DESCRIPCION: UNIDAD: m2

ESTRUCTURA METÁLICA

EQUIPOS CANTIDAD TARIFA COSTO HORA RENDIMIENTO COSTO


HERRAMIENTA MENOR (5% M.O.) 1.12
AMOLADORA 1 1.17 1.17 1.55 1.81
SOLDADORA ELÉCTRICA 300 A 1 2.23 2.23 1.55 3.46
TALADRO ELÉCTRICO 1 1.10 1.10 1.55 1.71
COMPRESOR 1 0.75 0.75 1.55 1.16
TECLE 500 KG 1 5.00 5.00 1.55 7.75
ANDAMIO 2 0.05 0.1 1.55 0.16

SUBTOTAL M 17.17

MANO DE OBRA CANTIDAD JORNAL COSTO HORA RENDIMENTO COSTO


/HR
PEON (ESTRUC.OCUP.E2) 2.00 3.51 7.02 1.5500 10.88
MAESTRO DE OBRA(ESTRUC.OCUP.C1) 0.10 3.93 0.39 1.5500 0.61
FIERRERO(ESTRUC.OCUP.D2) 1.00 3.55 3.55 1.5500 5.50
PINTOR(ESTRUC.OCUP.E2) 1.00 3.55 3.55 1.5500 5.50

SUBTOTAL N 22.50

MATERIALES UNIDAD CANTIDAD P.UNITARIO COSTO


ELECTRODO E6011 kg 0.16 3.55 0.56
PERFIL ESTRUCTURAL C 100X50X4 mm kg 4.37 1.12 4.89
PERFIL ESTRUCTURAL G 80X40X15X2 mm kg 1.78 0.89 1.59
PERFIL ESTRUCTURAL G 60X30X10X2 mm kg 2.44 0.89 2.17
PLANCHON grado 50 3mm hasta 12mm kg 17.30 0.81 14.01
VARILLA SISMO RESISTENTE SOLDABLE D=16mm kg 10.36 0.79 8.18
DISCO DE CORTE PARA ACERO u 0.06 1.59 0.10
FONDO LACA GRIS gl 0.08 25.95 2.08
ANTICORROSIVO MATE OXIDO NEGRO gl 0.08 15.74 1.26
THINNER COMERCIAL gl 0.04 15.35 0.64

SUBTOTAL O 35.49
TOTAL COSTO DIRECTO USD (M+N+O) 75.15

ESTOS PRECIOS NO INCLUYEN EL IVA


ANÁLISIS DE PRECIOS UNITARIOS REFERENCIALES
DESCRIPCION: UNIDAD: pto
SOLDADURA SMAW

EQUIPOS CANTIDAD TARIFA COSTO HORA RENDIMIENTO COSTO


HERRAMIENTA MENOR (5% M.O.) 0.01
SOLDADORA 225 A 1.00 2.15 2.15 0.03 0.05

SUBTOTAL M 0.06

JORNAL
MANO DE OBRA CANTIDAD /HR COSTO HORA RENDIMENTO COSTO
PEON (ESTRUC.OCUP.E2) 1 3.55 3.55 0.0250 0.09
INSPECTOR DE OBRA(ESTRUC.OCUP.B3) 0.2 3.94 0.79 0.0250 0.02
FIERRERO(ESTRUC.OCUP.D2) 1 3.55 3.55 0.0250 0.09

SUBTOTAL N 0.20

MATERIALES UNIDAD CANTIDAD P.UNITARIO COSTO


ELECTRODO 7018 1/8" kg 0.140 3.78 0.53

SUBTOTAL O 0.53
TOTAL COSTO DIRECTO USD (M+N+O) 0.79 100
0.20 24.966379
ESTOS PRECIOS NO INCLUYEN EL IVA
ANÁLISIS DE PRECIOS UNITARIOS REFERENCIALES
DESCRIPCION: UNIDAD: pto
SOLDADURA GTAW

EQUIPOS CANTIDAD TARIFA COSTO HORA RENDIMIENTO COSTO


HERRAMIENTA MENOR (5% M.O.) 0.01
SOLDADORA TIG 1.00 4.38 4.38 0.03 0.13

SUBTOTAL M 0.14

MANO DE OBRA CANTIDAD JORNAL COSTO HORA RENDIMENTO COSTO


/HR
PEON (ESTRUC.OCUP.E2) 1 3.55 3.55 0.0300 0.11
INSPECTOR DE OBRA(ESTRUC.OCUP.B3) 0.2 3.94 0.79 0.0300 0.02
FIERRERO(ESTRUC.OCUP.D2) 1 3.55 3.55 0.0300 0.11

SUBTOTAL N 0.24

MATERIALES UNIDAD CANTIDAD P.UNITARIO COSTO

BLUEBOX: ELECTRODO TUNGSTENO AL 2% CERIO Ø 1/8" mm kg 1.000 2.49 2.49

ARGÓN(9m³) u 0.002 122.22 0.20

SUBTOTAL O 2.69
TOTAL COSTO DIRECTO USD (M+N+O) 3.07 100
0.24 7.7214485
ESTOS PRECIOS NO INCLUYEN EL IVA
ANÁLISIS DE PRECIOS UNITARIOS REFERENCIALES
DESCRIPCION: SOLDADURA EN TUBERÍA DE COBRE 3/4 UNIDAD: pto
ANTORCHA

EQUIPOS CANTIDAD TARIFA COSTO HORA RENDIMIENTO COSTO


HERRAMIENTA MENOR (5% M.O.) 0.04
ANTORCHA VALVULA ENCENDIDO ELÉCTRICO GAS 1.00 4.50 4.50 0.08 0.37

SUBTOTAL M 0.41

MANO DE OBRA CANTIDAD JORNAL COSTO HORA RENDIMENTO COSTO


/HR
PEON (ESTRUC.OCUP.E2) 1 3.55 3.55 0.0250 0.09
MAESTRO DE OBRA(ESTRUC.OCUP.C1) 0.1 3.93 0.39 0.0830 0.03
ALBAÑIL(ESTRUCT.OCUP.D2) 1 3.55 3.55 0.0830 0.29
FIERRERO(ESTRUC.OCUP.D2) 1 3.55 3.55 0.0830 0.29

SUBTOTAL N 0.71

MATERIALES UNIDAD CANTIDAD P.UNITARIO COSTO


VARILLA PLATA 15%- COBRE 85% u 0.300 6.07 1.82

SUBTOTAL O 1.82 100


TOTAL COSTO DIRECTO USD (M+N+O) 2.23 31.868087
0.71
ESTOS PRECIOS NO INCLUYEN EL IVA
ANÁLISIS DE PRECIOS UNITARIOS REFERENCIALES
DESCRIPCION: UNIDAD: pto
SOLDADURA EN TUBERÍA DE COBRE 3/4 - OXICORTANTE

EQUIPOS CANTIDAD TARIFA COSTO HORA RENDIMIENTO COSTO


HERRAMIENTA MENOR (5% M.O.) 0.04
OXICORTANTE GPL 1.00 1.54 1.54 0.08 0.13

SUBTOTAL M 0.16 7.3660714

MANO DE OBRA CANTIDAD JORNAL/HR COSTO HORA RENDIMENTO COSTO


PEON (ESTRUC.OCUP.E2) 1 3.55 3.55 0.0250 0.09
MAESTRO DE OBRA(ESTRUC.OCUP.C1) 0.1 3.93 0.39 0.0830 0.03
ALBAÑIL(ESTRUCT.OCUP.D2) 1 3.55 3.55 0.0830 0.29
FIERRERO(ESTRUC.OCUP.D2) 1 3.55 3.55 0.0830 0.29

SUBTOTAL N 0.71

MATERIALES UNIDAD CANTIDAD P.UNITARIO COSTO


GAS OXIGENO m3 0.030 5.36 0.16
GAS PROPANO m3 0.030 45.00 1.35
VARILLA PLATA 0%-COBRE 100% u 0.300 0.45 0.14

SUBTOTAL O 1.65 100


TOTAL COSTO DIRECTO USD (M+N+O) 2.52 28.203138
0.71
ESTOS PRECIOS NO INCLUYEN EL IVA
ANÁLISIS DE PRECIOS UNITARIOS REFERENCIALES