You are on page 1of 1

PROJECT: MODALA LEISURE VILLAGE MALL AND HOTEL

LOCATION: PUROK 5, DOLJO, PANGLAO, BOHOL


CONTRUCTOR: MONOCRETE CONSTRUCTION.INC

DESIGN: 50000 PSI CONCRETING MONITORING FOR HOTEL (5000 PSI)


DATE COVERED MARCH1-31 2018
NO DATE AREA DESIGN LEVEL STRUCTURE EST. VOL (cu.m) ACT. VOL(cu.m) MANPOWER DURATION PRODUCTIVITY RATE UNIT
1 27-Mar-08 TOWER CRANE H3 5000 PSI(ORD) FOUNDATION LEVEL FOOTING 52 46 - - - cu.m/man.hr
2 28-Mar-08 TEMFACIL. 3000 PSI(ORD) FOUNDATION LEVEL SLAB 12 12 - - - cu.m/man.hr
DATE COVERED APRIL 1-30, 2018
3 16-Apr-18 TOWER CRANE H3 3000 PSI(ORD) FOUNDATION LEVEL RETAINING WALL 1.8 1.8 9 3 0.0666666667 cu.m/man.hr
4 21-Apr-18 OFFICE CR 3000 PSI(ORD) FOUNDATION LEVEL SLAB 0.8 0.8 5 3.68 0.0434782609 cu.m/man.hr
5 28-Apr-18 FOOTING 5000 PSI(ORD) FOUNDATION LEVEL FOOTING & PEDESTAL 8 8 7 1.5 0.7619047619 cu.m/man.hr
6 30-Apr-18 BARRACKS SLAB 3000 PSI(ORD) FOUNDATION LEVEL SLAB 3 3 9 4.5 0.0740740741 cu.m/man.hr
DATE COVERED MAY 1-31, 2018
7 9-May-18 PHASE 1 5000 PSI(ORD) FOUNDATION LEVEL FOOTING 43 40 17 6 0.3921568627 cu.m/man.hr
8 9-May-18 SLAB(CR. BARRACKS) 5000 PSI(ORD) FOUNDATION LEVEL SLAB 2 2 4 1.3 0.3846153846 cu.m/man.hr
9 12-May-18 PEDESTAL @ PHASE 1 5000 PSI(ORD) FOUNDATION LEVEL PEDESTAL 3 3 6 1 0.5 cu.m/man.hr
10 25-May-18 PHASE 1 HOTEL 5000 PSI(ORD) FOUNDATION LEVEL FOOTING 40 40 9 5.4 0.8230452675 cu.m/man.hr
11 31-May-18 PHASE 1 HOTEL 4000 PSI(ORD) FOUNDATION LEVEL COLUMN 5 5 4 1.117 1.1190689346 cu.m/man.hr
DATE COVERED JUNE 1-30, 2018
12 4-Jun-18 PHASE 1 HOTEL 5000 PSI(ORD) FOUNDATION LEVEL FOOTING & PEDESTAL 5 5 5 1 1 cu.m/man.hr
13 8-Jun-18 PHASE 1 5000 PSI(ORD) FOUNDATION LEVEL FOOTING & PEDESTAL 22 22 4 0.9667 5.6894589842 cu.m/man.hr
14 12-Jun-18 HOTEL PHSE 1 5000 PSI(ORD) FOUNDATION LEVEL FOOYING & PEDESTAL 14 14 4 2.366 1.4792899408 cu.m/man.hr
15 18-Jun-18 PHASE 2 5000 PSI(ORD) FOUNDATION LEVEL FOOTING 45 40 6 3.2167 2.0725173832 cu.m/man.hr
16 21-Jun-18 PHASE 2 5000 PSI(ORD) FOUNDATION LEVEL MF-7 1 UNIT 15 15 5 0.9833 3.0509508797 cu.m/man.hr
17 23-Jun-18 HOTEL PEDESTAL 5000 PSI(ORD) FOUNDATION LEVEL C-8 4 UNITS & C7 2 UNITS,C7A 1 UNIT 3.5 3.5 5 1.12 0.625 cu.m/man.hr
18 26-Jun-18 PHASE 1 HOTEL 5000 PSI(ORD) FOUNDATION LEVEL (MF-1 & MF-3) FOOTING 32 32 6 5.33 1.0006253909 cu.m/man.hr
DATE COVERED JUNE 1-30, 2018
19 3-Jul-18 PHASE 2 5000 PSI (ORD) FOUNDATION LEVEL FOOTING F-17 4 UNITS 32 30 6 4.833 1.0345541072 cu.m/man.hr
20 4-Jul-18 PHASE 1 5000 PSI (PCD) FOUNDATION LEVEL C-1 4 UNITS 4 4 4 1.08 0.9259259259 cu.m/man.hr
21 6-Jul-18 PHASE 2 5000 PSI (ORD) FOUNDATION LEVEL C1 1 UNIT & F-22 11 10 6 1.7 0.9803921569 cu.m/man.hr
22 6-Jul-18 PHASE 2 5000 PSI (ORD) FOUNDATION LEVEL MF-15 & C8 4 UNIT 33.5 29 6 4.95 0.9764309764 cu.m/man.hr
23 7-Jul-18 PHASE 2 5000 PSI (ORD) FOUNDATION LEVEL MF-6 & F-19 36 34.5 7 5.65 0.8723135272 cu.m/man.hr
24 12-Jul-18 PHASE 2 5000 PSI (PCD) FOUNDATION LEVEL MF-5 & MF-9 41 40 6 7.95 0.8385744235 cu.m/man.hr
25 14-Jul-18 PHASE 2 5000 PSI (PCD) FOUNDATION LEVEL C-6 6 UNITS, C-9 1 UNIT & C-1 3 UNITS 6.5 6.5 6 1.4167 0.7646878897 cu.m/man.hr
26 21-Jul-18 HOTEL 5000 PSI (PCD) FOUNDATION LEVEL PEDESTAL 4 4 5 1.5 0.5333333333 cu.m/man.hr
27 23-Jul-18 HOTEL 5000 PSI (PCD) FOUNDATION LEVEL F.T.B 25 25 6 8 0.5208333333 cu.m/man.hr
28 25-Jul-18 HOTEL 5000 PSI (ORD) FOUNDATION LEVEL FOOTING 21.127 20 7 5 0.5714285714 cu.m/man.hr
29 27-Jul-18 HOTEL 5000 PSI (PCD) FOUNDATION LEVEL F.T.B 20 20 7 5.667 0.5041720235 cu.m/man.hr
30 31-Jul-18 PHASE 2 5000 PSI (PCD) FOUNDATION LEVEL F.T.B-2 & MF-12 20 20 7 3 0.9523809524 cu.m/man.hr
DATE COVERED AUGUST 1-31, 2018
31 6-Aug-18 PHASE 1 5000 PSI (PCD) FOUNDATION LEVEL F.T.B-2 20 20 6 4 0.8333333333 cu.m/man.hr
32 8-Aug-18 PHASE 1 5000 PSI (PCD) GROUND LEVEL C-2 3 UNTIS 8.4 8 6 1.2833 1.0389880257 cu.m/man.hr
33 8-Aug-18 PHASE 1 & PHASE 3 5000 PSI (PCD) FOUNDATION LEVEL F.T.B-2 36 36 7 8.833 0.5822322136 cu.m/man.hr
34 9-Aug-18 PHASE 2 5000 PSI (PCD) FOUNDATION LEVEL F.T.B-2 15 15.5 6 4.1833 0.6175348011 cu.m/man.hr
35 10-Aug-18 PHASE 1 AND 2 5000 PSI (PCD) FOUNDATION LEVEL COLUMN & F.T.B-2 25 25 6 6 0.6944444444 cu.m/man.hr
36 13-Aug-18 PHASE 1 AND 2 5000 PSI (PCD) FOUNDATION LEVEL F.T.B-2 AND COLUMN ( C-2 2 UNITS) 17 17 5 6.167 0.5513215502 cu.m/man.hr
37 16-Aug-18 PHASE 1 & 2 5000 PSI (PCD) FOUNDATION LEVEL/GROUND LEVEL MF-10 &C-7 1 UNIT, C-2 1 UNIT 26 26 5 6.133 0.847872167 cu.m/man.hr
38 18-Aug-18 PHASE 1 5000 PSI (PCD) GROUND LEVEL C-2A 1 UNIT 3.5 3.5 5 0.75 0.9333333333 cu.m/man.hr
39 25-Aug-18 PHASE 1 5000 PSI (PCD) GROUND LEVEL C-1 1 UNIT & C-7 1 UNIT 8 8 5 1.5 1.0666666667 cu.m/man.hr
40 30-Aug-18 PHASE 2 5000 PSI (ORD) FOUNDATION LEVEL MF-8 22 20 8 2.02 1.2376237624 cu.m/man.hr
41 31-Aug-18 HOTEL 5000PSI (PCD) GROUND FLOOR COLUMN 13 cu.m/man.hr
DATE COVERED SEPTEMBER 1-30, 2018
42 4-Sep-18 HOTEL PHASE 1 & PHASE 2 5000PSI (PCD) GROUND FLOOR COLUMN (C-7A, C1 & C8 5 SETS) 16 16 5 4.2 0.7619047619 cu.m/man.hr
43 5-Sep-18 HOTEL PHASE 1 & PHASE 2 5000 PSI (PCD) GROUND FLOOR COLUMN 8 UNITS 8 8 4 1.92 1.0416666667 cu.m/man.hr
44 7-Sep-18 HOTEL PHASE 1 & PHASE 2 5000 PSI (PCD) GROUND FLOOR COLUMN 14.5 14.5 4 4 0.90625 cu.m/man.hr
45 10-Sep-18 HOTEL 5000PSI (PCD) GROUND FLOOR COLUMN 21.5 21.5 6 9 0.3981481481 cu.m/man.hr
46 13-Sep-18 HOTEL 5000PSI (PCD) GROUND FLOOR COLUMN 13 13 4 4.5 0.7222222222 cu.m/man.hr
47 22-Sep-18 HOTEL 5000PSI (PCD) GROUND FLOOR COLUMN 5 5 6 3 0.2777777778 cu.m/man.hr
48 28-Sep-18 HOTEL 5000PSI (PCD) GROUND FLOOR COLUMN 7.5 7.5 6 4 0.3125 cu.m/man.hr
49 29-Sep-18 HOTEL 5000PSI (PCD) GROUND FLOOR MAT FOOTING 62.5 62.5 10 10 0.625 cu.m/man.hr
50 cu.m/man.hr

TOTAL 903.127 788.1 AVERAGE 0.9540285687 cu.m/man.hr

DATE COVERED APRIL 1-30, 2018 CONCRETING MONITORING FOR COMMERCIAL (4000 PSI)
1 10-Apr-18 TOWER CRANE F0 5000 PSI(ORD) FOUNDATION LEVEL FOOTING 43 43 - - cu.m/man.hr
2 19-Apr-18 TOWER CRANE F-0 3000 PSI(ORD) FOUNDATION LEVEL RETAINING WALL 1.8 1.8 7 3.5 0.0734693878 cu.m/man.hr
DATE COVERED MAY 1-31,2018
3 23-May-18 CLUSTER 1 W.T 4000 PSI(ORD) FOUNDATION LEVEL WATER TANK SLAB 105 91 18 7.13 0.7090540751 cu.m/man.hr
4 26-May-18 CLUSTER 1 COMM. 5000 PSI(ORD) FOUNDATION LEVEL PEDESTAL 3 3 3 0.6 1.6666666667 cu.m/man.hr
5 31-May-18 CLUSTER 2 COMM. 5000 PSI(ORD) FOUNDATION LEVEL FOOTING 14 14 6 1.75 1.3333333333 cu.m/man.hr
DATE COVERED JUNE 1-30, 2018
6 1-Jun-18 CLUSTER 2 4000 PSI(ORD) FOUNDATION LEVEL FOUNDATION/SLAB 65 65.5 16 8.1667 0.5012734642 cu.m/man.hr
7 6-Jun-18 CLUSTER 2 COMM. 4000 PSI(PCD) FOUNDATION LEVEL RETAINING WALL 88 77 8 16.47 0.5843958713 cu.m/man.hr
8 7-Jun-18 CLUSTER 2 COMM. 4000 PSI(ORD) FOUNDATION LEVEL FOOTING 3 3 5 1.1 0.5454545455 cu.m/man.hr
9 9-Jun-18 CLUSTER 2 4000 PSI(ORD) FOUNDATION LEVEL COLUMN @ W.T.2 4 4 5 1.5 0.5333333333 cu.m/man.hr
10 12-Jun-18 CLUSTER 1 4000 PSI(ORD) FOUNDATION LEVEL FOOTING(f2,f4,f7,f1, 10 units) 6 6 4 0.4667 3.2140561388 cu.m/man.hr
11 12-Jun-18 CLUSTER 2 4000 PSI(ORD) FOUNDATION LEVEL RETAINING WALL 80 70 7 16.4 0.6097560976 cu.m/man.hr
12 14-Jun-18 CLUSTER 2 4000 PSI(PCD) FOUNDATION LEVEL COLUMN & FOOTING (C13 &F1) 4 4 5 1.6 0.5 cu.m/man.hr
13 15-Jun-18 CLUSTER 2 4000 PSI(PCD) FOUNDATION LEVEL COLUMN @ FOOTING (C13 & F1) 6.5 6.5 4 2.33 0.6974248927 cu.m/man.hr
14 19-Jun-18 CLUSTER 2 & CLUSTER 3 4000 PSI(ORD) FOUNDATION LEVEL COLUMN & FOOTING (C15 & F1 & F2) 12 12 6 3.333 0.600060006 cu.m/man.hr
15 19-Jun-18 CLUSTER 1 4000 PSI(PCD) FOUNDATION LEVEL SUSP. SLAB 57 75.5 13 5.1667 1.1240622269 cu.m/man.hr
16 20-Jun-18 TOILET CLUSTER 1 4000 PSI(PCD) FOUNDATION LEVEL COLUMN(C-13 10 UNITS) 7 2.3 6 5.1667 0.0741930697 cu.m/man.hr
17 22-Jun-18 CLUSTER 2 & CLUSTER 3 4000 PSI(ORD) FOUNDATION LEVEL F1, 3 UNITS & C-15 8 UNITS 10.5 10.5 4 2.169 1.2102351314 cu.m/man.hr
18 25-Jun-18 CLUSTER 3 4000 PSI(PCD) FOUNDATION LEVEL COLUMN & FOOTING 5.5 5.5 4 1.13 1.2168141593 cu.m/man.hr
19 26-Jun-18 SUSP. SLAB CLUSTER 2 4000 PSI(PCD) FOUNDATION LEVEL SUSPENDED SLAB 50 48 14 3.9 0.8791208791 cu.m/man.hr
20 27-Jun-18 CLUSTER 1 4000 PSI(ORD) FOUNDATION LEVEL FOOTING (F-5 7 UNITS & F6 1 UNIT) 10 10 6 1.383 1.205109665 cu.m/man.hr
21 27-Jun-18 CLUSTER 3 4000 PSI(ORD) FOUNDATION LEVEL FOOTING (F2 4 UNIT& F4, F3, F1 4 UNITS 7.5 7.5 5 1.217 1.2325390304 cu.m/man.hr
22 28-Jun-18 CLUSTER 3 & CLUSTER 2 4000 PSI(PCD) FOUNDATION LEVEL COLUMN ( C-15, 11 UNITS ) 10 10 6 2.05 0.8130081301 cu.m/man.hr
23 29-Jun-18 CLUSTER 3 & CLUSTER 2 4000 PSI(PCD) FOUNDATION LEVEL COLUMN ( C-15 8 UNITS) 7.5 7.5 5 2.82 0.5319148936 cu.m/man.hr
DATE COVERED JUNE 1-30, 2018
24 3-Jul-18 CLUSTER 1 AND CLUSTER 2 4000 PSI (PCD) FOUNDATION LEVEL C-13 1 UNIT, C-15 1 UNIT, F-6 & F-1 3.5 3.5 4 1.07 0.8177570093 cu.m/man.hr
25 4-Jul-18 CLUSTER 1 4000 PSI (PCD) FOUNDATION LEVEL C-15 4 UNITS 4 4 4 1.02 0.9803921569 cu.m/man.hr
26 6-Jul-18 CLUSTER 1 4000 PSI (PCD) GROUND FLOOR C-13 4 UNITS 1.5 1.5 4 1.2 0.3125 cu.m/man.hr
27 9-Jul-18 CLUSTER 1 4000 PSI (PCD) GROUND FLOOR C-13 12 UNITS 4.5 4.5 5 3.52 0.2556818182 cu.m/man.hr
28 9-Jul-18 CLUSTER 4 & 3 4000 PSI (PCD) FOUNDATION LEVEL FOOTING AND WATER TANK SLAB 75.5 93.5 16 7.25 0.8060344828 cu.m/man.hr
29 10-Jul-18 CLUSTER 3 & CLUSTER 1 4000 PSI (PCD) FOUNDATION LEVEL/GROUND FLR COLUMN C-15 6 UNITS AND C-13 2 UNITS 5.5 5.5 5 3.2 0.34375 cu.m/man.hr
30 12-Jul-18 CLUSTER 3 & CLUSTER 4 4000 PSI (PCD) FOUNDATION LEVEL COLUMN C-16 4 UNITS & C-15 3 UNITS 8.146 8 4 1.5 1.3333333333 cu.m/man.hr
31 16-Jul-18 CLUSTER 4 4000 PSI (PCD) FOUNDATION LEVEL C-15 15 UNITS, RTW-1 79 71 7 6.5 1.5604395604 cu.m/man.hr
32 17-Jul-18 CLUSTER 6 4000 PSI (PCD) FOUNDATION LEVEL SLAB ON GRADE 78 95.5 13 6.8333 1.0750521485 cu.m/man.hr
33 18-Jul-18 CLUSTER 2 AND CLUSTER 3 4000 PSI (PCD) FOUNDATION LEVEL COLUMN AND FOOTING 3 3 5 1.9 0.3157894737 cu.m/man.hr
34 19-Jul-18 PHASE 1 HOTEL 5000 PSI (ORD) FOUNDATION LEVEL FOOTING 15 15 6 3.5 0.7142857143 cu.m/man.hr
35 24-Jul-18 COMMERCIAL 4000 PSI (PCD) GROUND FLOOR COLUMN 3 3 5 1 0.6 cu.m/man.hr
36 25-Jul-18 COMMERCIAL 4000 PSI (PCD) GROUND FLOOR SUSPENDED SLAB 44 50 8 9.5 0.6578947368 cu.m/man.hr
37 30-Jul-18 COMMERCIAL 4000 PSI (PCD) FOUNDATION LEVEL COLUMN&FOOOTING 3.5 3.5 6 2.467 0.2364545332 cu.m/man.hr
38 31-Jul-18 COLUMN 4000 PSI (PCD) FOUNDATION LEVEL COLUMN 4.5 4.5 6 3.683 0.2036383383 cu.m/man.hr
DATE COVERED AUGUST 1-31, 2018
39 3-Aug-18 COLUMN 4000 PSI (PCD) GROUND FLOOR LEVEL COLUMN 3 3 6 1.71667 0.2912615704 cu.m/man.hr
41 7-Aug-18 WATER TANK 4 4000 PSI (PCD) FOUNDATION LEVEL RETAINING WALL 75 71 8 22.867 0.3881138759 cu.m/man.hr
42 11-Aug-18 CLUSTER 2 4000 PSI (PCD) FOUNDATION LEVEL F.T.B-4, C-13 6 UNITS 8.5 8.5 6 7 0.2023809524 cu.m/man.hr
43 13-Aug-18 CLUSTER 2, CLUSTER 1 4000 PSI (PCD) F.T.B-4, C-13 5 UNITS 18 18 5 5.7 0.6315789474 cu.m/man.hr
44 17-Aug-18 CLUSTER 5 4000 PSI (ORD.) FOUNDATION LEVEL W.T. FOUNDATION 105 90 12 9 0.8333333333 cu.m/man.hr
45 18-Aug-18 CLUSTER 2 4000 PSI (PCD) GROUND FLOOR COLUMN (C-15 5 UNITS) 2 2 5 1.33 0.3007518797 cu.m/man.hr
46 20-Aug-18CLUSTER 5 (WATER TANK 4 & 5 COLUMN) & CLUSTER 2 4000 PSI (PCD) GROUND FLOOR/FOUNDATION LEVEL SUSP. SLAB, COLUMN C-15 4 UNITS & C-15 UNIT 61 66 8 23.517 0.3508100523 cu.m/man.hr
47 23-Aug-18 CLUSTER 1 4000 PSI (PCD) FOUNDATION LEVEL F-1 4 UNITS F3 2 UNITS, F-5 1 UNIT & F-4 1 UNIT 6 6 4 1.367 1.0972933431 cu.m/man.hr
48 24-Aug-18 CLUSTER 5 4000 PSI (PCD) FOUNDATION LEVEL WATER TANK 5 RETAINING WALL 84 70 5 5.5 2.5454545455 cu.m/man.hr
49 CLUSTER 1 4000 PSI (PCD) FOUNDATION LEVEL& GROUND FLOOR LEVEL STAIRS & PEDESTAL 10 10 6 1.5 1.1111111111 cu.m/man.hr
50 29-Aug-18 CLUSTER 1, 2, & 3 4000 PSI (PCD) GROUND FLOOR & FOUNDATION SLAB, PEDESTAL & FOOTING TIED BEAM 110 100 16 8.5 0.7352941176 cu.m/man.hr
51 31-Aug-18 CLUSTER 1 4000 PSI (PCD) SECOND FLOOR COLUMN 4.5 4.5
DATE COVERED SEPTEMBER 1-30, 2018
52 7-Sep-18 CLUSTER 1 4000 PSI (PCD) 3RD FLOOR ROOF BEAM 15 15 6 5.833 0.4285959198 cu.m/man.hr
53 11-Sep-18 CLUSTER 2 4000 PSI (PCD) GROUND FLOOR COLUMN & STAIRS 18.5 18.5 6 7.733 0.3987240829 cu.m/man.hr
54 15-Sep-18 CLUSTER 1 4000 PSI (PCD) FOUNDATION FOOTING TIED BEAM 43.5 45 8 4.0833 1.3775622658 cu.m/man.hr
55 18-Sep-18 CLUSTER 2 4000 PSI (PCD) 2ND FLOOR SUSPENDED SLAB 66 63 13 5.633 0.8603149026 cu.m/man.hr
56 18-Sep-18 CLUSTER 1 4000 PSI (PCD) FOUNDATION LEVEL FOOTING TIED BEAM 15 14 7 2.0633 0.9693209906 cu.m/man.hr
57 18-Sep-18 CLUSTER 5, CLUSTER 1, WATER TANK 4 4000 PSI (PCD) GROUND FLOOR SUSPENDED SLAB, S.O.G, COLUMN 79 75 12 5.55 1.1261261261 cu.m/man.hr
58 20-Sep-18 CLUSTER 2 & PHASE 2 (SA KABILA) 4000 PSI (PCD) 2ND FLOOR 9 COLUMN / PHASE 2 8.5 8.5 7 7.733 0.1570264728 cu.m/man.hr
59 22-Sep-18 CLUSTER 2/ 2F 4000 PSI (PCD) 2ND FLOOR 3 COLUMN 30 30 8 10 0.375 cu.m/man.hr
60 22-Sep-18 CLUSTER 3/ FDN 4000 PSI (PCD) FDN 8 FOOTINGS
61 22-Sep-18 CLUSTER 1/ GRND 4000 PSI (PCD) GRND 14 COLUMN
62 22-Sep-18 CLUSTER 3/ FDN 4000 PSI (PCD) FDN 2 PEDESTAL
63 22-Sep-18 WTR TANK 4/ GRND 4000 PSI (PCD) GRND 1 COLUMN
64 24-Sep-18 CLUSTER 2 / 2F 4000 PSI (PCD) 2ND FLOOR BEAM 11 11 4 10 0.275 cu.m/man.hr
65 24-Sep-18 CLUSTER 3/ FDN 4000 PSI (PCD) FDN 6 PEDESTAL
66 24-Sep-18 CLUSTER 1/ GRND 4000 PSI (PCD) GRND 13 COLUMNS
67 24-Sep-18 WTR TANK 4/ GRND 4000 PSI (PCD) GRND
68 25-Sep-18 CLUSTER 3 4000 PSI (PCD) 2ND FLOOR TIE BEAM 3 3 3 6 0.1666666667 cu.m/man.hr
69 25-Sep-18 CLUSTER 1 / 2F 4000 PSI (PCD) 2ND FLOOR 1 PEDESTAL #DIV/0! cu.m/man.hr
70 25-Sep-18 WTR TANK 4/ GRND 4000 PSI (PCD) GRND 3 COLUMN #DIV/0! cu.m/man.hr
71 26-Sep-18 CLUSTER 3 4000 PSI (PCD) GRND TIE BEAM CONTINUATION 9 9 4 5 0.45 cu.m/man.hr
72 26-Sep-18 CLUSTER 5 / GRND 4000 PSI (PCD) GRND 5 COLUMN #DIV/0! cu.m/man.hr
73 26-Sep-18 CLUSTER 1 / 2F 4000 PSI (PCD) 2ND FLOOR 1 PEDESTAL #DIV/0! cu.m/man.hr
74 26-Sep-18 CLUSTER 4 4000 PSI (PCD) 2ND FLOOR 8 FOOTING #DIV/0! cu.m/man.hr
#DIV/0! cu.m/man.hr
#DIV/0! cu.m/man.hr
#DIV/0! cu.m/man.hr
PREPARED BY:
DOMINIC A. SALAZAR TOTAL 1718.446 1680.1 AVERAGE 0.8526023872 cu.m/man.hr