However, with the soon expected commencement of operation of two new 1320 MW of new HUBCO
Power plant the transmitting capacity of the existing interconnecting line was found to be insufficient
under the N-1 mode of operation of T/ L. Executive CEO suggested a remedial stipulation to the uprising
conundrum by shifting the interconnection point of PQEPC-NKI grid station to the interconnection point
on Jamshoro-Dadu substation interconnecting transmission line. Advantaged location and near vicinity
crossing of the phase two of 500 KV double circuit T/L connecting Jamshoro interconnection point to
Matiari substation made the solution effective and applicable.
The construction of interconnecting Transmission line from Jamshoro interconnection point to Matiari
sub-station is under execution by sub dividing in to three lots .LOT I,II,III. Inspection visit was carried out
to observe and inspect the progress of construction of lot I, II, III. The brief overview of each lot is listed
below categorically,
LOT 1
Total number of towers;146
Tower no 14 is already erected. Due to ROW issue tower No 15 erection was delayed however the
erection is expected to complete tonight.
Stringing ;
Stringing is expected to start tomorrow for setup ranging from T# 40-49. Insulator hanging and
allocation and arrangement of material is in progress. Tomorrow the task is expected to commence with
expectation to be finished in coming three to four days
Stringing of the tower (40-49) was delayed and was expected to start earlier, due to the ROW issue at
tower no 41, however the issue is cleared now and hopefully the work will start tomorrow.
Jumpers/V Assembly of any of the dead towers is not being installed in the span of towers being
stringed i.e. from T# 49-146. The installation of Jumpers on dead towers will commence in two
days.
Normally one or two days are required for the installation of jumpers per dead tower.
Row issues are cleared on all set ups, so tower # 40 till 146 are all clear. All three installments are paid.
ROW issues are persistent on tower no 107,108, due to which the spacers are not installed at the
aforementioned towers.
ROW is the major and problematic enigma faced by the constructor and consultant and acts as a hurdle
and slows down or delays the construction work significantly. ROW charges are divided in to three
categories. The client is supposed to pay three stepwise installments to the PQA to be handed over to
the landowner.
Installments 1 and 2 are paid by the client and there is no issue remaining pertaining to those two,
however the third installment for the stringing process is yet to be paid by NTDC for LOT 3 and thus the
process of stringing is delayed and carried out and snail pace due to lack of payment of third installment.
NTDC should be pushed to clear the payment as early as possible for the frictionless and timely
operation and construction of towers.
CREWS:
Stringing crew: 5
Total Persons in all 5 crews; 85 persons
Total numbers of persons are subdivided in to 5 subgroups or crews and deployed at different locations
mentioned below:
The main problem faced in LOT 1 is non-availability of Compression Dye for the dead end bodies
of shield wire. Shield wire is being pulled presently and the pulling is complete from tower 49 -
146. From tower 90-146 the dead ending of bodies has not been done due to non-availability of
compression dye. The issue was raised to NTDC two weeks ago; however no progress is made on
the issue. The progress of work is hindered by the non-availability of compression dye. The issue
is still lurking and causing the delay in the work completion. NTDC should be pushed to provide
requisite compression Dye as early as possible so the dead ending of bodies of shield wire can
commence.
LOT 2
Total towers; 130
Erected; 129
Foundations 130
Civil work is complete in this LOT .with all the towers erected and foundations being
constructed.
Stringing:
Crew
Stringing crew is deployed currently at T#41-45 for the sacking of the conductor.
Man Power is sufficient in this stringing crew of LOT2.
As mentioned before the interim scheme suggesting the shifting of the interconnection point from NKI
jamshoro T/L to Jamshoro-dadu grid connecting T/L was approved for execution by NTDC. The
intersection point for the Jamshoro –Dadu line lies in the LOT 2. Tower no 80-81 is the intersection point
for the two 500 kv T/L. Two additional towers A1 and A2 are still to be erected in the range of the
interconnection point in lot 2. Towers A1 and A2 require power shutdown for the erection as they are
the interconnection point. Foundations for tower A1 is complete. Preparation for construction of
foundation of A2 is undergoing, the foundation construction will start soon. The erection of these two
towers is expected to be carried out later under the maintenance period with shutdown on the dadu-Jso
T/L. However, no official scheme and plan for the erection of aforementioned towers is finalized yet.
Lot 3
Total number of tower: 70
Erected: 44
Completed 49.25
Conventional foundation =6
Completed=6
Crew
Crew will arrive next week for the starting of stringing of Setup 2
Stringing: