Minimum Wage 396 As of: 2/16/2019

Category/Designation: Labor Cost Index Basic Daily Basic Month Leave Thirteenth Benefits (SSS)
Construction Foreman 1.80 712.80 18,651.60 1,554.30 1,554.30 1,178.70
Lead Man 1.65 653.40 17,097.30 1,424.78 1,424.78 1,178.70
Heavy Equipment Operator 1.50 594.00 15,543.00 1,295.25 1,295.25 1,141.80
Highly Skilled Laborer 1.40 554.40 14,506.80 1,208.90 1,208.90 1,068.20
Light Equipment Operator 1.40 554.40 14,506.80 1,208.90 1,208.90 1,068.20
Driver 1.30 514.80 13,470.60 1,122.55 1,122.55 994.50
Skilled Laborer 1.30 514.80 13,470.60 1,122.55 1,122.55 994.50
Unskilled Laborer 1.00 396.00 10,362.00 863.50 863.50 773.50
Philhealth PAGIBIG ECC Total Rate p Rate per Day Rate per Hour
225.00 100.00 30.00 23,293.90 890.21 111.28
212.50 100.00 30.00 21,468.05 820.44 102.55
187.50 100.00 30.00 19,592.80 748.77 93.60
175.00 100.00 10.00 18,277.80 698.51 87.31
175.00 100.00 10.00 18,277.80 698.51 87.31
162.50 100.00 10.00 16,982.70 649.02 81.13
162.50 100.00 10.00 16,982.70 649.02 81.13
125.00 100.00 10.00 13,097.50 500.54 62.57
Detailed Unit Price Analysis
Description: Aggregate Sub-base Course
Output per Day: 400 m3/day
2000 m2/day

Designation No. of Person No. of Days Daily Rate Amount


A. Labor
a. Construction Foreman 1 1 890.21 890.21
b. Laboratory Technician 1 1 698.51 698.51
c. Laborer 4 1 500.54 2,002.17

Name and Capacity No. of Equipment Capacity No. of Days Daily Rate Amount
B. Equipment
a. Road Roller 1 600 0.67 18,658.40 12,438.93
b. Road Grader 2 300 1.33 21,870.88 58,322.35
c. Water Truck 1 600 0.67 12,010.64 8,007.09

Description: Portland Cement Concrete Pavement


Output per Day: 90 m3/day
450 m2/day

Designation No. of Person No. of Days Daily Rate Amount


A. Labor
a. Construction Foreman 1 1 890.21 890.21
b. Laboratory Technician 1 1 698.51 698.51
c. Skilled Laborer 6 1 649.02 3,894.12
d. Laborer 10 1 500.54 5,005.41

Name and Capacity No. of Equipment Capacity No. of Days Daily Rate Amount
B. Equipment
a. Concrete Vibrator 3 450 1.00 1,788.00 5,364.00
b. Water Truck with Pump 3 450 1.00 12,010.64 36,031.92
Cost per unit

0.45 PhP/m2
0.35 PhP/m2
1.00 PhP/m2
1.80 PhP/m2

Cost per unit

6.22 PhP/m2
29.16 PhP/m2
4.00 PhP/m2
39.38 PhP/m2

Cost per unit

1.98 PhP/m2
1.55 PhP/m2
8.65 PhP/m2
11.12 PhP/m2
23.31 PhP/m2

Cost per unit

11.92 PhP/m2
80.07 PhP/m2
91.99 PhP/m2