Professional Documents
Culture Documents
GROUND ANCHORS
Limelette test field results
VOLUME 1
14 May 2008
Hotel Métropole – Brussels
Ground anchors are commonly used in Belgium in different building and civil
engineering applications (anchorage of retaining walls, submerged structures, quay
walls, stabilisation of slopes, …). Unfortunately, up to now no Belgian geotechnical
standards, which deal with such elements, exist. As a consequence, the project
specifications of different owners integrate generally, without coherence, different
design and test methodologies coming from other countries, mostly from French and
German standards.
In addition a lot of new anchoring techniques, for which the current geotechnical codes
are in general not yet adapted, appeared the last decade on the Belgian market.
Particular situations are those where not all the anchors are tested and/or pre-stressed.
Finally, within the framework of the European standardisation, which is fully
developing, the construction sector experienced a strong need for a better understanding
of the applied anchoring techniques and appropriate design methods, in particular for
the establishment of the Belgian national annex of the Eurocode 7.
All the above-mentioned aspects encouraged the Belgian Building Research Institute
(BBRI - CSTC - WTCB) to undertake the establishment of a uniform guidance for the
execution, the design and the testing of anchoring systems in Belgium. In order to
address this issue the BBRI initiated in 2004 a national research project on ground
anchors. The project is guided by an inter-professional Working Group under
supervision of the project partners K.U. Leuven (Prof. J. Maertens) and UCL (Prof. A.
Holeyman). Financial support for the research project has been obtained from the
Belgian Federal Public Service “Economy” and the Belgian Normalisation Institute.
Backbone of the research project is the extended real scale load test campaign on
approximately 50 ground anchors performed at the proof station of the BBRI in
Limelette.
During this symposium the various aspects of this extended load test campaign in
Limelette (B) will be reviewed : soil investigation, anchor installation methods, load
testing and interpretation, as well as observations related to the excavated anchors.
Suggestions for an approach to design and test ground anchors in Belgium following the
Eurocode 7 principles will be put forward.
Moreover attention will be paid to the experience with ground anchors of three main
organisations on the Belgian building market: Tuc Rail, the Federal Public Buildings
Service, and the Ministry of the Flemish community.
Finally three contributions from neighbouring countries (NL, F & DE) will deal with
developments in anchoring techniques and design approaches in their country and/or in
Europe.
It is the hope of the organizers that the results of the Limelette load test campaign and
the discussions held during this international symposium might be of value in the
development of European geotechnical standardization.
ir Maurice Bottiau
ABEF – President
BGGG/GBMS – Vice-President
Franki Foundations Group Belgium – Group Commercial Director
ORGANIZATION
Ir. G. Breyne,
Chairman of the Technical Committee “Structural Work” of the Belgian Building
Research Institute (BBRI) & SERCK
Prof. A. Holeyman
Catholic University of Louvain (UCL)
Ir. N. Huybrechts,
Belgian Building Research Institute (BBRI)
Prof. C. Bauduin
Besix & University of Brussels (VUB)
Ir. M. Bottiau
Chairman of ABEF (Belgian Member Society of EFFC) & Franki Geotechnics B
Prof. J. Maertens
Jan Maertens bvba & Catholic University of Leuven (K.U.Leuven)
Ir. G. Simon
Ministry of Equipment and Transport of the Walloon Region, Geotechnical Direction
Ir. O. Tomboy
Belgian Building Research Institute (BBRI)
WORKING GROUP ‘GROUND ANCHORS’
The BBRI staff, responsible for the research program “ground anchors”, wishes to
thank:
for the development of the inclined CPT device and the performance of the inclined
CPT:
- Ministry of Flanders, MOW, Geotechnics Division
for the organization of the Symposium “Ground Anchors – Limelette test field results”:
- The Symposium Organizing Committee
CONTRIBUTIONS
BBRI BGGG – GBMS
1. INTRODUCTION
When starting the BBRI research program on ground anchors there was a lot of
discussion within the Working Group concerning the types of anchors to be
tested. This was mainly due to the fact that there is no clear definition and/or
classification of ground anchors. So the difference between ground anchors, soil
nails and tension piles is not always clear.
The existing European Standards for ground anchors, micropiles and soil nailing
contain a lot of valuable information. However a lot of cases exist which are not
covered by the existing execution standards and/or by Eurocode 7.
Figure 1: sketch of a ground anchor – details of anchor head and head protection omitted.
Comment :
According to EN 1537 – 1999 a ground anchor has an anchor head, a free anchor
length and a fixed anchor length and has to be subjected to an acceptance test.
General framework and viewpoint with regard to ground anchors, J. Maertens – 14.05.2008
soil nails and tension piles p. 3/9
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
9.3.2.2. Table 1 describes the principal types of soil nail load tests, their
purpose, when they are required and actions to be taken in the event of an non-
compliant test result. Annex A gives guidance on test procedures, acceptance
General framework and viewpoint with regard to ground anchors, J. Maertens – 14.05.2008
soil nails and tension piles p. 4/9
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
criteria and the equipment to be used for soil nail load tests. Table 2 suggests
the frequency of soil nail load tests based on the category of geotechnical
structure.
General framework and viewpoint with regard to ground anchors, J. Maertens – 14.05.2008
soil nails and tension piles p. 5/9
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
In Belgium the following anchor types and installation methods are used
actually:
Comment :
With tendon elements of high tension steel prestressing is always necessary to
limit the deformations . Testing is not always possible. In some cases it is not
possible to fully test ground anchors installed on Berlin walls with laggings of
prefabricated concrete and installed in very soft upper layers.
b) Anchors with tendon elements of low strength steel (= GEWI bars or self
drilling rods) and with a free length:
- Drilling method : double or single rod system.
- Injection :
- double rod system : under pressure
- single rod system : under pressure or gravitary
- sometimes post grouting through self drilling rods (after 1 or 2 hours).
- Testing :
- not always.
- Prestressing:
- not always.
Comment :
With tendon elements of low strength steel it is not necessary to prestress the
ground anchors when certain deformations can be allowed, f.i. for retaining
walls along streets, … .
c) Anchors with tendon elements of low strength steel and without a free length
( = mostly self drilling rods):
- Drilling method : single rod system;
- Injection : under pressure or gravitary;
- Testing : not possible
General framework and viewpoint with regard to ground anchors, J. Maertens – 14.05.2008
soil nails and tension piles p. 6/9
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Comment :
This anchor types should be considered as tension piles (= micropiles working
in tension) or soil nails.
4. PROPOSAL
4.1. Classification
In order to cover all types of ground anchors which are actually installed in
Belgium the following classification is proposed :
- prestressed ground anchors;
- passive ground anchors;
- tension (micro)piles;
- soil nails.
c) Tension Piles:
- tension (micro)piles may have a tendon element of high strength or of low
strength steel;
- they have only a fixed length;
General framework and viewpoint with regard to ground anchors, J. Maertens – 14.05.2008
soil nails and tension piles p. 7/9
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
- the length of the piles is determined in this way that the necessary factor of
safety is available for the overall stability, cfr. figure R 66-1 from EAU
Recommendations.
d) Soil nails:
- soil nails have always a tendon element of low strength steel;
- they have only a fixed length;
- soil nails are used as soil reinforcement and not as anchors.
4.2. Design
The ultimate skin friction over the fixed length is determined taking into account
the applied drilling and injection technique.
The factors of safety to be introduced are determined based on the type and
number of executed tests :
- preliminary tests
- tests on sacrificial anchors
- acceptance tests on working anchors.
General framework and viewpoint with regard to ground anchors, J. Maertens – 14.05.2008
soil nails and tension piles p. 8/9
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
c) Tension piles:
- preliminary tests on sacrificial piles
- suitability tests on sacrificial anchors or on selected working anchors
(provided with a free length for inclined anchors)
- acceptance tests on selected working anchors (provided with a free length
for inclined anchors).
d) Soil nails:
- preliminary tests on sacrificial nails
- suitability tests on sacrificial nails.
5. CONCLUSIONS
In Belgium there is actually a lot of confusion concerning the design of ground
anchors. This is mainly due to the fact that almost always the same design
method is used regardless the installation method and the type and the number of
tests performed.
The information given in the available European Standards is not precise enough
to allow a correct design of all the types of anchors that are actually installed.
In order to obtain a better agreement with the actual daily practice it is necessary
to extend EN 1537 with passive ground anchors and to define in EN 1997 (= EC
7) the safety factors which have to be taken in to account when acceptance tests
are not performed on all working anchors. Further on it is proposed to elaborate
a technical document dealing with the use of tension (micro)piles as anchoring
elements.
General framework and viewpoint with regard to ground anchors, J. Maertens – 14.05.2008
soil nails and tension piles p. 9/9
BBRI BGGG – GBMS
1. INTRODUCTION
Together with the large variety in applications, ground conditions, specific
project demands, local experience, etc. a wide panoply of ground anchor types
has been developed over the last 40-50 years. The developments have meanly
been focussing on:
• improving the soil-anchor interaction, allowing for higher capacities or
shorter anchor lengths
• simplifying, improving or accelerating the installation process
• assuring faster or longer activity of the anchor.
The tendon bond length Ltb (which is the bond length to be considered in the
design) corresponds to the part of the tendon that is bonded directly to the grout
and may be equal to or less than the fixed anchor length depending on location
of the end point of the debonding sleeve.
We also considered the different aspects that may distinguish the anchors :
• The shape and configuration of the anchor : e.g. cylindrical, with bulb(s), with
anchor plate or helix, with one or several tendon elements (multi stage), …
• The nature of the tendon or anchoring body; e.g. steel strands, bars, wires,
tubes, plates, …; glass fibre, …
• The bonding material : cement-grout, mortar, resin, …
• The installation method : drilling tools and auxiliaries, one phase or 2-phase
installation, …
• The grouting method (if any)
• The terms of use : temporary or permanent, recoverable, …
• The method(s) of corrosion protection
• Prestressed or not
• The method of anchor-soil interaction.
The proposed classification is given in Figure 3, which starts from the latter
aspect, related to the fixation method of the anchor body to the ground. In
parallel, the grouting method (which is an essential influencing factor for the
anchor capacity) as well as the term of use, are incorporated in the classification
scheme.
e.g. strand anchor e.g. Duplex anchor e.g. plate anchor e.g. Grouted screw
threadbar anchor helix anchor anchor
hollow bar anchor expander body
TMD anchor
GROUTING METHODS
TERM OF USE
Temporary Permanent
* remaining in the ground * remaining in the ground
* recoverable
* partially removable (free length)
* entirely removable (free length and bond length)
* destructable
length; the distribution along the bonding length depends on the soil shear-
characteristics (shear stress as a function of displacement) and the anchor
tendon elasticity. When this shear stress has reached the maximum shear
strength and drops to a residual value, progressive debonding occurs as
anchor load increases and the bonding is more and more transferred towards
the distal end of the fixed length. To reduce this detrimental effect of the
progressive debonding, the concept of multiple anchors may be used (Barley,
1997). This system involves the installation of a multiple of unit anchors into
a single borehole. Each unit anchor has its own individual tendon, its own unit
fixed length of borehole, and is loaded with its own unit stressing jack. The
loading of all the unit anchors is carried out simultaneously by a multiple
synchronised jacks which ensures that the load in all unit anchors is always
identical.
• Compressive type anchors also use the shear stress at the grout/ground
interface, but contrary to the tensile type anchors, the total anchor load is
transferred to the very end of the anchor by a central steel tendon which is
fixed to the end cap and the outer steel compression tube. As the elasticity of
this tube and the surrounding grout mantle under compression is smaller than
the elasticity of the steel tendons in tensile type anchors, the distribution of
the bonding stress – initiated at the anchor end – is more uniform than with
tensile type anchors and so the progressive failure effect is less pronounced.
• Plate or helix anchors meanly consist of a steel tendon which transfers the
anchor load to a steel end blade. The anchor load generates compressive
ground pressures at the blade/ground interface which tends to develop a slip
surface in the ground. These anchors also may be called “end bearing”.
Figure 4c and 4d : Anchor-ground interaction for compressive and end bearing type anchors
1. THE DRILLING
Instead of water, also drilling-muds or water-bentonite may be used. In e.g. rock
or hard clays, percussion or rotary-percussion drilling with air pressure is
common.
Figure 6: installation of friction anchors using the very high pressure technique (Jetgrouting)
For specific needs and demands of the client, the anchor tendon can be made
partially or entirely removable, e.g. :
• For threadbars : by using a specific coupler between free length and bond
length or at the anchor foot
• For strands : by incorporating a “weaker” breaking point between free length
and bond length (Figure 9)
Over the free anchor length, the tendon strands or threadbar are surrounded by a
smooth sheathing, often in PVC, to allow for a friction-free extension of the free
tendon length.
Finally, over the free anchor length as well as the bond length, the tendon and its
surrounding first grout mantle, a plastic or steel sheathing for corrosion
protection may be incorporated.
The system takes benefit of the triple use of hollow steel threadbars provided
with a sacrificial drill bit. In fact, the bar elements are used :
• as drill rod
• as injection tube for the water-, air- or grout-flush
• and as final anchor tendon.
As such, the phases 1, 2 and 3 as mentioned above in §5.1 for the “traditional”
installation, are combined in 1 single process step. The continuous thread with
slow pitch can be cut on site to the required segments and easily extended by
screwed couplers. Sheathing assures for the free anchor length (which can be
recovered). (Figures 10a and 10b).
Figure 10a and 10 b: schematical drawing of self boring anchors (DSI and Ischebeck)
The outer diameter of the bars typically goes from about 30 mm up to 70 mm.
With steel yield strengths of about 500 to 600 N/mm², the yield load ranges
from about 200 kN up to 1200 kN. The oversized drill bit type is chosen as a
function of the ground conditions.
• the flexibility and simplicity to adjust and assemble the anchor length
• the ability to work with small drill rigs in confined conditions
The drilling method, the type, flow and injection pressure of the flushing
material and the penetration speed (including sometimes a moving up and down
of the bars) shall be chosen adequately in order to stabilize the bore hole and to
minimize soil disturbance and relaxation. After drilling the required anchor
length, cement grout with low W/C ratio (in the order of 0.5) is pumped through
the hollow bar and the drill bit, while the drill hammer continues rotating. It is
claimed that the effect of this grouting in combination with the rotating and
vibrating rods, is similar to a pressure grouting as in the conventional anchor
types.
For temporary duplex anchors, the tie-rod can be easily recovered by simple
unscrewing. In order to make the compression element destructible, the steel
compression tube will not be made in one piece, but of a volley of elements
joined together by point welding only. This fragmented compression tube will
perfectly resist the compression during the post-tensioning, but will easily break
under flexion and future foundation works or earthworks.
The plate surface typically ranges from about 100 cm² up to 1.000 cm²
(exceptionally 2.500 cm²), what corresponds to an equivalent diameter of about
120 mm to 350 mm. The structural strength of the anchor lies in the order of 100
kN up to 400 kN.
The helix diameter ranges between about 150 and 350 mm. The structural
strength of the anchor system goes from about 250 kN through 800 kN.
Diameters of the expanded body commonly ranges from about 400 mm through
800 mm and allows to achieve capacities of 300-800 kN in dense sands.
(Phase 1) The outer casing provided with a spherical drill bit and the drill rod
with a drill head are simultaneously inserted by rotational flush-drilling. The
diameter of the spherical drill bit is only a few mm larger than the outer
diameter casing (e.g. 140mm for a ø133mm casing). The diameter of the drill
head on the drill rod is chosen such as to allow a free movement of the rods
inside the casings.
The spoil and soil cuttings are evacuated to surface by the annular space in
between the casing and the rods. This allows to minimise the bore hole to the
diameter of the casing-bit, and so also to minimise the ground relaxation and
disturbance.
(Phase 2) After reaching final depth, the bore hole is cleaned by intensive
injection of clean water throughout the rods. Next, the same rods are used to
inject the grout, while the rods are systematically recovered. The casings – so far
– are kept in place.
(Phase 3) The anchor body is inserted in the casing, after which the casing is
extracted while additional cement-grout is pumped.
(Phase 1) In the single drill system, only the casings, provided with a spherical
recovered drill bit or with a full-surface sacrificial drill head, are inserted by
rotational flush-drilling. Both drill bit and drill head are only slightly larger than
the casing.
The soil cuttings have now to be evacuated by the outside space between casing
and ground. Generally, the required flow rate and pressure are higher than with
the double drill system. This may lead to an excessive ground transport; beside
the advantage of having as such an increased anchor diameter, the enlarged bore
hole may collapse and result in soil disturbance and subsidence.
(Phase 2) After reaching final depth, the bore hole is cleaned and filled with
grout by means of a flexible that is lowered in the casing.
Compared to the double drill system, the installation procedure is easier and
faster, and therefor also more economical. However, it should not be used for
drilling underneath existing structures or in collapsible soils. The grout
consumption is likely to be higher than in the double system, but the grout
pressure is generally smaller.
(Phase 1) This drilling method differs from the former by the use of a drill rod
with an oversized sacrificial drill head (e.g. drill head of 150mm for rods
90mm). One often uses a stabilising fluid, such as bentonite or cement-
bentonite, to prevent collapse of the bore hole. The ground spoil is evacuated by
the stabilising fluid at low pressures and low flow rate. Consequently, there is no
increased bore hole diameter, nor any risk for instability of the bore hole.
(Phase 4) As the single rod system does not allow for a primary pressure
grouting, a post-grouting is required. One of the methods, referred to as the IRS-
method, is described hereunder.
4. Rammed casing
The casing is provided with a sacrificial end bit which is soil- and watertight.
The casing is driven by high frequency percussion drilling. At final depth, the
casing is internally cleaned with water, the drill bit is disconnected, after which
the further procedure as mentioned in point 3. is followed.
Basically, the soil is not removed but laterally displaced during the driving. This
is beneficial for the grouting effect and the anchor capacity. But because of
inconveniences, such as frequent material brake by hard driving or early driving
stop, the method has lost interest. It only remains frequently and successfully
used in hard clays and soft rocks (e.g. marl, shale, chalk) by using percussion
drilling and air-flush to evacuate the cuttings.
Photo’s 6-1 to 6-4 : Steel TAM for post-grouting in IRS-FR anchor type
The whole is inserted in the bore hole, filled with fresh cement grout. The
casings (if any) are extracted. One allows now for the grout to set, what
generally takes about 12 hours. After that, the post-grouting operation can start.
Therefore, a single packer (in the case of a global post-grouting – IGU-FR) or a
double packer (in the case of the IRS-FR) is used. Photo’s 6-5 and 6-6 show the
packer devices in un-inflated and inflated situation.
The un-inflated double packer is inserted in the grouting tube and positioned in
front of a manchette. The 2 rubber packers are pneumatically inflated by means
and cement-grout is pumped in the closed space in between both packers; this
fresh grout escapes through the manchette openings, breaks the initial grout
mantle and permeates in the surrounding ground. This operation is repeated at
every single manchette.
Photo’s 6-5 and 6-6 : packer for post-grouting in IRS-FR anchor type
7. REFERENCES
Barley, A.D. The single bore multiple anchor system. ICE seminar. London
1997.
EN 1537:1999 Execution of special geotechnical work – Ground anchors. CEN
Samwoo. Company website www.swanchor.com.
1. INTRODUCTION
The Belgian Building Research institute (BBRI) initiated in 2004 a research
program on ground anchors” (BBRI 2004-2008). This research program is
subsidized by the Belgian Federal Public Service ‘Economy’ and the Belgian
standardization institute NBN.
The main objective of the project is the establishment of a uniform guidance for
the execution, the design and the testing of anchoring systems in Belgium. Such
guidance should be complementary to the content of European standards
addressing anchors.
The research program was elaborated under supervision of the project partners
K.U.Leuven (prof. J. Maertens) and UCL (prof. A. Holeyman) and in
collaboration with the inter-professional BBRI Working Group “Ground
anchors”, composed of all relevant parties, the anchorage contractors in
particular.
Within the framework of the project a major real scale load test campaign has
been organized on the Limelette test field.
At this occasion, different types of ground anchors were installed in different
soil layers encountered in Limelette (quaternary loam, heterogeneous clayey
sand and tertiary Bruxellian sand) and load tested.
This contribution gives a general overview of the test campaign, the set up and
its results. Where relevant, reference is made to the other contributions to this
symposium.
Figure 1 gives some typical CPT that have been performed on the ground anchor
test site in Limelette.
Full scale load test program Limelette – N. Huybrechts et al. – 14.05.2008 p. 3/18
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
qc (MPa)
0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44
0
-1
-2
-3
-4 Quaternary loam (silt)
-5
-6
-7
-8 Heterogeneous
-9 clayey sand
-10
-11 Bruxellian tertiary
-12 sand
-13
Relative Depth (R+xxm)
-14
-15
-16
-17
-18
-19
-20
-21
-22
-23
-24
-25
-26
-27
-28
-29
-30
CPT 21
CPT E34
CPT E10
CPT E11
-31
-32
-33
-34
22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1 0
Friction Ratio Rf (%)
Figure 1 : Some typical CPT results on the ground anchor site in Limelette
Full scale load test program Limelette – N. Huybrechts et al. – 14.05.2008 p. 4/18
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
All three layers were found interesting to install and test ground anchors but it
was however decided to operate in two phases.
In phase 1 a preliminary test campaign on 5 classical IGU ground anchors
(Injection Globale et Unique) was performed in 2005. The aim of these
preliminary tests was:
- to have a first estimate of the ultimate anchor capacity in the loam (silt)
layer, for which the grout body is situated at limited depth (± 4m below the
soil surface) , and to verify the total stability of the ground mass above the
anchor during the tests,
- to have a first estimate of the anchor capacity in the dense Bruxellian sand
layer,
- to evaluate the feasibility of the instrumentation principles for strand anchors
that were worked out in the laboratory;
- to evaluate the usefulness of a supplementary extended load tests campaign
on different ground anchor types at the Limelette test site.
Based on the results of the preliminary tests and the discussions in the Working
Group “Ground Anchors”, phase 2 of the test program (extended test campaign)
was established: 49 more anchors of the following anchor types, significant for
the techniques applied on the Belgian market, were installed and load tested (44)
in 2006:
- strand anchors for which the drilling is performed with casing and inner
tubes (IGU or 2T) in Tertiary Bruxellian sand and in a heterogeneous clayey
sand layer
- strand anchors for which the drilling is performed with casing and lost
oversized point (1T) in the Tertiary Bruxellian sand layer
- strand anchors of the previous type but with provision to perform a two stage
post-injection (1T+inj) in Tertiary Bruxellian sand and in the heterogeneous
clayey sand layer
- self boring hollow bar anchors from the Dywidrill type in the Quaternary
loam layer and in Tertiary Bruxellian sand
- self boring hollow bar anchors from the Ischebeck Titan type in Tertiary
Bruxellian sand and in the heterogeneous clayey sand layer.
In Figure 2, the position of the different test anchors is given. With regard to
Figure 2 it should be remarked that:
All the cone penetration tests were performed with an electrical E1 cone. It
concerns also a series of inclined CPT. With regard to the results of these
CPT, reference is made to Volume 2 of the proceedings of this symposium.
The heterogeneous clayey sand layer (see figure 1) was only significantly
present in the zone E5-6 to E12-13.
Full scale load test program Limelette – N. Huybrechts et al. – 14.05.2008 p. 5/18
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
VE15
VE14
E15 E16
E14 E17
VE13 E18
E19
E37 E20
E13 E21
E36 E22
E12
VE12
E23
E16-17
E11
E15
VE11 E35
E1
-1
4- 1 E24
E17-18
6
E18-19
E1
0
5
3
E19-2
-1
-2 1
E1
E10
4
VE10
2-
E2 0
2
1-2
E25
13
E1
E34 1-
3
E2
-2
12
2
E1
E2
0-1 24
E9
1 3- E26
VE9 E2
25
E9 - 4-
10 E2
6 is E27
E2
5-2 -27b
VE8
E8 E33 E8-9 E26
-27
E26 8 bis
E27-2 E28
E7-8 8
E7 E27-2
VE7
E28-29 bis
E6-7 E28-29 E29
E32
E6 E29-30
VE6 E5-6 E30
E30-3
1
E5 E4-5
E31
4
E3-
VE5
-3
E2
E4
VE4
E3
VE3
L3 L2 L1
E2
LCM2 LCM1
VE2
E1
VE1
L4
SCM3 SCM1
L0
SCM2
S1
VE17 S2
8
9 10
VE16 7 VE18
VERTICAL CPTE
6
INCLINED CPTE
Figure 2 : Ground anchor test site Limelette : position of the ground anchors phase 1 (2005);
Phase 2 (2006-2007); Phase 3 (2008) and position of the inclined and vertical CPTE
With the extensive load test program on anchors in Limelette it has been
envisaged to obtain more information with regard to the several aspects and
parameters that are summarised below:
Full scale load test program Limelette – N. Huybrechts et al. – 14.05.2008 p. 6/18
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
3. ANCHOR INSTALLATION
Different types of ground anchors, significant for the systems applied on the
Belgian market, were installed on the Limelette test site. The different systems
are briefly illustrated in the Figures 3 to 5. For a detailed report of the
installation, and the observations and monitoring data during installation,
reference is made to Volume 2 of the proceedings of this symposium.
For a more general overview of ground anchors types, reference is made to the
contribution of F. De Cock (2008) to this volume.
Figure 3 : Installation of IGU anchors – drilling with casing – water flushing via inner tubes –
stepwise grout injection procedure of Lfixed
Full scale load test program Limelette – N. Huybrechts et al. – 14.05.2008 p. 7/18
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Figure 4 : Installation of 1T anchors – drilling with casing only at its end provided with an
oversized lost point – flushing with water
Figure 5 : Installation of SA anchors – drilling with hollow bar at its end provided with an
oversized drill bit – flushing with water- cement mix
Full scale load test program Limelette – N. Huybrechts et al. – 14.05.2008 p. 8/18
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Full scale load test program Limelette – N. Huybrechts et al. – 14.05.2008 p. 9/18
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
110
100
90
80
70
load [% Pp]
60
50
40
30
20
10
0
0 50 100 150 200 250 300 350 400 450 500 550 600
Time [min]
Load level
[% Pp]
# step Datum Step Step Step Step Step Step Step Step
load 1 2 3 4 5 6 7 8
% Pp 10 20 40 50 60 70 80 90 100
Period of
observation 0 60 60 60 60 60 60 60 60
[min](*)
(*)
Reduced period of 30 to 45 min has been generally applied for Steps 1 & 2
Figure 6 : General test scheme Test Method 3 of the prEN ISO 22477-5: MLT-procedure
110
100
90
80
70
load [% Pp]
60
50
40
30
20
10
0
0 20 40 60 80 100 120 140 160 180 200 220 240
Time [min]
Figure 7 : General test scheme Test Method 1 based on prEN ISO 22477-5: cyclic procedure
Full scale load test program Limelette – N. Huybrechts et al. – 14.05.2008 p. 10/18
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
For the maintained load test procedure TM3 it was the aim to obtain anchor
failure in ± 8 load steps, starting from a datum load Pa = Min[50kN;10%Pp],
with Pp the maximum estimated test load.
In reality anchor failures have been obtained after 5 to 15 load steps. This
corresponds with 70 to 150 % of the estimated maximum load.
In general the first two load steps have been reduced to 30 or 45 minutes
For the cyclic load tests, some slight changes have been integrated in the test
procedures TM1 of the PrEN ISO 22477-5 (6 cycles until maximum load). The
magnitude of the load step ΔQ was determined, in order to obtain anchor failure
after ±8 cycles. The duration of the load steps has been based on the evaluation
of the creep (α). Hereby the load was maintained until α was constant.
For the cyclic tested anchors in Limelette, anchor failure was in general obtained
after 7 to 9 cycles.
Two tests have on purpose been performed with a very low number of cycles (5)
and a very high number of cycles (14), in order to evaluate the possible effect of
the number of cycles on the ultimate anchor load.
Figure 8 gives some illustrations from the load test set up for the inclined and
the vertical anchors.
The load was applied by means of hollow hydraulic jacks and transmitted to the
reaction wall (inclined anchors) or bearing plates on the ground surface (vertical
anchors). The force was regulated by means of a high precision PLC-controlled
700 bar hydraulic central of the BBRI. In this way it is possible to ensure a
Full scale load test program Limelette – N. Huybrechts et al. – 14.05.2008 p. 11/18
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
continue regulation of the applied load in a very accurate way (±0.1% of the
maximum jack capacity).
Measurements of the hydraulic jack pressure (digital manometer on hydraulic
central), the applied force (dynamometer), the anchor head displacement
(displacement transducers), and the deformation measurements of the tendon
(strain gauges or extensometer) were automatically and continuously recorded
(each 10 seconds). The displacement of the reference system was regularly
controlled by means of optical measurements.
The results of the load test on each individual anchor is reported in Volume 2 of
the proceedings of this symposium. Figures 9 to 16 illustrate the reported test
results on one anchor.
Full scale load test program Limelette – N. Huybrechts et al. – 14.05.2008 p. 12/18
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
qc (MPa)
0 4 8 12 16 20 24 28 32 36 40 44
0
-1
-2
CPT E36
CPT E14
CPT E13
-3 Ext 5
-4 Ext 6
-5
Relative Depth (R+xxm)
-6
Ext 1
-7
-8
Ext 2
-9 Ext 4
Ext 12
-10
Ext 11
-11
-12
-13
-14
-15
-16
-17
-18
22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1 0
Friction Ratio Rf (%)
Figure 10 : Position of anchor E13-14 with regard to nearby CPT, position of instrumentation
Full scale load test program Limelette – N. Huybrechts et al. – 14.05.2008 p. 13/18
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
1600 160
P_load cell (kN)
1400 P_correlation (kN) 140
1000 100
800 80
600 60
400 40
200 20
0 0
0:00 1:00 2:00 3:00 4:00 5:00 6:00 7:00 8:00 9:00 10:00 11:00 12:00
Time (hours:minutes)
Figure 11 : Time data (each 10 sec.) of Pload cell, hydraulic pressure, and the anchor head
displacement s(mm)
3000
EXT 11
Deformation measurements Lfixed (µstrain)
2700
EXT 12
2400 EXT 4
EXT 2
2100
EXT 1
1800 EXT 6
EXT 5
1500
Theor.
1200
900
600
300
0
0:00 1:00 2:00 3:00 4:00 5:00 6:00 7:00 8:00 9:00 10:00 11:00 12:00
Time (hours:minutes)
Full scale load test program Limelette – N. Huybrechts et al. – 14.05.2008 p. 14/18
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
20
Anchor head displacement s (mm)
40
(a)
60 (b)
(6')
80
100
20
Anchor head displacement s (mm)
40
(a)
60 (b)
80
(6')
100
Full scale load test program Limelette – N. Huybrechts et al. – 14.05.2008 p. 15/18
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
step 2 : 353 kN
step 3 : 469 kN
20 step 4 : 560 kN
step 5 : 650 kN
step 6 : 740 kN
step 7 : 831 kN
40
Anchor head displacement (mm)
step 8 : 918 kN
60
80
100
120
Full scale load test program Limelette – N. Huybrechts et al. – 14.05.2008 p. 16/18
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
5
5' --> 60'
30' --> 60'
4
(6')
3 Pmax
α (mm)
0
0 200 400 600 800 1000 1200 1400 1600
Load Pcorrelation (kN)
5. CONCLUSIONS
This contribution has given a general overview of the set up of a real scale load
test campaign on different ground anchor types in Limelette. It concerns phase
1 (5 preliminary test anchors) and phase 2 (extended test campaign on 44
anchors) in particular. It has been shown that an overall quality control for the
project planning, the anchor installation, and the load testing itself has been
assured in order to obtain test results of high quality. For more details reference
is made to Volume 2 of the proceedings of this symposium.
Finally, a 3rd phase of the test campaign in Limelette has been activated. 8 more
ground anchors have recently been installed (March and April 2008) and will be
load tested in May/June 2008. It concerns 5 self boring hollow bar anchors
performed in sand with intensive percussive drilling and 3 anchors of the IRS
type installed in the loam (silt) layer.
A supplementary Addendum to these Volumes, dealing with the phase 3 load
tests, will be published later.
Full scale load test program Limelette – N. Huybrechts et al. – 14.05.2008 p. 17/18
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
6. REFERENCES
AFNOR 1992, Fondations profondes pour le bâtiment, NFP 11-212, DTU 13.2
Full scale load test program Limelette – N. Huybrechts et al. – 14.05.2008 p. 18/18
BBRI BGGG – GBMS
1. INTRODUCTION
Within the framework of the BBRI Research program on ground anchors and
more specifically at the location of the extended test campaign in Limelette it
was decided to excavate a number of the tested anchors. The main reason for
this decision was:
- to measure the real dimensions and shape of the different anchor types,
- to determine the real position (inclination) of the anchors,
- to observe the effects of post-grouting operations on the shape and the
dimension of the anchor,
- to look at the surface roughness,
- to observe fissuring patterns.
All this information has been analysed in detail and an overview is given in this
contribution. For more details about the results of the investigation, reference is
made to Volume 2 of the proceedings of this symposium.
The further objective of the excavation is to link this detailed information with:
- the anchor installation procedures and the observed installation parameters,
- the nominal values of anchor material and/or drill tools applied on the site,
- the theoretical imposed position of the anchors,
- the results of the anchor load tests.
This integrated analysis is summarized in the contribution of Huybrechts et al.
(2008a) to this volume,
Details about the excavated anchor (types and nominal dimensions) are given in
the Table 1. The symbols used to indicate the different anchor types as well as
details about the different installation procedures are given in Huybrechts et al.
(2008b). With regard to the nominal dimensions, it should be mentioned that
they correspond with the dimensions of the boring tools (casing diameter, drill
bit diameter, and oversized lost point diameter)
VE15
VE14
E15 E16
E14 E17
E18
VE13 E19
E37 E20
E13 E21
E36 E22
E12
VE12 E23
E16-17
E11
E 15
E35
E1
VE11
-16
E24
4- 1
E17-18
E18-19
E1
0
5
3-
E19-2
-2 1
14
E1
E10
2
E2 0
VE10
-1
1-2
E1 E25
3
E34 1-
E2
12
E1
E9 0-1 E26
VE9 1
25
E9- 4-
10 E2
6 E27
E8 E33 25-2
VE8 E 8- E
9
-27
E26 E28
E7-8 8
E7 E27-2
VE7
E6-7 E28-29 E29
E32
E6 E29-30
E5-6 E30
VE6
E30-3
1
E5 E4-5
E31
VE5 4
E3-
-3
E2
E4
VE4
E3
VE3
L3 L2 L1
E2
LCM2 LCM1
VE2
E1
VE1
L4
SCM3 SCM1
L0
SCM2
CPTE
S1
VERTICAL ANCHOR
S2
Particular remarks to be made with regard to the excavation works are the
following:
- the excavation is realised with a crane of CAT 330C type (Figure 3),
- permanent standby of BBRI staff was provided in order to guide the crane
operator, and to avoid damage of the ground anchors (Figure 3),
- the soil in the direct neighbourhood of the anchors was manually removed,
- observations detected during the excavation works were noted by the site
staff.
Due to the limited bending stiffness of the vertical anchors and due to the effect
of load testing on the anchor grout, a lot of material in the free length of the
vertical anchors was lost during the excavation works. In order to limit the loss
of information with regard to Lfree of the vertical anchors, it was decided to
perform as much as possible observations and measurements during the
excavation works and to cut them off at regular levels. This implied that
excavation process was a very delicate operation.
For each excavated anchor a detailed data fiche has been established. This data-
fiche contains all the above-mentioned information. An example is given in
Figures 4 to 6. Each data fiche is incorporated in the Annex F of the Volume 2
of the proceedings of the symposium.
Figure 5: Example of detailed report on excavated anchors: description of the encountered soil,
fissuring patterns and general remarks with regard to the observations
9 -7.8 -5
total station
8 -8.3
-6
-7
7
-8.8 -8
6
pressure sensor CSTC
-9.3 -9
pressure sensor VLAAO
5 free-fixed -10
-9.8
-11.8
-16
0
-17
-1 -12.3
-18
-200 -100 0 100 200
22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1 0
Equivalent radius (mm)
Friction Ratio Rf (%)
Figure 6: Example of detailed report on excavated anchors: measured versus nominal anchor diameter (left) - measured versus theoretical anchor
position (right)
For strands anchors (IGU, 1T, and 1T+inj) transversal (micro-)fissures at regular
distance (±15 à 20 cm) are remarked in several zones of Lfixed. In general the
transition zone Lfixed/Lfree is characterized by transversal and longitudinal grout
cracks, but large differences between individual anchors have been reported.
For all types of anchors with strand tendons, it has been observed that for several
anchors at the physical end of the tendon a (unreinforced) block of grout is
completely torn off.
Figure 7: Overview of the grout degradation of vertical anchors near the ground surface (left) –
Typical fissuring patterns in Lfixed for strand anchors (right)
In the tertiary sand (Lfixed) - For the IGU systems, the surface shows traces due
to the withdrawal procedure of the casing (Figure 8). A regular shape has also
been observed for the 1T and SA anchors (Figure 8).
Conversely, the 1T-∅red presented a shape by far more irregular than 1T. For the
SA finally, no effect (enlargement) due to the post-injection operation was
observed at the bottom of the anchors.
The effects of post-grouting 1T+inj can be clearly observed; a secondary grout
mantle is present around the anchor body up to 1 m beneath and above the
position of the manchettes, the grout surface is irregular and rough, and grout
vanes on the surface can be observed (Figure 8).
In the (weaker) silt layer - The erosion induced during drilling involved local
large diameters, in particular for 1T and 1T+inj. Unfortunately, little information
is available due to (a) the limited anchors’ excavated length in this layer
(inclined anchors) or (b) the high degradation of the grout in this layer (vertical
anchors)
Finally it should be mentioned that in some zones of the SA anchors’ free length
Lfree some soil inclusions have been observed (Figure 9). This is probably due to
the less intensive flushing in Lfree during drilling.
Figure 8. Grout surface for IGU system (left), SA system (centre), and 1T + inj. System (right)
Figure 10. Example of decentred tendons for inclined and vertical anchors
In general, the diameter of the IGU & 2T-grav type anchors is relatively
constant and coincides well with the nominal diameter, except in sand where
local thickenings manifest, probably due to the drilling procedure, e.g. the more
intensive rinsing (moving up & down inner tubes) before a new 2-m length
casing element is added. Those thickenings imply a Dmeas which is somewhat
higher than Dnom.
For the 1T anchors, the diameter remains relatively constant with respect to the
depth and a somewhat higher diameter (±10%) than the nominal one is observed
in the sand layer. However, the average Dmeas of the 1T-∅red anchor in sand, for
which the same drilling procedure as that one for 1T has been applied but with a
reduced casing diameter of 133 mm (instead of 152 mm) and a lost drill point
diameter of 150 mm (instead of 180 mm), is significantly higher (±40%) than
Dnom. From the measurements and observations, it can be concluded that the real
anchor diameter and the obtained anchor shape depends strongly on the flow rate
of the drill fluid and in particular the ratio between flow rate and drilling
diameter. It is obvious that during drilling those parameters determine in a
direct way the (impact) velocity of the drill fluid on the surrounding soil, and are
a determining factor for the amount of soil that is eroded.
For the 1T+inj system that was provided with two post-grouting tubes, the effect
of the post-grouting operations has clearly been observed. The secondary grout
mantel increases significantly the anchor diameter with regard to Dnom. Along
the zone of Lfixed where the manchettes were present, one can observe an
increase of the diameter with 16 % with regard to Dmeas observed for the 1T
system (in sand and in heterogeneous layer)
It is remarkably that for inclined anchors the largest effect of the post-injection
can be observed 0.5 to 1 m beneath the lowest injection point (manchette). After
investigation it has been found that the end of the post-injection tube was still
closed.
14 14 14 14
D meas. D meas. D meas. D meas.
D nom -5.8 D nom -5.8 D nom -5.8 D nom -5.8
13 13 13 13
-6.3 -6.3 -6.3 -6.3
12 12 12 12
4 free-fixed 4 4 4
-10.3 -10.3 -10.3 -10.3
3 3 3 3
-10.8 -10.8 -10.8 -10.8
2 2 2 2
-11.3 -11.3 -11.3 -11.3
1 1 1 1
Figure 11. Dmeas versus Dnom for the inclined IGU anchors in sand (inclination 25°: with regard to the horizontal)
14 14 14 14
D meas. D meas. D meas. D meas.
D nom -5.8 D nom -5.8 D nom -5.8 D nom -5.8
13 13 13 13
-6.3 -6.3 -6.3 -6.3
12 12 12 12
7 7 7 7
-8.8 -8.8 -8.8 -8.8
6 6 6 6
-9.3 -9.3 -9.3 -9.3
5 free-fixed 5 free-fixed 5 free-fixed 5 free-fixed
Dmeas,Lfixed = 1.11* Dnom Dmeas,Lfixed = 1.04* Dnom Dmeas,Lfixed = 1.11* Dnom Dmeas,Lfixed = 1.11* Dnom
Figure 12. Dmeas versus Dnom for the inclined IGU anchors in the heterogeneous clayey sand layer (inclination 25°: with regard to the horizontal)
2 2 2 2
D meas. D meas. D meas. D meas.
D nom D nom D nom D nom
1 1 1 top 1 top
top
0 0 0 0
top
-1 -1 -1 -1 soil surface
soil surface soil surface
-2 -2 -2
-2
soil surface
-3
-3 -3 -3
-4
-4 -4 -4
-5
-5 -5 -5
-6
-6 -6 -6
-7
-7 -7 -7
-8 free-fixed
free-fixed -8
Relative Depth (R+xxm)
-8
Equivalent radius (mm) Equivalent radius (mm) Equivalent radius (mm) Equivalent radius (mm)
Dmeas,Lfixed = 1.09* Dnom Dmeas,Lfixed = 1.01* Dnom Dmeas,Lfixed = 1.02* Dnom Dmeas,Lfixed = 1.04* Dnom
Figure 13. Dmeas versus Dnom for the vertical IGU anchors, Lfixed mainly in sand
2 2
D meas. D meas.
D nom D nom
1 1
top
0 0
top
-1 -1
soil surface
-2 -2
soil surface
-3 -3
-4 -4
-5 -5
-6 -6
-7 -7
-8 -8 free-fixed
-10 -10
-11 -11
-14 -14
-200 -100 0 100 200 -200 -100 0 100 200
Equivalent radius (mm) Equivalent radius (mm)
Figure 14. Dmeas versus Dnom for the vertical 2T-grav anchors, Lfixzd mainly in sand
1T – 25° - Sand 1T-∅red – 25° - Sand 1T+inj – 25° - Heterogen. 1T+inj – 25° - Heterogen.
Dnom = 180 mm Dnom = 150 mm Dnom = 180 mm Dnom = 180 mm
BBRI Research 'Ground anchors' BBRI Research 'Ground anchors' BBRI Research 'Ground anchors' BBRI Research 'Ground anchors'
Anchor E17-18 (Sand 1T-180) Anchor E14-15 (Sand 1T∅red.- Anchor E10-11 (Het. 1T+inj.-180) Anchor E11-12 (Het. 1T+inj.-180)
150)
14 -4.8 14 14 14
D meas. D meas. D meas. D meas.
D nom -5.8 -5,8 -5,8
13 D nom 13 13 13 D nom
D nom
-5.3
-6.3 -6,3 -6,3
12 12 12 12
-5.8
11 11 -6.8 11 -6,8 11 -6,8
-6.3
10 10 -7.3 10 -7,3 10 -7,3
-6.8
9 9 -7.8 9 -7,8 9 -7,8
8 -7.3 8 8 8
-8.3 -8,3 -8,3
7 -7.8 7 7 7
-8.8 -8,8 -8,8
6 -8.3 6 6 6
-9.3 -9,3 -9,3
5 free-fixed 5 free-fixed 5 free-fixed 5 free-fixed
-8.8 -9.8 -9,8
4 4 4 4
-9.3 -10.3 -10,3 -10,3
3 3 3 3
-9.8 -10.8 -10,8 -10,8
2 2 2 2
-10.3 -11.3 -11,3 -11,3
1 1 1 1
Dmeas,Lfixed = 1.12* Dnom Dmeas,Lfixed = 1.41* Dnom Dmeas,Lfixed = 1.24* Dnom Dmeas,Lfixed = 1.16* Dnom
Figure 15. Dmeas versus Dnom for the inclined 1T and 1T-∅red anchors in sand and the inclined 1T+inj anchors in the heterogeneous clayey sand layer (for all
anchors : inclination equals 25° with regard to the horizontal and Dnom corresponds with the diameter of the lost drill point)
2 2 2 2
D meas. D meas. D meas. D meas. top
D nom D nom
1 1 1 top 1 D nom
D nom
top
0 top
0 0 0
soil surface soil surface
-1 -1 -1 -1
soil surface
-2 soil surface
-2 -2 -2
-3 -3 -3 -3
-4 -4 -4 -4
-5 -5 -5 -5
-6 -6 -6 -6
-7 -7 -7 -7
-8 free-fixed -8 -8
free-fixed
-9 -9 -9 -9
Dmeas,Lfixed = 1.07* Dnom Dmeas,Lfixed = 1.08* Dnom Dmeas,Lfixed = 1.28* Dnom Dmeas,Lfixed = 1.30* Dnom
Figure 16. Dmeas versus Dnom for the vertical 1T and 1T+inj anchors with Lfixed mainly in sand (Dnom corresponds with the diameter of the lost drill point)
SA-175-Is – 25° - Sand SA-130-Is – 25° - Sand SA-175-Is – 25° - Heterog. SA-130-Is – 25° - Heterog.
Dnom = 175 mm Dnom = 130 mm Dnom = 175 mm Dnom = 130 mm
BBRI Research 'Ground anchors' BBRI Research 'Ground anchors' BBRI Research 'Ground anchors' BBRI Research 'Ground anchors'
Anchor E03-04 (Sand SA-175-Is) Anchor E13-14 (Sand SA-130-Is) Anchor E06-07 (Heterog. SA-175- Anchor E08-09 (Heterog. SA-130-
Is) Is)
14 14 14 14
D meas. D meas. D meas. D meas.
D nom -5.8 D nom -5.8 D nom -5.8 D nom -5.8
13 13 13 13
-6.3 -6.3 -6.3 -6.3
12 12 12 12
7 7 7 7
-8.8 -8.8 -8.8 -8.8
6 6 6 6
-9.3 -9.3 -9.3 -9.3
5 free-fixed 5 free-fixed 5 free-fixed 5 free-fixed
-9.8 -9.8 -9.8 -9.8
Dmeas,Lfixed = 1.03* Dnom Dmeas,Lfixed = 0.99* Dnom Dmeas,Lfixed = 0.86* Dnom Dmeas,Lfixed = 1.12* Dnom
Figure 17. Dmeas versus Dnom for the inclined self boring hollow bar anchors SA-xx-Is in sand and in the heterogeneous clayey sand layer (for all anchors :
inclination equals 25° with regard to the horizontal and Dnom=xx corresponds with the diameter of the drill bit)
2 2 2
D meas. D meas. D meas.
D nom D nom D nom
1 1 1
0 0 0
-1 -1 -1 top
top top soil surface
soil surface soil surface
-2 -2 -2
-3 -3 -3
-4 -4 -4
-5 -5 -5
-6 -6 -6
-7 -7 -7
free-fixed free-fixed
-8 -8 free-fixed
Figure 18. Dmeas versus Dnom for the vertical self boring hollow bar anchors SA-150-Dy and SA-150-Is, Lfixed mainly in sand (Dnom corresponds with the diameter of
the drill bit)
5-
10-
15-
Figure 20 presents for both anchors the measured diameter as a function of the
length from the anchor bottom. Due to the presence of the ground water level, it
was not possible to excavate the last 50 cm of the anchors. Moreover, the
stability of the surrounding slopes enforced the site staff to stop the excavation
of the anchor A1 at 1.5 m from the bottom. Due to this, the effect of the post-
grouting operation at the anchor bottom could not be observed.
Figure 20 shows that the measured diameter of the anchor is in good agreement
with the nominal diameter (90 mm). A ratio Dmeas,av/Dreal of about 1.1 is found.
180
A1
A2
150
measured anchor diameter [mm]
120
90
60
30
0
0 1 2 3 4 5 6 7 8 9
length from the anchor bottom [m]
Figure 20: Dmeas versus Dnom for the inclined self boring hollow bar anchors SA-90—Is
investigated on the work site of Knokke
Table 2 summarises for each anchor type an overview of the average ratios of
Dmeas/Dnom along Lfixed, that were obtained from the observations in Limelette
and Knokke
From the values in Table 2 and the observations mentioned before the following
conclusions can be drawn:
For the IGU anchors it can in general be concluded that the measured diameter
is somewhat higher than the nominal anchor diameter due to local thickenings
induced during the drilling
For the systems with lost oversized drill point (1T) or drill bit (SA), it can be
concluded that the real anchor diameter Dmeas and the obtained anchor shape
depend strongly on the drilling procedure, i.e. the flow rate of the drill fluid
and/or the ratio between flow rate en drilling diameter in particular. The
comparison between the diameter measured on 1T-∅red and 1T anchors shows
clearly this effect. For SA installed on the Limelette site, it can be stated that the
flow rate (and/or the pressure) of the drill fluid, cement grout in this case, was
probably too low in order to realise an increase of the real anchor diameter with
regard to the drill bit diameter Dnom.
For the 1T+inj system that was provided with two post-grouting tubes, the effect
of the post-grouting operations has clearly been observed. Along the zone of
Lfixed where the manchettes were present, a significant increase of the diameter
up to 30% may be expected with regard to Dnom (in sand and heterog. layer)
Table 2 Overview of the Dmeas/Dnom ratios along Lfixed deduced from the investigated sites
VERTICAL ANCHORS
TYPE Dmeas Dnom Dmeas. / Dnom.
[mm]. [mm]. [-]
IGU 144 140 ± 1.03 (1.00 - 1.08)
1T 194 180 ± 1.08 (1.07 & 1.09)
1T+inj. 233 180 ± 1.29 (1.28 & 1.30)
SA-150 156 150 ± 1.04 (1.03 - 1.07)
INCLINED ANCHORS
IGU 154 140 ± 1.10 (1.04 - 1.14)
1T 201 180 ± 1.12
1T+inj. 216 180 ± 1.20 (1.15 - 1.24)
1T+∅red. 209 150 ± 1.40
SA-90(*) 98 90 ± 1.09
SA-130 136 130 ± 1.05 (0.97 & 1.12)
SA-175 166 175 ± 0.95 (0.86 & 1.04)
(*)
values deduced from the work site in Knokke
These results can be compared with the values in Table 3 that contains data
concerning empirical factors (αEXP) that accounts for an increase of the anchor
dimension in Lfixed with regard to the nominal diameter.
Table 3. Value of the coefficient α commonly used in Belgium [TA 95 (1995) and EBA (2004)]
Soil IRS (after TA 95) IGU (after TA 95) SA (after EBA)
Gravelly sands 1.5 – 1.6 1.2 – 1.3 2.0
Fine to coarse sands 1.4 – 1.5 1.1 – 1.2 1.5
Silt 1.4 – 1.6 1.1 – 1.2
Clay 1.8 - 2 1.2
When comparing the values in Tables 2 & 3, one can concluded that the values
of αEXP obtained from the observations in the framework of the BBRI research
on ground anchors deviate from the literature data, in particular for the self
boring hollow bar anchors.
With regard to those self boring hollow bar anchors, supplementary tests (phase
3) are actually performed on the Limelette test field in order to assess the
influence of the drilling procedure (intensive percussive drilling) on the real
anchor diameter and on the anchor capacity.
During this phase 3 of the test program, IRS anchors were installed in the loam
layer and are actually load tested as well.
In the coming months, some of the IRS and SA anchors installed in the loam
will probably be excavated in order to assess their real dimensions. The results
of these observations will be subject of an addendum to the Volumes of this
symposium.
Finally, based on the observations made in the (clayey) sand layer on IGU
systems and systems with lost point (1T) or drill bit (SA), it is proposed for the
moment to introduce Dnom (diameter of the casing, lost point or drill bit) in the
design.
5. REFERENCES
Huybrechts, N., De Vos, M., Tomboy, O., and Maertens, J. 2008. Integrated
analysis of the anchor load test results in Limelette and suggestions for a
harmonized anchor design and test methodology in Belgium in a EC7
framework, Proceedings of the international symposium on ground anchors,
May 14th 2008, Brussels.
Bustamante, M. & Doix, B. 1985. Une méthode pour le calcul des tirants et des
micropieux injectés, In Bull. liaison laboratoire des Ponts et Chaussées, n° 140,
Nov.-Dec. page 75-92
Annex A
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
A1
Instrumentation : NA
Type : Sand
Soil information
qc,av ,global [MPa] : 20-30
The lengths are given with respect to the retaining wall. The anchor bottom is situated at 8.5 m from the retaining wall.
0 – 7.2 m Yellow/white coloured dune sand Not fissured except at 2.0 m where a
longitudinal fissure occurred.
General comments :
- Visual aspect : relatively straight anchor with some local deviations (picture a)
- Surface shows traces due to the drilling procedure. The traces disappear along the 2
last meters close to the bottom.
- Due to practical reasons, the anchor bottom could not be excavated, no enlargement
due to post-injection could consequently be observed
- Local small enlargement at 3m (picture b)
Picture a Picture b
3
Length from wall (m)
8 assumed
end
A2
Instrumentation : NA
Type : Sand
Soil information
qc,av ,global [MPa] : 20-30
The lengths are given with respect to the retaining wall. The anchor bottom is situated at 8.5 m from the retaining wall.
General comments :
- Visual aspect : relatively straight anchor with some local deviations (picture a)
- Surface shows traces due to the drilling procedure. The traces disappear along the 2
last meters close to the bottom
- Due to practical reasons, the anchor bottom could not be excavated, no enlargement
due to post-injection could consequently be observed
Picture a
3
Length from wall (m)
8 assumed
end
Ir. Noel Huybrechts, Ir. Monika De Vos & Ir. Olivier Tomboy
Belgian Building Research Institute (BBRI)
Geotechnical & Structural Division
1. INTRODUCTION
This contribution summarizes the analysis of the load test results on different
anchor types performed in the framework of phase 1 and phase 2 of the anchor
test campaign in Limelette. In the contributions of Huybrechts & Maertens
(2008) and Tomboy & Huybrechts (2008) to this Volume a general overview
has been given of the anchor installation techniques, the test results and the
observations and measurements on the excavated anchors.
In this contribution it is the objective to summarize the methodology that has
been applied to analyse the test data taking into account all available data and to
formulate some general conclusions with regard to the Limelette anchor test
campaign.
For a detailed report of this integrated analysis, reference is made to Volume 2
of the proceedings of this symposium.
Finally, some suggestions for a harmonised anchor design and test methodology
in Belgium taking into account Eurocode 7 principles and anchor practice in
Belgium are formulated.
Integrated analysis & suggestions for NA-EC7 – N. Huybrechts et al. – 14.05.2008 p. 3/21
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Table 1 : Ultimate anchor load Pu of the anchors tested in Limelette – Pu determined out of
creep curve following prEN 22477-5 conventional criteria α=5 (TM3) or α=2 (TM1)
(*)Preliminary anchors
Integrated analysis & suggestions for NA-EC7 – N. Huybrechts et al. – 14.05.2008 p. 4/21
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
1000
Load (kN)
(increasing)
Pmax
800
Pu
600
400
200
IGU-5m-TM3 IGU-6m-TM3 IGU-4m-TM3 IGU-5m-TM1
0
E16-17 E28-29 E15-16 E27-28 S1 S2 E2-3 E26-27 E4-5 E21-22 E30-31
Figure 1 : Comparison of ultimate anchor load Pu versus maximum applied test load (the value
between brackets equals the time in minutes that Pmax has been maintained before the anchor
failed – when increasing is noted that means that the anchor failed during increasing the load
for the next step – if no value is given than Pmax corresponds with mechanical steel limit or Pu)
Integrated analysis & suggestions for NA-EC7 – N. Huybrechts et al. – 14.05.2008 p. 5/21
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
900
800
700
600
stress (MPa)
500
400
300
Fellenius Ischebeck TITAN 73/45 (A=2260mm²)
Fellenius Dywidrill T76N (A=1900m²)
200
Fellenius strands (A=1057 mm²)
theoretical relationship (E=210 GPa)
100 fy TITAN 73/45
fy T76N
0
0 500 1000 1500 2000 2500 3000 3500 4000 4500
-6
strain (10 )
With this approach the following could be obtained for several anchors;
the friction losses in the free length Lfree, which exist out of internal friction
losses between tendon and plastic tubing and out of friction mobilised along
the outer of the grout column in Lfree
the load distribution in the anchor’s fixed length Lfixed
the mobilisation curves of the unit shaft friction (qsi – curves).
For the anchors installed in the heterogeneous clayey sand and the tertiary sand
layer, this analysis revealed average total friction losses in Lfree of 14% of the
ultimate anchor load Pu for the strand anchors and 19% of Pu for the self boring
hollow bar anchors.
For the anchors installed in loam, the load losses in Lfree corresponding with the
ultimate anchor load Pu have been estimated on 7% (based on limited
information).
For more details with regard to this analysis reference is made to Volume 2 of
the proceedings of this symposium.
Integrated analysis & suggestions for NA-EC7 – N. Huybrechts et al. – 14.05.2008 p. 6/21
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Belgium based on CPT data; i.e. curves from TA95 (CFMS, 1995) for IGU and
IRS anchors and an empirical rule which states that qs=0.0033.qc with a
maximum of 466 kPa.
BBRI project Ground Anchors - Result Limelette qs(qc) in Sand & Heterogeneous layer
1000
qs = [Pu-W tot]/(π.α.Dnom.Lfixed)
IGU-TA95
900 - with real α or average if not available
- with real loss W tot or average if not available IRS-TA95
800 qc/30
IGU-sand-TM3
700 IGU-sand-TM1
IGU-Verticaal-TM3
600 IGU-Verticaal-TM1
qsu (kPa)
IGU-Het.-TM3
500 IGU-Het.-TM1
1T-sand-TM3
400 1T-Dred.-sand-TM3
1T-Verticaal-TM3
300 1T+inj-Verticaal-TM3
1T+inj-Het.-TM3
200 SA-sand-TM3
SA-Verticaal.-TM3
100 SA-Het.-TM3
2T-grav -Verticaal
0
0 4 8 12 16 20 24 28 32 36 40
qc,av (MPa)
Figure 3 : qsu-qc,av for anchors tested in tertiary sand and clayey sand in Limelette – only the
real load on the fixed length is considered (by taking into account friction losses in Lfree and the
real anchor diameter)
300
250
IGU-TA95
200 IRS-TA95
qc/30
qsu (kPa)
150 IGU-silt-TM3
SA150-silt-TM3
100 SA76mm-silt-TM3
qs = [Pu-W tot]/(π.α.Dnom.Lfixed)
50
- with α = 1 for SA and IGU
- with average loss W tot
0
0 2 4 6 8 10
qc,av (MPa)
Figure 4 : qsu-qc,av for anchors tested in silt (loam) in Limelette - only the real load on the fixed
length is considered (by taking into account friction losses in Lfree - α is assumed to be 1)
Integrated analysis & suggestions for NA-EC7 – N. Huybrechts et al. – 14.05.2008 p. 7/21
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Figure 5 : Dmeas versus Dnom for an inclined 1T+inj anchor in the heterogeneous clayey sand
layer and an inclined IGU anchor in the tertiary sand layer - inclination equals 25° with regard
to the horizontal and Dnom corresponds with the diameter of the lost drill point(1T+inj.) or
diameter of the casing (IGU).
Integrated analysis & suggestions for NA-EC7 – N. Huybrechts et al. – 14.05.2008 p. 8/21
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Anchor capacity of the different anchorage systems in sand and clayey sand
From Figure 6, which is an adopted representation of the qsu-qc values from
Figure 3, it can be deduced that, for the anchors of which Lfixed is installed in
clayey sand with average cone resistances qc,av along Lfixed of 12 to 14 MPa and
in tertiary Bruxellian sand with qc,av between 16 and 26 MPa, the following
values of the ultimate global unit shaft friction qsu are obtained for anchors with
Lfixed between 4 to 6 m (after correction for losses in the free length and taking
into account Dreal) :
For the IGU anchors : 0.015qc,av < qsu < 0.030qc,av
For the 1T anchors : 0.013qc,av < qsu < 0.020qc,av
For the SA anchors : 0.015qc,av < qsu < 0.020qc,av
The gravity filled anchors 2T-grav show qsu value in the neighbourhood of
the lower boundaries of 1T and SA anchors at ± 0.013qc,av to 0.015qc,av
The 1T +inj. show qsu value in the neighbourhood of the higher boundary of
the IGU anchors at ± 0.025qc,av to 0.030qc,av
BBRI project Ground Anchors - Result Limelette qs(qc) in Sand & Heterogeneous layer
1000
qs = [Pu-W tot]/(π.α.Dnom.Lfixed) Min.-qc/65
900 - with real α or average if not available Max - qc/33
- with real loss W tot or average if not available Min.-qc/75
800 Max - qc/50
Min.-qc/65
700 Max - qc/50
IGU-sand-TM3
IGU-sand-TM1
600 IGU-Verticaal-TM3
qsu (kPa)
IGU-Verticaal-TM1
500 IGU-Het.-TM3
IGU-Het.-TM1
400 1T-sand-TM3
1T-Dred.-sand-TM3
300 1T-Verticaal-TM3
1T+inj-Verticaal-TM3
1T+inj-Het.-TM3
200 SA-sand-TM3
SA-Verticaal.-TM3
100 SA-Het.-TM3
2T-grav -Verticaal
0
0 4 8 12 16 20 24 28 32 36 40
qc,av. (MPa)
Figure 6 : qsu – qc curves of the anchors tested in clayey sand and sand - – only the real load on
the fixed length is considered (by taking into account friction losses in Lfree and the real anchor
diameter)
Integrated analysis & suggestions for NA-EC7 – N. Huybrechts et al. – 14.05.2008 p. 9/21
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Out of these observations it might be concluded that the 1T and the SA anchors
that have been performed at the Limelette test site can be considered as gravity
filled anchors. This is not surprising when looking at the installation monitoring
of these anchors (almost no pressure during injection).
The fact that for the SA anchors the results can be situated in a narrower interval
is probably due to the very regular form of these anchors (see Tomboy, 2008).
Moreover the high variation obtained for the IGU anchors evidences the effect
of the stepwise grout injection procedure, and the beneficial effect of pressure
grouting on the obtained qs values. It is not surprising that the qsu values of
vertical IGU anchors are situated in the zone of the gravity filled anchors, as it
could in general be observed that the grout injection procedure was not very
successful for the vertical anchors (probably due to the shorter lengths Lfixed and
Lfree). Moreover, the shape of the vertical anchors seems in general to be some
what more regular than the shape of the inclined anchors.
The beneficial effect of pressure grouting and an irregular anchor form on the
anchor capacity is also confirmed by the results obtained for the 1T+inj anchors.
Integrated analysis & suggestions for NA-EC7 – N. Huybrechts et al. – 14.05.2008 p. 10/21
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
For the SA-150-Dy anchors installed with a drill bit with diameter of 150 mm,
the qsu values that are obtained are somewhat lower than those obtained for the
IGU anchors.
Out of the differences between the results of the IGU and the SA-150-Dy
anchors in loam, and out of the observations during installation, one could
conclude that the SA-150 anchors in loam can be considered as gravity filled
anchors and that the grout injection procedure for the IGU anchors show some
beneficial effect but less significant than in sand.
For the SA-76-Dy anchors installed with a drill bit with diameter of 76 mm, the
obtained qs values are ± 50% higher than the SA-150-Dy. As in general it is
assumed that in cohesive layers the unit shaft friction is independent from the
anchor diameter (cfr. Ostermayer & Barley, 2003), especially for gravity filled
anchors, this could possibly indicate that the real diameter is considerably higher
than the nominal drill bit diameter.
Based on this argumentation it can be concluded that the inclination in itself has
no significant influence on the anchor capacity in the Limelette sand layer.
This was also confirmed by the comparison between cone resistances obtained
with vertical and inclined CPT showing no significant differences (See Volume
2 of the proceedings of this symposium).
With regard to the influence of the length on the bond stress, the bond stress
evolution and/or the (non-) linear increase of anchor capacity with Lfixed
Based on the obtained information about bond stress evolution along Lfixed as
deduced from the load distribution measurements (see Volume 2) it can be
concluded that:
For SA anchors with Lfixed up to 6 m in heterogeneous clayey sand and
tertiary sand tested according to the maintained load test procedure (TM3),
the value of the unit shaft friction qsi in the different anchor zones in Lfixed
continue to increase; no peak value and consecutively no residual value of qsi
have been observed. For some of these anchors that did not fail under Pmax
such behaviour was however observed when the anchor was submitted to
subsequent Pa-Pmax cyclic loading.
Integrated analysis & suggestions for NA-EC7 – N. Huybrechts et al. – 14.05.2008 p. 11/21
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
For IGU and 1T anchors in heterogeneous clayey sand and tertiary sand only
limited information was obtained from the measurements, but it is assumed
that the same conclusions as for SA anchors can be drawn.
For IGU anchors in loam (silt) with Lfixed= 5m, that were all tested according
to the maintained load test procedure TM3, measurements on one
preliminary tested strand anchor show that the qsi values of the first part of
Lfixed evolutes to a peak value and drops back to a residual value.
Although observed in a limited way for the more cohesive loam layer, it is
assumed that when anchors are submitted to a maintained load test procedure
(TM3), fixed anchor lengths up to 6m are too short to observe in the soil
layers in Limelette a non-linear increase of anchor capacity with length.
It also assumed that submitting anchors to cyclic testing favours a non-linear
increase of anchor capacity with length; as design methods in the UK and
Germany are calibrated with cyclic test methods, this is probably the reason
that they have introduced a length dependent efficiency factor in their design
(decreasing anchor capacity with length).
With regard to the influence of the test method on the anchor capacity
The maintained load test procedure (Test Method 3 or TM3 according to the
PrEN ISO 22477-5) has been applied as reference test method.
However, some anchors have been tested according to the cyclic test procedure
Test Method 1 (TM1) of PrEN ISO 22477-5. It concerns;
3 inclined IGU anchors in sand
2 vertical IGU anchors in sands
2 inclined IGU anchors in the heterogeneous clayey sand layer
In Table 2 the results of the load tests in terms of an ultimate global unit shaft
friction qsu (corrected for friction losses in Lfree and based on Dreal) and the ratio
with regard to the average cone resistance is given for the anchors tested
according to the TM1 method. In the same table the results of the reference
tests on the similar anchor types tested according to TM3 are also given.
Based on the results in Table 2 the following conclusions can be drawn:
For the IGU anchors in sand the ultimate unit shaft friction qsu for anchors tested
with TM1 is somewhat lower (~6%) than for the anchors tested with the TM3
method. Within the high variation obtained for all IGU anchors, such a
difference can not be considered as significant. This seems not surprisingly for
the Bruxellian sand layer and for limited fixed anchor lengths of 5 m.
Within the anchors tested according to the TM1 method no influence of the
number of cycles on the anchor capacity could be deduced.
For the IGU anchors in the heterogeneous clayey sand layer the difference
between qsu obtained from TM1 versus TM 3 method is higher, even up to 15%.
The more cohesive character of this soil layer could possibly explain such a
difference.
However as mentioned before it should be emphasized that large variations are
obtained for the IGU anchors.
Furthermore, as highlighted before, the ultimate anchor load Pu that has been
considered in this analysis has been determined according to the conventional
creep criteria of the PrEN ISO 22477-5. Analysis has shown that the Pu value
obtained in this way is, in some cases, lower than the ultimate anchor load
Integrated analysis & suggestions for NA-EC7 – N. Huybrechts et al. – 14.05.2008 p. 12/21
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
deduced from an asymptotic approach in the creep curve. This was especially
the case for the anchors installed in the more cohesive layers and the anchors
tested according to the cyclic TM1 method (example see Figure 1).
Table 2 : Comparison of qsu values obtained for IGU anchors tested with TM1 and TM3
With regard to the influence of the anchor diameter on the unit shaft friction
For the SA anchors in sand, different anchor diameters have been realised (Dnom
= 130 mm, 150 mm and 175 mm). Based on the measurements of the real
anchor diameters where it was shown that Dmeas ≈ Dnom and the detailed analysis
of the test results, represented in Figures 3 and 6 it can be concluded that the
obtained ultimate unit shaft friction is independent from the anchor diameters in
this diameter range.
For the SA anchors installed in loam; anchors with Dnom=76 mm and 150 mm
were installed. Assuming Dreal ≈ Dnom, large differences in qs values were
obtained. However these anchors have not been excavated and the real anchor
diameter could not be determined. Anyway, from literature (cfr. Ostermayer &
Barley, 2003) it is assumed that in cohesive soil layers anchor diameter does not
influence the qs value.
The same reference mention however that for pressure grouted anchors realised
in sand the anchor capacity in terms of kN/m is independent from the anchor
diameter (in a range of 100 to 150 mm). This means that qsu decreases with
anchor diameter.
In the Limelette test campaign this parameter has not been investigated for the
IGU anchors in sand.
For the 1T anchors in sand this parameter was introduced but upon excavation it
was shown that, although the drilling was performed with different diameters of
the drill tools, that the real diameter were ± equal, so that no conclusions could
be drawn on that point.
Integrated analysis & suggestions for NA-EC7 – N. Huybrechts et al. – 14.05.2008 p. 13/21
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
With regard to the effectiveness of the free length (Lfree) of self boring hollow
bar anchors (SA)
One of the parameters that has been investigated is the effectiveness of the free
length of the self boring hollow bar anchors. This was questioned, especially
due to the fact that the plastic tubing in Lfree is not continuously present over the
complete length (only between the coupling sleeves) and because grout
infiltration between tendon and plastic tubing is to be expected during
installation.
Based on the results of the load tests on self boring hollow bar anchors and
especially based on the load distribution obtained from the extensometer
measurements it can be concluded that:
For loads up 20 to 30% of Pmax, a relative stiff load-displacement behaviour was
measured. Together with the load distribution measurements it could be
deduced that the load was almost completely transferred to the soil in the free
length of the anchor.
However from that moment it could be deduced from the measurements that the
plastic tubing was detached from the surrounding grout and load was transferred
to the fixed length. This means that the plastic tubing fulfils its role to guarantee
a free anchor length.
The only difference that could be observed compared with the strand anchors,
for which the strands in the free length were greased, is that for the SA anchors
the internal friction between tendon and plastic tubing is ±5% higher.
With regard to the influence of the absence of spacers between the strands.
Some anchors have been installed without spacers between the strands. It
concerns the IGU anchors E09-10 and E07-08 installed in the heterogeneous
clayey sand layer. No influence on tendon-grout bond capacity nor on the
anchor capacity (grout-ground bond) has been observed for these anchors.
Integrated analysis & suggestions for NA-EC7 – N. Huybrechts et al. – 14.05.2008 p. 14/21
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Integrated analysis & suggestions for NA-EC7 – N. Huybrechts et al. – 14.05.2008 p. 15/21
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Acceptance tests
Suitability Design
Investigation tests
tests approach
Active Passive
anchor anchor
Remark that the type and number of anchor tests is an important variable in this
table. Furthermore a difference is made between active anchors and passive
anchors. This anticipates on Belgian practice, in particular on the application of
hollow bar anchors, existing out of steel with considerably lower yield strength
compared to pre-stressed steel, and which are in certain conditions not always
pre-stressed. For passive anchors, also a design situation (6) that is only based
on a calculation rule without any testing at all is proposed.
Integrated analysis & suggestions for NA-EC7 – N. Huybrechts et al. – 14.05.2008 p. 16/21
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
DESIGN APPROACH
qc 1 1 1
Ra , d ≈ α a .α EXP . . . .
η γ Rd ξi γ a
*
p
J CPT results
J values Ra,calc,i
J values
Ra,calib,i = Ra,calc,i / γRd
characteristic value
Ra,k = min (Ra,calib,mean / ξa3 ; Ra,calib,min / ξa4)
γa =f(#Accept. tests)
design value
Ra,d = Ra,k / γa
Figure 7 : Proposal for an approach for the determination of the pull-out resistance
Integrated analysis & suggestions for NA-EC7 – N. Huybrechts et al. – 14.05.2008 p. 17/21
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Integrated analysis & suggestions for NA-EC7 – N. Huybrechts et al. – 14.05.2008 p. 18/21
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
1T-sand-TM3
500 1T-Dred.-sand-TM3
1T-Verticaal-TM3
400 1T+inj-Verticaal-TM3
1T+inj-Het.-TM3
SA-sand-TM3
300 SA-Verticaal.-TM3
SA-Het.-TM3
200 2T-grav -Verticaal
TA 95 - 1.15*IGU
100 TA 95 - 1.15*IRS
qc/30*1.3
NA EC7 - pile
0
EBA Ischebeck (1.5*150kPa)
0 4 8 12 16 20 24 28 32 36 Ostermayer
40 (Lf=4-6m / m.d. to d.)
qc,av. (MPa)
Figure 8 : Comparison of experimental data Limelette anchor test campaign and main rules
found in the literature; – for the experimental data from Limelette only the real load on the
fixed length is considered (by taking into account friction losses in Lfree and the real anchor
diameter)
Integrated analysis & suggestions for NA-EC7 – N. Huybrechts et al. – 14.05.2008 p. 19/21
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
• For the systems with flushing around casing or hollow bar (1T, SA) it has
been observed that the ratio (flow rate drill fluid)/(diameter drill tool)
influences the anchor dimensions, but for the moment it seems very difficult
to quantify this effect in practice.
• A multiplication factor on the diameter (αEXP > 1) may be applied if post-
grouting operations are performed, or if it can be proved by the contractor.
Based on the observations on the 1T+inj anchors in Limelette, it seems
reasonable to propose for each successful injection stage with the simple
serial injection system a factor αEXP ≈ ± 1.10 over the anchor area where the
injection points (manchettes) are present. For the IRS anchors a more
detailed study is necessary. As mentioned before, in phase three of the
anchor test campaign in Limelette, IRS anchors have been installed in the
loam (silt) layer and will probably be excavated soon. These observations
and other experimental data with regard to IRS anchors, a.o. validated in the
TA-95, will be used to determine αEXP factors for IRS anchors.
5. CONCLUSIONS
In this contribution an overview has been given of the methodology to analyse
the results of the anchor load tests (phase 1 and phase 2) on the Limelette test
field. The ultimate skin friction qsu along Lfixed has been deduced taking into
account friction losses in the anchors’ free length and the real anchor diameters.
The results of this analysis have been linked with the anchor execution
parameters and the results of the inclined versus vertical CPT in order to draw
the general conclusions.
Furthermore the principles of a uniform test and design approach for anchors in
Belgium according to Eurocode 7 have been explained.
The principles set out in this contribution take into account the Belgian
anchorage practice on the one hand. On the other hand it is inspired on the
methodology for pile foundations that was recently published in the Belgian
recommendations for the design of axially loaded piles according to EC7
(BBRI, 2008). Herewith it is aimed to obtain a coherent application of the EC7
in Belgium, and to link the safety factors with aspects as quality assurance
during execution and the number of tests on anchors that are performed.
Together with other available test data, a.o. from the third anchor test phase that
is going on for the moment in Limelette, this information will be transmitted to
the Belgian Commission responsible for the establishment of the national annex
(and background documents) of the Eurocode 7.
It is the role of this commission to work out these principles and to propose
values for the different factors.
Integrated analysis & suggestions for NA-EC7 – N. Huybrechts et al. – 14.05.2008 p. 20/21
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
6. REFERENCES
BBRI, 2004-2006 & 2006-2008. Ground Anchors – Establishment of a
standardized design method for ground anchor taking into account execution
methodology. Research program subsidized by the Belgian Federal Public
Service ‘Economy’ and the Belgian standardization institute, Conventions CC
CCN-119 & CC CCN-169
Maekelberg, W., Bollens, Q., Verstraeten, J., Theys, F., De Clercq, E. &
Maertens, J., 2008. Practical Experience of TUC RAIL with Ground Anchors
and Micro-Piles, Proceedings of the international symposium on ground
anchors, May 14th 2008, Brussels
Integrated analysis & suggestions for NA-EC7 – N. Huybrechts et al. – 14.05.2008 p. 21/21
BBRI BGGG – GBMS
Ir Maekelberg Wim
Ir Bollens Quentin
Ir Verstraelen Jan
Ir Theys Frank
Ir De Clercq Eric
1. INTRODUCTION
The latest years, the most important jobsites of TUC RAIL are the realizations
of the high speed railway in Belgium and the regional express network around
Brussels.
The high-speed railway, presently constructed, passes through Belgium and
links Paris-Brussels-Liège-Köln and Paris-Brussels-Antwerp-Amsterdam. At
this moment, the first jobsites of the regional express network around Brussels
are being started. For these projects, new constructions are often realized next to
the existing tracks in service, so special care must be given to the stability of
those tracks.
Soil anchors and micro-piles are often used to limit the deformations of the
retraining walls and to stabilize embankments of pore quality. Furthermore, new
constructions often have to be realized within limited work space, which has an
impact on the installation methods used to install the foundations. As micro-
piles can be installed with little rigs to great depths, these techniques are often
used in those situations.
Soil anchors and micro-piles also have an important implication on the stability
of the construction, so different kinds of in situ-tests are necessary to verify the
calculated bearing capacity and the integrity of those elements.
The results of these tests as well as the applied design methods and some
practical experiences, are discussed in this article.
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 3/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 4/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
When access to the site is difficult, the boom can also be fixed to an excavator,
as shown in photo 2. This gives the ability to work at greater heights and at
further distance from the working platform.
In some cases, the ground anchors and micro-piles are installed by hand, as
shown in photo 3. The boom is fixed to a small and mobile structure.
However ground anchors and micro-piles installed with smaller rigs are limited
in borehole diameter, depth and bearing capacity.
Figure 1a: Rig for installation of ground anchors and micro-piles – Cross section
Figure 1b: Rig for installation of ground anchors and micro-piles – Plan view
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 5/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 6/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 7/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Ground anchors drilled with the dual casing technique can be reinforced with
soft steel rods, S460N, or strands. When strands are used, the free length of each
strand should be sealed within a PVC tubing filled with anti-corrosive grease.
Ground anchors installed with self-boring rods are always reinforced with a
hollow rod in soft steel, S460N. The hollow rods have a continuous thread along
their full length.
Independent of drilling technique, the free length is realized with a smooth PVC
piping across the soft steel reinforcement. For temporary ground anchors, these
smooth pipes can be placed along the reinforcement rods, between the couplers.
The inner diameter of the pipes is a little smaller than the outer diameter of the
couplers, and the length of the pipe is a little longer than the theoretical distance
between the couplers. This ensures a tight seal between the couplers and pipe.
For permanent ground anchors, the smooth pipe needs to be placed continuously
along the reinforcement rod and couplers to avoid long-term corrosion around
both the rods and couplers. The inner annulus of the PVC pipe needs to be filled
with cement fluid or any other corrosion protective material.
For permanent ground anchors, the use of strands is not allowed since the use of
a corrosion protection agent on these strands can lead to an improper installation
and these types of reinforcements tend to fail in a more brittle way and are more
susceptible to corrosion, certainly in railway applications. The strands work as
separate elements, and with corrosion of the strands and failing of one strand,
the force is distributed among the remaining strands, which are also subjected to
corrosion. This can lead to failure of the ground anchor as a whole.
Micro-piles are always reinforced with rods of soft steel, with a continuous
thread along their full length. For permanent micro-piles, a corrugated PVC pipe
is placed along the head of the pile in the fresh cement fluid. The length of this
pipe amounts to 2 m, of which 1,5 m is placed within the fresh cement fluid of
the pile. After execution of the pile, a lowering of the grouted top level can
occur, this has to be replenished within 24h. During replenishment of the micro-
pile, the inner part of the corrugated PVC pipe needs to be filled to a level of 0,5
m above the top of the pile. Both insure that settlements will not cause the hole
to collapse and that the reinforcement rod is grouted along its full length. For
inclined micro-piles, the corrugated PVC pipe aids in protecting the
reinforcement at the pile cut-off level (as shown in figure 2).
When micro-piles are anchored in foundation footings, the corrugated PVC pipe
is cut off at about 10 cm above the bottom level of the footing (see figure 3).
This section is anchored to the foundation footing and presents a corrosion
protection against infiltrating water that is situated beneath the foundation.
For micro-piles which are attached to a wale, the PVC pipe is removed till the
outer limit of the wale (see figure 2).
It is most important to guarantee the grout coverage of the reinforcements. For
this purpose, spacers are used for both permanent and temporary ground anchors
or micro-piles. These are placed every 3 m and must guarantee coverage of at
least 15 mm at the couplers. Minimal coverage at the reinforcement rods or
strands is 25 mm. For permanent ground anchors, the reinforcement is limited to
soft steel to which an excess thickness is added to account for corrosion. This
excess thickness amounts to 2 mm.
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 8/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
After drilling the borehole for the ground anchor or micro-pile with a dual
casing, relaxation of the surrounding soil can occur. This is compensated for by
an injection of cement fluid every 2 m while pulling the casing (IGU, Injection
Globale et Unique sous faible pression, Global and unique injection under low
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 9/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
pressure pi) (0,5pl<pi<pl 2 and pi>1,0 MPa) [2]. Alternatively, IRS injection
(Injection Répétitive et Sélective sous pression élevée, repeatedly and selective
injection under high pressure) (pi>pl and pi<4 MPa) [2] uses specialized
equipment to inject through injection tubes at selected injection sleeves
(manchettes), one by one. This has so far been used only once at sites of TUC
RAIL.
Sometimes, separate injection pipes (min of 2) are added to the reinforcement
with injection openings every 0,5 m, which can’t be individually selected for
injection. This enables a final injection with a minimum of two phases. With this
type of installation, the injection opening with the least resistance will open first,
and others may not open at all. So it can thus not be guaranteed that the injection
is carried out across the entire length of the ground anchor. Since injection is
carried out with a minimum of 2 phases, this technique can only be regarded as
an enhanced IGU injection.
In the case of self-drilling rods, relaxation of the soil around the hole is
compensated for by performing a post-injection through the inner annulus of the
reinforcement rods. This injection is done with a cement fluid with a W/C-ratio
of 0,6 for temporary anchors and 0,5 for permanent anchors. The waiting time
between installing the ground anchor or micro-pile and the post-injection
depends mainly on soil types and length of the ground anchor or micro-pile, and
varies between a minimum of 30 min and a maximum of 3 h.
With every post-injection, it is attempted to inject around 5 l/m of anchor at a
moderate injection rate. The maximum injection pressure is 60 bars. Surface
breakthrough must be avoided during post- injection.
2.4. Applications
Ground anchors and micro-piles are used for various purposes and different
structures, both as temporarily and permanent reinforcements and foundations.
Temporary applications consist mainly of:
Tied-back walls (see figure 4). The primary functions of the ground anchor
are to ensure the stability of the construction and to limit displacements of
the wall as well as the accompanying settlement behind the wall. This is an
important issue next to active railways,
Temporary foundations of a building to allow excavations close to the
building (see figure 5). This is often the case with soil remediation,
Soil nailing for retaining construction pits (see photo 4).
Permanent applications are mainly:
Foundations of bridges and overpasses where limited working space is
available for the installation of piles,
Deepening of foundations and walls (see figure 6),
Tying-back of walls (see figure 7),
Stabilizing existing railway embankments (see figure 4).
2
Pi = injection pressure; pl = Ménard limit pressure (pressiometer)
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 10/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 11/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 12/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 13/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
cases, the use of different types of rigs may become necessary to attain a
feasible design.
E.g. the use of smaller rig may be required to install the first rows of nails in a
deep cut, hereby creating a working platform for bigger rigs to carry out the
remaining part of the installation. These first rows may be installed with manual
equipment, to a limited depth (see photo 3 and figure 8a and b). After
installation of these first rows, a working platform can be created on which a
bigger rig can install longer nails between the shorter, manually installed, nails,
insuring stability of the complete deep cut (see figure 8c). These secondary nails
can be installed with a boom fixed to an excavator, which enables the machine
to reach greater heights. Progressive cuts may make use of more ‘regular’ rigs,
increasing construction efficiency (see figure 8d).
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 14/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Figure 8c: Nailed wall – 2nd phase: nails executed with boom fixed on excavator
Figure 8d: Nailed wall – other phases : nailed installed with ‘normal’rigs
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 15/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
To minimize the risk of failure of the structure, the design of retaining walls has
to ensure that at least 2 ground anchors are placed on each wale. For permanent
ground anchors, the maximum load is limited to about 350 kN per ground
anchor. This way, the structure is anchored by several ground anchors, which
minimizes the effect of failure of one of the ground anchors. The minimum
length of the fixed section of the ground anchor is 4 m.
To determine the free length of a ground anchor, the safety against deep sliding
needs to be determined. The ground anchor is always anchored behind the slip
plane with the lowest safety. In the case of a single row of ground anchors, the
KRANZ method can be used to perform the stability check (see [2], annex 1, pp
117-128). However, the minimal (practical) free length amounts to 3 m.
With micro-piles, the different permanent and variable loads are summed to
obtain a maximum load for each loading condition. This is done by:
For each load condition these maximum loads are compared to the minimal
required resistance of the micro-pile, as indicated in table 1.
In each loading condition, the resistance of the micro-pile requires a specific
factor of safety against failure of the micro-pile.
R Rug Rus
R = u = min( ; ) (3)
S Sg Ss
With
Ru = failure of the ground anchor or micro-pile (kN)
Rug = geotechnical failure resistance of ground anchor or micro-pile
(kN)
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 16/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Rug = α ⋅ Dd ⋅ π ⋅ ∑ Li ⋅ q sui
i (5)
With
α = drill bit diameter expansion factor
Dd = diameter of drill bit (m)
α ⋅ Dd = diameter of drilled hole (m)
Li = fixed length of the ground anchor or micro-pile in the
considered soil (m)
q sui = unit friction resistance of the ground anchor or micro-pile in the
considered soil (kN/m2)
The unit friction resistance q sui is always based on soil investigation. In
Belgium, soil investigation consists mostly of CPT tests. In certain cases, also
pressiometer test results are available. TUC RAIL’s view on soil investigation
was already discussed in W. Maekelberg 2003 [5].
Based on the soil identification obtained through drillings, and the cone
resistance from CPT tests, the unit friction resistance is determined by abacuses
for each soil type [2]. The cone resistance used to determine the unit friction
resistances is an average value for each distinct soil layer. Based on experience
from pull-out tests on ground anchors and micro-piles in similar soil conditions,
these values can be modified.
The α − value to be used depends on soil type and technical installation. Table 2
presents an overview of the α − value as described by TA95 [2].
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 17/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 18/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Table 3: Specific factors of safety against Rug for each load condition
Sg
RULSfundamental 1,40
RSLScharacteristic 1,54 = 1,40 ⋅ 1,10
RSLSpermanent 1,96 = 1,40 ⋅ 1,40
For temporary conditions, the safety factor for the SLS loading condition is
reduced to 1,7 instead of 1,96.
The structural failure resistance Rus of a ground anchor or micro-pile is
determined by the steel section of the reinforcement.
The structural failure resistance is calculated as follows:
Rus = f y ⋅ As (6)
With
fy = elastic limit of steel (N/mm2)
For permanent ground anchors, only soft steel reinforcement is used. The steel
section incorporates an excess thickness of generally 2 mm to account for
corrosion. Up to 4 mm of excess thickness is used for permanent pre-tensioned
ground anchors.
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 19/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 20/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Figure 10a: Reaction device for pull out test – Cross section
Figure 10b: Reaction device for pull out test – plan view
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 21/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Figure 11 shows the test set up for an inclined ground anchor. The load is
applied with a hydraulic piston which is operated manually with a feeding
pump. The flow rate of the pump allows precise control of the applied pressure,
which needs to remain constant during each loading step. Since the difference
between consecutive load steps may be significant in some cases, the use of
electric pumps in parallel with the manual pump is allowed. In any case, the
pumps must avoid any abrupt changes in pressure to occur and certainly any
temporary overloads.
Figure 11: Reaction device for pull out test – ground anchor
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 22/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
with
L free = the free length of the groundanchor (m)
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 23/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 24/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
The first construction phase (1998 – 2001) consists of the realisation of the
tunnel side walls and roof. This was done in two sub phases. As separation
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 25/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
between both work areas, a soil nail reinforced wall is situated across the entire
length between the work area and an active railway between Berchem and
Antwerp station (see figure 13). The soil nails were installed with self-drilling
rods. During the construction, several suitability tests were carried out, and
some installed nails were excavated and measured.
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 26/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
The test-nails have a free length, obtained with a PVC pipe along the first 2 m of
the tie rod. Every test nail had a fixed length of 3 m. Both the free and fixed
lengths are minimal lengths to avoid side effects of the embankment walls (see
figure 13).
The test procedure used was described in paragraph 4. The maximum load was
applied in 8 or 10 steps, each lasting 30 min. A maximum load with a value of 2
times RSLS , or thus the theoretical failure load, was proposed.
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 27/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
the service load. Only when a nail approaches its failure load, the behavior starts
to become more diverse. It can also be noted that elongation of the nail quickly
rises above the elongation of the free length + ½ of the fixed length. This means
that the force in the nail is rather quickly transferred towards the tip of the nail.
Both observations and the failure of the nails clearly shows the importance of
the post-injection to attain the specified ultimate failure resistance, especially
when the nails are placed in loose sands.
Figure 15: Tunnel under Antwerp - Test results – Force displacement diagram
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 28/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 29/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Figure 17a: Tunnel under Antwerp - Excavation of nails – Measured Diameters of nails
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 30/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Figure 17b: Tunnel under Antwerp - Excavation of nails – Shell extent of nails
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 31/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
During the excavation, it could also be noted that the grout in section 2 showed
an inner void between the outer limit and reinforcement (see figure B7 and B8).
Cutting of the nail showed the presence of pure water under pressure, even
though the nails were not drilled through a groundwater table.
These observations can be explained by the fact that a W/C-ratio of 1 is too high
to obtain a solid grout body. The high W/C–ratio causes the cement fluid to
become unstable, and as a result, hardening of the grout causes a decantation of
cement particles. The water filling the void in the first phase, has evacuated
through the outer shell of the grout. The cement shell present at the outer limit
of the void, is caused by the cake formation during drilling of the nail. At the
inside of the rebar, a similar decantation occurred, while the water remained
present until cutting of the nail.
To avoid such voids, the use of a W/C-ratio < 0,70 was advised, as noted in
reference [11]. For loose soils, a W/C-ratio of 0,5 is advised for both the drilling
cement fluid as injected cement fluid.
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 32/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 33/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Figure 18:
Plan of regional network project around Brussels
Embankment
Alluvium
Weathered rock
Figure 19a: CPT-test through existing railway embankment in the vicinity of compressive valley
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 34/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Alluvium
Weathered rock
Figure 19b: CPT-test at the basis of the existing railway embankment in the vicinity of
compressive valley
6.3. Design
The viaduct structure on this main railway, at Ottignies south, is conceived as a
“tunnel in open air”, and consists of 3,4 meters long prefabricated elements of
viaduct, founded on four micro-piles drilled through the embankment and the
alluvial layers and anchored in the rocky, sandy or clayey layers under the
alluvial deposit.
The basic principle of this structure is represented on the cross section in figure
20.
The structure is progressively built “back ahead”, working in consecutive
phases. The elements of this structure are necessary for the stability of the
structure, during construction or in service state. Those elements and their role
are described hereafter:
Berliner retaining wall: In order to be able to build a working platform,
which will become the future foundation of the railway platform, two Berlin
type retaining walls have to be built (see photo 9):
o The wall A, realised in the slope of the embankment, aims to create
the working platform for the execution of the micropiles of the
viaduct.
o The wall B, realised along the existing tracks, aims to retain the
current embankment during earthworks.
In order to realise those walls, HEA soldier piles are placed through the
embankment. The distance between the HEA profiles is 1,7 m for the wall
A, 1,33 m for the Wall B. The sheeting of those walls consists of concrete
flagstone. (see photo 9).
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 35/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 36/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 37/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 38/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
In order to prevent these problems, TUC RAIL required to weld the spacer on to
the rod couplers (see photo 15) and to rotate with a rotational speed of min 120
rpm, or 1,5 rotations per cm. In this way the helical-shaped pile can be avoid
and the total replacement of the drilling mud, cement fluid mixed with soil
particles, by the injection cement fluid can be more guaranteed.
Photo 11: Cross-shaped drill-bit eroded by the drilling through hard rocks (on the right)
compared with unused drill bit
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 39/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Photo 12: Drill bit especially designed for the rock drilling, and furnished with metal sheets to
shear the soft soil layers
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 40/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
7. CONCLUSION
An overview of the practical experiences of TUC RAIL with ground anchors
and micro-piles has been given.
In the vicinity of railways, different design aspects have to be considered. A part
from the calculation of the ground anchors and micro-piles, other design
considerations referring to the feasability of the installations as well as the
different execution details for long term durability of the ground anchors and
micro-piles are taken into account.
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 41/42
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Given the importance of the ground anchors and micro-piles for the stability of
the constructions, different tests are done to guarantee the bearing capacity of
the ground anchors or micro-piles. In two case studies, TUC RAIL’s point of
view is presented. In some cases, excavation of the ground anchors or micro-
piles is done, which leads to a greater understanding of the importance of certain
execution details.
8. REFERENCES
[1] Ground Anchors: Overview of types, installation methods and recent trends,
F. De Cock, Proceedings of International Symposium on Ground Anchors,
Brussels, May 2008
[2] Tirants d’Ancrage, Recommandations T.A. 95, Recommandations
concernant la conception, le calcul, l’exécution et le contrôle, Comité Français
de la Mécanique des Sols et des Travaux de Fondations, Editions Eyrolles, ISBN
2-212-01813-4, 1995
[3] Règles Techniques de Conception et de Calcul des Fondations des Ouvrages
de Génie Civil, Fascicule N° 62 – Titre V, Ministère de l’équipement, du
logement et des transports, Circulaire n° 93-66 du 20 décembre 1993,
[4] Execution of Special Geotechnical Work – Ground Anchors, NBN-EN 1537,
maart 2000,
[5] De grondmechanische aspecten bij de aanleg van de HSL in België, W.
Maekelberg e.a., Proceedings of Conference on Geotechnical Aspects for
Important Projects in Belgium – KVIV september 2003
[6] Essai statique de pieu isolé sous charge axiale, L.C.P.C. (Laboratoire
Central des Ponts et Chaussées-France), februari 1989
[7] Subcommittee on Field and Laboratory Testing - Int. Soc. Soil Mechanics
Foundation Engineering - Axial Pile Loading Test part 1: static Loading-
geotechnical Testing - June 85.
[8] Essai statique de tirants d’ancrage, NF P 94-153, AFNOR, Décembre 1993
[9] Praktische ervaringen met nagels met zelfborende stangen voor de HSL-
werken te Berchem, W. Maekelberg e.a., Proceedings of Innovative conference,
11nd Edition, KVIV november 2001
[10] Projet National Clouterre ; Recommandations CLOUTERRE, pour la
conception, le calcul, l’exécution et le contrôle des soutènements réalisés par
clouage des sols, Presses de l’école nationale des Ponts et Chaussées, 1991.
[11] Verankerungen und vernagelungen im grundbau; Wichter, L en Meiniger,
W. ; Bauingenieur-Praxis ; Ernst & Sohn 2000
Practical experience of TUC RAIL with ground anchors and micro-piles–Maekelberg et al. p. 42/42
BBRI BGGG – GBMS
Annex A
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Practical experience of TUC RAIL with ground anchors and micro-piles Annex A - p. 3/5
Maekelberg et al.
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Figure 17a: Tunnel under Antwerp - Excavation of nails – Measured Diameters of nails
Practical experience of TUC RAIL with ground anchors and micro-piles Annex A - p. 4/5
Maekelberg et al.
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Figure 17b: Tunnel under Antwerp - Excavation of nails – Shell extent of nails
Practical experience of TUC RAIL with ground anchors and micro-piles Annex A - p. 5/5
Maekelberg et al.
BBRI BGGG – GBMS
Annex B
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Practical experience of TUC RAIL with ground anchors and micro-piles p. 3/6
Maekelberg et al.
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Practical experience of TUC RAIL with ground anchors and micro-piles p. 4/6
Maekelberg et al.
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Practical experience of TUC RAIL with ground anchors and micro-piles p. 5/6
Maekelberg et al.
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Practical experience of TUC RAIL with ground anchors and micro-piles p. 6/6
Maekelberg et al.
BBRI BGGG – GBMS
On the one hand, the agency makes studies and builds every year a number of
new buildings, most of the time in an urban environment with all the technical
complications that result from this situation.
On the other hand, the agency also renovates or rebuilds every year a number of
old already existing buildings.
Among the new buildings there are, for instance, the Belgian prisons and
courthouses, the main Brussels museums, office buildings, buildings for the
European Community, all of the European schools, the Belgian buildings for the
international exhibitions in Sevilla, Hannover, Nagoya, Zaragoza and soon in
Shanghai.
Among the old buildings, renovation works have been carried out at the Saint
Michael's cathedral, the arcades of the Jubilee Park, the Palace of Congresses at
the Mont des Arts and even the Lion's Mound on the Hill of Waterloo which has
been consolidated by a whole series of ground anchors.
As you might have guessed when mentioning our activities concerning the
buildings in urban environment, it regularly happens that we have to open an
excavation so that we can place one or more lower ground floors.
This leaves us then with the technique that consist of looking in the ground
external to the excavation for the reaction necessary to maintain the retaining
wall.
Experience with ground anchors of the Federal Public Buildings Service– Ph. Debacker p. 3/15
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
When the floor adjacent to the wall (Figure 2) supports a pavement, a road or
even an average building built on a raft foundation, we are not against the use of
nails combined with a normal wall or even with the technique of guniting
combined with successive excavations. The item of the dimensions of these nails
is nevertheless not relevant for this symposium for two main reasons :
And this leads us finally to the ground anchors that are the subject of this study
day.
During the study that precedes the contracting (Figure 3), we choose the levels
of the different anchoring beds, as a rule ± 1m above the future floors. The
calculation of the wall, which we won’t develop further here, takes into account
the different phases of realization : successive excavations with the
corresponding positions of the anchorages. This way, we obtain for every
anchoring bed a horizontal linear force, expressed in kN/running m (SLS value).
The total quantity of kN thus obtained and expressed in fixed quantities or even
in presumed quantities is the only item of the contract that allows us to pay the
ground anchors. We simply ask the tenderer to commit himself to a unit price : a
certain amount in euros per horizontal kN.
From here, the subcontractor indicated by the awarding Contractor is in charge
of the further dimensioning :
On the basis of this horizontal linear force, this subcontractor chooses:
- the tonnage(s) of his ground anchors
- their angle inclination α
- their free length and their fixed length.
This whole reasoning is freely carried out by the subcontractor who has to
present to the approval of the Buildings Agency, his realization plans
mentioning, for every anchor, its capacity, its inclination, its free length, its fixed
length and its position on the wall.
He therefore uses the results of the in situ soil tests, executed in sufficient
numbers, preceding the tender. These tests are added to the tender file. These in
situ tests are essentially CPT tests. For buildings designed for the European
Communities, we add frequently PMT tests to simplify the price offerings of
non Belgian contractors.
Experience with ground anchors of the Federal Public Buildings Service– Ph. Debacker p. 4/15
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
We think that it’s better to multiply the in situ tests, rather than to take samples
so-called “non reworked” accompanied by tedious and expensive laboratory
tests.
On the other hand, the dimensions of the free length (Figure 4) is justified by the
application of the Krantz method or by every other similar method.
This whole technical procedure linked to the anchors and the corresponding
contractual aspect are the subject of a standard text for Special Specifications
(Figure 5). This text is integrated in the Standard Specifications n° 904 of the
Buildings Agency in the same way as all the other articles concerning the
structuring elements of a construction.
I hereby seize the opportunity to mention that all the texts of the 904, which are
regularly updated, are available for free on the website of the Buildings Agency.
Under the general title – Prestressed ground anchors – there is, in French and in
Dutch, a text for the temporary ground anchors, the definitive ground anchors
and for the possible preliminary tests.
These articles of the Special Specifications find their origins in old documents of
the Ministry of public Works that have been entirely revised and adapted to the
current practices. The French document TA 95 is the main basis for their
drafting.
A particular attention is paid to the tightening of the ground anchors. I will give
you a brief survey of these Special Specifications (Figure 6) : If TS is the
contractual Service Load of the ground anchor (SLS value), the tightening is
carried out in successive stages until reaching 125% of the Service Load TS.
These stages correspond successively to 12.5%, 25%, 50%, 75%, 100% and
finally 125% of TS. At each stage, the load T is measured in the ground anchor
together with the corresponding lengthening Δ L of the extremity of the
reinforcement of the ground anchor. The stopping time at each stage is limited
to the time which is strictly necessary for taking the measurements.
These couples of values ( Δ L, T) are put into a graph. This graph is filled
up with 2 straight lines passing through the origin. The equation of this two lines
is T = AE ΔL
L
AE represents the steel of the ground anchor. L is equal to the free length for the
first straight line and equal to the free length increased by half of the fixed
length for the second straight line.
Experience with ground anchors of the Federal Public Buildings Service– Ph. Debacker p. 5/15
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
This has also allowed us to do without the Acceptance Tests that were formerly
executed on a certain number of ground anchors picked by hazard after the
realization of all the ground anchors.
The last problem to deal with is that of the temporary ground anchors and the
definitive ground anchors.
As a rule, we set aside the definitive ground anchors because you can ask
yourself what the importance is of an anti-corrosion guarantee of 10 or even 20
years for a public building designed to last for at least a hundred years. It is
always possible to let the structure of the ground floors take over the ground
pressures which were initially taken over by the ground anchors. When there’s a
great unbalance in the pressures resulting from a highly inclined site, the use of
buttresses is the only reasonable solution (Figure 7).
Experience with ground anchors of the Federal Public Buildings Service– Ph. Debacker p. 6/15
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Finally, it’s only after a lot of discussions and hesitations that we definitively
kept this temporary ground anchors under pressure.
A last reflection to finish this presentation.
Here is a picture of the head of a ground anchor, taken on a building site (Figure
8).
How can we justify the lack of horizontal stiffeners between the heads of the
ground anchors while the retaining wall executed in contiguous piles doesn’t
allow the flexion in the horizontal plane? Let’s take into account that there is not
any upper connection cross beam put in place before the beginning of the
excavations.
Under the bearing plate, the pressure on the concrete has to be close to its
maximum allowable value. The vertical component of the load in the ground
anchor that equals TS.sin α , seems only to be equilibrated by the concrete
acting under the lateral section of the steel plate.
But all those things are kept in place and that’s for the better; this is the charm of
geotechnics.
Experience with ground anchors of the Federal Public Buildings Service– Ph. Debacker p. 7/15
Figure 1- “Stress method”
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Experience with ground anchors of the Federal Public Buildings Service– Ph. Debacker p. 9/15
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Experience with ground anchors of the Federal Public Buildings Service– Ph. Debacker p. 10/15
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Experience with ground anchors of the Federal Public Buildings Service– Ph. Debacker p. 11/15
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Figure 5- “Standard text of the Buildings Agency Special Specifications (n° 904)”
Experience with ground anchors of the Federal Public Buildings Service– Ph. Debacker p. 12/15
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Experience with ground anchors of the Federal Public Buildings Service– Ph. Debacker p. 13/15
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Figure 7
Experience with ground anchors of the Federal Public Buildings Service– Ph. Debacker p. 14/15
Figure 8 – Anchor Head
Experience with ground anchors of the Federal Public Buildings Service– Ph. Debacker p. 15/15
BBRI BGGG – GBMS
Deurganckdock
Embankment renovation
New lock in Evergem
Projects given in concession by the Flemish government
Port of Genk
Strand anchors
Principle:
Failure of one random anchor may not lead
to the failure of the entire construction.
Specified in tender
Working load
Breaking load
Lock-off load
Anchor type (strands / bar)
Spacing anchors
Minimum steel section
Inclination
Start level grout body
(IRS)
Ir. Inge Mariën
Regional Government of Flanders, Dept. of Mobility and Public Works
Ground anchor design
Suitability tests:
Ground anchors in chalk – bridge in Kanne
Ground anchors for quay walls at the Leie in Kortrijk
4 test anchors
IGU-anchors
Working load = 215 kN
Bond length = 10 m
Suitability test according to
DIN 4125. Extra load levels:
2x, 3x, 3.5x, 4x working
load
90
80
70
Low creep
Displacement (mm)
60
50
40
30
20
No failure at 860 kN
10
ks < 2 mm
0
0 200 400 600 800 1000
Test load (kN)
2 test campaigns:
3 IGU and 6 IRS
Working load = 700 kN
→ Breaking load = 1400 kN
Bond length:
9Anchor 1 IGU = 12 m
9Anchor 2 IGU = 14.5 m
9Anchor 3 IGU = 15 m
9Anchor 3 and 4 IRS = 15 m
9Anchor 5 IRS = 8 m
IRS Anchors 4 and 5: Extra
load levels until 2.25x working
load
Ir. Inge Mariën
Regional Government of Flanders, Dept. of Mobility and Public Works
Ground anchors for quay walls at the Leie in Kortrijk
100
90
80
Displacement (mm)
70
60
50
40
30
Failure at
20
10
700 kN
0
0 100 200 300 400 500 600 700 800
Test load (kN)
250
200
High creep
Displacement (mm)
150
100
Failure at
50
1400 kN
0
0 200 400 600 800 1000 1200 1400 1600
Test load (kN)
250
200
High creep
Displacement (mm)
150
100
No failure
50
at 1400 kN
0
0 200 400 600 800 1000 1200 1400 1600
Test load (kN)
120
100
Displacement (mm)
80 Low creep
60
40
No failure
20 at 1050 kN
0
0 200 400 600 800 1000 1200
Test load (kN)
0.25
0.2
0.15
alfa
0.1
0.05 No failure
at 1575 kN
0
0 0.2 0.4 0.6 0.8 1
T / TP
180
160
140
Displacement (mm)
120
100
80
60 No failure
40 at 1575 kN
20
0
0 200 400 600 800 1000 1200 1400 1600 1800
Test load (kN)
Ir. Ad Vriend
Acécon
Adviesbureau voor funderingstechnieken bv
Dordrecht, The Netherlands
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
ABSTRACT
In The Netherlands there is no specific guideline available for the design and
testing of vertical ground anchors. In daily practice design engineers often make
use of different standards and guidelines related to inclined ground anchors and
micro piles, but in many cases these documents do not cover all specific design
issues essential for vertical ground anchors or could even lead to wrong
conclusions.
This paper describes the highlights of ongoing studies by the Dutch CUR
committee C152 which is responsible for writing a guideline dedicated to the
design, testing and quality control of vertical ground anchors when applied to
support under water concrete slabs against uplift by water pressures.
It must be emphasized that the studies are still ongoing and consequently values
as presented in this paper are to be interpreted as indicative only as they are still
to be determined by the committee for final use.
INTRODUCTION
During the last 10 to 15 years in The Netherlands there has been a strong and
successful increase of applying vertical ground anchors and micro piles as vertical
tensile elements preventing the uplift of under water concrete slabs in building
pits. Most of these tensile elements are well known and commonly practiced in
the application as inclined anchors to support vertical retaining structures. Most of
the experience in both design and execution rests with specialist contractors that
install these ground anchors. In daily practice this is not a real problem as these
contractors are responsible for their own products and after installation, all of
these anchors are subjected to either suitability tests and/or acceptance tests to
prove their capacity. In case of vertical anchors however this is quite different as
in most projects only a small percentage of these anchors can be tested as it is too
expensive and too time consuming to test them all. How to be sure that these
vertical elements do meet their requirements regarding the bearing capacity and
how can that bearing capacity be calculated anyway?
Another difference between inclined ground anchors and vertical anchors is that
the anchors supporting retaining structures can be pre-stressed after being tested
in order to reduce the expected elongation to an acceptable level. Therefore in
most projects the so called axial stiffness of the applied anchors does not play an
important role and if so, counter measures can be taken by choosing a specified
level of pre-stressing. In case of vertical ground anchors however the axial
stiffness plays quite an important role due to it’s relative strong influence on the
behaviour of and development of tensile stresses in the under water concrete slab
that is being supported by these anchors. At the same time most of these relative
slender anchors and micro piles are quite sensible for elongation due to the
economical drive not to put too much steel into the ground. Unfortunately in most
situations pre-stressing of vertical tensile elements is not a realistic option, so
calculation of the rising of the pile head that can be expected when tensile force is
increasing from zero to it’s maximum level has become a critical aspect in the
Design guidelines for non-driven tension piles underneath under water concrete slabs - Developments in
The Netherlands – A. Vriend – 14.05.2008 p. 3/15
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
design. The design of vertical tensile elements and under water concrete is
following quite an interactive procedure.
At the moment there is no specific code or guideline that can be referred to for the
design of these piles and because of the essential differences between inclined and
vertical ground anchors as describe above, there is a strong demand both by
independent design engineers and specialist contractors to develop dedicated
recommendations in which design aspects of both bearing capacity and axial
stiffness are described as well as how to deal with in situ testing and quality
control. The Dutch CUR Committee C152 is now working on these
recommendations and in this paper the most important issues regarding design
and testing are highlighted.
Basically the bearing capacity of a vertical ground anchor and micro pile is
calculated by using the following equation as presented in the Dutch
recommendations CUR 2001-4 “Design rules for tension piles” [1]:
L
Fr ; tension ; max; d = ∫ πφsf 1 f 2αtqc ; red ; ddz (1)
0
where:
Fr;tension;max;d = factored design value of the tension bearing capacity
∅s = diameter of pile shaft or anchor (in case of ground anchors or
micro piles commonly in the range of approximately 150 to 300
mm)
f1 = factor describing the possible positive influence caused by
increased density of the soil layer due to pile installation (in case of
soil displacement piles f1>1.0; in case of anchors f1=1.0)
f2 = factor describing the influence of reduced effective stresses due to
the so called group effect, where piles are positioned with relative
short ctc distances and more or less pulling onto the same sand
particles (depending on ctc distances f2 varies between 1.0 to 0.5 or
even less)
αt = friction factor, different per type of pile or anchor (see below)
qc;red;d = design value for the cone resistance, in which aspects as reduced
effective stresses due to excavation, reduced capacity due to time
depended variation of axial forces as well as a partial material
factor for piles or anchors under tension are taken into account
Design guidelines for non-driven tension piles underneath under water concrete slabs - Developments in
The Netherlands – A. Vriend – 14.05.2008 p. 4/15
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
It must be noted that for slender anchors an additional factor describing the
effectiveness of anchors with a relative long bond length should be taken into
account in the equation as presented above. At the moment in the Dutch design
practice there is no commonly used approach for this aspect, and will be assessed
within the C152 committee.
The determination of values for the friction factor αt for tension bearing capacity
of vertical ground anchors and micro piles as most commonly used in The
Netherlands is still in the process of intensive study within the C152 committee,
where numerous available load testing results are assessed.
The following table presents ranges of indicative values that are generally used
in daily practice (final design values are still to be determined by the C152
Committee).
Table 1. Overview of friction values for different types of ground anchors (indicative only)
Type of ground anchor Friction factor
αt (1), (2)
Traditional bored ground anchor with double casing (overburden flush drilling) 1.5 – 2.0 %
Bored ground anchors using one single casing (percussion flush drilling with lost bit) 2.0 – 2.5%
Self boring anchors 1.0 – 1.5%
Screwed ground anchors 1.0 – 1.5%
(1) It must be noted that values could be well less when no (over)pressure is
being built up during grout injection and formation of the fixed bond length;
under good circumstances higher values can also been found.
(2) Applicable for qc values of max 15 – 20 MPa.
It is essential to realize that the above presented types of anchors all have in
common that they are quite sensitive for the method of pile installation. The man
who is operating the anchor rig is the one who can make or brake the end product;
so the bearing capacity strongly depends on the experience and craftsmanship of
the operator. Of course the human factor is not the only factor that determines the
results, as the specific soil conditions on the site also play a very important role.
When still in the process of making the first design it is therefore recommended to
take a sufficiently safe design value for the friction factor αt;d and we are inclined
to propose to use more or less the average of the above presented values,
depending on the specific type of anchor that is being used in the design.
Once a project is approaching the start of the actual pile installation then we
strongly are in favour of steering in the direction of executing in situ pile tests in
order to determine the actual project specific design value. The proposed design
value can then be verified and, in case of testing up to failure, even be optimized.
For larger projects pile testing should always be a part of the process, but when
having a smaller project one could from an economic point of view choose not to
test but to use a relative safe design value in combination with a somewhat higher
partial safety factor. The values of these partial material factors will depend on
the testing regime that is chosen on the job site; at the moment the C152
Committee is studying the values of these factors and will try to follow the
proposals as specified in the Eurocode.
Design guidelines for non-driven tension piles underneath under water concrete slabs - Developments in
The Netherlands – A. Vriend – 14.05.2008 p. 5/15
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
The C152 committee is still studying how to calculate the axial stiffness, but as
per own experience of the author the following design approach proved to be a
workable method in several large projects.
where:
krep = representative value of the axial stiffness
Frep = representative value of the tension force from the under water concrete
acting on the pile
Δpile head = increase in rise of the anchor head caused by Frep
This approach is valid only for tension forces slowly increasing form 0 to the
unfactored Frep, corresponding with the loading of the tension piles during the
process of pumping the water out of the building pit.
The rise of the anchor head is the cumulative result of the following three
contributing risings:
where:
lelastic = elastic elongation of the anchor
lanchorbody = rising of the anchor along soil particles during mobilisation of friction
lswelling = rising of lower soil layer(s) below toe level of the anchors due to
swelling
The contribution of the elastic elongation can easily be calculated by using the
following equation:
where:
Frep = representative value of the tension force acting on the anchor head
Design guidelines for non-driven tension piles underneath under water concrete slabs - Developments in
The Netherlands – A. Vriend – 14.05.2008 p. 6/15
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Leff = effective length, determined by the level of the anchor plate in the
under water concrete and the level of the so called fictive anchor point
which lies at approximately 1/2th – 2/3rd of the bond length below the
top level of the anchor body
The contribution by the rising of the anchor along the soil particles during
mobilisation of the friction is basically estimated at approximately 1-1.5 mm
when the anchor body is successfully formed by high pressure grouting, to
approximately 3-5 mm when the anchor body is formed under hydrostatic grout
pressures. This includes possible creep which contribution is supposed to be more
or less of minor importance when compared with all other cumulative
contributions in vertical rising, but it must be noted that the aspect of neglecting
the creep is still being studied at.
The contribution by the swelling of soil layer below toe level of the anchors is
more complicated to calculate, and should be dealt with by an experienced
geotechnical engineer. In the situation of only sand layers below toe level then
this contribution is often neglected, but when having a wide excavation and
having a clay layer below toe level then it can give quite a substantial or even
governing contribution. It must be noted however that swelling of a deeper soil
layer(s) is not only influencing the rise of the anchors but also of the surrounding
retaining walls of the building pit so in the end not the total swelling has to be
taken into account but only a differential part.
Within the C152 committee the study on the contributions in the rising of the
anchor head is ongoing and promising results are expected. Complicated though is
the translation form a single anchor to a group of anchors that are influencing
each other.
Design guidelines for non-driven tension piles underneath under water concrete slabs - Developments in
The Netherlands – A. Vriend – 14.05.2008 p. 7/15
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
vertical ground anchors. One disadvantage however is the fact that in most cases
only a relative short fixed bond length can be used in order to be able to bring the
test pile to failure, so it can be questioned if the results are sufficiently
representative when used for longer fixed bond lengths of the actual production
piles.
The C152 committee is now in the process of evaluating and discussing several
testing regimes, but in short the following tests and objectives can be summarized
as presented in the following table.
Testing of vertical ground anchors before the start of the anchor works is not only
important to determine a safe design value for the friction factor, but it also
Design guidelines for non-driven tension piles underneath under water concrete slabs - Developments in
The Netherlands – A. Vriend – 14.05.2008 p. 8/15
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
enables comparison of all items that are relevant for pile installation (grout
injection pressures, volume of injected grout, w/c-factor, type of cement, diameter
drilling bit, diameter bore casing, etc) as registered during installation of the
initial test piles with the actual production piles. By using this information and
following this procedure the quality control can take place during and
immediately after installation of the production piles. In case of doubt over certain
piles, these piles can additionally be subjected to an acceptance test to verify the
load displacement behaviour.
6. CASE STUDY
In the west of The Netherlands as part of a large building pit, more than 700
vertical ground anchors had to be installed in order to prevent uplift of an under
water concrete slab. The vertical ground anchors (Gewi-piles) were installed from
existing ground level using a single casing and percussion flush drilling with a
lost bit. After lowering the tendon into the casing, the fixed bond lengths were
formed by grout injection of at least 5-10 bar and gradual extraction of the casing
at the moment of rapid increase of the torque on the casing which is slowly
turning around during this process.
The relevant specification of the vertical ground anchors and test piles are
presented in figure 1.
Test piles Test piles Pile type Fs;tension;d Gewi bar Diameter anchor Design value friction factor
I, II and III A0, A1, A2 and A3
0.5 m+ 1 1182 kN ∅ 63.5 mm FeB 555/700 ∅s = 200 mm αt = 2.0%
10.4 m-
11.6 m- sand 13.5 m-
clay
16.0 m-
17.5 m-
33.0 m- 33.0 m-
34.75 m-
36.5 m-
Design guidelines for non-driven tension piles underneath under water concrete slabs - Developments in
The Netherlands – A. Vriend – 14.05.2008 p. 9/15
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
to 1800 kN. By using a Gewi+ bar ∅63.5 mm with steel grade SAS 670/800 as
tendon the maximum test load could be increased up to 1910 kN.
Design guidelines for non-driven tension piles underneath under water concrete slabs - Developments in
The Netherlands – A. Vriend – 14.05.2008 p. 10/15
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Contrary to the expectations, all three test piles failed in a much too early stage, at
respectively 977 kN, 1355 kN and 1450 kN. The last load steps during which the
test piles were showing a stable behaviour (creep < 2.0 mm) were at 924 kN, and
1232 kN.
This disappointing result turned out to be caused by the characteristics of the sand
particles in the sand layer between 16.0 m- and 23.0 m- NAP in which the fixed
bond lengths were installed. After receiving a representative borehole description
and by doing some further geological investigation it was concluded that this sand
layer was described as Dune sand consisting of fine to very fine and rounded sand
particles. These specific characteristics could not be derived form the original
CPT, and it became clear that the bore hole data and geological information was
needed to determine the characteristics of this particularly sand layer.
The assumed cause for this low bearing zone effected by pile installation
capacity is hidden in the combination of the
installation process and the specific soil
conditions. During the process of pile
installation a relative thin zone around the
anchor
anchor is effected. At first, during boring of body
the anchor, this zone is slightly loosened
and then by forming the fixed bond length
by grout injection with sufficient grouting
pressures the sand particles are compacted sand surrounding anchor
and voids between the sand particles will
partially be filled with cement.
Figure 3. Effected zone around anchor body
In case of coarse and angled sand particles this zone is then brought back to the
original situation or even better, resulting in a high capacity for transferring shear
stresses to the surrounding sands. However, when having fine and rounded sand
particles this behaviour is different as this zone cannot be brought back to the
original situation due to the lower porosity and the lack of angled particles. The
fine rounded sand particles are not able to mobilise the same amount of friction
between the particles.
6.2 Second series of investigation tests (test piles A1, A2 and A3)
The disappointing results of the first three investigation tests have lead to the
decision to install a second series of three test piles, but then with the fixed length
in the deeper and very dense sand layer below 23.0 m- NAP. In order to have
relative long fixed lengths with toe levels as close as possible to the actual Gewi-
piles that were designed for the building pit, much effort was put into finding
special high capacity steel bars (strands were not favourable due to their relative
high strain that would certainly influence the results). The higher the capacity of
the tension bar the longer the fixed length could be, but on the other hand the
fixed length should not be too long because of the need to load these additional
test piles up to failure. This was not an easy task, but the piling contractor was
lucky in finding bars ∅75 with steel grade St. 835/1030. Based on the maximum
acceptable test load of 3320 kN that could be applied on these bars ∅75 mm, it
Design guidelines for non-driven tension piles underneath under water concrete slabs - Developments in
The Netherlands – A. Vriend – 14.05.2008 p. 11/15
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
was decided to install the 2nd series of test piles with 9.0 meter long fixed lengths.
Failure of these test piles was anticipated not to occur before approximately
2900 to 3100 kN. In this way fixed lengths could be created between 24.0 m- and
33.0 m- NAP which was quite close to the designed toe levels of the actual Gewi-
piles in the building pit (see figure 1) and thus as representative as possible.
During the installation of test piles A2 and A3, which now took place at a
somewhat deeper level of 2.75 m- NAP with freatic ground water table at 3.25 m-
NAP (and with a water head in the deeper sand layer below the clay layer at 0.50
m- NAP) the piling contractor encountered new problems as (due to grout
welling) it turned out to be difficult to build up the essential grout injection
pressure when forming the fixed length from 33.0 m- up to 24.0 m- NAP in the
coarse sand. To overcome this problem the piling contractor did not continue with
further installation of test pile A1, but made some additional trial piles first to the
depth of 33.0 m- NAP. After some successful adjustments the pile installation
procedure was improved leading to an increased and acceptable grout injection
(over)pressures of 4 to 5 bars.
The piling contractor then continued with the successful installation of test pile
A1 and an additional 4th test pile A0.
Testing of these 4 piles of the 2nd series went similar to the first series but then up
to a maximum test load of 3300 kN. Results were more or less in accordance with
expectations: A2 and A3 failed too early at respectively 1910 kN and 2640 kN,
where the other two piles A1 and A0 that were installed using the improved
installation procedure showed good stability even when loaded up to 3300 kN
without any indication of nearby failure.
Test pile A1 (grouting pressures > 5 bar) Test pile A2 (no grouting pressures)
After completion of this 2nd series of investigations tests again additional piles
were installed and tested, giving confirmation of the good results of previous test
piles A1 and A0.
Design guidelines for non-driven tension piles underneath under water concrete slabs - Developments in
The Netherlands – A. Vriend – 14.05.2008 p. 12/15
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
II 5.0 17.5 m- to 22.5 m- 1600 - 1800 kN 1355 kN 1232 kN 230 kN/m2 fine rounded sand
III 5.0 17.5 m- to 22.5 m- 1600 - 1800 kN 1450 kN 1232 kN 260 kN/m2 fine rounded sand
A2 9.0 24.0 m- to 33.0 m- 2900 - 3100 kN 1910 kN 1800 kN 310 kN/m2 no grout pressure
A3 9.0 24.0 m- to 33.0 m- 2900 - 3100 kN 2640 kN 2400 kN 290 kN/m2 no grout pressure
A0 9.0 24.0 m- to 33.0 m- 2900 - 3100 kN > 3300 kN 3300 kN 560 kN/m2 grout pressure 4-6 bar
A1 9.0 24.0 m- to 33.0 m- 2900 - 3100 kN > 3300 kN 3300 kN 540 kN/m2 grout pressure 4-6 bar
(1) Diameter pile shaft in calculation ∅s=200 mm (drill bit ∅=180 mm).
(2) Design values effective shear stress based on last stable load step and after taking into
account estimated friction along free anchor length (respectively: 40 kN, 500 kN, 400 kN, -
kN, 730 kN, 100 kN and 220 kN).
(3) Design of Gewi-piles in building pit based on τd = αt qc;limited = 2,0%x15,0MPa= 300 kN/m2.
Despite the somewhat disappointing results of the bearing capacity in the layer
with fine and rounded dune sands, the underlying very dense layer with coarse
sands provided more than sufficient compensation. Ultimately the proven bearing
capacity was higher than required so the designed Gewi-piles could safely be
installed, provided a good quality control for maintaining the adjusted and
improved installation process.
Recently we received information about another project in the same region where
Gewi-piles were installed by a different piling contractor but in similar soil layers,
and remarkably the same conclusions were drawn on the significant difference in
bearing capacity in the fine and rounded dune sands when compared with the
underlying coarse sands. This confirms the influence of the specific characteristics
of the sand particles.
For design of the under water concrete the representative value of the axial
stiffness was estimated in the range between 45 – 50 MN/m which was quite well
confirmed by the acceptance tests; most results showed even higher values.
Design guidelines for non-driven tension piles underneath under water concrete slabs - Developments in
The Netherlands – A. Vriend – 14.05.2008 p. 13/15
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
Photo 2. Acceptance test from floating pontoon Photo 3. Building pit after completion
Design guidelines for non-driven tension piles underneath under water concrete slabs - Developments in
The Netherlands – A. Vriend – 14.05.2008 p. 14/15
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
8. REFERENCES
[1] CUR 2001-4; Design rules for tension piles
Civieltechnisch Centrum Uitvoering Research en Regelgeving (CUR); juni
2001
[2] NEN-EN 1537; Execution of special geotechnical work – ground anchors
Nederlands Normalisatie-instituut; December 1999
[3] NEN 6743-1; Calculation method for bearing capacity of pile foundation –
compression piles
Nederlands Normalisatie-instituut; November 2006
[4] NEN 6745-2; Load test on foundation piles – static axial loading in tension
Nederlands Normalisatie-instituut; December 2005
[5] Proceedings of the international symposium on anchors in theory and
practice
Salzburg, Austria; 9-10 October 1995
[6] Proceedings of the international conference Ground anchorages and
anchored structures
Institution of Civil Engineers, London, UK; 20-21 March 1997
Design guidelines for non-driven tension piles underneath under water concrete slabs - Developments in
The Netherlands – A. Vriend – 14.05.2008 p. 15/15
BBRI BGGG – GBMS
Ground Anchors
Recommendations for
conception, calculation,
execution and testing
RECOMMENDATIONS T.A.95
Previous editions :
1972, 1976, 1986 in French
1989 Balkema in English
Prepared by 37 experienced
engineers (Cambefort, Graux,
Lebelle, Dupeuble, Clément,
Dupeuble, Logeais, … under the
“convenorship” of P. Habib)
180 pages
www.geotechnique.org
The recommendations T.A. 95 cover
1. Introduction
2. Definitions
3. Material specifications
4. Protection against corrosion
5. Execution
6. Testing
7. Periodical control of anchor load
8. Recommendations to the client
30 60 min
2 min
8 x 1h
20
Acceptance Suitability Investigation 5 min
10
10+15+5+5+1min 6 x 1h Time [min]
0
0 50 100 150 200 250 300 350 400 450 500
Proof loads and design parameters
• For investigation tests
Pp ≥1,25 Po or Pp ≥ Ra but Pp ≤ 0,9 Ptk
Po = estimated service load : Ra – resistance (failure)
The tendon section may be adapted to avoir steel failure
In addition, the service load is checked against the creep load obtained from tests.
Preliminary design
The pull out resistance Ra = qsπαsDLs.
IRS IGU
(Selective repeated injection) (Unique global injection)
αs qs αs qs
Dr Caesar M. Merrifield
Coffey Geotechnics Limited, Manchester, United Kingdom
Chairman CEN/TC 288/WG 13
BBRI & BGGG-GBMS “Ground Anchors 14.05.2008”
1. INTRODUCTION
1.1. Programme of European Geotechnical Standards
Work on the “Eurocodes” started in 1979 with the objective of developing European
design standards using the principle of partial safety factors and aiming at harmonizing
design approaches in Europe for the replacement of existing national standards which
were commonly using global safety factor approaches. Work was intensified after re-
lease by the European Commission of the Construction Products Directive (CPD) in
1988 which also necessitated European standardization of materials, building products,
construction methods and testing. For coordination and supervision of European stan-
dardization the European Standards Committee (CEN) was established which commis-
sioned the Technical Committee CEN/TC 250 to continue work on the Eurocodes. The
provisional time schedule aimed at their publication and introduction already in 1993
and 1996, respectively.
For geotechnical design and construction, the original programme foresaw four different
standard packages to be dealt with by the Sub Committee SC 7:
- EC 7-1: Geotechnical design,
- EC 7-2: Laboratory testing,
- EC 7-3: Field testing and
- EC 7-4: Geotechnical construction.
Taking account of the great range of the subjects and realizing that only a comprehen-
sive system of standards could be fully functional, the workload was later split between
CEN/TC 250 SC7 and two new TC’s:
CEN/TC 250 SC7: EN 1997-1: Geotechnical design - general rules and
EN 1997-2: Geotechnical design - ground investigation and testing;
CEN/TC 288: Geotechnical construction standards (“Execution of special geo-
technical work”), established 1991 and
CEN/TC 341: Ground investigation and testing, established 2000.
Scope of CEN/TC341 working groups (WG) is the development of standards for:
- identification and classification of soil and rock,
- drilling and sampling methods and groundwater measurement (WG 1),
- cone penetration tests (WG 2),
- dynamic probing (WG 3),
- testing of geotechnical structures (WG 4) and
- borehole expansion tests (WG 5).
Whilst the work of the other WG’s is running smoothly, that of WG 4 was initially
sometimes controversial because of the different nature of subjects addressed in the
standard. Testing of piles is an issue not directly connected to the execution of piles:
Testing of prestressed ground anchors is however an integral part of the execution and
an execution standard for anchors remains incomplete unless it contains respective pro-
visions or is complemented by a testing standard available simultaneously.
A summary of the most important geotechnical design, execution and testing standards
is given in Table 1.
CEN has prescribed strict rules for all parts of its standards including the presentation,
figures, tables and the wording. The rules are contained in Internal Directives (CEN
CENELEC (2006) “Internal Regulations Part 3”) and are identical for all CEN and ISO
standards. The Standards distinguish between Requirements, Recommendations, Per-
missions, Possibilities or just Notes and respective wordings are prescribed. It must be
kept in mind that common understanding and use of the language can deviate from the
standardized formulations. This fact is of particular importance for the application of
European Standards in different countries.
Similar strict and formal requirements including procedures and time schedules are in
place for the application for new works items for standardization, for the formation of
Technical Committees, the drafting process and the presentation of draft standards for
Enquiry, Formal Voting and Standard Review procedures.
Member Bodies (MB) of CEN are the national standards institutions, e.g. AFNOR, IBN,
NEN, BSI, DIN etc. Decisions regarding the acceptance of a new Work Item (WI), on
acceptance of a draft to become a EN-Standard through Formal Voting (FV) or for the
Systematic Review are taken by “double majority-voting” of MB’s, i.e. requiring the
single majority plus the 71 % weighted majority of MB’s voting. The latter reflects to
some extend the population of individual countries but is much in favour of smaller
countries.
Examples are the permission of reduced material testing requirements provided appro-
priate quality control systems are nationally specified (EN 1536) or different testing
procedures for ground anchors (EN 1537 and EN 22477-5).
The individual member countries are to check and provide for each individual standard
and how it is matched with the respective national conditions. Normally a short na-
tional foreword or national appendix (NA) should be sufficient. More complicated is-
sues can however require National Application Documents (NAD) for making a Euro-
pean standard operational.
P
τ
8
Figure 1: Elements of a pre-stressed ground anchor (from EN 1537) and load transfer
Figure 2: Elements of a permanent soil nail (from EN 14490) and load transfer; tension
micro piles act similar to nails
Table 2: Anchors, nails and tension micro piles covered by European standards
Type of Anchorage European Standard
Harmonisation
EN XXX: Steel, …
National Application Document
EN YYY: Grout, …
National Application Document
Figure 3: Context of execution, design and testing standards for ground anchors
The scope of the anchors covered in the standard is quite explicit. It is also widely be-
lieved that the scope should be better defined, only including anchors which are post-
tensioned and which have a free length. This certainly excludes alternative anchor solu-
tions such as tension piles, screw anchors, mechanical anchors, soil nails, expander an-
chors or deadman anchors.
It is not in the scope of this paper to discuss the roles of the fixed and free lengths in the
overall behaviour of ground anchors other than to say that the structural characteristics
of an anchor as defined in the standard suggest that the mechanisms of load transfer and
serviceability behaviour differ materially from other types of anchors which are not rep-
resented in the standard.
The standard highlights the importance of the anchor head in that this is the primary
load transfer element to the anchored system. The behaviour of the anchor as a load
transfer element is dependent upon two main characteristics of the anchor head. These
are; a) the ability of the head to maintain a load and, if necessary, to allow the anchor to
be restressed at some time in its working life and b) the ability of the anchor head to
resist wakening due to material degradation through corrosion.
Key
1 Anchorage point at jack during stressing 6 Soil/rock
2 Anchorage point at anchor head in service 7 Borehole
3 Bearing plate 8 Debonding sleeve
4 Load transfer block 9 Tendon
5 Structural element 10 Grout body in fixed length
The standard is rigorous in this definition for reasons of safety, both to that of the integ-
rity of the anchors and consequently the overall structures and also of third parties using
and maintaining the structures in question. Opinion is divided on the necessity for this
rigid definition and it has been suggested that a third definition of design life should be
promoted – that of extended temporary anchor. This, in essence would provide a
mechanism to provide design and execution guidance on a broader range of anchor uses.
With the development of more and more complex deep basement solutions to high rise
buildings and the extension of time required for the temporary works to be effective, the
application of extended temporary anchors to these solutions may well result in faster,
cheaper and less disruptive construction solutions to be applied in innovative designs.
chor fixed length designs using the most appropriate equilibrium analyses. (Merrifield
et al, 1997).
The recommendations in the design are predicated on the fact that the behaviour of the
high tensile steel tendon within an anchor is the most about which is known at the time
of design, and therefore this is the element upon which the design is based.
Likewise EN 1537 requires verification that the design value of the effect of stabilising
actions is at least or greater than the design value of the effect of the destabilising ac-
tions on the anchored structure. For example, when considering a limit state of rupture
or excessive deformation of a section, anchor or connection, the following should be
verified:
Ed ≤ Rd
where
Ed is the design value of the effect of actions, such as anchor force;
Rd is the corresponding design resistance, associating all structural properties
with the respective design values.
This simplified process is then followed when considering either a limit state of rupture
or excessive deformation of a section (i.e. tendon) safe in the assumption that Rd is con-
siderably lower than either the characteristic internal or external anchor resistance (i.e.
the tendon tensile strength Rik or the grout/ ground bond strength, Rak , respectively). In
fact EN 1537 requires that;-
Rk
Rd =
γR
where
γR = 1.35.
Furthermore the anchor lock-off load P0 should be no greater than 0.60Ptk, the charac-
teristic load capacity of the tendon.
By following these guidelines, the designer ensures that the anchor, as a stressed ele-
ment providing load transfer between the structure and the surrounding soil, should
never be loaded to a condition which would compromise the behaviour of the anchor.
The harmonisation process for EN 1537 and its subsequent revisions necessitate interac-
tion with other TC 288 standards and Eurocodes to ensure harmonisation of terminol-
ogy, symbols and, in some cases, basis of execution and design. The harmonisation
process should also be sensitive to the current legal systems prevailing in each sover-
eign state within the CEN area. In some countries the design and installation of anchors
is subject to a greater approval application regime by regulatory authorities than in oth-
ers. The standard should be cognisant of the differences in the regulatory and legal sys-
tems across Europe.
Each category of test above has a different set of objectives. The first two may be re-
garded as subdivisions of the general category of assessment tests as defined in
EN 1997-2.
The investigation tests have been designed to allow the designer to establish the load
resistance of the proposed anchors in relation tot the ground and the materials used in
the anchor itself. These tests may also be used to evaluate the competence of the pro-
posed contractor. Essentially these tests are undertaken to failure or the equivalent
thereof.
The suitability tests were designed to allow a greater understanding of the creep or load
loss characteristics at proof and lock-off load levels and to provide an indication of the
apparent free length of the anchor.
The objectives of the acceptance tests on each and every working anchor are to measure
the performance under working load conditions thus providing the designer and contrac-
tor with the assurance that both the design and installation processes have resulted in an
anchor which is fit for purpose in accordance with the standard.
The current standard does not prescribe a load or stress test method to be applied for any
of the test categories above, but provides examples of three methods which are deemed
to be acceptable. The inclusion of these methods is a consequence of the recognition
that each is favoured traditionally in different parts of Europe. In the interests of one of
the principles of harmonisation – that no current practice, which is deemed to be accept-
able, is to be discriminated against in the harmonisation process – they were incorpo-
rated into the standard as an informative annex.
Case studies have shown that corrosion at the head and in particular where the tendon is
restrained, is particularly severe and very often the area which suffers the most degrada-
tion due to corrosion.
As in the case of stress testing, the practice of designing and determining adequate an-
chor durability varies across Europe. For this reason the minimum corrosion protection
requirement for a permanent anchor tendon or tendon has been articulated as “a single
continuous layer of corrosion preventive material which does not degrade during the
design life of the anchor. “ This requirement is to be either verified by an appropriate
test, or the anchor is to be provided with a sacrificial layer of corrosion protection,
hence ensuring the integrity of a single layer insitu.
The standard provides details in informative annexes of systems tests to determine the
adequacy of corrosion protection. These are i) the electrical resistance test of anchors
insitu and under stress and ii) a laboratory based gun barrel systems test, again to check
for any protection damage under stress.
be confirmed, can extend the service life of anchored structures, such as post-tensioned
dams, dry docks, bridges, sports stadia and multi-storey buildings etc which represent
key elements of a country’s infrastructure. (Littlejohn and Mothersille, 2007).
EN 1537 provides a modicum of guidance on monitoring and the level of records that
should be retained. Very little is said on the necessity for regular maintenance. This
may be seen as a disadvantage to the use of an anchored solution. Records show, how-
ever, that even very large structures such as dams, high buildings and steep slopes
which, in the event of failure could cause dramatic loss of life and assets, are monitored
and maintained on a regular basis as part of the whole life asset management cycle.
Many examples of long term monitoring and maintenance and the current practices in
both European and other countries, such as South Africa, Australia and the USA are
recorded in the proceedings of the recent international conference on ground anchorages
and anchored structures in service (2007).
Plate 1
Severely corroded anchor head
showing deterioration of bearing
plate and barrel loss due to strand
slippage after 37 years service
Plate 2:
Heavily corroded anchor having
sustained tendon failure after 28
years in service in a marine envi-
ronment in the UK
Plate 3:
Anchor head after removal of cap
showing corroded barrels and
remnant grease after 30 years in
service
The working group is currently assessing the comments received through the
national enquiries and resolving issues associated with these comments. In each
case the comments are being considered and incorporated within the draft revi-
sion, where appropriate.
CEN recognises the importance of maintaining the right balance between the
different interests when appointing experts to ensure that the breadth of technical
and user expertise is obtained and to ensure that no interest group has a dominat-
ing position. This is the case with respect to CEN/TC288/WG14.
Appropriate reference to these matters will be made in the revised EN 1537 but
the substantive text on these matters will reside in the standards into which these
topics will be placed.
7. REFERENCES
CEN CENELEC, (2006) “Internal Regulations Part 3: Rules for the structure
and drafting of CEN/CENELEC Publications”, Brussels.
Ivanović A., Neilson R., Starkey A., and Rodger A. (2007) “Common anchorage
issues addressed by numerical modelling”. pp209-219, Proc. International Con-
ference on Ground Anchorages and Anchored Structures in Service, ICE, Lon-
don.
Merrifield C., Barley A., Von Matt U. (1997) “The execution of ground anchor
works: The European Standard prEN1537”. pp492-502, Proc. International
Conference on Ground Anchorages and Anchored Structures, ICE, London.
Tanaka K., Okada H. and Izakura M. (2007) “The development of the method of
detecting the anchor tensile force to impact elastic wave”. pp238-249, Proc. In-
ternational Conference on Ground Anchorages and Anchored Structures in Ser-
vice, ICE, London.
Whitworth, M and Parrish, S (2007) “Long term monitoring and routine main-
tenance of ground anchorages at Devonport Royal Dockyard, Plymouth UK”
pp63-71, Proc. International Conference on Ground Anchorages and Anchored
Structures in Service, ICE, London.