Professional Documents
Culture Documents
Judgment was entered in the court below in favor of the "(2) The true value of the goods insured . . .
plaintiffs for the sum of 5,265 pesos and 25 centavos, with
interest from the 24th of June, 1905, and costs. It is "(3) The value of the same goods after the fire, and
claimed by the appellant that the finding of the court everything else which may be submitted to their
below as to the amount of the loss is not justified by the judgment.
evidence. A great many witnesses were presented by
each side, but the only persons who had any real As it is seen, the above are the principal precepts on
knowledge as to the amount of stock in the store at the which the insured must rely from the time the underwriter
time of the fire, and as to its value, were the plaintiff refuses to come to an amicable settlement or
Chang and his clerk. They testified that it was worth more extrajudicial agreement. There is no law in force which
than 10,000 pesos, the amount named in the policy. No contains such a provision as that which the judgment
one of the witnesses for the defendant fixed the value of appealed from sets forth in the manner of a rule in the
the stock then on hand at more than 500 pesos. The following words:jgc:chanrobles.com.ph
arbitrators appointed by the defendant found that the
value was 2,106 pesos. The defendant’s agent testified "It is a duty incumbent on said defendant company to
that during negotiations he offered to settle for 3,000 return, within a reasonable period of time after the
pesos. That the plaintiff (Chang) was carrying on a presentation of the claim and proof of the loss, said proof
business of some importance was proved at the trial by of the loss together with a clear and itemized statement
the introduction of the records of the customs in Cebu, by of the reasons why they are not considered sufficient and
which it appeared that between the month of July, 1904, satisfactory. Noncompliance with this duty, or failure to
and February, 1905, he had imported through the notify the assured with reasonable time, amounts to a
custom-house goods which with the duty added were of waiver on the part of the insurance company to require
the value of 4,758 dollars and 48 cents, money of the the presentation of other proof, and is also equivalent to
a denial of the loss or responsibility, and, consequently, The insured might be excused from submitting his claim to
under the arbitration clause of said policy, there is arbitration in case of an express refusal of the underwriter
nothing left for its submission to arbitration." (Bill of to heed the former’s demand to carry out that essential
exceptions, pp. 19 and 20.) condition of the contract. Yet, the writer of this dissenting
opinion does not hold the insured exempt from
The insured complied with the first part of article 404, by compliance with this special condition, because of the
informing the underwriter of the fire. Not so with the more or less correct constitute which he might give to the
second part of the same, concerning the statement to action of the underwriter in regard to his claim, neither
be filed with the municipal judge or justice of the peace, because of this phrase, "I can not go on with your case,
in accordance with the proposed change inserted in the Mr. Sleeper; I have not enough proof," nor because of this
preamble (Exposicion de Motivos) of the Code of other one, "I think, as far as I can remember, that he said
Commerce of the Philippine Islands (p. 8). Aside from this, he wanted to bring the matter to a basis."cralaw
since all the steps taken to come to an agreement of a virtua1aw library
private nature had been ended by the words addressed
to Mr. Sleeper, and since a legal suit had already been Such is the opinion of the writer in regard to the first
commenced, nothing contained in the above-quoted question brought before us by the appeal.
precepts bear any relation to the matter in controversy.
Instead of presuming on the part of the underwriter an With reference to the second question, or the amount in
implicit waiver of the stipulation agreed upon under the controversy, if the contention that the bringing of the suit
policy, it was necessary to make a finding of fact or of without first complying with that condition be right, the
law, which should explain the manifest neglect of the writer does not see any reason why the amount of the
procedure required by the above-named articles of the judgment shall be 5,265 pesos and 25 centavos, and not
Code of Commerce now in force. Unless this neglect is 10,000 pesos, the sum stipulated in the policy and
properly justified, the infringement of the general demanded in the complaint.
provisions of law on the subject of this litigation becomes
self-evident. Nor is he of the opinion that such obligation, once take
subject of a litigation, should consist of the sum awarded
Although the requirements of articles 409 and 410 are of by the arbitrators appointed by the underwriter, because
an adjective nature (Which do not certainly correspond the case has never been submitted to arbitration, as
with any of the judicial proceedings of the old Spanish stipulated in the insurance contract.
Code of Civil Procedure), those of articles 404 to 408 and
411 are substantive, and constitute the essential elements As the judgment appealed from does not specify facts
on which an action for the exercise of the right arising sufficient to justify a decision for the amount adjudged, I
from the insurance contract should be based. This am of the opinion that the case should be returned to the
contract being a fire insurance personal property, trial court, in order that expert witnesses may furnish the
factories, or stores, requires, as its — evidence mentioned in paragraph 2 and 3 of article 407
of the Code of Commerce; the proof stated in
"First and essential condition, the exercise of a real and paragraph 1 of said article not being necessary in view of
certain subject-matter, not only at the time of the signing the fact that both the insured and the underwriter have
of the same, but likewise at the time of the fire, it being come to an understanding as to the cause of the fire.
also essential that said subject-matter shall not have
suffered, during the stated period, any change or G.R. No. 96283 February 25, 1992
alteration in the nature or place designated in the policy;
and this doctrine is based on the very nature of the CHUNG FU INDUSTRIES (PHILIPPINES) INC., its Directors and
insurance contract, whose object is the prevention of Officers namely: HUANG KUO-CHANG, HUANG AN-
loss, and not the securing of profit . . ." [Preamble CHUNG, JAMES J.R. CHEN, TRISTAN A. CATINDIG, VICENTE
(Exposicion de Motivos) of the Code of Commerce. ] B. AMADOR, ROCK A.C. HUANG, JEM S.C. HUANG, MARIA
TERESA SOLIVEN and VIRGILIO M. DEL
Besides the general provisions of law governing the ROSARIO, petitioners,
contract, the policy embodies a special requirement,
compulsory for both the insured and the underwriter, in vs.
order that the actual loss suffered at the time of the fire
might be the basis for the institution of an action arising COURT OF APPEALS, HON. FRANCISCO X. VELEZ (Presiding
from the contract. And this is the arbitration agreed upon Judge, Regional Trail Court of Makati [Branch 57]) and
— "as an essential element of the contract between the ROBLECOR PHILIPPINES, INC., respondents.
corporation and the insured, that unless the corporation
shall demand exemption from liability by reason of fraud,
breach of the conditions, or waiver, as stated (waiver by
claimant), the assured, or claimant, shall have no right to ROMERO, J.:
commerce suit or other proceedings before any court
whatever upon this policy until the amount of the loss or This is a special civil action for certiorari seeking to annul
damage shall been referred, investigated, and the Resolutions of the Court of Appeals* dated October
determined as above provided, and then only for the 22, 1990 and December 3, 1990 upholding the Orders of
amount awarded, and the obtaining of such an award July 31, 1990 and August 23, 1990 of the Regional Trial
shall be a condition precedent to the institution of any Court of Makati, Branch 57, in Civil Case No. 90-1335.
suit upon this policy and to the liability and obligation of Respondent Court of Appeals affirmed the ruling of the
the corporation to pay or satisfy any claim or demand trial court that herein petitioners, after submitting
based upon this policy, "etc. themselves for arbitration and agreeing to the terms and
conditions thereof, providing that the arbitration award
shall be final and unappealable, are precluded from
The compliance with this special provision is compulsory
seeking judicial review of subject arbitration award.
under article 1255 of the Civil Code.
It appears that on May 17, 1989, petitioner Chung Fu either party is entitled to
Industries (Philippines) (Chung Fu for brevity) and private seek judicial assistance
respondent Roblecor Philippines, Inc. (Roblecor for short) for purposes of
forged a construction agreement 1 whereby respondent enforcing the arbitrator's
contractor committed to construct and finish on award;
December 31, 1989, petitioner corporation's
industrial/factory complex in Tanawan, Tanza, Cavite for xxxxxxxxx 4
and in consideration of P42,000,000.00. In the event of
disputes arising from the performance of subject
(Emphasis supplied)
contract, it was stipulated therein that the issue(s) shall be
submitted for resolution before a single arbitrator chosen
by both parties. Respondent Regional Trial Court approved the arbitration
agreement thru its Order of May 30, 1990. Thereafter,
Engr. Willardo Asuncion was appointed as the sole
Apart from the aforesaid construction agreement, Chung
arbitrator.
Fu and Roblecor entered into two (2) other ancillary
contracts, to wit: one dated June 23, 1989, for the
construction of a dormitory and support facilities with a On June 30, 1990, Arbitrator Asuncion ordered petitioners
contract price of P3,875,285.00, to be completed on or to immediately pay respondent contractor, the sum of
before October 31, 1989; 2 and the other dated August P16,108,801.00. He further declared the award as final
12, 1989, for the installation of electrical, water and and unappealable, pursuant to the Arbitration
hydrant systems at the plant site, commanding a price of Agreement precluding judicial review of the award.
P12.1 million and requiring completion thereof one month
after civil works have been finished. 3 Consequently, Roblecor moved for the confirmation of
said award. On the other hand, Chung Fu moved to
However, respondent Roblecor failed to complete the remand the case for further hearing and asked for a
work despite the extension of time allowed it by Chung reconsideration of the judgment award claiming that
Fu. Subsequently, the latter had to take over the Arbitrator Asuncion committed twelve (12) instances of
construction when it had become evident that Roblecor grave error by disregarding the provisions of the parties'
was not in a position to fulfill its obligation. contract.
Claiming an unsatisfied account of P10,500,000.00 and Respondent lower court denied Chung Fu's Motion to
unpaid progress billings of P2,370,179.23, Roblecor on Remand thus compelling it to seek reconsideration
May 18, 1990, filed a petition for Compulsory Arbitration therefrom but to no avail. The trial court granted
with prayer for Temporary Restraining Order before Roblecor's Motion for Confirmation of Award and
respondent Regional Trial Court, pursuant to the accordingly, entered judgment in conformity therewith.
arbitration clause in the construction agreement. Chung Moreover, it granted the motion for the issuance of a writ
Fu moved to dismiss the petition and further prayed for of execution filed by respondent.
the quashing of the restraining order.
Chung Fu elevated the case via a petition for certiorari to
Subsequent negotiations between the parties eventually respondent Court of Appeals. On October 22,1990 the
led to the formulation of an arbitration agreement which, assailed resolution was issued. The respondent appellate
among others, provides: court concurred with the findings and conclusions of
respondent trial court resolving that Chung Fu and its
officers, as signatories to the Arbitration Agreement are
2. The parties mutually agree that the
bound to observe the stipulations thereof providing for
arbitration shall proceed in accordance
the finality of the award and precluding any appeal
with the following terms and conditions:
therefrom.
—
Considering the insistence of the plaintiff that The reasons given by the respondent Court in
the said Conditions of Contract was not duly denying petitioners motion to suspend
executed or signed by the parties, and the proceedings are untenable.
failure of the defendants to submit any signed
copy of the said document, this Court entertains 1. The notarized copy of the articles of agreement
serious doubt whether or not the arbitration attached as Annex A to petitioners reply dated August
clause found in the said Conditions of Contract 26, 1993, has been submitted by them to the respondent
is binding upon the parties to the Articles of Court (Annex G, petition). It bears the signature of
Agreement. (Underscoring supplied.) petitioner Rufo B. Colayco, president of petitioner
The lower court then ruled that, assuming that the Shangri-La Properties, Inc., and of Bayani Fernando,
arbitration clause was valid and binding, still, it was too president of respondent Corporation (Annex G-1,
late in the day for defendants to invoke arbitration. It petition). At page D/4 of said articles of agreement it is
quoted the following provision of the arbitration clause: expressly provided that the conditions of contract are
`deemed an integral part thereof (page 188, rollo). And it
Notice of the demand for arbitration of a is at pages D/42 to D/44 of the conditions of contract
dispute shall be filed in writing with the other that the provisions for arbitration are found (Annexes G-3
party to the contract and a copy filed with the to G-5, petition, pp. 227-229). Clause No. 35 on arbitration
Project Manager. The demand for arbitration specifically provides:
shall be made within a reasonable time after
the dispute has arisen and attempts to settle Provided always that in case any dispute or difference
amicably have failed; in no case, however, shall shall arise between the Owner or the Project Manager on
the demand he made be later than the time of his behalf and the Contractor, either during the progress
final payment except as otherwise expressly or after the completion or abandonment of the Works as
stipulated in the contract. to the construction of this Contract or as to any matter or
thing of whatsoever nature arising thereunder or in
Against the above backdrop, the lower court found
connection therewith (including any matter or being left
that per the May 30, 1991 agreement, the project was to
by this Contract to the discretion of the Project Manager
be completed by October 31, 1991. Thereafter, the
or the withholding by the Project Manager of any
contractor would pay P80,000 for each day of delay
certificate to which the Contractor may claim to be
counted from November 1, 1991 with liquified (sic)
entitled or the measurement and valuation mentioned in
damages up to a maximum of 5% of the total contract
clause 30 (5) (a) of these Conditions or the rights and
price.
liabilities of the parties under clauses 25, 26, 32 or 33 of
The lower court also found that after the project was these Conditions), the Owner and the Contractor hereby
completed in accordance with the agreement that agree to exert all efforts to settle their differences or
contained a provision on progress payment billing, SPI dispute amicably. Failing these efforts then such dispute
took possession and started operations thereof by or difference shall be referred to Arbitration in
accordance with the rules and procedures of the (i) THE PARTIES DID NOT ENTER
Philippine Arbitration Law. INTO AN AGREEMENT
TO ARBITRATE.
The fact that said conditions of contract containing the (ii) ASSUMING THAT THE PARTIES
arbitration clause bear only the initials of respondent DID ENTER INTO THE
Corporations representatives, Bayani Fernando and AGREEMENT TO
Reynaldo de la Cruz, without that of the representative of ARBITRATE,
petitioner Shangri-La Properties, Inc. does not militate RESPONDENTS ARE
against its effectivity. Said petitioner having categorically ALREADY IN DEFAULT IN
admitted that the document, Annex A to its reply dated INVOKING THE
August 26, 1993 (Annex G, petition), is the agreement AGREEMENT TO
between the parties, the initial or signature of said ARBITRATE.
petitioners representative to signify conformity to
arbitration is no longer necessary. The parties, therefore, On the first assigned error, petitioner contends that
should be allowed to submit their dispute to arbitration in the Order of the lower court denying the motion to
accordance with their agreement. suspend proceedings is a resolution of an incident on the
merits. As such, upon the continuation of the
2. The respondent Court held that petitioners `are in proceedings, the lower court would appreciate the
default in proceeding with such arbitration. It took note of evidence adduced in their totality and thereafter render
`the fact that under the supposed Arbitration Clause a decision on the merits that may or may not sustain the
invoked by defendants, it is required that Notice of the existence of an arbitration clause. A decision containing
demand for arbitration of a dispute shall be filed in writing a finding that the contract has no arbitration clause can
with the other party x xx in no case x xx later than the then be elevated to a higher court in an ordinary appeal
time of final payment, which apparently, had elapsed, where an adequate remedy could be obtained. Hence,
not only because defendants had taken possession of to petitioner, the Court of Appeals should have dismissed
the finished works and the plaintiffs billings for the the petition for certioraribecause the remedy of appeal
payment thereof had remained pending since would still be available to private respondents at the
November, 1991 up to the filing of this case on July 14, proper time.[7]
1993, but also for the reason that defendants have failed
The above contention is without merit.
to file any written notice of any demand for arbitration
during the said long period of one year and eight The rule that the special civil action of certiorari may
months, x xx. not be invoked as a substitute for the remedy of appeal is
succinctly reiterated in Ongsitco v. Court of Appeals[8]as
Respondent Court has overlooked the fact that under the follows:
arbitration clause
x xx. Countless times in the past, this Court has held that
Notice of the demand for arbitration dispute shall be filed `where appeal is the proper remedy, certiorari will not lie.
in writing with the other party to the contract and a copy The writs of certiorari and prohibition are remedies to
filed with the Project Manager. The demand for correct lack or excess of jurisdiction or grave abuse of
arbitration shall be made within a reasonable time after discretion equivalent to lack of jurisdiction committed by
the dispute has arisen and attempts to settle amicably a lower court. `Where the proper remedy is appeal, the
had failed; in no case, however, shall the demand be action for certiorari will not be entertained. x
made later than the time of final payment except as xx. Certiorari is not a remedy for errors of judgment. Errors
otherwise expressly stipulated in the contract of judgment are correctible by appeal, errors of
(underscoring supplied) jurisdiction are reviewable by certiorari.
quoted in its order (Annex A, petition). As the respondent Rule 65 is very clear. The extraordinary remedies
Court there said, after the final demand to pay the of certiorari, prohibition and mandamus are available
amount of P110,883,101.52, instead of paying, petitioners only when `there is no appeal or any plain, speedy and
set up its own claim against respondent Corporation in adequate remedy in the ordinary course of law x xx. That
the amount of P220,000,000.00 and set a conference is why they are referred to as `extraordinary. x xx.
thereon on July 12, 1993. Said conference proved futile.
The next day, July 14, 1993, respondent Corporation filed The Court has likewise ruled that certiorari will not be
its complaint against petitioners. On August 13, 1993, issued to cure errors in proceedings or correct erroneous
petitioners wrote to respondent Corporation requesting conclusions of law or fact. As long as a court acts within
arbitration. Under the circumstances, it cannot be said its jurisdiction, any alleged errors committed in the
that petitioners resort to arbitration was made beyond exercise of its jurisdiction will amount to nothing more
reasonable time. Neither can they be considered in than errors of judgment which are reviewable by timely
default of their obligation to respondent Corporation. appeal and not by a special civil action of certiorari.[9]v.
Court of Appeals, 327 Phil. 1, 41-42 (1996).9
Hence, this petition before this Court. Petitioner
This is not exactly so in the instant case. While this
assigns the following errors:
Court does not deny the eventual jurisdiction of the lower
A. court over the controversy, the issue posed basically is
whether the lower court prematurely assumed jurisdiction
THE COURT OF APPEALS ERRED IN ISSUING over it. If the lower court indeed prematurely assumed
THE EXTRAORDINARY WRIT jurisdiction over the case, then it becomes an error of
OF CERTIORARI ALTHOUGH THE REMEDY OF jurisdiction which is a proper subject of a petition
APPEAL WAS AVAILABLE TO RESPONDENTS. for certiorari before the Court of Appeals. And if the lower
court does not have jurisdiction over the controversy,
B.
then any decision or order it may render may be
THE COURT OF APPEALS ERRED IN FINDING annulled and set aside by the appellate court.
GRAVE ABUSE OF DISCRETION IN THE
However, the question of jurisdiction, which is a
FACTUAL FINDINGS OF THE TRIAL COURT
question of law depends on the determination of the
THAT:
existence of the arbitration clause, which is a question of
fact. In the instant case, the lower court found that there
exists an arbitration clause. However, it ruled that in (said) office as Notarial Registry Entry only, (e) the same
contemplation of law, said arbitration clause does not certification attests that the document entered in the
exist. notarial registry pertains to the Articles of Agreement only
without any other accompanying documents, and
The issue, therefore, posed before the Court of therefore, it is not a formal trade contract, and (f) the
Appeals in a petition for certiorari is whether the compilation submitted by respondents are a mere
Arbitration Clause does not in fact exist. On its face, the hodge-podge of documents and do not constitute a
question is one of fact which is not proper in a petition single intelligible agreement.
for certiorari.
In other words, petitioner denies the existence of the
The Court of Appeals found that an Arbitration arbitration clause primarily on the ground that the
Clause does in fact exist. In resolving said question of fact, representatives of the contracting corporations did not
the Court of Appeals interpreted the construction of the sign the Conditions of Contract that contained the said
subject contract documents containing the Arbitration clause. Its other contentions, specifically that insinuating
Clause in accordance with Republic Act No. 876 fraud as regards the alleged insertion of the arbitration
(Arbitration Law) and existing jurisprudence which will be clause, are questions of fact that should have been
extensively discussed hereunder. In effect, the issue threshed out below.
posed before the Court of Appeals was likewise a
question of law. Being a question of law, the private This Court may as well proceed to determine
respondents rightfully invoked the special civil action whether the arbitration clause does exist in the parties
of certiorari. contract. Republic Act No. 876 provides for the formal
requisites of an arbitration agreement as follows:
It is that mode of appeal taken by private
respondents before the Court of Appeals that is being
questioned by the petitioners before this Court. But at the Section 4. Form of arbitration agreement. A contract to
heart of said issue is the question of whether there exists arbitrate a controversy thereafter arising between the
an Arbitration Clause because if an Arbitration Clause parties, as well as a submission to arbitrate an existing
does not exist, then private respondents took the wrong controversy, shall be in writing and subscribed by the
mode of appeal before the Court of Appeals. party sought to be charged, or by his lawful agent.
For this Court to be able to resolve the question of The making of a contract or submission for arbitration
whether private respondents took the proper mode of described in section two hereof, providing for arbitration
appeal, which, incidentally, is a question of law, then it of any controversy, shall be deemed a consent of the
has to answer the core issue of whether there exists an parties of the province or city where any of the parties
Arbitration Clause which, admittedly, is a question of fact. resides, to enforce such contract of submission.
(Underscoring supplied.)
Moreover, where a rigid application of the rule
that certiorari cannot be a substitute for appeal will result
in a manifest failure or miscarriage of justice, the The formal requirements of an agreement to
provisions of the Rules of Court which are technical rules arbitrate are therefore the following: (a) it must be in
may be relaxed.[10] As we shall show hereunder, had the writing and (b) it must be subscribed by the parties or
Court of Appeals dismissed the petition for certiorari, the their representatives. There is no denying that the parties
issue of whether or not an arbitration clause exists in the entered into a written contract that was submitted in
contract would not have been resolved in accordance evidence before the lower court. To subscribe means to
with evidence extant in the record of the case. write underneath, as ones name; to sign at the end of a
Consequently, this would have resulted in a judicial document.[11] That word may sometimes be construed to
rejection of a contractual provision agreed by the parties mean to give consent to or to attest.[12]
to the contract.
The Court finds that, upon a scrutiny of the records
In the same vein, this Court holds that the question of this case, these requisites were complied with in the
of the existence of the arbitration clause in the contract contract in question. The Articles of Agreement, which
between petitioner and private respondents is a legal incorporates all the other contracts and agreements
issue that must be determined in this petition for review between the parties, was signed by representatives of
on certiorari. both parties and duly notarized. The failure of the private
respondents representative to initial the `Conditions of
Petitioner, while not denying that there exists an Contract would therefor not affect compliance with the
arbitration clause in the contract in question, asserts formal requirements for arbitration agreements because
that in contemplation of law there could not have been that particular portion of the covenants between the
one considering the following points. First, the trial court parties was included by reference in the Articles of
found that the conditions of contract embodying the Agreement.
arbitration clause is not duly signed by the
parties. Second, private respondents misrepresented Petitioners contention that there was no arbitration
before the Court of Appeals that they produced in the clause because the contract incorporating said provision
trial court a notarized duplicate original copy of the is part of a hodge-podge document, is therefore
construction agreement because what were submitted untenable.A contract need not be contained in a single
were mere photocopies thereof. The contract(s) writing. It may be collected from several different writings
introduced in court by private respondents were which do not conflict with each other and which, when
therefore of dubious authenticity because: (a) the connected, show the parties, subject matter, terms and
Agreement for the Execution of Builders Work for the consideration, as in contracts entered into by
EDSA Plaza Project does not contain an arbitration correspondence.[13] A contract may be encompassed in
clause, (b) private respondents surreptitiously attached several instruments even though every instrument is not
as Annexes `G-3 to `G-5 to their petition before the Court signed by the parties, since it is sufficient if the unsigned
of Appeals but these documents are not parts of the instruments are clearly identified or referred to and made
Agreement of the parties as there was no formal trade part of the signed instrument or instruments. Similarly, a
contract executed, (c) if the entire compilation of written agreement of which there are two copies, one
documents is indeed a formal trade contract, then it signed by each of the parties, is binding on both to the
should have been duly notarized, (d) the certification same extent as though there had been only one copy of
from the Records Management and Archives Office the agreement and both had signed it.[14]
dated August 26, 1993 merely states that the notarial
The flaw in petitioners contentions therefore lies in its
record of Nilberto Briones x xx is available in the files of
having segmented the various components of the whole
contract between the parties into several parts. This disagreement between the parties would therefore be a
notwithstanding, petitioner ironically admits the execution step backward.
of the Articles of Agreement. Notably, too, the lower
court found that the said Articles of Agreement also WHEREFORE, the questioned Decision of the Court of
provides that the `Contract Documents therein listed Appeals is hereby AFFIRMED and the petition
`shall be deemed an integral part of this Agreement, and for certiorari DENIED. This Decision is immediately
one of the said documents is the `Conditions of Contract executory.Costs against petitioner.
which contains the Arbitration Clause. It is this Articles of SO ORDERED.
Agreement that was duly signed by Rufo B. Colayco,
president of private respondent SPI, and Bayani F.
G.R. No. 103200 August 31, 1994
Fernando, president of petitioner corporation. The same
agreement was duly subscribed before notary public
Nilberto R. Briones. In other words, the subscription of the LA NAVAL DRUG CORPORATION, petitioner,
principal agreement effectively covered the other vs.
documents incorporated by reference therein. THE HONORABLE COURT OF APPEALS and WILSON C.
YAO, respondents.
This Court likewise does not find that the Court of
Appeals erred in ruling that private respondents were not
Jerome T. Paras for petitioner.
in default in invoking the provisions of the arbitration
clause which states that (t)he demand for arbitration shall
be made within a reasonable time after the dispute has Quasha, Asperilla, Ancheta, Peña &Nolasco for private
arisen and attempts to settle amicably had failed. Under respondent.
the factual milieu, private respondent SPI should have
paid its liabilities under the contract in accordance with
its terms. However, misunderstandings appeared to have
cropped up between the parties ostensibly brought
about by either delay in the completion of the VITUG, J.:
construction work or by force majeure or the fire that
partially gutted the project. The almost two-year delay in
In an effort to declog the courts of an increasing volume
paying its liabilities may not therefore be wholly ascribed
of work load and, most importantly, in order to accord
to private respondent SPI.
contending parties with expenditious alternatives for
Besides, private respondent SPIs initiative in calling settling disputes, the law authorities, indeed encourages,
for a conference between the parties was a step towards out of court settlements or adjudications. Compromises
the agreed resort to arbitration. However, petitioner and arbitration are widely known and used as such
posthaste filed the complaint before the lower acceptable methods of resolving adversarial claims.
court. Thus, while private respondent SPIs request for
arbitration on August 13, 1993 might appear an Arbitrations, in particular, is governed by a special law,
afterthought as it was made after it had filed the motion Republic Act 876, suppletory to which are laws and rules
to suspend proceedings, it was because petitioner also of general application. This case before us concerns the
appeared to act hastily in order to resolve the jurisdiction of courts, in relation to the provisions of Section
controversy through the courts. 6 of Republic Act No. 876, and, in that respect, the
applicability of the doctrine of estoppel. The law (R.A.
The arbitration clause provides for a reasonable time
876), specifically Section 6 thereof, provides:
within which the parties may avail of the relief under that
clause. Reasonableness is a relative term and the
question of whether the time within which an act has to Sec. 6. Hearing by court. — A party
be done is reasonable depends on attendant aggrieved by the failure, neglect or
circumstances.[15] This Court finds that under the refusal of another to perform under an
circumstances obtaining in this case, a one-month period agreement in writing providing for
from the time the parties held a conference on July 12, arbitration may petition the court for an
1993 until private respondent SPI notified petitioner that it order directing that such arbitration
was invoking the arbitration clause, is a reasonable time. proceed in the manner provided for in
Indeed, petitioner may not be faulted for resorting to the such agreement. Five days notice in
court to claim what was due it under the writing of the hearing of such application
contract. However, we find its denial of the existence of shall be served either personally or by
the arbitration clause as an attempt to cover up its registered mail upon the party in default.
misstep in hurriedly filing the complaint before the lower The court shall hear the parties, and
court. upon being satisfied that the making of
the agreement or such failure to comply
In this connection, it bears stressing that the lower therewith is not in issue, shall make an
court has not lost its jurisdiction over the case. Section 7 of order directing the parties to proceed to
Republic Act No. 876 provides that proceedings therein arbitration in accordance with the terms
have only been stayed. After the special proceeding of of the agreement. If the making of the
arbitration[16] has been pursued and completed, then the agreement or default be in issue the
lower court may confirm the award[17] made by the court shall proceed to summarily hear
arbitrator. such issue. If the finding be that no
agreement in writing providing for
It should be noted that in this jurisdiction, arbitration
arbitration was made, or that there is no
has been held valid and constitutional. Even before the
default in the proceeding thereunder,
approval on June 19, 1953 of Republic Act No. 876, this
the proceeding shall be dismissed. If the
Court has countenanced the settlement of disputes
finding be that a written provision for
through arbitration.[18] Republic Act No. 876 was adopted
arbitration was made and there is a
to supplement the New Civil Codes provisions on
default in proceeding thereunder, an
arbitration.[19] Its potentials as one of the alternative
order shall be made summarily directing
dispute resolution methods that are now rightfully
the parties to proceed with the
vaunted as the wave of the future in international
arbitration in accordance with the terms
relations, is recognized worldwide. To brush aside a
thereof.
contractual agreement calling for arbitration in case of
The court shall decide all motions, written notices to the former, expressed
petitions or application filed under the his intention to submit their disagreement
provisions of this Act, within ten days to arbitration, in accordance with
after such motions, petitions, or Republic Act 876, otherwise known as
applications have been heard by it. the Arbitration Law, and paragraph 7 of
their lease contract, providing that:
In chronology, the events that have led to the case at
bench are detailed in the appealed decision of 7. . . . Should the parties
respondent appellate court, which we here reproduce in fail to agree on the rate
toto. of rentals, the same shall
be submitted to a group
Original action for Certiorari and of Arbitrators composed
Prohibition for Annulment of the Orders, of three (3) members,
dated April 26, 1990 and June 22, 1990, one to be appointed by
respectively, of Branch LXI, Regional Trial LESSOR, another by
Court, Angeles City, in Special Case No. LESSEE and the third one
6024 for Enforcement of ARBITRATION to be agreed upon by
Agreement with Damages. Petitioner the two arbitrators
assails that portion of subject Order of previously chosen and
April 26, 1990, stating as follows: the parties hereto shall
submit to the decision of
the arbitrators.
(1) Petitioner's claim for
damages predicated
on alleged tortuous acts Thus, on May 6, 1989, respondent Yao
of respondents La Naval appointed Domingo Alamarez, Jr. as his
Drug corporation such arbitrator, while on June 5, 1989,
as their alleged petitioner chose Atty. CasianoSabile as
interference and its arbitrator. The confirmation of the
dilatory tactics, etc. in appointment of Aurelio Tupang, as third
the implementation of arbitrator, was held in abeyance
the Arbitration because petitioner instructed Atty. Sabile
Agreement in the to defer the same until its Board of
Contract of Lease, Directors could convene and approve
thereby compelling Tupang's appointment. Respondent Yao
among others the theorizes that this was petitioner's design
petitioner to go to Court to delay the arbitration proceedings, in
for redress; and violation of the Arbitration Law, and the
respondent La Naval governing stipulation of their contract of
Drug Corporation's lease.
counterclaim for
damages may be On the basis of the aforesaid allegations,
entertained by this respondent Yao prayed that after
Court in a hearing — not summary hearing pursuant to Section 6
summary — for the of the Arbitration Law, Atty.
purpose, under the Rules CasianoSabile and Domingo Alamarez
of Court. be directed to proceed with the
arbitration in accordance with Section 7
(2) A preliminary hearing of subject Contract of Lease and the
of the special and applicable provisions of the Arbitration
affirmative defense to law, by appointing and confirming the
show that Petitioner has appointment of the Third Arbitrator; and
not cause of action that the Board of Three Arbitrators be
against respondent's ordered to immediately convene and
claim for damages is resolve the controversy before it,
denied; a resolution on pursuant to Section 12 and the
this issue is deferred after succeeding sections of the Arbitration
the trial of the case on Law. (Annex "A," Petition.)
the merits.
In its Answer with Counterclaim (Annex
And challenges the Order of June 22, "C," Petition), petitioner here specifically
1990 denying its motion for denied the averments of the petition
reconsideration of the said earlier Order. below; theorizing that such petition is
premature since respondent Yao has not
yet formally required arbitrators
From the petition below of respondent
Alamarez and Sabile to agree on the
Yao, it appears that he is the present
third arbitrator, within ten (10) days from
owner of a commercial building a
notice, and that the delay in the
portion of which is leased to petitioner
arbitration was due to respondent Yao's
under a contract of lease executed on
failure to perform what is incumbent
December 23, 1993 with the former
upon him, of notifying and thereafter,
owner thereof, La Proveedora, Inc.,
requiring both arbitrators to appoint the
which contract expired on April 30, 1989.
third member of the Board of Arbitrators.
However, petitioner exercised its option
According to petitioner, it actually gave
to lease the same building for another
arbitrators Sabile and Alamarez a free
five years. But petitioner and respondent
hand in choosing the third arbitrator;
Yao disagreed on the rental rate, and to
and, therefore, respondent Yao has no
resolve the controversy, the latter, thru
cause of action against it (petitioner). By
way of Counterclaim, petitioner alleged proceed or not to arbitration, it, however, considered
that it suffered actual damages of petitioner in estoppel from questioning the competence
P100,000.00; and incurred attorney's fees of the court to additionally hear and decide in the
of P50,000.00, plus P500.00 for every court summary proceedings private respondent's claim for
appearance of its counsel. damages, it (petitioner) having itself filed similarly its own
counterclaim with the court a quo.
On October 20, 1989, respondent Yao
filed an amended petition for It is hardly disputable that when a court is called upon to
"Enforcement of Arbitration Agreement exercise limited and special jurisdiction, that court cannot
with Damages;" praying that petitioner stray to matters outside the area of its declared authority
be ordered to pay interest on the unpaid or beyond what has been expressly invested by law
rents, at the prevailing rate of interest in (Elumbaring vs. Elumbaring, 12 Phil. 384, 387), particularly,
commercial banks, and exemplary such as in this instance, where the proceedings are
damages of at least P250,000.00. summary in nature.
On October 24, 1989, despite petitioner's Prefatorily, recalling the distinctions, pertinent to the case,
opposition to the motion to admit the between the court's lack of jurisdiction over the person of
amended petition, the respondent court the defendant, on the one hand, and its lack of
admitted the same. jurisdiction over the subject matter or the nature of the
action, upon the other hand, should be useful.
On October 31, 1989, petitioner
answered the amended petition; The lack of jurisdiction over the person of the defendant
contending, among others, that the may be waived either expressly or impliedly. When a
amended petition should be dismissed defendant voluntarily appears, he is deemed to have
on the ground of non-payment of the submitted himself to the jurisdiction of the court. If he so
requisite filing fees therefor; and it being wishes not to waive this defense, he must do so
in the nature of an ordinary civil action, a seasonably by motion for the purpose of objecting to the
full blown and regular trial, is necessary; jurisdiction of the court; otherwise, he shall be deemed to
so that respondent Yao's proposition for have submitted himself to that jurisdiction. The decisions
a summary hearing of the arbitration promulgated heretofore by this Court would likewise
issue and separate trial for his claim for seemingly apply estoppel to bar the defendant from
damages is procedurally untenable and pursuing that defense by alleging in his answer any other
implausible. issue for dismissing the action.
Invoking Section 5, Rule 16 of the Rules of A citation of a few of our decisions might be apropos.
Court, petitioner presented a "Motion to
Set Case for Preliminary Hearing" of its In Wang Laboratories, Inc., vs. Mendoza (156 SCRA 44),
special and affirmative defenses, which this Court has ruled that if the defendant, besides setting
are grounds fro a motion to dismiss. up in a motion to dismiss his objection to the jurisdiction of
the court, alleges at the same time any other ground for
In its Order of November 14, 1989, the dismissing the action, he is deemed to have submitted
respondent court announced that the himself to the jurisdiction of the court. In the process, it
two arbitrators chose Mrs. Eloisa R. has equated the matter to a situation where, such as
Narciso as the third arbitrator. And on in Immaculata vs. Judge Navarro, et al. (146 SCRA 5), the
November 21, 1989, it ordered the defendant invokes an affirmative relief against his
parties to submit their position papers on opponent.
the issue as to whether or not respondent
Yao's claim for damages may be In De Midgely vs. Judge Ferandos (64 SCRA 23, 31), the
litigated upon in the summary Court elaborated thusly:
proceeding for enforcement of
arbitration agreement. It likewise
We are of the opinion that the lower
informed the parties that petitioner's
court has acquired jurisdiction over the
Motion to Set Case for Preliminary
person of Mrs. Midgely by reason of her
Hearing" of Special and Affirmative
voluntary appearance. The reservation in
Defenses would be resolved together
her motion to dismiss that she was
with the question of damages.
making a special appearance to
contest the court's jurisdiction over her
On April 26, 1990, the aforequoted person may be disregarded.
assailed Order issued. In moving for
reconsideration of the said Order,
It may be disregarded because it was
petitioner argued that in Special Case
nullified by the fact that in her motion to
No. 6024, the respondent court sits as a
dismiss she relied not only on the ground
special court exercising limited
of lack of jurisdiction over her person but
jurisdiction and is not competent to act
also on the ground that there was no
on respondent Yao's claim for damages,
showing that earnest efforts were
which poses an issue litigable in an
exerted to compromise the case and
ordinary civil action. But the respondent
because she prayed "for such other relief
court was not persuaded by petitioner's
as" may be deemed "appropriate and
submission. On June 22, 1990, it denied
proper."
the motion for reconsideration. (Rollo,
pp. 89-93).
xxxxxxxxx
While the appellate court has agreed with petitioner that,
under Section 6 of Republic Act No. 876, a court, acting When the appearance is by motion for
within the limits of its special jurisdiction, may in this case the purpose of objecting to the
solely determine the issue of whether the litigants should jurisdiction of the court over the person, it
must be for the sole and separate a defendant to set up the court's lack of jurisdiction over
purpose of objecting to the jurisdiction of the person of the defendant.
the court. If his motion is for any other
purpose than to object to the jurisdiction Not inevitably.
of the court over his person, he thereby
submits himself to the jurisdiction of the
Section 1, Rule 16, of the Rules of Court, provides that a
court. A special appearance by motion
motion to dismiss may be made on the following grounds:
made for the purpose of objecting to the
jurisdiction of the court over the person
will be held to be a general (a) That the court has no jurisdiction over
appearance, if the party in said motion the person of the defendant or over the
should, for example, ask for a dismissal of subject of the action or suit;
the action upon the further ground that
the court had no jurisdiction over the (b) That the court has no jurisdiction over
subject matter. (Syllabus, Flores vs. the nature of the action or suit;
Zurbito, supra, at page 751. That rule was
followed in Ocampo vs. Mina and (c) The venue is improperly laid;
Arejola, 41 Phil. 308).
(d) That the plaintiff has no legal
The justification for the rule was expressed in Republic vs. capacity to sue;
Ker and Companry, Ltd. (18 SCRA 207, 213-214), in this
wise:
(e) That there is another action pending
between the same parties for the same
We observed that the motion to dismiss cause;
filed on April 14, 1962, aside from
disputing the lower court's jurisdiction
over defendant's person, prayed for (f) That the cause of action is barred by
dismissal of the complaint on the ground a prior judgment or by statute of
that plaintiff's cause of action had limitations;
prescribed. By interposing such second
ground in its motion to dismiss, Ker & Co., (g) That the complaint states no cause of
Ltd. availed of an affirmative defense on action;
the basis of which it prayed the court to
resolve controversy in its favor. For the (h) That the claim or demand set forth in
court to validly decide the said plea of the plaintiff's pleading has been paid,
defendant Ker & Co., Ltd., it necessarily waived, abandoned, or otherwise
had to acquire jurisdiction upon the extinguished;
latter's person, who, being the
proponent of the affirmative defense,
( i ) That the claim on which the action or
should be deemed to have abandoned
suit is founded is unenforceable under
its special appearance and voluntarily
the provisions of the statute of frauds;
submitted itself to the jurisdiction of the
court.
( j ) That the suit is between members of
the same family and no earnest efforts
Voluntary appearance cures defects of
towards a compromise have been
summons, if any, Such defect, if any, was
made.
further cured when defendant filed its
answer to the complaint. A defendant
can not be permitted to speculate upon Any ground for dismissal in a motion to dismiss, except
the judgment of the court by objecting improper venue, may, as further set forth in Section 5 of
to the court's jurisdiction over its person if the same rule, be pleaded as an affirmative defense and
the judgment is adverse to it, and a preliminary hearing may be had thereon as if a motion
acceding to jurisdiction over its person if to dismiss had been filed. An answer itself contains the
and when the judgment sustains its negative, as well as affirmative, defenses upon which the
defenses. defendant may rely (Section 4, Rule 6, Rules of Court). A
negative defense denies the material facts averred in the
complaint essential to establish the plaintiff's cause of
The doctrine of estoppel is predicated on, and has its
action, while an affirmative defense in an allegation of a
origin in, equity which, broadly defined, is justice
new matter which, while admitting the material
according to natural law and right. It is a principle
allegations of the complaint, would, nevertheless,
intended to avoid a clear case of injustice. The term is
prevent or bar recovery by the plaintiff. Inclusive of these
hardly distinguishable from a waiver of right. Estoppel, like
defenses are those mentioned in Rule 16 of the Rules of
its said counterpart, must be unequivocal and intentional
Court which would permit the filing of a motion to dismiss.
for, when misapplied, it can easily become a most
convenient and effective means of injustice. Estoppel is
not understood to be a principle that, as a rule, should In the same manner that the plaintiff may assert two or
prevalently apply but, such as it concededly is, as a mere more causes of action in a court suit, a defendant is
exception from the standard legal norms of general likewise expressly allowed, under Section 2, Rule 8, of the
application that can be invoked only in highly Rules of Court, to put up his own defenses alternatively or
exceptional and justifiable cases. even hypothetically. Indeed, under Section 2, Rule 9, of
the Rules of Court, defenses and objections not pleaded
either in a motion to dismiss or in an answer, except for
Tested by the above criteria, the Court sees it propitious
the failure to state a cause of action, are deemed
to re-examine specifically the question of whether or not
waived. We take this to mean that a defendant may, in
the submission of other issues in a motion to dismiss, or of
fact, feel enjoined to set up, along with his objection to
an affirmative defense (as distinguished from an
the court's jurisdiction over his person, all other possible
affirmative relief) in an answer, would necessarily
defenses. It thus appears that it is not the invocation of
foreclose, and have the effect of a waiver of, the right of
any of such defenses, but the failure to so raise them, that
can result in waiver or estoppel. By defenses, of course, an inconsistent position — that the lower
we refer to the grounds provided for in Rule 16 of the court had jurisdiction. Here, the principle
Rules of Court that must be asserted in a motion to dismiss of estoppel applies. The rule that
or by way of affirmative defenses in an answer. jurisdiction is conferred by law, and does
not depend upon the will of the parties,
Mindful of the foregoing, in Signetics Corporation vs. has not bearing thereon.
Court of Appeals and Freuhauf Electronics Phils., Inc. (225
SCRA 737, 738), we lately ruled: The rule was reiterated in Calimlim vs. Ramirez (118 SCRA
399, 406), and quite recently, in Southeast Asian Fisheries
This is not to say, however, that the Development Center-Aquaculture Department vs.
petitioner's right to question the National Labor Relations Commission (206 SCRA 283).
jurisdiction of the court over its person is
now to be deemed a foreclosed matter. Jurisdiction over the nature of the action, in concept,
If it is true, as Signetics claims, that its only differs from jurisdiction over the subject matter. Illustrated,
involvement in the Philippines was lack of jurisdiction over the nature of the action is the
through a passive investment in Sigfil, situation that arises when a court, which ordinarily would
which it even later disposed of, and that have the authority and competence to take a case, is
TEAM Pacific is not its agent, then it rendered without it either because a special law has
cannot really be said to be doing limited the exercise of its normal jurisdiction on a
business in the Philippines. It is a defense, particular matter or because the type of action has been
however, that requires the contravention reposed by law in certain other courts or quasi-judicial
of the allegations of the complaint, as agencies for determination. Nevertheless, it can hardly
well as full ventilation, in effect, of the be questioned that the rules relating to the effects of
main merits of the case, which should want of jurisdiction over the subject matter should apply
not thus be within the province of a mere with equal vigor to cases where the court is similarly
motion to dismiss. So, also, the issue bereft of jurisdiction over the nature of the action.
posed by the petitioner as to whether a
foreign corporation which has done In summary, it is our considered view, as we now so
business in the country, but which has hereby express,
ceased to do business at the time of the that —
filing of a complaint, can still be made to
answer for a cause of action which
(1) Jurisdiction over the person must be seasonably
accrued while it was doing business, is
raised, i.e., that it is pleaded in a motion to dismiss or by
another matter that would yet have to
way of an affirmative defense in an answer. Voluntary
await the reception and admission of
appearance shall be deemed a waiver of this defense.
evidence. Since these points have
The assertion, however, of affirmative defenses shall not
seasonably been raised by the
be constructed as an estoppel or as a waiver of such
petitioner, there should be no real cause
defense.
for what may understandably be its
apprehension, i.e., that by its
participation during the trial on the (2) Where the court itself clearly has no jurisdiction over
merits, it may, absent an invocation of the subject matter or the nature of the action, the
separate or independent reliefs of its invocation of this defense may be done at any time. It is
own, be considered to have voluntarily neither for the courts nor the parties to violate or
submitted itself to the court's jurisdiction. disregard that rule, let alone to confer that jurisdiction,
this matter being legislative in character. Barring highly
meritorious and exceptional circumstances, such as
Lack of jurisdiction over the subject matter of the suit is
hereinbefore exemplified, neither estoppel nor waiver
yet another matter. Whenever it appears that the court
shall apply.
has no jurisdiction over the subject matter, the action
shall be dismissed (Section 2, Rule 9, Rules of Court). This
defense may be interposed at any time, during appeal In the case at bench, the want of jurisdiction by the court
(Roxas vs. Rafferty, 37 Phil. 957) or even after final is indisputable, given the nature of the controversy. The
judgment (Cruzcosa vs. Judge Concepcion, et al., 101 arbitration law explicitly confines the court's authority only
Phil. 146). Such is understandable, as this kind of to pass upon the issue of whether there is or there is no
jurisdiction is conferred by law and not within the courts, agreement in writing providing for arbitration. In the
let alone the parties, to themselves determine or affirmative, the statute ordains that the court shall issue
conveniently set aside. In People vs. Casiano (111 Phil. 73 an order "summarily directing the parties to proceed with
93-94), this Court, on the issue of estoppel, held: the arbitration in accordance with the terms thereof." If
the court, upon the other hand, finds that no such
agreement exists, "the proceeding shall be dismissed."
The operation of the principle of
The proceedings are summary in nature.
estoppel on the question of jurisdiction
seemingly depends upon whether the
lower court actually had jurisdiction or All considered, the court a quo must then refrain from
not. If it had no jurisdiction, but the case taking up the claims of the contending parties for
was tried and decided upon the theory damages, which, upon the other hand, may be
that it had jurisdiction, the parties are not ventilated in separate regular proceedings at an
barred, on appeal, from assailing such opportune time and venue. The circumstances obtaining
jurisdiction, for the same "must exist as a in this case are far, we hold, from justifying the
matter of law, and may not be application of estoppel against either party.
conferred by consent of the parties or by
estoppel" (5 C.J.S., 861-863). However, if WHEREFORE, the decision of the Court of Appeals and
the lower court had jurisdiction, and the the orders of the trial court in question are SET ASIDE. The
case was heard and decided upon a court a quo, in the instant proceedings, is ordered to
given theory, such, for instance, as that DESIST from further hearing private respondent's claim, as
the court had no jurisdiction, the party well as petitioner's counterclaim, for damages. No costs.
who induced it to adopt such theory will
not be permitted, on appeal, to assume
SO ORDERED. USA and Paul E. Derby, Jr., apparently upset with the
publication, instructed private respondent MMI to stop
DEL MONTE CORPORATION-USA, PAUL E. DERBY, JR., coordinating with Antonio Ongpin and to communicate
DANIEL COLLINS and LUIS HIDALGO, petitioners, directly instead with petitioner DMC-USA through Paul E.
vs. COURT OF APPEALS, JUDGE BIENVENIDO L. Derby, Jr.
REYES in his capacity as Presiding Judge, RTC-Br. Private respondents further averred that petitioners
74, Malabon, Metro Manila, MONTEBUENO knowingly and surreptitiously continued to deal with the
MARKETING, INC., LIONG LIONG C. SY and former in bad faith by involving disinterested third parties
SABROSA FOODS, INC., respondents. and by proposing solutions which were entirely out of
their control. Private respondents claimed that they had
DECISION exhausted all possible avenues for an amicable resolution
and settlement of their grievances; that as a result of the
BELLOSILLO, J.:
fraud, bad faith, malice and wanton attitude of
petitioners, they should be held responsible for all the
This Petition for Review on certiorari assails the 17 July actual expenses incurred by private respondents in the
1998 Decision[1] of the Court of Appeals affirming the 11 delayed shipment of orders which resulted in the extra
November 1997 Order[2] of the Regional Trial Court which handling thereof, the actual expenses and cost of money
denied petitioners Motion to Suspend Proceedings in Civil for the unused Letters of Credit (LCs) and the substantial
Case No. 2637-MN. It also questions the appellate opportunity losses due to created out-of-stock situations
courts Resolution[3] of 30 October 1998 which denied and unauthorized shipments of Del Monte-USA products
petitioners Motion for Reconsideration. to the Philippine Duty Free Area and Economic Zone; that
the bad faith, fraudulent acts and willful negligence of
On 1 July 1994, in a Distributorship Agreement,
petitioners, motivated by their determination to squeeze
petitioner Del Monte Corporation-USA (DMC-USA)
private respondents out of the outstanding and ongoing
appointed private respondent Montebueno Marketing,
Distributorship Agreement in favor of another party, had
Inc. (MMI) as the sole and exclusive distributor of its Del
placed private respondent LILY SY on tenterhooks since
Monte products in the Philippines for a period of five (5)
then; and, that the shrewd and subtle manner with which
years, renewable for two (2) consecutive five (5) year
petitioners concocted imaginary violations by private
periods with the consent of the parties. The Agreement
respondent MMI of the Distributorship Agreement in order
provided, among others, for an arbitration clause which
to justify the untimely termination thereof was a
states -
subterfuge. For the foregoing, private respondents
claimed, among other reliefs, the payment of actual
12. GOVERNING LAW AND ARBITRATION[4] damages, exemplary damages, attorneys fees and
litigation expenses.
This Agreement shall be governed by the laws of the
On 21 October 1996 petitioners filed a Motion to
State of California and/or, if applicable, the United States
Suspend Proceedings[13] invoking the arbitration clause in
of America. All disputes arising out of or relating to this
their Agreement with private respondents.
Agreement or the parties relationship, including the
termination thereof, shall be resolved by arbitration in the In a Resolution[14] dated 23 December 1996 the trial
City of San Francisco, State of California, under the Rules court deferred consideration of petitioners Motion to
of the American Arbitration Association. The arbitration Suspend Proceedings as the grounds alleged therein did
panel shall consist of three members, one of whom shall not constitute the suspension of the proceedings
be selected by DMC-USA, one of whom shall be selected considering that the action was for damages with prayer
by MMI, and third of whom shall be selected by the other for the issuance of Writ of Preliminary Attachment and not
two members and shall have relevant experience in the on the Distributorship Agreement.
industry x xxx
On 15 January 1997 petitioners filed a Motion for
In October 1994 the appointment of private Reconsideration to which private respondents filed
respondent MMI as the sole and exclusive distributor of their Comment/Opposition. On 31 January 1997
Del Monte products in the Philippines was published in petitioners filed their Reply.Subsequently, private
several newspapers in the country. Immediately after its respondents filed an Urgent Motion for Leave to Admit
appointment, private respondent MMI appointed Supplemental Pleading dated 2 April 1997. This Motion
Sabrosa Foods, Inc. (SFI), with the approval of petitioner was admitted, over petitioners opposition, in an Order of
DMC-USA, as MMIs marketing arm to concentrate on its the trial court dated 27 June 1997.
marketing and selling function as well as to manage its As a result of the admission of the Supplemental
critical relationship with the trade. Complaint, petitioners filed on 22 July 1997
On 3 October 1996 private respondents MMI, SFI and a Manifestation adopting their Motion to Suspend
MMIs Managing Director LiongLiong C. Sy (LILY SY) filed a Proceedings of 17 October 1996 and Motion for
Complaint[5] against petitioners DMC-USA, Paul E. Derby, Reconsideration of 14 January 1997.
Jr.,[6] Daniel Collins[7] and Luis Hidalgo,[8] and Dewey On 11 November 1997 the Motion to Suspend
Ltd.[9] before the Regional Trial Court of Malabon, Metro Proceedings was denied by the trial court on the ground
Manila. Private respondents predicated their complaint that it "will not serve the ends of justice and to allow said
on the alleged violations by petitioners of Arts. suspension will only delay the determination of the issues,
20,[10] 21[11] and 23[12] of the Civil Code. According to frustrate the quest of the parties for a judicious
private respondents, DMC-USA products continued to be determination of their respective claims, and/or deprive
brought into the country by parallel importers despite the and delay their rights to seek redress."[15]
appointment of private respondent MMI as the sole and
exclusive distributor of Del Monte products thereby On appeal, the Court of Appeals affirmed the
causing them great embarrassment and substantial decision of the trial court. It held that the alleged
damage. They alleged that the products brought into the damaging acts recited in the Complaint, constituting
country by these importers were aged, damaged, fake or petitioners causes of action, required the interpretation of
counterfeit, so that in March 1995 they had to cause, Art. 21 of the Civil Code[16] and that in determining
after prior consultation with Antonio Ongpin, Market whether petitioners had violated it "would require a full
Director for Special Markets of Del Monte Philippines, Inc., blown trial" making arbitration "out of the
the publication of a "warning to the trade" paid question."[17] Petitioners Motion for Reconsideration of the
advertisement in leading newspapers. Petitioners DMC- affirmation was denied. Hence, this Petition for Review.
The crux of the controversy boils down to whether between parties of different nationalities within a
the dispute between the parties warrants an order contracting state.[23]
compelling them to submit to arbitration.
A careful examination of the instant case shows that
Petitioners contend that the subject matter of the arbitration clause in the Distributorship Agreement
private respondents causes of action arises out of or between petitioner DMC-USA and private respondent
relates to the Agreement between petitioners and MMI is valid and the dispute between the parties is
private respondents. Thus, considering that the arbitration arbitrable. However, this Court must deny the petition.
clause of the Agreement provides that all disputes arising
out of or relating to the Agreement or the parties The Agreement between petitioner DMC-USA and
relationship, including the termination thereof, shall be private respondent MMI is a contract. The provision to
resolved by arbitration, they insist on the suspension of the submit to arbitration any dispute arising therefrom and
proceedings in Civil Case No. 2637-MN as mandated by the relationship of the parties is part of that contract and
Sec. 7 of RA 876[18] - is itself a contract. As a rule, contracts are respected as
the law between the contracting parties and produce
effect as between them, their assigns and
Sec. 7. Stay of Civil Action. If any suit or proceeding be heirs.[24] Clearly, only parties to the Agreement, i.e.,
brought upon an issue arising out of an agreement petitioners DMC-USA and its Managing Director for Export
providing for arbitration thereof, the court in which such Sales Paul E. Derby, Jr., and private respondents MMI and
suit or proceeding is pending, upon being satisfied that its Managing Director LILY SY are bound by the
the issue involved in such suit or proceeding is referable Agreement and its arbitration clause as they are the only
to arbitration, shall stay the action or proceeding until an signatories thereto. Petitioners Daniel Collins and Luis
arbitration has been had in accordance with the terms of Hidalgo, and private respondent SFI, not parties to the
the agreement. Provided, That the applicant for the stay Agreement and cannot even be considered assigns or
is not in default in proceeding with such arbitration. heirs of the parties, are not bound by the Agreement and
the arbitration clause therein. Consequently, referral to
Private respondents claim, on the other hand, that arbitration in the State of California pursuant to the
their causes of action are rooted in Arts. 20, 21 and 23 of arbitration clause and the suspension of the proceedings
the Civil Code,[19] the determination of which demands a in Civil Case No. 2637-MN pending the return of the
full blown trial, as correctly held by the Court of arbitral award could be called for[25] but only as to
Appeals. Moreover, they claim that the issues before the petitioners DMC-USA and Paul E. Derby, Jr., and private
trial court were not joined so that the Honorable Judge respondents MMI and LILY SY, and not as to the other
was not given the opportunity to satisfy himself that the parties in this case, in accordance with the recent case
issue involved in the case was referable to of Heirs of Augusto L. Salas, Jr. v. Laperal Realty
arbitration. They submit that, apparently, petitioners filed Corporation,[26] which superseded that of Toyota Motor
a motion to suspend proceedings instead of sending a Philippines Corp. v. Court of Appeals.[27]
written demand to private respondents to arbitrate
because petitioners were not sure whether the case In Toyota, the Court ruled that "[t]he contention that
could be a subject of arbitration. They maintain that had the arbitration clause has become dysfunctional
petitioners done so and private respondents failed to because of the presence of third parties is untenable
answer the demand, petitioners could have filed with the ratiocinating that "[c]ontracts are respected as the law
trial court their demand for arbitration that would warrant between the contracting parties"[28] and that "[a]s such,
a determination by the judge whether to refer the case the parties are thereby expected to abide with good
to arbitration.Accordingly, private respondents assert that faith in their contractual commitments."[29] However,
arbitration is out of the question. in Salas, Jr., only parties to the Agreement, their assigns or
heirs have the right to arbitrate or could be compelled to
Private respondents further contend that the arbitrate. The Court went further by declaring that in
arbitration clause centers more on venue rather than on recognizing the right of the contracting parties to
arbitration. They finally allege that petitioners filed their arbitrate or to compel arbitration, the splitting of the
motion for extension of time to file this petition on the proceedings to arbitration as to some of the parties on
same date[20] petitioner DMC-USA filed a petition to one hand and trial for the others on the other hand, orthe
compel private respondent MMI to arbitrate before the suspension of trial pending arbitration between some of
United States District Court in Northern California, the parties, should not be allowed as it would, in effect,
docketed as Case No. C-98-4446. They insist that the filing result in multiplicity of suits, duplicitous procedure and
of the petition to compel arbitration in the United States unnecessary delay.[30]
made the petition filed before this Court an alternative
remedy and, in a way, an abandonment of the cause The object of arbitration is to allow the expeditious
they are fighting for here in the Philippines, thus determination of a dispute.[31] Clearly, the issue before us
warranting the dismissal of the present petition before this could not be speedily and efficiently resolved in its
Court. entirety if we allow simultaneous arbitration proceedings
and trial, or suspension of trial pending
There is no doubt that arbitration is valid and arbitration. Accordingly, the interest of justice would only
constitutional in our jurisdiction.[21] Even before the be served if the trial court hears and adjudicates the
enactment of RA 876, this Court has countenanced the case in a single and complete proceeding.[32]
settlement of disputes through arbitration. Unless the
agreement is such as absolutely to close the doors of the WHEREFORE, the petition is DENIED. The Decision of
courts against the parties, which agreement would be the Court of Appeals affirming the Order of the Regional
void, the courts will look with favor upon such amicable Trial Court of Malabon, Metro Manila, in Civil Case No.
arrangement and will only interfere with great reluctance 2637-MN, which denied petitioners Motion to Suspend
to anticipate or nullify the action of the Proceedings, is AFFIRMED. The Regional Trial Court
arbitrator.[22] Moreover, as RA 876 expressly authorizes concerned is directed to proceed with the hearing of
arbitration of domestic disputes, foreign arbitration as a Civil Case No. 2637-MN with dispatch. No costs.
system of settling commercial disputes was likewise
recognized when the Philippines adhered to the United G.R. No. 174938 October 1, 2014
Nations "Convention on the Recognition and the
Enforcement of Foreign Arbitral Awards of 1958" under GERARDO LANUZA, JR. AND ANTONIO O.
the 10 May 1965 Resolution No. 71 of the Philippine OLBES, Petitioners,
Senate, giving reciprocal recognition and allowing vs.
enforcement of international arbitration agreements BF CORPORATION, SHANGRI-LA PROPERTIES, INC.,
ALFREDO C. RAMOS, RUFO B. COLAYCO, MAXIMO G. thing of whatsoever nature arising there under or
LICAUCO III, AND BENJAMIN C. RAMOS, Respondents. inconnection therewith (including any matter or thing left
by this Contract to the discretion of the Project Manager
DECISION or the withholding by the Project Manager of any
certificate to which the Contractor may claim to be
entitled or the measurement and valuation mentioned in
LEONEN, J.:
clause 30(5)(a) of these Conditions or the rights and
liabilities of the parties under clauses 25, 26, 32 or 33 of
Corporate representatives may be compelled to submit these Conditions), the owner and the Contractor hereby
to arbitration proceedings pursuant to a contract agree to exert all efforts to settle their differences or
entered into by the corporation they represent if there dispute amicably. Failing these efforts then such dispute
are allegations of bad faith or malice in their acts or difference shall be referred to arbitration in
representing the corporation. accordance with the rules and procedures of the
Philippine Arbitration Law.
This is a Rule 45 petition, assailing the Court of Appeals'
May 11, 2006 decision and October 5, 2006 resolution. x xx x xx x xx
The Court of Appeals affirmed the trial court's decision
holding that petitioners, as director, should submit
(6) The award of such Arbitrators shall be final and
themselves as partiestothe arbitration proceedings
binding on the parties. The decision of the Arbitrators shall
between BF Corporation and Shangri-La Properties, Inc.
be a condition precedent to any right of legal action
(Shangri-La).
that either party may have against the other. . .
.12 (Underscoring in the original)
In 1993, BF Corporation filed a collection complaint with
the Regional Trial Court against Shangri-Laand the
On August 19, 1993, BF Corporation opposed the motion
members of its board of directors: Alfredo C. Ramos,
to suspend proceedings.13
RufoB.Colayco, Antonio O. Olbes, Gerardo Lanuza, Jr.,
Maximo G. Licauco III, and Benjamin C. Ramos.1
In the November 18, 1993 order, the Regional Trial Court
denied the motion to suspend proceedings.14
BF Corporation alleged in its complaint that on
December 11, 1989 and May 30, 1991, it entered into
agreements with Shangri-La wherein it undertook to On December 8, 1993, petitioners filed an answer to BF
construct for Shangri-La a mall and a multilevel parking Corporation’s complaint, with compulsory counter claim
structure along EDSA.2 against BF Corporation and crossclaim against Shangri-
La.15 They alleged that they had resigned as members of
Shangri-La’s board of directors as of July 15, 1991.16
Shangri-La had been consistent in paying BF Corporation
in accordance with its progress billing
statements.3However, by October 1991, Shangri-La After the Regional Trial Court denied on February 11, 1994
started defaulting in payment.4 the motion for reconsideration of its November 18, 1993
order, Shangri-La, Alfredo C. Ramos, Rufo B.
Colayco,Maximo G. Licauco III, and Benjamin Ramos
BF Corporation alleged that Shangri-La induced BF
filed a petition for certiorari with the Court of Appeals.17
Corporation to continue with the construction of the
buildings using its own funds and credit despite Shangri-
La’s default.5 According to BF Corporation, ShangriLa On April 28, 1995, the Court of Appeals granted the
misrepresented that it had funds to pay for its obligations petition for certiorari and ordered the submission of the
with BF Corporation, and the delay in payment was dispute to arbitration.18
simply a matter of delayed processing of BF
Corporation’s progress billing statements.6 Aggrieved by the Court of Appeals’ decision, BF
Corporation filed a petition for review on certiorari with
BF Corporation eventually completed the construction of this court.19On March 27, 1998, this court affirmed the
the buildings.7 Shangri-La allegedly took possession of the Court of Appeals’ decision, directing that the dispute be
buildings while still owing BF Corporation an outstanding submitted for arbitration.20
balance.8
Another issue arose after BF Corporation had initiated
BF Corporation alleged that despite repeated demands, arbitration proceedings. BF Corporation and Shangri-La
Shangri-La refused to pay the balance owed to it.9 It also failed to agree as to the law that should govern the
alleged that the Shangri-La’s directors were in bad faith arbitration proceedings.21 On October 27, 1998, the trial
in directing Shangri-La’s affairs. Therefore, they should be court issued the order directing the parties to conduct
held jointly and severally liable with Shangri-La for its the proceedings in accordance with Republic Act No.
obligations as well as for the damages that BF 876.22
Corporation incurred as a result of Shangri-La’s default.10
Shangri-La filed an omnibus motion and BF Corporation
On August 3, 1993, Shangri-La, Alfredo C. Ramos, Rufo B. an urgent motion for clarification, both seeking to clarify
Colayco, Maximo G. Licauco III, and Benjamin C. Ramos the term, "parties," and whether Shangri-La’s directors
filed a motion to suspend the proceedings in view of BF should be included in the arbitration proceedings and
Corporation’s failure to submit its dispute to arbitration, in served with separate demands for arbitration.23
accordance with the arbitration clauseprovided in its
contract, quoted in the motion as follows:11 Petitioners filed their comment on Shangri-La’s and BF
Corporation’s motions, praying that they be excluded
35. Arbitration from the arbitration proceedings for being non-parties to
Shangri-La’s and BF Corporation’s agreement.24
(1) Provided always that in case any dispute or difference
shall arise between the Owner or the Project Manager on On July 28, 2003, the trial court issued the order directing
his behalf and the Contractor, either during the progress service of demands for arbitration upon all defendants in
or after the completion or abandonment of the Works as BF Corporation’s complaint.25 According to the trial court,
to the construction of this Contract or as to any matter or Shangri-La’s directors were interested parties who "must
also be served with a demand for arbitration to give
them the opportunity to ventilate their side of the Petitioners point out thatour arbitration laws were
controversy, safeguard their interest and fend off their enacted to promote the autonomy of parties in resolving
respective positions."26 Petitioners’ motion for their disputes.43 Compelling them to submit to arbitration
reconsideration ofthis order was denied by the trial court is against this purpose and may be tantamount to
on January 19, 2005.27 stipulating for the parties.44
Petitioners filed a petition for certiorari with the Court of Separate comments on the petition werefiled by BF
Appeals, alleging grave abuse of discretion in the Corporation, and Maximo G. Licauco III, Alfredo C.Ramos
issuance of orders compelling them to submit to and Benjamin C. Ramos.45
arbitration proceedings despite being third parties to the
contract between Shangri-La and BF Corporation.28 Maximo G. Licauco III Alfredo C. Ramos, and Benjamin C.
Ramos agreed with petitioners that Shangri-La’sdirectors,
In its May 11, 2006 decision,29 the Court of Appeals being non-parties to the contract, should not be made
dismissed petitioners’ petition for certiorari. The Court of personally liable for Shangri-La’s acts.46 Since the
Appeals ruled that ShangriLa’s directors were necessary contract was executed only by BF Corporation and
parties in the arbitration proceedings.30 According to the Shangri-La, only they should be affected by the
Court of Appeals: contract’s stipulation.47 BF Corporation also failed to
specifically allege the unlawful acts of the directors that
[They were] deemed not third-parties tothe contract as should make them solidarily liable with Shangri-La for its
they [were] sued for their acts in representation of the obligations.48
party to the contract pursuant to Art. 31 of the
Corporation Code, and that as directors of the Meanwhile, in its comment, BF Corporation argued that
defendant corporation, [they], in accordance with Art. the courts’ ruling that the parties should undergo
1217 of the Civil Code, stand to be benefited or injured arbitration "clearly contemplated the inclusion of the
by the result of the arbitration proceedings, hence, being directors of the corporation[.]"49 BF Corporation also
necessary parties, they must be joined in order to have argued that while petitioners were not parties to the
complete adjudication of the controversy. Consequently, agreement, they were still impleaded under Section 31 of
if [they were] excluded as parties in the arbitration the Corporation Code.50Section 31 makes
proceedings and an arbitral award is rendered, holding directorssolidarily liable for fraud, gross negligence, and
[Shangri-La] and its board of directors jointly and solidarily bad faith.51 Petitioners are not really third parties to the
liable to private respondent BF Corporation, a problem agreement because they are being sued as Shangri-La’s
will arise, i.e., whether petitioners will be bound bysuch representatives, under Section 31 of the Corporation
arbitral award, and this will prevent complete Code.52
determination of the issues and resolution of the
controversy.31 BF Corporation further argued that because petitioners
were impleaded for their solidary liability, they are
The Court of Appeals further ruled that "excluding necessary parties to the arbitration proceedings.53 The full
petitioners in the arbitration proceedings . . . would be resolution of all disputes in the arbitration proceedings
contrary to the policy against multiplicity of suits."32 should also be done in the interest of justice.54
The dispositive portion of the Court of Appeals’ decision In the manifestation dated September 6, 2007, petitioners
reads: informed the court that the Arbitral Tribunal had already
promulgated its decision on July 31, 2007.55 The Arbitral
WHEREFORE, the petition is DISMISSED. The assailed orders Tribunal denied BF Corporation’s claims against
dated July 28, 2003 and January 19, 2005 of public them.56Petitioners stated that "[they] were included by
respondent RTC, Branch 157, Pasig City, in Civil Case No. the Arbitral Tribunal in the proceedings conducted . . .
63400, are AFFIRMED.33 notwithstanding [their] continuing objection thereto. . .
."57 They also stated that "[their] unwilling participation in
the arbitration case was done ex abundanteadcautela,
The Court of Appeals denied petitioners’ motion for
as manifested therein on several occasions."58 Petitioners
reconsideration in the October 5, 2006 resolution.34
informed the court that they already manifested with the
trial court that "any action taken on [the Arbitral Tribunal’s
On November 24, 2006, petitioners filed a petition for decision] should be without prejudice to the resolution of
review of the May 11, 2006 Court of Appeals decision and [this] case."59
the October 5, 2006 Court of Appeals resolution.35
Upon the court’s order, petitioners and Shangri-La filed
The issue in this case is whether petitioners should be their respective memoranda. Petitioners and Maximo G.
made parties to the arbitration proceedings, pursuant to Licauco III, Alfredo C. Ramos, and Benjamin C. Ramos
the arbitration clause provided in the contract between reiterated their arguments that they should not be held
BF Corporation and Shangri-La. liable for Shangri-La’s default and made parties to the
arbitration proceedings because only BF Corporation
Petitioners argue that they cannot be held personally and Shangri-La were parties to the contract.
liable for corporate acts or obligations.36 The corporation
is a separate being, and nothing justifies BF Corporation’s In its memorandum, Shangri-La argued that petitioners
allegation that they are solidarily liable with Shangri- were impleaded for their solidary liability under Section 31
La.37Neither did they bind themselves personally nor did of the Corporation Code. Shangri-La added that their
they undertake to shoulder Shangri-La’s obligations exclusion from the arbitration proceedings will result in
should it fail in its obligations.38 BF Corporation also failed multiplicity of suits, which "is not favored in this
to establish fraud or bad faith on their part.39 jurisdiction."60 It pointed out that the case had already
been mooted by the termination of the arbitration
Petitioners also argue that they are third parties to the proceedings, which petitioners actively participated
contract between BF Corporation and Shangri- in.61 Moreover, BF Corporation assailed only the
La.40Provisions including arbitration stipulations should correctness of the Arbitral Tribunal’s award and not the
bind only the parties.41 Based on our arbitration laws, part absolving Shangri-La’s directors from liability.62
parties who are strangers to an agreement cannot be
compelled to arbitrate.42
BF Corporation filed a counter-manifestation with motion arbitration, as an inexpensive, speedy and amicable
to dismiss63 in lieu of the required memorandum. method of settling disputes, and as a means of avoiding
litigation, should receive every encouragement from the
In its counter-manifestation, BF Corporation pointed out courts which may be extended without contravening
that since "petitioners’ counterclaims were already sound public policy or settled law" (3 Am. Jur., p. 835).
dismissed with finality, and the claims against them were Congress has officially adopted the modern view when it
likewise dismissed with finality, they no longer have any reproduced in the new Civil Code the provisions of the
interest orpersonality in the arbitration case. Thus, there is old Code on Arbitration. And only recently it approved
no longer any need to resolve the present Petition, which Republic Act No. 876 expressly authorizing arbitration of
mainly questions the inclusion of petitioners in the future disputes.72 (Emphasis supplied)
arbitration proceedings."64 The court’s decision in this
case will no longer have any effect on the issue of In view of our policy to adopt arbitration as a manner of
petitioners’ inclusion in the arbitration proceedings.65 settling disputes, arbitration clauses are liberally
construed to favor arbitration. Thus, in LM Power
The petition must fail. Engineering Corporation v. Capitol Industrial Construction
Groups, Inc.,73 this court said:
The Arbitral Tribunal’s decision, absolving petitioners from
liability, and its binding effect on BF Corporation, have Being an inexpensive, speedy and amicable method of
rendered this case moot and academic. settling disputes, arbitration — along with mediation,
conciliation and negotiation — is encouraged by the
Supreme Court. Aside from unclogging judicial dockets,
The mootness of the case, however, had not precluded
arbitration also hastens the resolution of disputes,
us from resolving issues so that principles may be
especially of the commercial kind. It is thus regarded as
established for the guidance of the bench, bar, and the
the "wave of the future" in international civil and
public. In De la Camara v. Hon. Enage,66 this court
commercial disputes. Brushing aside a contractual
disregarded the fact that petitioner in that case already
agreement calling for arbitration between the parties
escaped from prison and ruled on the issue of excessive
would be a step backward.
bails:
Indeed, as petitioners point out, their personalities as Because a corporation’s existence is only by fiction of
directors of Shangri-La are separate and distinct from law, it can only exercise its rights and powers through
Shangri-La. itsdirectors, officers, or agents, who are all natural
persons. A corporation cannot sue or enter into contracts
A corporation is an artificial entity created by fiction of without them.
law.76 This means that while it is not a person, naturally,
the law gives it a distinct personality and treats it as such. A consequence of a corporation’s separate personality is
A corporation, in the legal sense, is an individual with a that consent by a corporation through its representatives
personality that is distinct and separate from other is not consent of the representative, personally. Its
persons including its stockholders, officers, directors, obligations, incurred through official acts of its
representatives,77 and other juridical entities. The law vests representatives, are its own. A stockholder, director, or
in corporations rights,powers, and attributes as if they representative does not become a party to a contract
were natural persons with physical existence and just because a corporation executed a contract through
capabilities to act on their own.78 For instance, they have that stockholder, director or representative.
the power to sue and enter into transactions or contracts.
Section 36 of the Corporation Code enumerates some of
Hence, a corporation’s representatives are generally not
a corporation’s powers, thus:
bound by the terms of the contract executed by the
corporation. They are not personally liable for obligations
Section 36. Corporate powers and capacity.– Every and liabilities incurred on or in behalf of the corporation.
corporation incorporated under this Code has the power
and capacity:
Petitioners are also correct that arbitration promotes the
parties’ autonomy in resolving their disputes. This court
1. To sue and be sued in its corporate name; recognized in Heirs of Augusto Salas, Jr. v. Laperal Realty
Corporation79 that an arbitration clause shall not apply to
2. Of succession by its corporate name for the persons who were neither parties to the contract nor
period of time stated in the articles of assignees of previous parties, thus:
incorporation and the certificate ofincorporation;
A submission to arbitration is a contract. As such, the
3. To adopt and use a corporate seal; Agreement, containing the stipulation on arbitration,
binds the parties thereto, as well as their assigns and heirs.
4. To amend its articles of incorporation in But only they.80 (Citations omitted)
accordance with the provisions of this Code;
Similarly, in Del Monte Corporation-USA v. Court of
5. To adopt by-laws, not contrary to law, morals, Appeals,81 this court ruled:
or public policy, and to amend or repeal the
same in accordance with this Code; The provision to submit to arbitration any dispute arising
therefrom and the relationship of the parties is part of that
6. In case of stock corporations, to issue or sell contract and is itself a contract. As a rule, contracts are
stocks to subscribers and to sell treasury stocks in respected as the law between the contracting parties
accordance with the provisions of this Code; and and produce effect as between them, their assigns and
to admit members to the corporation if it be a heirs. Clearly, only parties to the Agreement . . . are
non-stock corporation; bound by the Agreement and its arbitration clause as
they are the only signatories thereto.82 (Citation omitted)
7. To purchase, receive, take or grant, hold,
convey, sell, lease, pledge, mortgage and This court incorporated these rulings in Agan, Jr. v.
otherwise deal with such real and personal Philippine International Air Terminals Co., Inc.83 and
property, including securities and bonds of other Stanfilco Employees v. DOLE Philippines, Inc., et al.84
corporations, as the transaction of the lawful
business of the corporation may reasonably and As a general rule, therefore, a corporation’s
necessarily require, subject to the limitations representative who did not personally bind himself or
prescribed by law and the Constitution; herself to an arbitration agreement cannot be forced to
participate in arbitration proceedings made pursuant to
8. To enter into merger or consolidation with an agreement entered into by the corporation. He or she
other corporations as provided in this Code; is generally not considered a party to that agreement.
9. To make reasonable donations, including However, there are instances when the distinction
those for the public welfare or for hospital, between personalities of directors, officers,and
charitable, cultural, scientific, civic, or similar representatives, and of the corporation, are disregarded.
purposes: Provided, That no corporation, We call this piercing the veil of corporate fiction.
domestic or foreign, shall give donations in aid of
any political party or candidate or for purposes Piercing the corporate veil is warranted when "[the
of partisan political activity; separate personality of a corporation] is used as a means
to perpetrate fraud or an illegal act, or as a vehicle for
the evasion of an existing obligation, the circumvention
of statutes, or to confuse legitimate issues."85 It is also
warranted in alter ego cases "where a corporation is
merely a farce since it is a mere alter ego or business When there are allegations of bad faith or malice against
conduit of a person, or where the corporation is so corporate directors or representatives, it becomes the
organized and controlled and its affairs are so duty of courts or tribunals to determine if these persons
conducted as to make it merely an instrumentality, and the corporation should be treated as one. Without a
agency, conduit or adjunct of another corporation."86 trial, courts and tribunals have no basis for determining
whether the veil of corporate fiction should be pierced.
When corporate veil is pierced, the corporation and Courts or tribunals do not have such prior knowledge.
persons who are normally treated as distinct from the Thus, the courts or tribunals must first determine whether
corporation are treated as one person, such that when circumstances exist towarrant the courts or tribunals to
the corporation is adjudged liable, these persons, too, disregard the distinction between the corporation and
become liable as if they were the corporation. the persons representing it. The determination of these
circumstances must be made by one tribunal or court in
a proceeding participated in by all parties involved,
Among the persons who may be treatedas the
including current representatives of the corporation, and
corporation itself under certain circumstances are its
those persons whose personalities are impliedly the
directors and officers. Section 31 of the Corporation
sameas the corporation. This is because when the court
Code provides the instances when directors, trustees, or
or tribunal finds that circumstances exist warranting the
officers may become liable for corporate acts:
piercing of the corporate veil, the corporate
representatives are treated as the corporation itself and
Sec. 31. Liability of directors, trustees or officers. - Directors should be held liable for corporate acts. The
or trustees who willfully and knowingly vote for or assent corporation’s distinct personality is disregarded, and the
to patently unlawful acts of the corporation or who are corporation is seen as a mere aggregation of persons
guilty of gross negligence or bad faith in directing the undertaking a business under the collective name of the
affairs of the corporation or acquire any personal or corporation.
pecuniary interest in conflict with their duty as such
directors or trustees shall be liable jointly and severally for
Hence, when the directors, as in this case, are impleaded
all damages resulting therefrom suffered by the
in a case against a corporation, alleging malice orbad
corporation, its stockholders or members and other
faith on their part in directing the affairs of the
persons.
corporation, complainants are effectively alleging that
the directors and the corporation are not acting as
When a director, trustee or officer attempts to acquire or separate entities. They are alleging that the acts or
acquires, in violation of his duty, any interest adverse to omissions by the corporation that violated their rights are
the corporation in respect of any matter which has been also the directors’ acts or omissions.90 They are alleging
reposed inhim in confidence, as to which equity imposes that contracts executed by the corporation are
a disability upon him to deal in his own behalf, he shall be contracts executed by the directors. Complainants
liable as a trustee for the corporation and must account effectively pray that the corporate veilbe pierced
for the profits which otherwise would have accrued to because the cause of action between the corporation
the corporation. (n) and the directors is the same.
Based on the above provision, a director, trustee, or In that case, complainants have no choice but to
officer of a corporation may be made solidarily liable institute only one proceeding against the
with it for all damages suffered by the corporation, its parties.1âwphi1 Under the Rules of Court, filing of multiple
stockholders or members, and other persons in any of the suits for a single cause of action is prohibited. Institution of
following cases: more than one suit for the same cause of action
constitutes splitting the cause of action, which is a ground
a) The director or trustee willfully and knowingly for the dismissal ofthe others. Thus, in Rule 2:
voted for or assented to a patently unlawful
corporate act; Section 3. One suit for a single cause of action. — A party
may not institute more than one suit for a single cause of
b) The director or trustee was guilty of gross action. (3a)
negligence or bad faith in directing corporate
affairs; and Section 4. Splitting a single cause of action;effect of. — If
two or more suits are instituted on the basis of the same
c) The director or trustee acquired personal or cause of action, the filing of one or a judgment upon the
pecuniary interest in conflict with his or her duties merits in any one is available as a ground for the dismissal
as director or trustee. of the others. (4a)
Solidary liability with the corporation will also attach in the It is because the personalities of petitioners and the
following instances: corporation may later be found to be indistinct that we
rule that petitioners may be compelled to submit to
a) "When a director or officer has consented to arbitration.
the issuance of watered stocks or who, having
knowledge thereof, did not forthwith file with the However, in ruling that petitioners may be compelled to
corporate secretary his written objection submit to the arbitration proceedings, we are not
thereto";87 overturning Heirs of Augusto Salas wherein this court
affirmed the basic arbitration principle that only parties to
b) "When a director, trustee or officer has an arbitration agreement may be compelled to submit to
contractually agreed or stipulated to hold himself arbitration. In that case, this court recognizedthat persons
personally and solidarily liable with the other than the main party may be compelled to submit
corporation";88 and to arbitration, e.g., assignees and heirs. Assignees and
heirs may be considered parties to an arbitration
agreement entered into by their assignor because the
c) "When a director, trustee or officer is made, by assignor’s rights and obligations are transferred to them
specific provision of law, personally liable for his upon assignment. In other words, the assignor’s rights and
corporate action."89 obligations become their own rights and obligations. In
the same way, the corporation’s obligations are treated
as the representative’s obligations when the corporate The facts:
veil is pierced. Moreover, in Heirs of Augusto Salas, this
court affirmed its policy against multiplicity of suits and The Donation
unnecessary delay. This court said that "to split the
proceeding into arbitration for some parties and trial for Fedders Koppel, Incorporated (FKI), a manufacturer of
other parties would "result in multiplicity of suits, air-conditioning products, was the registered owner of a
duplicitous procedure and unnecessary delay." 91 This parcel of land located at Km. 16, South Superhighway,
court also intimated that the interest of justice would be Parañaque City (subject land).3 Within the subject land
best observed if it adjudicated rights in a single are buildings and other improvements dedicated to the
proceeding.92 While the facts of that case prompted this business of FKI.4
court to direct the trial court to proceed to determine the
issues of thatcase, it did not prohibit courts from allowing In 1975, FKI 5 bequeathed the subject land (exclusive of
the case to proceed to arbitration, when circumstances the improvements thereon) in favor of herein respondent
warrant. Makati Rotary Club Foundation, Incorporated by way of
a conditional donation.6 The respondent accepted the
Hence, the issue of whether the corporation’s acts in donation with all of its conditions.7 On 26 May1975, FKI
violation of complainant’s rights, and the incidental issue and the respondent executed a Deed of
of whether piercing of the corporate veil is warranted, Donation8evidencing their consensus.
should be determined in a single proceeding. Such
finding would determine if the corporation is merely an The Lease and the Amended Deed of Donation
aggregation of persons whose liabilities must be treated
as one with the corporation. One of the conditions of the donation required the
respondent to lease the subject land back to FKI under
terms specified in their Deed of Donation.9 With the
However, when the courts disregard the corporation’s
distinct and separate personality from its directors or respondent’s acceptance of the donation, a lease
officers, the courts do not say that the corporation, in all agreement between FKI and the respondent was,
instances and for all purposes, is the same as its directors, therefore, effectively incorporated in the Deed of
stockholders, officers, and agents. It does not result in an Donation.
absolute confusion of personalities of the corporation
and the persons composing or representing it. Courts Pertinent terms of such lease agreement, as provided in
merely discount the distinction and treat them as one, in the Deed of Donation , were as follows:
relation to a specific act, in order to extend the terms of
1. The period of the lease is for twenty-five (25) years,10 or
the contract and the liabilities for all damages to erring
corporate officials who participated in the corporation’s until the 25th of May 2000;
illegal acts. This is done so that the legal fiction cannot be
2. The amount of rent to be paid by FKI for the first twenty-
used to perpetrate illegalities and injustices.
five (25) years is ₱40,126.00 per annum .11
Thus, in cases alleging solidary liability with the The Deed of Donation also stipulated that the lease over
corporation or praying for the piercing of the corporate the subject property is renewable for another period of
veil, parties who are normally treated as distinct twenty-five (25) years " upon mutual agreement" of FKI
individuals should be made to participate in the and the respondent.12 In which case, the amount of rent
arbitration proceedings in order to determine ifsuch shall be determined in accordance with item 2(g) of the
distinction should indeed be disregarded and, if so, to
Deed of Donation, viz:
determine the extent of their liabilities.
g. The rental for the second 25 years shall be the subject
In this case, the Arbitral Tribunal rendered a decision, of mutual agreement and in case of disagreement the
finding that BF Corporation failed to prove the existence matter shall be referred to a Board of three Arbitrators
of circumstances that render petitioners and the other appointed and with powers in accordance with the
directorssolidarily liable. It ruled that petitioners and Arbitration Law of the Philippines, Republic Act 878,
Shangri-La’s other directors were not liable for the whose function shall be to decide the current fair market
contractual obligations of Shangri-La to BF Corporation.
value of the land excluding the improvements, provided,
The Arbitral Tribunal’s decision was made with the
that, any increase in the fair market value of the land
participation of petitioners, albeit with their continuing
objection. In view of our discussion above, we rule that shall not exceed twenty five percent (25%) of the original
petitioners are bound by such decision. value of the land donated as stated in paragraph 2(c) of
this Deed. The rental for the second 25 years shall not
exceed three percent (3%) of the fair market value of the
WHEREFORE, the petition is DENIED. The Court of Appeals'
decision of May 11, 2006 and resolution of October 5, land excluding the improvements as determined by the
2006 are AFFIRMED. Board of Arbitrators.13
1. The MeTC was not able to validly acquire jurisdiction As to the existing improvements belonging to the
over the instant unlawful detainer case in view of the defendant-appellee, as these were built in good faith,
insufficiency of respondent’s demand.46 The First Demand the provisions of Art. 1678of the Civil Code shall apply.
Letter did not contain an actual demand to vacate the SO ORDERED.57
premises and, therefore, the refusal to comply there with
does not give rise to an action for unlawful detainer.47 The ruling of the RTC is premised on the following
ratiocinations:
2. Assuming that the MeTC was able to acquire
jurisdiction, it may not exercise the same until the 1. The respondent had adequately complied with the
disagreement between the parties is first referred to requirement of demand as a jurisdictional precursor to an
arbitration pursuant to the arbitration clause of the 2005 unlawful detainer action.58 The First Demand Letter, in
Lease Contract.48 substance, contains a demand for petitioner to vacate
when it mentioned that it was a notice " per Section12 of
3. Assuming further that the MeTC has jurisdiction that it the 2005 Lease Contract."59 Moreover, the issue of
can exercise, ejectment still would not lie as the 2005 sufficiency of the respondent’s demand ought to have
Lease Contract is void abinitio.49 The stipulation in the been laid to rest by the Second Demand Letter which,
2005 Lease Contract requiring petitioner to give yearly " though not submitted in evidence, was nonetheless
donations " to respondent is a simulation, for they are, in admitted by petitioner as containing a" demand to eject
fact, parts of the rent. 50 Such grants were only " in its Answer with Compulsory Counterclaim.60
denominated as " donations " in the contract so that the
respondent—anon-stock and non-profit corporation— 2. The petitioner cannot validly invoke the arbitration
could evade payment of the taxes otherwise due clause of the 2005 Lease Contract while, at the same
thereon.51 time, impugn such contract’s validity.61 Even assuming
that it can, petitioner still did not file a formal application
In due course, petitioner and respondent both submitted before the MeTC so as to render such arbitration clause
their position papers, together with their other operational.62 At any rate, the MeTC would not be
documentary evidence.52 Remarkably, however, precluded from exercising its jurisdiction over an action
respondent failed to submit the Second Demand Letter for unlawful detainer, over which, it has exclusive original
as part of its documentary evidence. jurisdiction.63
Rulings of the MeTC, RTC and Court of Appeals 3. The 2005 Lease Contract must be sustained as a valid
On 27 April 2010, the MeTC rendered judgment53 in favor contract since petitioner was not able to adduce any
of the petitioner. While the MeTC refused to dismiss the evidence to support its allegation that the same is
action on the ground that the dispute is subject to void.64 There was, in this case, no evidence that
arbitration, it nonetheless sided with the petitioner with respondent is guilty of any tax evasion.65
respect to the issues regarding the insufficiency of the Aggrieved, the petitioner appealed to the Court of
respondent’s demand and the nullity of the 2005 Lease Appeals.
Contract.54 The MeTC thus disposed:
On 19 August 2011, the Court of Appeals affirmed66 the
WHEREFORE, judgment is hereby rendered dismissing the decision of the RTC:
case x xx, without pronouncement as to costs.
WHEREFORE , the petition is DENIED . The assailed Decision
SO ORDERED.55 of the Regional Trial Court of Parañaque City, Branch 274,
The respondent appealed to the Regional Trial Court in Civil Case No. 10-0255 is AFFIRMED.
(RTC). This appeal was assigned to Branch 274 of the RTC x xxx
of Parañaque City and was docketed as Civil Case No.
10-0255. SO ORDERED.67
On 29 October 2010, the RTC reversed56 the MeTC and Hence, this appeal.
ordered the eviction of the petitioner from the subject
land: On 5 September 2011, this Court granted petitioner’s
prayer for the issuance of a Temporary Restraining
WHEREFORE, all the foregoing duly considered, the Order68staying the immediate implementation of the
appealed Decision of the Metropolitan Trial Court, Branch decisions adverse to it.
77, Parañaque City, is hereby reversed, judgment is thus
rendered in favor of the plaintiff-appellant and against OUR RULING
the defendant-appellee, and ordering the latter – Independently of the merits of the case, the MeTC, RTC
and Court of Appeals all erred in overlooking the
significance of the arbitration clause incorporated in the policy.72 The Supreme Court, in Gonzales v. Climax
2005 Lease Contract . As the Court sees it, that is a fatal Mining, Ltd.,73 held that " the validity of contract cannot
mistake. be subject of arbitration proceedings " as such questions
are " legal in nature and require the application and
For this reason, We grant the petition. interpretation of laws and jurisprudence which is
Present Dispute is ArbitrableUnder the necessarily a judicial function ." 74
Arbitration Clause of the 2005 Lease 2. The petitioner cannot validly invoke the arbitration
Agreement Contract clause of the 2005 Lease Contract while, at the same
Going back to the records of this case, it is discernable time, impugn such contract’s validity.75
that the dispute between the petitioner and respondent 3. Even assuming that it can invoke the arbitration clause
emanates from the rental stipulations of the 2005 Lease whilst denying the validity of the 2005 Lease Contract ,
Contract. The respondent insists upon the enforce ability petitioner still did not file a formal application before the
and validity of such stipulations, whereas, petitioner, in MeTC so as to render such arbitration clause
substance, repudiates them. It is from petitioner’s operational.76 Section 24 of Republic Act No. 9285
apparent breach of the 2005 Lease Contract that requires the party seeking arbitration to first file a " request
respondent filed the instant unlawful detainer action. " or an application therefor with the court not later than
One cannot escape the conclusion that, under the the preliminary conference.77
foregoing premises, the dispute between the petitioner 4. Petitioner and respondent already underwent Judicial
and respondent arose from the application or execution Dispute Resolution (JDR) proceedings before the
of the 2005 Lease Contract . Undoubtedly, such kinds of RTC.78 Hence, a further referral of the dispute to
dispute are covered by the arbitration clause of the 2005 arbitration would only be circuitous.79 Moreover, an
Lease Contract to wit: ejectment case, in view of its summary nature, already
19. Governing Law – The provisions of this 2005 Lease fulfills the prime purpose of arbitration, i.e. , to provide
Contract shall be governed, interpreted and construed in parties in conflict with an expedient method for the
all aspects in accordance with the laws of the Republic resolution of their dispute.80 Arbitration then would no
of the Philippines. longer be necessary in this case.81
Any disagreement as to the interpretation, application or None of the arguments have any merit.
execution of this 2005 Lease Contract shall be submitted First. As highlighted in the previous discussion, the
to a board of three (3) arbitrators constituted in disagreement between the petitioner and respondent
accordance with the arbitration law of the Philippines. falls within the all-encompassing terms of the arbitration
The decision of the majority of the arbitrators shall be clause of the 2005 Lease Contract. While it may be
binding upon FKI and respondent.69 (Emphasis supplied) conceded that in the arbitration of such disagreement,
The arbitration clause of the 2005 Lease Contract the validity of the 2005 Lease Contract, or at least, of
stipulates that "any disagreement" as to the " such contract’s rental stipulations would have to be
interpretation, application or execution " of the 2005 determined, the same would not render such
Lease Contract ought to be submitted to arbitration.70 To disagreement non-arbitrable. The quotation from
the mind of this Court, such stipulation is clear and is Gonzales that was used to justify the contrary position
comprehensive enough so as to include virtually any kind was taken out of context. A rereading of Gonzales would
of conflict or dispute that may arise from the 2005 Lease fix its relevance to this case.
Contract including the one that presently besets In Gonzales, a complaint for arbitration was filed before
petitioner and respondent. the Panel of Arbitrators of the Mines and Geosciences
The application of the arbitration clause of the 2005 Bureau (PA-MGB) seeking the nullification of a Financial
Lease Contract in this case carries with it certain legal Technical Assistance Agreement and other mining
effects. However, before discussing what these legal related agreements entered into by private parties.82
effects are, We shall first deal with the challenges posed Grounds invoked for the nullification of such agreements
against the application of such arbitration clause. include fraud and unconstitutionality.83 The pivotal issue
Challenges Against the Application of the that confronted the Court then was whether the PA-MGB
Arbitration Clause of the 2005 Lease has jurisdiction over that particular arbitration complaint.
Contract Stated otherwise, the question was whether the
complaint for arbitration raises arbitrable issues that the
Curiously, despite the lucidity of the arbitration clause of PA-MGB can take cognizance of.
the 2005 Lease Contract, the petitioner, as well as the
MeTC, RTC and the Court of Appeals, vouched for the Gonzales decided the issue in the negative. In holding
non-application of the same in the instant case. A that the PA-MGB was devoid of any jurisdiction to take
plethora of arguments was hurled in favor of bypassing cognizance of the complaint for arbitration, this Court
arbitration. We now address them. pointed out to the provisions of R.A. No. 7942, or the
Mining Act of 1995, which granted the PA-MGB with
At different points in the proceedings of this case, the exclusive original jurisdiction only over mining disputes,
following arguments were offered against the application i.e., disputes involving " rights to mining areas," "mineral
of the arbitration clause of the 2005 Lease Contract: agreements or permits," and " surface owners, occupants,
claim holders or concessionaires" requiring the technical
1. The disagreement between the petitioner and knowledge and experience of mining authorities in order
respondent is non-arbitrable as it will inevitably touch to be resolved.84 Accordingly, since the complaint for
upon the issue of the validity of the 2005 Lease arbitration in Gonzales did not raise mining disputes as
Contract.71 It was submitted that one of the reasons contemplated under R.A. No. 7942 but only issues relating
offered by the petitioner in justifying its failure to pay to the validity of certain mining related agreements, this
under the 2005 Lease Contract was the nullity of such Court held that such complaint could not be arbitrated
contract for being contrary to law and public
before the PA-MGB.85 It is in this context that we made Once again instructive is Cargill, wherein this Court held
the pronouncement now in discussion: that, as a further consequence of the doctrine of
separability, even the very party who repudiates the main
Arbitration before the Panel of Arbitrators is proper only contract may invoke its arbitration clause.94
when there is a disagreement between the parties as to
some provisions of the contract between them, which Third . The operation of the arbitration clause in this case
needs the interpretation and the application of that is not at all defeated by the failure of the petitioner to file
particular knowledge and expertise possessed by a formal "request" or application therefor with the MeTC.
members of that Panel. It is not proper when one of the We find that the filing of a "request" pursuant to Section
parties repudiates the existence or validity of such 24 of R.A. No. 9285 is not the sole means by which an
contract or agreement on the ground of fraud or arbitration clause may be validly invoked in a pending
oppression as in this case. The validity of the contract suit.
cannot be subject of arbitration proceedings. Allegations
of fraud and duress in the execution of a contract are Section 24 of R.A. No. 9285 reads:
matters within the jurisdiction of the ordinary courts of law. SEC. 24. Referral to Arbitration . - A court before which an
These questions are legal in nature and require the action is brought in a matter which is the subject matter
application and interpretation of laws and jurisprudence of an arbitration agreement shall, if at least one party so
which is necessarily a judicial function.86(Emphasis requests not later that the pre-trial conference, or upon
supplied) the request of both parties thereafter, refer the parties to
The Court in Gonzales did not simply base its rejection of arbitration unless it finds that the arbitration agreement is
the complaint for arbitration on the ground that the issue null and void, inoperative or incapable of being
raised therein, i.e. , the validity of contracts, is per se non- performed. [Emphasis ours; italics original]
arbitrable. The real consideration behind the ruling was The " request " referred to in the above provision is, in turn,
the limitation that was placed by R.A. No. 7942 upon the implemented by Rules 4.1 to 4.3 of A.M. No. 07-11-08-SC
jurisdiction of the PA-MGB as an arbitral body . Gonzales or the Special Rules of Court on Alternative Dispute
rejected the complaint for arbitration because the issue Resolution (Special ADR Rules):
raised therein is not a mining dispute per R.A. No. 7942
and it is for this reason, and only for this reason, that such RULE 4: REFERRAL TO ADR
issue is rendered non-arbitrable before the PA-MGB. As
stated beforehand, R.A. No. 7942 clearly limited the Rule 4.1. Who makes the request. - A party to a pending
jurisdiction of the PA-MGB only to mining disputes.87 action filed in violation of the arbitration agreement,
whether contained in an arbitration clause or in a
Much more instructive for our purposes, on the other submission agreement, may request the court to refer the
hand, is the recent case of Cargill Philippines, Inc. v. San parties to arbitration in accordance with such
Fernando Regal Trading, Inc.88 In Cargill , this Court agreement.
answered the question of whether issues involving the
rescission of a contract are arbitrable. The respondent in Rule 4.2. When to make request. - (A) Where the
Cargill argued against arbitrability, also citing therein arbitration agreement exists before the action is filed . -
Gonzales . After dissecting Gonzales , this Court ruled in The request for referral shall be made not later than the
favor of arbitrability.89 Thus, We held: pre-trial conference. After the pre-trial conference, the
court will only act upon the request for referral if it is
Respondent contends that assuming that the existence made with the agreement of all parties to the case.
of the contract and the arbitration clause is conceded,
the CA's decision declining referral of the parties' dispute (B) Submission agreement . - If there is no existing
to arbitration is still correct. It claims that its complaint in arbitration agreement at the time the case is filed but the
the RTC presents the issue of whether under the facts parties subsequently enter into an arbitration agreement,
alleged, it is entitled to rescind the contract with they may request the court to refer their dispute to
damages; and that issue constitutes a judicial question or arbitration at any time during the proceedings.
one that requires the exercise of judicial function and Rule 4.3. Contents of request. - The request for referral
cannot be the subject of an arbitration proceeding. shall be in the form of a motion, which shall state that the
Respondent cites our ruling in Gonzales, wherein we held dispute is covered by an arbitration agreement.
that a panel of arbitrator is bereft of jurisdiction over the
complaint for declaration of nullity/or termination of the A part from other submissions, the movant shall attach to
subject contracts on the grounds of fraud and oppression his motion an authentic copy of the arbitration
attendant to the execution of the addendum contract agreement.
and the other contracts emanating from it, and that the
complaint should have been filed with the regular courts The request shall contain a notice of hearing addressed
as it involved issues which are judicial in nature. to all parties specifying the date and time when it would
be heard. The party making the request shall serve it
Such argument is misplaced and respondent cannot rely upon the respondent to give him the opportunity to file a
on the Gonzales case to support its argument.90(Emphasis comment or opposition as provided in the immediately
ours) succeeding Rule before the hearing. [Emphasis ours;
italics original]
Second. Petitioner may still invoke the arbitration clause
of the 2005 Lease Contract notwithstanding the fact that Attention must be paid, however, to the salient wordings
it assails the validity of such contract. This is due to the of Rule 4.1.It reads: "a party to a pending action filed in
doctrine of separability.91 violation of the arbitration agreement x xx may request
the court to refer the parties to arbitration in accordance
Under the doctrine of separability, an arbitration with such agreement."
agreement is considered as independent of the main
contract.92Being a separate contract in itself, the In using the word " may " to qualify the act of filing a "
arbitration agreement may thus be invoked regardless of request " under Section 24 of R.A. No. 9285, the Special
the possible nullity or invalidity of the main contract.93 ADR Rules clearly did not intend to limit the invocation of
an arbitration agreement in a pending suit solely via such of Lease in this case, We find that the instant unlawful
"request." After all, non-compliance with an arbitration detainer action was instituted in violation of such clause.
agreement is a valid defense to any offending suit and, The Law, therefore, should have governed the fate of the
as such, may even be raised in an answer as provided in parties and this suit:
our ordinary rules of procedure.95
R.A. No. 876 Section 7. Stay of civil action. - If any suit or
In this case, it is conceded that petitioner was not able to proceeding be brought upon an issue arising out of an
file a separate " request " of arbitration before the MeTC. agreement providing for the arbitration thereof, the court
However, it is equally conceded that the petitioner, as in which such suit or proceeding is pending, upon being
early as in its Answer with Counterclaim ,had already satisfied that the issue involved in such suit or proceeding
apprised the MeTC of the existence of the arbitration is referable to arbitration, shall stay the action or
clause in the 2005 Lease Contract96 and, more proceeding until an arbitration has been had in
significantly, of its desire to have the same enforced in accordance with the terms of the agreement: Provided,
this case.97 This act of petitioner is enough valid That the applicant for the stay is not in default in
invocation of his right to arbitrate. Fourth . The fact that proceeding with such arbitration.[Emphasis supplied]
the petitioner and respondent already under went
through JDR proceedings before the RTC, will not make R.A. No. 9285
the subsequent conduct of arbitration between the Section 24. Referral to Arbitration. - A court before which
parties unnecessary or circuitous. The JDR system is an action is brought in a matter which is the subject
substantially different from arbitration proceedings. matter of an arbitration agreement shall, if at least one
The JDR framework is based on the processes of party so requests not later that the pre-trial conference,
mediation, conciliation or early neutral evaluation which or upon the request of both parties thereafter, refer the
entails the submission of a dispute before a " JDR judge " parties to arbitration unless it finds that the arbitration
who shall merely " facilitate settlement " between the agreement is null and void, in operative or incapable of
parties in conflict or make a " non-binding evaluation or being performed. [Emphasis supplied]
assessment of the chances of each party’s case." 98 Thus It is clear that under the law, the instant unlawful detainer
in JDR, the JDR judge lacks the authority to render a action should have been stayed;101 the petitioner and
resolution of the dispute that is binding upon the parties in the respondent should have been referred to arbitration
conflict. In arbitration, on the other hand, the dispute is pursuant to the arbitration clause of the 2005 Lease
submitted to an arbitrator/s —a neutral third person or a Contract . The MeTC, however, did not do so in violation
group of thereof— who shall have the authority to render of the law—which violation was, in turn, affirmed by the
a resolution binding upon the parties.99 RTC and Court of Appeals on appeal.
Clearly, the mere submission of a dispute to JDR The violation by the MeTC of the clear directives under
proceedings would not necessarily render the R.A. Nos.876 and 9285 renders invalid all proceedings it
subsequent conduct of arbitration a mere surplusage. undertook in the ejectment case after the filing by
The failure of the parties in conflict to reach an amicable petitioner of its Answer with Counterclaim —the point
settlement before the JDR may, in fact, be supplemented when the petitioner and the respondent should have
by their resort to arbitration where a binding resolution to been referred to arbitration. This case must, therefore, be
the dispute could finally be achieved. This situation remanded to the MeTC and be suspended at said point.
precisely finds application to the case at bench. Inevitably, the decisions of the MeTC, RTC and the Court
Neither would the summary nature of ejectment cases be of Appeals must all be vacated and set aside.
a valid reason to disregard the enforcement of the The petitioner and the respondent must then be referred
arbitration clause of the 2005 Lease Contract . to arbitration pursuant to the arbitration clause of the
Notwithstanding the summary nature of ejectment cases, 2005 Lease Contract.
arbitration still remains relevant as it aims not only to
afford the parties an expeditious method of resolving This Court is not unaware of the apparent harshness of
their dispute. the Decision that it is about to make. Nonetheless, this
Court must make the same if only to stress the point that,
A pivotal feature of arbitration as an alternative mode of in our jurisdiction, bona fide arbitration agreements are
dispute resolution is that it is, first and foremost, a product recognized as valid;102 and that laws,103 rules and
of party autonomy or the freedom of the parties to " regulations104 do exist protecting and ensuring their
make their own arrangements to resolve their own enforcement as a matter of state policy. Gone should be
disputes."100 Arbitration agreements manifest not only the the days when courts treat otherwise valid arbitration
desire of the parties in conflict for an expeditious agreements with disdain and hostility, if not outright "
resolution of their dispute. They also represent, if not more jealousy,"105 and then get away with it. Courts should
so, the parties’ mutual aspiration to achieve such instead learn to treat alternative means of dispute
resolution outside of judicial auspices, in a more informal resolution as effective partners in the administration of
and less antagonistic environment under the terms of justice and, in the case of arbitration agreements, to
their choosing. Needless to state, this critical feature can afford them judicial restraint.106 Today, this Court only
never be satisfied in an ejectment case no matter how performs its part in upholding a once disregarded state
summary it may be. policy.
Having hurdled all the challenges against the application Civil Case No. CV 09-0346
of the arbitration clause of the 2005 Lease Agreement in
this case, We shall now proceed with the discussion of its This Court notes that, on 30 September 2009, petitioner
legal effects. filed with the RTC of Parañaque City, a complaint107 for
the rescission or cancellation of the Deed of Donation
Legal Effect of the Application of the and Amended Deed of Donation against the
Arbitration Clause respondent. The case is currently pending before Branch
Since there really are no legal impediments to the 257 of the RTC, docketed as Civil Case No. CV 09-0346.
application of the arbitration clause of the 2005 Contract
This Court recognizes the great possibility that issues raised
in Civil Case No. CV 09-0346 may involve matters that are
rightfully arbitrable per the arbitration clause of the 2005
Lease Contract. However, since the records of Civil Case
No. CV 09-0346 are not before this Court, We can never
know with true certainty and only speculate. In this light,
let a copy of this Decision be also served to Branch 257of
the RTC of Parañaque for its consideration and, possible,
application to Civil Case No. CV 09-0346.