Contractor Consultant PM / CM Client

SOUTH TROUGH ZONE 4

Package #: CP07B
Wednesday, March 06, 2019
Contract #: 5297
Project Name: CP7B‐Lusail Plaza Infastructure, LRT Station, Public Car Parks and Landscape   
Actual dates Actual Progress, Qty
S.No Activity Description Location Budgetted Qty Unit Remarks
Start Finish Previous Today Cumulative
2
1 EXCAVATION  Zone 4 m
Zone 4
2 SLOPE STABLITY/INSTALLATION OF DROP CHAIN LINK  Zone 4 m

3 ROCK NAILING, GROUTING, AND SHOTCRETE APPLICATION zone 4 m

4 BLINDING and MASS CONCRETE and INFILL Zone 4 m2
seg 20 to 19b west side along w11 infill Zone 4 Feb‐19 ongoing
seg 18 to 19a west side along w11 infill Zone 4 Feb‐19 ongoing
seg 23 east ramp, c5 layer 3rd Zone 4 5‐Mar‐19 6‐Mar‐19 completed
seg 19b along w10 east, infill c5 layer up to 1m below frl Zone 4 5‐Mar‐19 6‐Mar‐19 completed
seg 18b2 along w10 east, infill c5 layer up to 1m below frl Zone 4 5‐Mar‐19 6‐Mar‐19 completed
seg 18b2 along center wall east side, c30 layer up to level 260mm below FRL Zone 4 5‐Mar‐19 6‐Mar‐19 completed
seg 198A2/18b1 EJ, along center wall east side, c30 layer up to level 260mm below FRL Zone 4 5‐Mar‐19 6‐Mar‐19 completed
seg 19a, west along w11 box‐out area, c30 layer up to 260mm below frl Zone 4 5‐Mar‐19 6‐Mar‐19 completed
seg 28/27 ej upper east ramp c30 layer, up to level 260 mm below FRL Zone 4 5‐Mar‐19 6‐Mar‐19 completed
seg 25/24 ej upper east ramp c30 layer, up to bottom of channel Zone 4 5‐Mar‐19 6‐Mar‐19 completed
seg 22 east ramp, c5 layer 3rd Zone 4 5‐Mar‐19 6‐Mar‐19 completed
seg 35 east side w12, filling for cancelled MEP boxout, level 260mm below FRL, updated Zone 4 5‐Mar‐19 6‐Mar‐19 completed
seg 20/21 EJ along east side infill c5 layer Zone 4 6‐Mar‐19 ongoing
seg 18a2/18b1 ej along center wall west side, c30 layer up to 260mm below FRL Zone 4 6‐Mar‐19 ongoing
seg 23 upper east ramp infill c5 4th layer Zone 4 6‐Mar‐19 ongoing
seg 22 upper east ramp infill c5 4th layer Zone 4 6‐Mar‐19 ongoing
seg 20a west ramp raft, for closing deep well dewatering pipe Zone 4 6‐Mar‐19 ongoing
5 PANELS (top reinforced layer after infill) Zone 4
seg 27 west ramp reinforced layer, 1 panel along w13 Zone 4 Feb‐19 ongoing
seg 22 east side along w10 reinforced layer sidewalk panel Zone 4 6‐Mar‐19 6‐Mar‐19 completed
seg 26 upper east ramp reinforced layer infill, 1 panel remaining along w12 Zone 4 6‐Mar‐19 6‐Mar‐19 completed
seg 21 east side along w10 reinforced layer sidewalk panel Zone 4 6‐Mar‐19 6‐Mar‐19 completed
seg 28 upper west ramp reinforced layer infill, 1 panel  Zone 4 6‐Mar‐19 6‐Mar‐19 completed
6 WALL (18A to 44B) Zone 4
seg 31 B ej west ramp concrete upstand wall Zone 4 Feb‐19 ongoing
7 PARAPET Zone 4

8 SLAB

9 COLUMN
Contractor Consultant PM / CM Client

SOUTH TROUGH ZONE 4

Package #: CP07B
Wednesday, March 06, 2019
Contract #: 5297
Project Name: CP7B‐Lusail Plaza Infastructure, LRT Station, Public Car Parks and Landscape   
Actual dates Actual Progress, Qty
S.No Activity Description Location Budgetted Qty Unit Remarks
Start Finish Previous Today Cumulative
10 Drainage Channel and Manhole
drainage channel seg 36 west ramp Zone 4 Feb‐19 ongoing
manhole ITS handole M38 m39 m40 (in seg 22 23 24 east side along w10), ongoing additional Zone 4 5‐Mar‐19 ongoing
manhole LV M17, M18 along center wall east side seg 18a1  steel and formwork Zone 4 Feb‐19 ongoing
manhole LV M16 M20 along center wall west side seg 18a1  steel and formwork Zone 4 Feb‐19 ongoing
manhole LV M19 along east w10 seg 18a1  steel and formwork Zone 4 Feb‐19 ongoing
manhole LV M21 along west w11 seg 18a1  steel and formwork Zone 4 Feb‐19 ongoing
seg 18a east side along 10, drainage channel (walls) Zone 4 6‐Mar‐19 ongoing
11 Installation Crash Barrier and Kerb stone
interlock/pavement blocks seg 33 to 41 median Zone 4 9‐Jan‐19 ongoing
interlock/pavement blocks seg 42, 41 to 33 east and west (w12 w13 sidewalks) Zone 4 9‐Jan‐19 ongoing
seg 22 concrete backing for kerbstone, west along w11 Zone 4 6‐Mar‐19 ongoing
12 Substation 3

13 F3 E14 Road/ utilities

14 Miscellaneous