must be connected in parallel of AC source
and CT.
5. Primary of CT shown open circuit, it is actually in-
formed that breaker is at off and ground position.
6. Unmarked outputs of primary and secondary of CT
must be short by Jumpers, Jumpers are flexible thin
copper conductors
7. Safe distance of work must be 7 to 8 feet (min)
8. This demagnetization process is similar to the exci-
tation voltage test
9. Test Power supply is AC with Variable Transformer
9. 1st Raise voltage with the help of Variable Trans-
former , and identify the point of CT saturation, by
point i mean identify the voltage level at which slight
increase give more deflection/reading as compare to
previous reading in Ammeter, that point is identify as
minimum value of saturation/knee point voltage.
10. Now reduce the voltage supply gradually to Zero
value, wait for the Ammeter reading of Zero Ampere,
once you observe this value.it is information that your
CT is demagnetized.
2nd method
Connect CT as shown on next page
11
1.1st put off circuit breaker
2. Confirm supply zero by short and ground method
3. Remove Test block of CT
4. Insert Test plugs of your power source, as per circuit
the ammeter must be in series with AC source and CT,
Voltmeter must be connected in parallel of AC source
and CT.
5. Connect Low Value of Variable Resistor across Pri-
mary conductor of CT
6. Safe distance of work must be 7 to 8 feet (min)
7. Test Power supply is AC with Variable Transformer
8. 1st Raise voltage with the help of Variable trans-
former, and same time raise the resistor value, observe
the knee point voltage and excitation current values,
now reduce voltage from variable transformer and re-
sistance from variable resistor value to zero, your CT
is demagnetized.
12
9. you can series connected Ammeter on Primary conductor of CT, when you reduced resistance to zero value , it is out of service method, out of service you need to
there is significant drop in current value at primary conductor which will be shown by this series ammeter, this remove CT from compartment or switch chamber.
reduction notify that CT is now demagnetized.
1. Shut off breaker
Ratio Test: 2. Check Supply Zero state
Connect CT as shown below 3. short and ground the circuit breaker
4. Remove CT from Chamber
5. CT Primary bar, you can use as primary conductor
for CT Test
6. Now connect Primary bar conductor of CT to Test
Power Supply Circuit
7. Test Power Supply circuit is consist of AC Power
Supply, Variable Transformer, Loading Transforme
and Reference CT , Ammeter is connected at second-
ary of reference CT.
8. Reference CT is CT with know ratio, i.e.
100:1,200:1etc.i used 200:1.
9. Loading Transformer is controlling transformer and
designed to provide rated output voltage at full output
VA.
9. place jumpers at loading transformer and unmarked
outputs of CTs primary and secondary.
10. Variable Transformer rating is 8KVA, 240v/6v, and
will inject upto 1200A.(Safe Distance must maintain)
11. We will inject 25% of CT primary current rating, if
CT ratio is 1200:1, i will inject 25% of 1200A, which is
144A.
13 14
12. Then observe values at Ammeter of reference CT method is using CT Analyzer. CT Analyzer is composed of meters, calibrated CTs, holding, filtering and sampling
and Ammeter at CT secondary. microprocessor circuits.
In-service Method is mention below 1. in this method, no need to take CT out of Chamber
1. Maintain Safe Distance of work 2. For Connections, we need to shut off the breaker
2. Use Clamp meter on secondary 3. Connect CT Analyzer as mention below
3. As per IEEE Std C57.13.1-2017, Guide advised
clampmeter on primary side also, but i suggest to take
primary current reading from associated microproces-
sor relay or energy meter.
4. Note Reading of secondary current from clamp on
ammeter
5. From Energymeter, please note circuit current or
feeder current which will be primary current
6. Now if we have 400:1, and Energymeter or micro-
processor is showing 200A or 1% less as compare to
rated value at primary and Clamp on meter on sec-
ondary is showing 0.5 or 0.49 or 0.48 or 0.47A, then
ratio is correct as per nameplate data.
7. Always remember the safe distance of work in this
method is 3 to 4 feet, you must wear safety PPE during 4. After connection, put on circuit breaker, so supply will be normal.
clamping of meter 5. Sample and hold circuit of analyzer will capture the simultaneous primary and secondary current amplitudes
8. Please note your Clamp meter must be calibrated and phase angles between them,Calibrated CTs in CT analyzer are used to provide low scale replica of Under
and allowable errors of clamp meter must be known to study or at Test CT’s current values.
you. 6. microprocessor will do math on these captured values and show result on display
7. The result then will be compared with nameplate data
Another method and we can say precious and modern This method is more accurate and modern.
15 16
Polarity test
Warning: A dangerous voltage may be generated while disconnecting the battery from the transformer winding;
therefore, a resistor may be connected in parallel with the CT winding before disconnecting the dc source. The
ohmic value of the resistor should be in the range of the dc resistance of the winding and should be of appropriate
wattage. This would avoid overvoltage and arcing when the dc source is disconnected. After a few seconds the re-
sistance can be disconnected. Alternatively, if a knife switch is not used, a hot stick or rubber gloves must be used
for connecting and disconnecting the battery.
AC voltage test—oscilloscope
Connect CT as per below mention circuit, please note circuit breaker must be at off & ground position
18
If only a single-channel oscilloscope is available, the preferred method is to apply secondary voltage to the 1.In this method, the main role is played by two am-
vertical input terminals, V, and primary voltage to the horizontal input terminals, H, with polarities as indicated meters A1 and A2.
in the diagram. If the slope of the line is positive as shown as it would be when the same voltage is applied to both 2. The correct polarity is identified when Reading on
inputs, then the polarity is in accordance with terminal markings. If a dual-channel oscilloscope is available, pri- A2 is more then A1.
mary and secondary voltages should be displayed on separate channels. If the resulting waveforms are in polarity
agreement (as they would be when the same voltage is applied to both channels), the polarity is correct. If the os- Insulation resistance test
cilloscope is calibrated, the current-transformer ratio can be obtained directly by measuring the magnitude of the Equipment we require in this test is Insulation Resist-
voltage waveforms and multiplying by the scale constants of the oscilloscope. The ammeter is provided only for ance Tester.
indication of excessive excitation current.
Current method
Connect CT as per below mention circuit, please note circuit breaker must be at off & ground position
19 20
Connect CT as per below mention circuit, please note circuit breaker must be at off & ground position Insulation tester leads shall be connected as defined below
Test voltage shall be selected according to given table. The durationcould be 1min to 10min, and the reading shall be taken after this
The voltage shall be applied between duration.Before disconnecting the test leads test object shall be discharged throughground. The same procedure shall be followed
1. Primary to secondary plus ground (covered during switchgear test). for other phases.
2. Secondary to primary plus ground. Influencing factors: Insulation resistance value is influenced by various factors like temperature,humidity, and moisture. The ambi-
3. Secondary core to core.Test voltage limits mentioned in table given below. The ambient temperature shall ent temperature value shall be noted during test. The relation between temperature and insulation resistance is inversely propor-
benoted down during test. tional.
Test methods:
Short time or spot reading:In this method the megger instrument is connected insulation to be tested andis applied for 60sec.
The reading is recorded at the end of that time.
Time resistance method:In this method the testing is fairly independent of temperature providesconsiderably more information
about the condition of insulation than the spotmeasurement. The test voltage shall be applied for 10minutes and readings are taken
every 15sec for the first minute and every minute for 10 minutes.Dielectric absorption factor, polarization index could be calculated
as below,
Dielectric absorption factor = 60sec reading/ 30sec reading.Polarization index = 10min reading / 1min reading.The insulation con-
dition could be categorized as shown in the Polarisation index table given above.
Step or multi- voltage method:This method requires a multi voltage megger instrument, preferably with 1:5voltage ratio
ranges. Any reduction of insulation resistance at higher voltage isa sign of an insulation weakness.
21 22
Winding and lead resistance (internal resistance) MAGNETIZATION CURVE TEST
Secondary resistance test is to verify the CT secondary Magnetization Curve test is to confirm the magnetisation characteristics of CT with nameplate specification.This
winding resistance withspecified one and no discon- test shall be conducted before ratio test and after secondary resistance and polarity test, since residual magnetism
tinuity in the winding. This value can be used inother left in the core due to DC test(polarity, resistance), which leads additional error in ratio test. The meters used for
calculations. Loop resistance to ensure load is con- this test shall be having true RMS measurement.The circuit connection shall be made as shown Figure.
nected properly andcircuits not left open.
The circuit connection shall be made as shown Figure
given below for secondary resistance.
Admittance test
A CT analyzer with admittance testing capability checks for abnormal admittance by injecting
1. Please note this primary injection Test, so an audio frequency into the secondary winding of an in-service CT, and by detecting the circuit
please maintain safe distance of work admittance. Any audio frequency signal between 1 kHz and 2 kHz would probably be satisfac-
2. Secondary of CT is remain off tory. One analyzer uses an audio frequency of 1575 Hz to avoid the probability of any multiple
3. One Voltmeter(better i suggest digital meter) harmonic of the fundamental system frequency being present in the system, and possibly caus-
will be connected in parallel to CT open Second- ing a false signal in the audio frequency-detecting circuitry.
ary Relaying or metering accuracy CTs have very small errors when operated within the specified
4. One ammeter must be connected in series with current and burden ratings. Therefore, it is known that the circuit admittance of any particu-
Primary current injector. lar CT and the circuit connected to it is very nearly constant throughout the normal operating
5. The secondary open-circuit voltage is range unless a fault condition develops. If the
plotted against the transformed primary exciting admittance measurement shows a deviation from normal while the CT is in service, it is likely
current. that the CT has: 1) an internal short (usually a shorted turn); 2) an abnormal internal or exter-
6. The observed values of current must be divid- nal resistance (such as a high-resistance connection—loose or corroded); or 3) the CT is op-
ed by the CT ratio in order to compare observed erating under abnormal conditions (such as a dc component in the primary current). Serious
data with the manufacturer’s data or other refer- faults are immediately obvious due to an abnormally high admittance reading, usually at least
ence. 1.5 times the normal reading. A CT with an incorrect ratio, or connected to the wrong tap will
provide readings substantially different than the normal readings.
25 26
BURDEN TEST
Please connect CT as per below connection draw-
ing, prior to this please shut off the breaker and
ground it
Bibliography:
1. IEEE Guide for Field Testing of Relaying Current
Transformers
2. Schneider Electric-Testing and Commissioning of
Electrical Equipment
28 29
OEP
O-Engineers
Publications