You are on page 1of 6

Environmental Management Plan – Matrix

Timing to
Environmental Locations to implement
Objectives Compliance Measures recommended implement Remark
concern Compliance
Measures
DESIGN and -
PRECONSTRUCTIN
STAGE
1. Review of EMP Ensure EMP sufficient to control Review EC and EMP & environmental assessment in line with All project alignment Site
PMC/EC Guidelines. Completion of detailed
impacts and compliance with Team/EMC
design.
statutory requirement of EC Team
2. Social Impacts and
Na NA NA NA NA
Resettlement
3. Project disclosure Ensure compliance with 1. Ensure all changes to alignment are included in the revised All project alignment.
EMP. Completion of detailed
statutory requirement of Project Team
design.
PMC/EC
4 Environmentally Ensure environmentally 1. Require in procurement specifications that transformers, Method statement during During Procurement negotiations.
responsible procurement responsible procurement. transformer oil and other equipment are to be free from PCB contractor selection, prior
and other petroleum fractions that may be injurious to to contract signing.
Look for opportunities to
environment or equipment.
enhance design No later than pre-
2. Require new switchgear to be free from CFCs in procurement
Avoid environmental pollution. qualification or tender
specifications. SF6 gas insulated equipment to be effectively
negotiations. Planning
leak free with nominal SF6 top up less than 1% per year.
Team
3. Choose non-polluting or enhancing methods. Contractor to
submit Method Statement and schedule of environmental
mitigation measures in response to EMP with tender. Include
enhancements, techniques to reduce impacts.
4. Contractual clauses included to tie the implementation of
environmental mitigation measures to a performance bond.
1. Create waste management policy and plan to identify sufficient
locations for, storage and reuse of transformers and recycling of
Ensure adequate disposal 1.Prior to detailed design
breaker oils and disposal of transformer oil, residually
options for all waste including stage no later than pre-
contaminated soils and scrap metal “cradle to grave”. Locations approved by local waste
5. Waste disposal transformer oil, residually qualification or tender EMC Team
2. Include in contracts for unit rates for re-measurement for disposal authorities.
contaminated soils, and scrap negotiations
disposal.
metal. 2. Include in contract.
3. After agreement with local authority, designate disposal sites in
the contract and cost unit disposal rates accordingly.
To ensure responsible disposal
6. Hazardous waste 1. Waste management plan to identify any equipment to be During tender
of hazardous waste in line with All substations EMC Team
disposal replaced and appropriate method for disposal. preparation.
best practice.
7. Noise and air quality Plan and design to ensure noise 1. Plan to prevent noise from GSS in the operational phase and 1. During designing Prescribed locations as agreed EMC Team
mitigation in design. impacts are acceptable in conduct consultation with affected communities to determine stage no later than pre- with EMC Team
operational phase. acceptability criteria for noise. qualification or tender
2. Follow up with detailed acoustic assessment for all residential, negotiations
school, temple (other sensitive structures) within 50m of GSS.
Base on measurement of existing equipment noise.
3. If noise at sensitive receiver exceeds Noise Rules criterion [e.g.
Timing to
Environmental Locations to implement
Objectives Compliance Measures recommended implement Remark
concern Compliance
Measures
Leq55db(A)] include design and installation of acoustic insulation
measures to control noise at denoted stations.
4. Consider solid barrier to attenuate noise at schools and
hospitals to below accepted criterion.
5. Prepare Air Quality and Noise Control plan for construction
stage
1. Assess expected hydrologic flow in all areas where it is sensitive Before the
To minimize hydrological and 2. Ensure surface flows are controlled and facilitated through early commencement of Considered locations to be as Site
8 Hydrological Impacts drainage impacts during re-provision of irrigation with appropriate drainage structures in the construction identified in the Detailed Drainage Team/EMC
constructions. road base including bridges and culverts. activities/during detailed Report. Team
3. Prepare Drainage Management Plan. designing stage.
1. Prevent runoff and control All stream and river crossings and
Site
9 Temporary drainage erosion.. 1. Identify locations for Erosion Control and Temporary Drainage During first month after all alignments where slopes
Team/EMC
and erosion control 2. Include preliminary designs along all of the line and around commencement indicate erosion will be a problem
Team
for Erosion Control based on observation.
1. Plan sites for worker camps and back up areas for stockpiling
To plan to minimize the effect of materials and equipment in advance.
10 Planning construction 2. Consult local community and locate to use waste/barren land During first month after Site
the work camps on the
camps and materials and non-agricultural plots. commencement of Locations decided by EMC Team Team/EMC
surrounding environment and
management construction Team
residents in the area. 3. Agree use of land before construction commences reconfirmed
by the Contractor
11.Traffic Condition Plan to minimize disturbance of Avoiding blocking existing roads and other access near the works During first month after Important locations to be identified Site
traffic route during construction. commencement of n revised EMP. Team/EMC
construction Team
12. Institutional Prepare EM Cell for Develop strengthening plan for the environmental management by Throughout the project
During first month after Site
strengthening and implementation of EMP. EMC Team. Train EMC officials to apply the EMP and to evaluate
commencement of Team/EMC
capacity building the environmental requirements and contractors’ mitigation
construction Team
measures.
13 Prepare contractors Full and effective 1. Prepare contractors to co-operate with the executing agency, During First Month Throughout the project
for implementation of implementation of project management, supervising consultants and local population
EMP environmental mitigation in the mitigation of impacts.
measures. 2. Must require full implementation of the EMP
3. Contractor to engage capable and trained environmental
management staff to audit the effectiveness and review mitigation
measures as project proceeds. Site
4. The effective implementation of the EMP audited. Team/EMC
Team
Timing to
Environmental Locations to implement
Objectives Compliance Measures recommended implement Remark
concern Compliance
Measures
CONSTRUCTION
STAGE
1. Conducting special briefing and / or on-site training for the
contractors and workers on the environmental requirement of the Induction for all site
To ensure that the Contractor, project. Record attendance and achievement. agents and above before
subcontractors and workers 2. Conducting special briefing and training for Contractor on the commencement of work.
All staff members in all categories.
understand and have the environmental requirement of the project. Record attendance and
1.Orientation for monthly induction and six month
capacity to ensure that the achievement. At early stages of EMC Team
Contractor, and Workers refresher course as necessary until
environmental requirements for 3. Agreement on critical areas to be considered and necessary construction for all
contractors comply / improve
mitigation measures are mitigation measures, among all parties who are involved in project construction employees
implemented. activities. as far as reasonably
4. Periodic progress review sessions to be conducted every six practicable.
months
1. Drainage management plan,
2. Temporary pedestrian and traffic management plan,
3. Erosion control and temporary drainage plan
Avoid impacts from unplanned 4. Materials management plan,
2. Plans to control Site
activities by penalizing
environmental and 5. Waste management plan; Deliverable in final form. All Locations. Team/EMC
contractors for not committing to
associated impacts Team
properly planning works. 6. Noise and dust control plan,
7. Safety Plan
8. Agreed schedule of costs for environmental mitigation measures
(including maintenance where applicable).
1. Proper construction of TD and EC measures , maintenance and
management including training of operators and other workers to
avoid pollution of water bodies by the considerate operation of
To prevent adverse water construction machinery and equipment and reporting and
feedback by ESIC cell Prior to construction,
quality impacts due to
2. Storage of lubricants, fuels and other hydrocarbons in self- 50m from water bodies Relevant locations are construction
3. Water quality negligence and ensure EMC Team
contained dedicated enclosures >50m away from water bodies. Timing will depend on the within 50m of rivers.
unavoidable impacts are
construction timetable.
managed effectively. 3. No stockpiles next ling to water bodies.
4. Proper disposal of solid waste from construction activities &
worker camps.
5. Borrow sites should not be close to sources of drinking water.
4. Water Resources To minimize impacts on local 1. Availability of water will be assessed to evaluate the impact on Prior to construction, at Relevant locations are all local Site
water supply caused by community resources. all local water supply water supply resources and rivers. Team/EMC
construction activities are 2. Project water will be obtained without depleting local village resources. Team
minimized. supplies.
3. Camps will be located at least 100m away from the nearest Timing will depend on the
local settlement. construction timetable.
4. The contractors will be required to maintain close liaison with
local communities to ensure that any potential conflicts related to
common resource utilization for project purposes are resolved
Timing to
Environmental Locations to implement
Objectives Compliance Measures recommended implement Remark
concern Compliance
Measures
quickly.
5. Guidelines will be established to minimize the wastage of water
during construction operations and at campsites.
1. Implement Waste Management Plan.
2. Confirm conditions and safety of proposed disposal sites.
3. Confirm amounts of surplus rock based materials that can be
reused in the project or by other interested parties for public
To minimize the environmental projects.
Locations approved by EMC Cell/
impacts arising from generation 4. Confirm sufficient locations 1. Before construction
5. Spoil disposal and local authority. Site
of spoil waste, reuse where 5. In contracts specify locations for disposal of all construction commences
construction waste A list of temporary dumping sites to Team/EMC
possible and provide adequate waste and spoil at unit rates for re-measurement. 2. UPDATE Once a
disposal be prepared at the bidding stage Team
disposal options for unsuitable 6. Used oil and lubricants shall be recovered and reused or month
for agreement
soils. removed from the site in full compliance with the EC regulations.
7. Waste oil must not be burned. – Oil and solid waste disposal
location to be agreed with EMC Team
8 Open burning is contrary to good environmental practice and will
not be allowed.
1. Strong follow up from EMC
1. Install, maintain and monitor all requisite acoustic insulation Team required to update locations
To minimize noise level Maximum allowable Site
2. Hammer-type pile driving operations shall be avoided during monthly
6. Noise increases and ground vibrations noise levels are Team/EMC
nighttime. 2. Potential noise impact locations
during construction operations. 65dB(A)LEQ. Team
Well-maintained haulage trucks will be used with speed controls. will be within 100m near all
settlements.
1. Control all dusty materials at source.
2. Stockpiled soil and sand shall be slightly wetted before loading, 1. Dust control planning
particularly in windy conditions. will be a line item in the
To minimize effectively and 3. Fuel-efficient and well-maintained haulage trucks shall be approval of setting up
Site
avoid complaints due to the employed to minimize exhaust emissions. dust producing activities. A list of locations to be prepared by
7. Air quality Team/EMC
airborne particulate matter 4. Vehicles transporting soil, sand and other construction materials the EMC Team
Team
released to the atmosphere. shall be covered. Limitations to speeds of such vehicles 2.A schedule of spraying
necessary. Transport through densely populated area should be water to be revised
avoided. monthly
5. Spray bare ground areas with water.
Contractors to instruct and train workforce in the storage and
handling of materials and chemicals that can potentially cause soil Instruct before works
Site
contamination. commence and
8. Soil Contamination Avoid soil contamination Throughout all locations Team/EMC
Accidentally spills on open ground including the top 2cm of any throughout all
Team
contaminated soil shall be disposed of as chemical waste to a construction works.
disposal site acceptable to the local authority / community.
9. Work Camp Location To ensure that the operation of 1. Confirm location of work camps in consultation with Design UPDATE Once a month Location Map is prepared by the Site
and Operation work camps does not adversely Team. If possible, camps shall not be located near settlements or Design Team Team/EMC
affect the surrounding near drinking water supply intakes. Team
environment and residents in 2. Water and sanitary facilities shall be provided for workers and
the area. employees.
3. Solid waste and sewage shall be managed according to the
Timing to
Environmental Locations to implement
Objectives Compliance Measures recommended implement Remark
concern Compliance
Measures
national and local regulations. As a rule, solid waste must not be
dumped, buried or burned at or near the project site, but shall be
disposed of to the nearest site approved by the local authority.
4. Portable lavatories or at least pit latrines will be installed and
open defecation shall be discouraged and prevented by keeping
lavatory facilities clean at all times.
5. The Contractor shall document that all liquid and solid
hazardous and non-hazardous waste are separated, collected and
disposed of according to the given requirements and regulations.
6. At the conclusion of the project, all debris and waste shall be
removed. All temporary structures, including shelters and toilets
shall be removed.
7. Exposed areas shall be planted with suitable vegetation.
1. Submit Safety Plan one month before commencement of
construction.
2. Providing adequate warning signs.
3. Providing every worker with skull guard or hard hat and safety
Site
10. Safety Precautions To ensure physical safety of shoes.
During construction All areas Team/EMC
for Workers workers 4. Establish all relevant safety measures as required by law and
Team
good engineering practices.
5. The Contractor shall instruct his workers in health and safety
matters, and require the workers to use the provided safety
equipment.
1. Use local labour as far as possible for manual work. A list of current construction areas
2. Use local educated people for clerical and office work where and planned works to be updated
To engage local workforce and Claims to be solved as
possible. by the Site Team monthly and
community. soon as possible
3. Encourage monitoring of the project by local village groups. displayed at local village offices.
To encourage local support for
11. Social Impacts 4. Claims/complaints of the people on construction Contractor
the project. Necessary evacuations
nuisance/damages close to ROW to be considered and responded Special attention to locations of
To ensure minimum impacts to to be done as when
to promptly by the Site/EMC Team irrigation systems, irrigated
people living close to the project necessary
5. Quarterly meeting for liaison purposes to monitor complaints. terraces and lands damaged due to
6. Set up or maintain local communication lines flood or landslide.
Before close out of
construction in all areas

To make environmental 1. Include planting of trees in addition to those removed such as


12. Enhancements enhancements and improve under lines in detailed design for visual interest and amenity. All areas of the alignment. Contractor
appearance.
OPERATIONAL STAGE
Environmental
Objectives Compliance measures recommended Proposed timing
Concern
To minimize and monitor air pollution and Before installation of equipment ensure supplied equipment commissioning is free from CFCs as
1. Air Quality During operation
release of greenhouse gasses required in procurement specifications.
1. Maintain and monitor boundary to prevent encroachment.
2. Encroachment 2. Involve local community in line monitoring
3. Conduct awareness campaigning with the local public to foster public stewardship of the area around
and community To control encroachment. During operation
the towers to prevent the encroachment.
awareness 4. Patrol and monitor the & involve local groups or an NGO in the protection
5. Report any areas of encroachment.
3 Crops and Monitor impacts from maintaining tree Operational phase
Track growth of large trees under the conductors.
vegetation clearance under transmission lines

Note: DDS=Detailed design stage. EIA=environmental impact Assessment. EMP=, environmental management action plan = environmental management plan, EMC= Environmental Management Cell, TD = Temporary drainage. EC = Erosion
control. NGO = non government organization.dadadadadadadada

You might also like