Professional Documents
Culture Documents
Revision: 7
TABLE OF CONTENTS
1.0 SCOPE ................................................................................................................................................................ 3
2.0 GENERAL ........................................................................................................................................................... 3
3.0 DEFINITIONS ...................................................................................................................................................... 3
4.0 LEGISLATION, REGULATIONS, CODES AND STANDARDS......................................................................... 3
5.0 GENERAL DESIGN CONSIDERATIONS .......................................................................................................... 5
6.0 ACCESSIBILITY ................................................................................................................................................. 9
7.0 MAINTENANCE ................................................................................................................................................ 10
8.0 CLEARANCES.................................................................................................................................................. 11
9.0 SPECIFIC DESIGN REQUIREMENTS ............................................................................................................. 12
10.0 DESIGN AND DRAWING PRACTICES............................................................................................................ 20
11.0 EXCEPTIONS AND EXEMPTIONS .................................................................................................................. 21
APPENDICES
APPENDIX A TYPICAL DETAIL FOR UTILITY STATION WITH MIXING VALVE
This Standard applies to Canadian Natural Resources Limited – Horizon Oil Sands
It specifies minimum management or technical requirements.
In cases where legislation imposes more stringent or additional requirements, the legislative requirements shall override
these standards until such time as these standards are updated to reflect new requirements.
00-FM-IM-0039_r3 Page 2 of 23
STANDARD: 00-STD-PI-0007
Revision: 7
1.0 SCOPE
1.1 This standard defines the requirements for the design of process and utility piping, including the
layout of process equipment and units for mechanical design and drafting.
1.2 This standard shall be used for process and utility piping design.
1.3 Any deviation from this Standard requires prior written acceptance by Canadian Natural
Resources Ltd.
2.0 GENERAL
2.1 The words “CNRL”, “Owner”, and Company when used in this standard shall mean Canadian
Natural Resources Ltd. and designated agents.
2.2 Where there is conflict resulting from the interpretation of the contents of this standard, the owner
shall be called upon to make a binding final decision, and a written ruling shall be obtained prior
to proceeding with affected work.
2.3 All equipment shall be of Manufacturer's standard design, if possible.
2.4 All work shall comply with the legislative and regulatory requirements of the province or territory
of the installation as well as the Government of Canada.
3.0 DEFINITIONS
P&ID shall mean Piping and Instrumentation Diagrams.
NPS shall mean Nominal Pipe Size.
ISO shall mean (Piping) Isometric (Drawing).
LDT shall mean Line Designation Table.
API shall mean the American Petroleum Institute.
ASME shall mean the American Society of Mechanical Engineers.
CSA shall mean Canadian Standards Association.
NFPA shall mean National Fire Protection Association.
4.0 LEGISLATION, REGULATIONS, CODES AND STANDARDS
4.1 The design and layout of the facilities shall be in accordance with the latest edition, as of the
Purchase Order date, of the following:
Government Legislation:
Safety Codes Act, Chapter S-1, RSA-2000, with related regulations and codes:
AR 49/2006 - Pressure Equipment Safety Regulation
AR 56/2006 - Pressure Equipment Exemption Order
AR 85/2003 - Power Engineers Regulation
AR 169/2002 - Pressure Welders Regulation
AR 117/2007 – Building Code Regulation
Occupational Health and Safety Act, Chapter O-2, RSA-2000, with related regulations
and codes:
AR 62/2003 – Occupational Health and Safety Regulation
00-FM-IM-0039_r3 Page 3 of 23
STANDARD: 00-STD-PI-0007
Revision: 7
00-FM-IM-0039_r3 Page 4 of 23
STANDARD: 00-STD-PI-0007
Revision: 7
00-FM-IM-0039_r3 Page 5 of 23
STANDARD: 00-STD-PI-0007
Revision: 7
00-FM-IM-0039_r3 Page 6 of 23
STANDARD: 00-STD-PI-0007
Revision: 7
5.3.3 Process fluids are classified into three levels, namely; Extreme Hazardous Fluids,
Hazardous Fluids and Non-Hazardous Fluids. Details of these fluid classifications are as
shown in the following table.
Fluid Classification. Fluid Criteria. Examples.
00-FM-IM-0039_r3 Page 7 of 23
STANDARD: 00-STD-PI-0007
Revision: 7
5.3.5 The guidelines for isolation design are shown in the matrix below, a higher level of
isolation may be designed into the system depending on specific circumstances. The
equipment and instrumentation isolation design must meet the minimum requirements as
stated in the Alberta Occupational Health and Safety Code, Part 15, Managing the
Control of Hazardous Energy. Designs using alternate means of isolation, certified by a
professional engineer, as allowed by the code, may not be used without written approval
by CNRL.
00-FM-IM-0039_r3 Page 8 of 23
STANDARD: 00-STD-PI-0007
Revision: 7
5.3.12 Reactors shall be provided with spacers at all nozzles except for the top head
“gooseneck” where a removable spool with blind for the open piping is installed.
5.3.13 All process and utility lines of 600# and above shall have double block and bleed isolation
scheme.
5.3.14 Protective shields shall be provided for isolation valves in all liquid acidic, caustic and
toxic services.
5.4 When dealing with large bore piping and equipment isolation, installing double block and bleed
isolations should be related to cost. One should consider the risks associated with single
isolation block valves and if they be mitigated by procedures or use of blinds, and the potential
risk severity and frequency. Where exposure to contained fluids and or gases can be safely
limited by any of these methods without any long or short term health risks, then single isolation
should be used.
5.4.1 Blinds must be rated to the full design pressure of the piping system.
Typical double block and bleed isolation arrangement
When utilizing blinds in conjunction with double block and bleeds, blinds should be
installed downstream of the bleed valve.
blind
block
bleed
6.0 ACCESSIBILITY
6.1 Provide a means of egress (a continuous and unobstructed way of exit travel) from any point in a
building or platform.
6.2 Provide a secondary means of escape where the travel distance from the furthest point on a
platform to an exit exceeds 23 m (75 ft).
6.3 Platforms, ladders, safety cages and stairways shall be as per Horizon Oil Sands Standard 00-
STD-ST-0001.
00-FM-IM-0039_r3 Page 9 of 23
STANDARD: 00-STD-PI-0007
Revision: 7
6.4 Access to elevated platforms shall be by stairway. Access to elevated process vessels and
equipment (not including auxiliaries) shall be by staircase or walkways.
6.5 Clear access shall be provided for handling and storage of bulk materials for all vessels charged
with desiccant, catalyst, bulk consumables or other bulk chemicals.
6.6 Spectacle blinds shall be accessible from grade or platform. Spectacle blinds that weigh over 45
kg shall be accessible by mobile equipment or davits and have lifting lugs.
6.7 Filters shall be provided with a permanent platform and shall be located 1m below the top cover
to allow for easy access. Stairs to filter are required. In the case of frequent filter maintenance the
platform shall have a landing space and removable hand rails to allow for fork lift loading of spare
filters and tools.
7.0 MAINTENANCE
7.1 Plant design and layouts are based on the assumption that mobile equipment will be used where
practical.
7.2 Building maintenance facilities generally will not be provided for equipment accessible by mobile
equipment.
7.3 Suitable cranes, monorails, or davits shall be provided to handle equipment components, not
accessible by mobile equipment.
7.4 Ensure adequate space including crane outriggers, is provided adjacent to vessels with
removable internals. Air cooler piping must not interfere with bundle removal.
7.5 Adequate space shall be provided for handling and storage of catalysts (fresh and spent),
including mobile equipment access where appropriate.
7.6 Exchangers or fired equipment with removable tube bundles shall have equivalent bundle length
plus 2 m from the tube sheet kept clear for maintenance. Plant access roads may be utilized for
tube pulling areas.
7.7 Provision shall be made in the piping layout and location for bundle removal. This includes, but is
not limited to the following:
7.7.1 The channel head of the exchanger shall be placed as close as possible to a walkway or
platform.
7.7.2 The shell flange must be no further back than 3m from the centerline of a bundle puller lift
point. Overhanging structures shall not impede the lift point of the bundle puller. Top
clearance shall be 3.2m from the bottom of the tube sheet to any overhanging structure.
7.7.3 Adequate top, bottom and side clearance shall be provided.
7.7.4 Removable hand rails are required (2.4m on centerline) on platforms where they may
interfere with the bundle or bundle puller.
7.7.5 CNRL Maintenance shall be contacted for clearance and bundle puller dimensions.
7.8 Sufficient access and clearance shall be provided at the plate and frame exchangers for the
replacement of entire plate packs.
7.9 For pumps or equipment which are maintained in an offsite workshop, provisions shall be
provided for lifting facilities or access for mobile lifting equipment. Sufficient access for bolt
tensioning shall be provided.
7.10 Removable spools NPS 24 and larger, for equipment isolation, shall be provided with lifting lugs.
Where insulated, lugs shall project outside of the insulation.
00-FM-IM-0039_r3 Page 10 of 23
STANDARD: 00-STD-PI-0007
Revision: 7
7.11 For rotating equipment located inside buildings or shelters, lifting facilities, such as an overhead
crane or monorail with moving carriage, shall be provided. The lifting arrangement shall be sized
for the maximum maintenance weight. Removal of roof panels for the purpose of normal
maintenance is not acceptable.
8.0 CLEARANCES
8.1 Minimum clearances for equipment structures, platforms and supports shall be in accordance
with the following table:
00-FM-IM-0039_r3 Page 11 of 23
STANDARD: 00-STD-PI-0007
Revision: 7
00-FM-IM-0039_r3 Page 12 of 23
STANDARD: 00-STD-PI-0007
Revision: 7
9.2.5 Drain and vent valves shall be provided for complete draining and purging of each
isolated exchanger, cooler, condenser and reboiler section. These valves shall be a
minimum of NPS 1.
9.2.6 Locate reboilers as close as possible to the equipment they serve.
9.2.7 Exchangers shall be grouped together wherever possible.
9.2.8 The design of exchangers that utilize dirty water on the cooling side shall allow back
flushing of the exchanger in situ.
9.3 Vessels and Columns
9.3.1 Wherever possible, locate piping at columns radially about the columns on the pipeway
side; locate manway and platforms on the access side. Maintenance access should be
on or about a common centerline to make use of a common lifting device or davit.
9.3.2 Valves and flanges shall not be located inside the vessel skirt.
9.3.3 Valve vents, drains and utility connections around vessels and columns shall be arranged
to prevent unintentional operation and undetected leakage.
9.3.4 Drain piping and valves shall be of the same size as the vessel drain connection.
9.3.5 Position platforms so the centerline of maintenance accesses is no less than 610 mm
above the platform, with 760 mm preferred. The bottom of the maintenance access entry
shall not be more than 1m above the platform.
9.3.6 Provide vessel davits for handling items such as internals and relief valves on vessels
exceeding a height of 9 m above the high point of the finished surface, and on vessels
not accessible by mobile crane. Orient davits to allow the lowering of appurtenances into
the access area.
9.3.7 Wherever possible, orient level instruments on horizontal vessels on the side toward the
pipeway. All level instruments should be accessible from grade or by platforms.
9.3.8 Blanking locations on columns shall be provided with a platform for access. The platform
shall extend to both sides of the flange to allow worker access to bolting.
9.4 Compressors
9.4.1 Suction and discharge piping for reciprocating compressors shall be run on supports near
grade and securely clamped to reduce vibration.
9.4.2 Supports shall be designed for piping around reciprocating compressors without causing
excessive local stresses in the pipe and without imposing excessive axial or lateral
friction forces that might preclude the desired freedom of movement.
9.4.3 Non-welded attachments, such as pipe clamps and ring girders, are preferred where they
will fulfill the supporting or anchoring function. Where welded attachments are required
for pipe designed to operate at stress levels above 50% of the specified minimum yield
strength of the pipe, such attachments shall be welded to a separate cylindrical member
that completely encircles the pipe and such encircling member shall be welded to the
pipe by continuous circumferential welds.
9.4.4 For wet gas or gas at dew point conditions, compressor suction piping must be designed
to avoid liquids at the compressor inlet. Consideration shall be given to inclusion of
suitable scrubbers, heat tracing at suction headers, providing scrubber drains and
avoiding suction from the bottom of the scrubber.
9.4.5 No cast iron valves shall be used on compressor process piping.
00-FM-IM-0039_r3 Page 13 of 23
STANDARD: 00-STD-PI-0007
Revision: 7
9.4.6 Crank case vents, distance piece vents, instrument gas vents and starting motor
exhausts shall be piped to the outside of the compressor building. Lube oil and distance
piece drain lines shall be piped to a spent oil collection tank.
9.4.7 The piping drawings shall indicate the limits to which compressor suction piping is subject
to special internal cleaning requirements. Temporary screens or strainers shall be
provided.
9.4.8 A manual blow down valve connected to flare shall be provided downstream of the
discharge check valve and upstream of the discharge block valve.
9.4.9 Process and auxiliary piping shall be routed such that easy access is provided to the
compressor and driver for operation and maintenance.
9.4.10 Removable spool pieces shall be provided at compressors where needed to permit
maintenance without major piping disassembly.
9.4.11 Piping shall meet the compressor specific installation design requirements in API RP 686.
9.4.12 Where compressor lube and seal units are located below the compressor, they shall be
offset from the compressor.
9.5 Fired Equipment
9.5.1 Locate snuffing steam manifolds and fuel gas shutoff valves a minimum of 15 m
horizontally from the heater they protect.
9.5.2 Terminate heater stacks a minimum of 5 m above any platform within a radius of 15 m.
9.5.3 Pressure relief doors and tube access doors shall be free from obstructions. Orient
pressure relief doors so as not to blow into adjacent equipment.
9.5.4 Access shall be provided at burner observation ports, process piping instrument
connections, stack instruments and tube observation doors.
9.5.5 Clearance under heaters shall be 2 m above high point of finished grade when operating
access is required.
9.5.6 Prevailing winds should be considered. Vessels, pumps, compressors and other
equipment handling light hydrocarbons shall be located downwind of fired equipment to
minimize vapours that may be carried towards open fires.
9.5.7 Grading under furnaces shall be sloped on one side to direct spills to a suitable drain
point.
9.6 Tanks
9.6.1 Provision shall be made to relieve pressure from thermal expansion or loading
operations. Packing/protecting covers on pressure relieving devices shall be removed
after installation to prevent choke-up.
9.6.2 Piping extraneous to the tanks shall not be located within a firewall.
9.6.3 Where a pipe is routed through an earth firewall the pipe shall be coated and wrapped.
Where the firewall is concrete, the pipe shall be sleeved and sealed.
9.6.4 Pumps associated with tankage operations shall be grouped together outside the firewall.
9.6.5 Tanks shall be spaced in accordance with the Horizon Oil Sands Standard, 00-STD-
PSFP-0001.
9.6.6 Piping shall be designed to ensure sufficient flexibility to provide for settlement of tanks
relative to pipe supports or anchors and differential settlement between tanks.
00-FM-IM-0039_r3 Page 14 of 23
STANDARD: 00-STD-PI-0007
Revision: 7
9.6.7 Block valves at tanks shall be steel. Other valves shall be installed in accordance with
P&IDs and line classifications.
9.7 Instruments
9.7.1 Locate liquid level transmitters, controllers and level glasses so as to be accessible from
grade, or platform. The level glass shall be readable from grade wherever practical.
9.7.2 Provide control, block, and bypass valve sizes as per P&IDs. Control valves shall be
accessible from grade or platforms.
9.7.3 All control valves NPS 2 and larger shall be flanged.
9.7.4 Control valve bypass valves shall be globe type and sized for a capacity at least equal to
the capacity of the control valve.
9.7.5 Block valves around control valves shall be line size flanged gate valves. If the control
valve is two or more line sizes smaller than the line, it is permissible to use block valves
one pipe size smaller than the line size.
9.7.6 All control valves shall have a NPS 1 gate valve drain located both upstream and
downstream of the control valve. These drain valves shall be located in the mainline prior
to any line size reducer. The drain valves shall have screwed plugs inserted.
9.7.7 Sufficient clearance on the axis of the control valve stem shall be provided, in all cases,
to permit removal of the super-structure and plug without removing the valve body from
the line. In no case should clearance below or above the valve assembly be less than
250 mm.
9.7.8 Eccentric reducers ahead of control valves shall be installed with the flat (straight) side on
the bottom. No reducers or other restrictions having a cross sectional area less than the
total maximum port area of the control valve shall be used in the control valve manifold.
9.7.9 Control valves where vaporization occurs shall be placed as close as practical to the
destination of the stream.
9.7.10 Orifice runs should preferably be located in the horizontal. Vertical orifice runs may be
used by exception only.
9.7.11 Orifice taps shall be located as follows:
9.7.11.1 Air and Gas [Top vertical centerline (preferred)] [45° above horizontal
centerline (alternative)]
9.7.11.2 Liquid and Steam [Horizontal centerline (preferred)] [45° below horizontal
centerline (alternative)]
9.7.11.3 The piping isometrics details shall show the required tap orientations; taps to
be top vertical for slurry service.
00-FM-IM-0039_r3 Page 15 of 23
STANDARD: 00-STD-PI-0007
Revision: 7
00-FM-IM-0039_r3 Page 16 of 23
STANDARD: 00-STD-PI-0007
Revision: 7
9.10.3 In general, keep valve hand wheels, handles, and stems out of the operating aisles.
9.10.4 Valves shall NOT be installed in overhead product outlets from vessels or where the cold
side of heat exchangers could be trapped full of liquid, unless absolutely required by
operation. Block valves, when required, shall be installed at nozzles of pressure vessels
or in lines connected to nozzles to permit operation of valves from grade or a platform.
Equipment shall be capable of being isolated if:
9.10.4.1 Operations can continue without it, or
9.10.4.2 De-pressurization of associated facilities will delay essential maintenance on
the equipment.
9.10.5 All blinding positions or other means of isolation, such as removable spool pieces which
require access during routine operation, shall be accessible without scaffolding. This
includes blinds/blanks which require swinging during normal start-up or shutdown
operations or other irregular but routine operations. Spectacle blinds/blanks shall be
provided at all blinding locations where piping cannot be sprung.
9.10.6 Open ended valves shall be fitted with blind flanges or threaded plugs.
9.10.7 Valve operation method shall be as stated in the Horizon Oil Sands Standard 00-STD-PI-
0002.
9.10.8 All valves shall have sufficient clearance to facilitate removal of the bonnet and internals,
where applicable.
9.10.9 Upon the approval of CNRL Engineering, extension stems may be used for easy valve
operations.
9.11 Underground Piping
9.11.1 The number of buried lines shall be kept to a minimum. Where it is necessary to bury
lines, they shall be protected from external corrosion by a Cathodic Protection System
and/or an appropriate coating approved by CNRL and inspected to ensure “holiday free”
integrity.
9.11.2 Underground pressure piping shall be in accordance with the Horizon Oil Sands Standard
00-STD-PI-0003. Underground fire water system design shall be in accordance with the
Horizon Oil Sands Standard 00-STD-PI-0006.
9.11.3 Lines with an operating temperature above 70 C shall not be buried without prior written
approval from CNRL.
9.11.4 Lines shall not be run underground inside tank firewalls.
9.11.5 Flanged or threaded connections shall not be buried. When burial of such piping is
unavoidable, connection preparation methods must be reviewed and approved by CNRL
Engineer. All buried joints shall be welded, cleaned and wrapped in accordance with
Horizon Oil Sands Standard 00-STD-PI-0013.
9.11.6 Underground piping shall have a minimum size of NPS 2.
9.11.7 Process lines running under roads shall be placed in concrete trenches equipped with
trench drains or cased and vented, as applicable. Uncased crossings are not permitted
unless they can be shown to comply with all applicable regulatory and Code
requirements and are approved in writing by CNRL.
9.11.8 It is preferred that lines run parallel to roads. The number of road crossings should be
minimized.
00-FM-IM-0039_r3 Page 17 of 23
STANDARD: 00-STD-PI-0007
Revision: 7
9.11.9 Below grade piping inside buildings shall be placed in concrete trenches covered with
open grating with trench drains to the drain system. All such drains shall be equipped
with P-traps. Firewalls shall be provided where required. For installations where solid
trench covers may be required instead of open gratings, such installations shall be
adequately sealed, drained and vented.
9.11.10 Lines shall not be routed under foundations without authorization from CNRL
Engineering.
9.11.11 Burial depth for lines susceptible to freezing shall have minimum cover from top of pipe to
finished grade at least equal to the frost line (3.7 m). For lines not susceptible to freezing,
minimum burial depth for mechanical protection shall be 1.2 m. Fire protection lines depth
shall be per NFPA 24.
9.11.12 Blanking locations on underground lines shall be provided with a suitable entry space.
9.12 Relieving Systems
9.12.1 Flare or vent systems shall include an above ground drain tank or knock-out pot in all
services. All lines upstream of the liquid collection vessel shall drain towards it and all
lines downstream shall drain back to it.
9.12.2 Drain tanks and knock out pots shall be insulated where necessary and equipped with
heat tracing or internal heating coils to prevent freeze-up of collected fluids prior to clean
out.
9.12.3 Flare stacks shall include a pilot flame with an automatic igniter or other form of ignition
system approved in writing by the Company. When specified by the Company, a flame
arrestor shall be installed as close to the flare stack as possible. Flame arrestors shall be
heat traced and insulated to ensure that blockage of the flare system due to freeze up will
not occur. Where a flame arrestor is not installed a continuous gas purge must be applied
to the flare system to ensure that air may not migrate down the flare stack and into the
flare system piping.
9.12.4 Flare and Vent system design shall meet all other recommendations included in API RP
520, Recommended Practice for the Design and Installation of Pressure Relieving
Systems in Refineries. All deviations from API RP 520 must be approved in writing by the
Company.
9.12.5 Purge gas connections shall be provided at the upstream end of the headers.
9.12.6 Relief valves shall be accessible. Wherever feasible, locate them at platforms that are
designed for other purposes.
9.12.7 Install thermal relief valves, NPS 1” and smaller inlet, in a horizontal position when it is
impractical to install in the vertical position. Install relief valves NPS 1-1/2 and larger inlet
in a vertical position.
9.12.8 Normally, install relief valves that discharge to a closed system higher than the collection
header. There shall be no pockets in the discharge line.
9.12.9 Relief valves that discharge to the atmosphere shall have tail pipes extended to a
minimum of 4.5 m above the nearest operating platform that is within a radius of 15 m.
This requirement may be waived, provided a review of the proposed arrangement
indicates that it does not present a hazard.
00-FM-IM-0039_r3 Page 18 of 23
STANDARD: 00-STD-PI-0007
Revision: 7
9.12.10 Relief valves discharging hydrocarbon vapours to the atmosphere within 30 m of fired
equipment are not permitted.
9.12.11 Each Relief valve shall have a separate connection to the line or vessel protected (i.e.
manifolding of PSV inlets is not permitted).
9.12.12 The size of the inlet line shall not be less than the size of the relief valve inlet.
9.12.13 The length of the inlet piping on a relief valve shall be kept to a minimum.
9.12.14 Where a block valve is installed to permit removal of a relief valve during unit operation it
shall be located immediately below the relief valve. All upstream or downstream block
valve handwheels must be located horizontally.
9.12.15 Any pressure relief valve discharging to a closed system shall be installed so that the
discharge piping slopes away from the relief valve, into the header.
9.12.16 At no time shall a branch connection be made into the bottom of a relief header. Branch
connections preferably should be made to the top of the header and only to the side of a
header where the possibility of liquids flowing from the header to the branch is small.
9.12.17 Any block valves installed on relieving systems shall be full port and shall be car sealed
open.
9.12.18 Adequate supporting must be provided to compensate for sudden opening of relief
valves.
9.12.19 Relief systems for B31.1 Boiler external piping shall be designed as per ASME Section 1
requirements.
9.13 Insulated Piping, Thermal Tracing
Insulation shall be in accordance with the applicable Horizon Oil Sands Standard 00-STD-MW-
0045.
9.14 Utility Piping and Stations
9.14.1 Hose stations for steam, water, nitrogen and air shall be located so that areas to be
served at grade, on elevated structures and in buildings can be reached with a 15 m
hose.
9.14.2 Hose stations shall have NPS 1 connections and shall be equipped with gate or globe
valves. Hose connections to be supplied by owner (CNRL).
9.14.3 The minimum size of utility pipe in pipeways shall be NPS 2.
9.14.4 Utility stations shall be clearly marked as for which service fluid is provided. Alternative
connection methods shall be provided for air, water, and steam.
9.14.5 Utility stations shall be installed in such a manner so that they may remain in operation
during a unit shutdown.
9.14.6 Provide water outlets at grade only in pump areas and near equipment that shall be water
washed during maintenance.
9.14.7 Provide steam outlets at grade level only or in areas subject to product spills and near
equipment that requires steaming out during maintenance.
9.14.8 Provide air outlets in areas where air driven tools are used such as at exchangers, both
ends of heaters, compressor areas, top platform of reactors and on columns, so that
each manway to be served is within a reach of 15 m.
00-FM-IM-0039_r3 Page 19 of 23
STANDARD: 00-STD-PI-0007
Revision: 7
00-FM-IM-0039_r3 Page 20 of 23
STANDARD: 00-STD-PI-0007
Revision: 7
00-FM-IM-0039_r3 Page 21 of 23
00-STD-PI-0007
PIPING DESIGN AND LAYOUT
APPENDIX A
TYPICAL DETAIL FOR UTILITY STATION WITH MIXING VALVE