You are on page 1of 1

S10

Ing, Javier Galdos Ballon

Precios y cantidades de insumos requeridos


Obra 0301003 I.E. SAN PEDRO
Fórmula 01 PRESUPUESTO I.E. SAN PEDRO
Fecha 24/06/2005
Código Insumo Unidad Precio Cantidad Parcial Presupuestado

370237 WINCHA DE 30m UND 35.00 20.31 710.85 711.10


370300 CIZALLA P/FIERRO CONST. HASTA 1" UND 130.00 2.06 267.80 268.70
375373 CORDEL ROLLO DE 50 M PZA 13.56 20.17 273.51 302.61
375417 JALON HM 0.65 322.78 209.81 201.74
375418 MIRA TOPOGRAFICA HM 1.06 161.39 171.07 201.74
480423 CAMION VOLQUETE 4x2 140-210 HP 6 M3. HM 126.18 211.22 26,651.74 26,663.53
481201 CAMION CISTERNA 4X2 (AGUA) 1,500 GAL. HM 65.40 34.63 2,264.80 2,308.65
481293 CONTROL AUTOMATICO P/ CISTERNA UND 39.60 1.00 39.60 39.60
488208 ELECTROBOMBA PARA AGUA DE 0.8 HP UND 719.40 2.00 1,438.80 1,438.80
489001 SIERRA CIRCULAR HM 5.73 202.90 1,162.62 1,160.60
490301 COMPACTADOR VIBR. TIPO PLANCHA 4 HP HM 18.62 49.90 929.14 929.48
490307 RODILLO LISO VIBR AUTOP 101-135HP 10-12T HM 110.00 234.77 25,824.70 25,824.68
490409 CARGADOR S/LLANTAS 125 HP 2.5 YD3. HM 145.40 52.88 7,688.75 7,695.06
490704 VIBRADOR DE CONCRETO 4 HP 2.40" HM 7.25 867.57 6,289.88 6,294.62
490750 MOTOSOLDADORA DE 250 AMP. HM 4.50 34.33 154.49 154.43
490893 TRACTOR D6 HM 238.20 58.41 13,913.26 13,916.18
490894 GRUA HIDRAULICA AUTOP. 9 TON HM 120.00 29.50 3,540.00 3,540.60
490895 ANDAMIO METALICO HM 186.50 29.50 5,501.75 5,504.52
490900 MOTONIVELADORA DE 125 HP HM 120.00 234.77 28,172.40 28,172.38
491007 MEZCLADORA CONCRETO TAMBOR 18HP 11P3 HM 23.20 1,039.21 24,109.67 24,113.03
491905 TEODOLITO HM 6.49 161.39 1,047.42 1,008.69
499001 PULIDORA DE TERRAZOS HM 10.08 915.97 9,232.98 9,228.38
499012 CEPILLADORA ELECTRICA HM 5.56 235.30 1,308.27 1,307.98
499013 TALADRO ELECTRICO HM 3.00 21.68 65.04 65.04
SUB-TOTAL 160,968.34 161,052.14
INSUMOS COMODIN
370101 HERRAMIENTAS MANUALES %MO 26,418.19
SUB-TOTAL 26,418.19
TOTAL 160,968.34 187,470.33
MONTO PARTIDAS ESTIMADAS 0.00

187,470.33

La columna parcial es el producto del precio por la cantidad requerida; y en la última columna se muestra el Monto Real que se
está utilizando