No : Design Review Meeting 3

Your ref. Letter : Design Review Meeting 3 Dated : December 6, 2017

REVIEW FOR APPROVAL DRAWINGS/DOCUMENTS CCR OUT DATE

DRAWING/DOCUMENT NUMBER
DRAWING/DOCUMENT TITLE
No. PLN REV CONTRACTOR REV STATUS
PID LEGEND
1. 11026B3.1-00-M-52-Z-0003-01-2 2 ENG-DED-SLR-PR-52-MJ-001 2 A
(SHEET 1 OF 3)

PID LEGEND
2. 11026B3.1-00-M-52-Z-0003-02-2 2 ENG-DED-SLR-PR-52-MJ-001 2 A
(SHEET 2 OF 3)

PID LEGEND
3. 11026B3.1-00-M-52-Z-0003-03-2 2 ENG-DED-SLR-PR-52-MJ-001 2 A
(SHEET 3 OF 3)

Comm’t Comm’t
PLN’S COMMENTS CONTRACTOR’S RESPONSE
No. No.
General Comments

Approval does not relieve contractor from responsibility for errors and deviation from
G1.
contract requirements.
Comply

Reviewed by : Checked by :

-1/1-
PT PLN (Persero) Pusat Enjiniring Ketenagalistrikan
PLTG/PLTMG TANJUNG SELOR 15 MW