Professional Documents
Culture Documents
BridgeCare
www.usluk.com
Britflex BEJ
Expansion Joints
Elastomeric In Metal Runners
USL Britflex BEJ
BridgeCare Expansion Joints
HAPAS
Roads and Bridges
Pitchmastic PmB Ltd FM11022
A close up of the BEJ expansion joint system not normally seen by the
travelling public.
Through
&IGURE Carrier rail
deck drainage
standard 48x25 Britflex “Dri-Deck unit”
low profile 43x25 resin
Sinusoidal mortar
anchorage
Plinth cast
monolithic with
bridge deck
C B C
D
E
Notes
1. Nominal nosing gap is that selected at average design effective bridge deck temperatures and does not take movement into
account other than temperature movements.
2. This is the standard design. Please refer to USL Technical and Advisory Service if a ‘special’ is required.
3. For optional kerb detail based on minimum nosing widths – see figure 8 and specification paragraph xi.
4. For skew movements, greater than ±15mm, please refer to USL Technical and Advisory Service.
5. For clarification of kerb upstand clearance (x) see figure 2 and 3.
04
&IGURE Kerb detail
Note: Upstand plinth reinforced and formed as part of Bridge Deck
Resin
nosing
Resin nosing
to suit kerb
Carriageway
25º
D
Change in
slope of
X
upstand
X
Face of kerb
Plan
Design guidelines
The ‘BEJ’ is a high performance Alternatively the nosing depth may When placing Britflex Resin Mortar It is recommended that the use of
expansion Joint system which is be increased to match the depth around services, the designer a more positive and larger capacity
easy to detail at design stage. of the bridge deck surfacing, both should give consideration to the ‘Dri-Deck’ drainage system is
The USL’s Technical and Advisory in the carriageway and the verges. spacing around them. considered, either in conjunction
Service is however able to assist However in so doing, attention must with or in place of the in joint relief.
and advise on all detailing matters, be paid to the aspect ratio of the A minimum clearance of 25mm is If this is adopted and the expansion
from the most simple to the most nosing, the passage of any service required beneath services/sleeves joint is built onto a structural concrete
complex installations. ducts through the resin mortar and the top clearance (E) is given up stand as per figure 1, in-joint
and the drainage of the surfacing in Table 1. This is to accommodate hydraulic relief may be considered
3IMPLICITY upstream of the joint. the insert which dips between the to be unnecessary.
Based on essentially three component nosings at maximum compression.
materials, the ‘BEJ’ system is flexible &LEXIBILITY A spacing of 125mm between In order to provide a satisfactory
and may be adapted in numerous Britflex resin mortar exhibits each duct is required to enable junction to the bridge deck
different configurations. excellent bond strength to steel proper construction of the joint. waterproofing system, the
as well as concrete. Therefore the It is normally sufficient to provide a membrane should be brought
The standard method of installation ‘BEJ’ system may also be placed debonding/sleeving arrangement 50mm into the joint area on both
for new works is to cast the resin onto metal deck plates or into a on the abutment side. sides of the joint.
nosings directly onto the structural recess provided by metal shelf
concrete that forms the bridge deck angle supports. Alternatively the (YDRAULIC 2ELIEF This is subsequently removed
and abutment. Should the deck end steel carrier rails of the ‘BEJ’ system A hydraulic relief may be used to during the installation of the ‘BEJ’
and / or abutment require alteration may actually be welded directly relieve hydrostatic pressure in the Expansion Joint and the free edge
to suit the joint system, the elevation to the lower steel substrate. surfacing which may occur at the of the waterproofing sealed with
or plinth must be cast monolithically (See figure 6 ) Steelwork should surfacing / nosing interface. resin at the priming stage.
with both. be clean and free from rust. Advice
should be taken prior to undertaking The channel is attached to a flexible -OVEMENT
At the kerbline, the deck and ballast this application. tube which is routed either down Table 1 indicates the basic
wall should be ramped to deal with the expansion gap or into pipework, movement capacity of each joint
the change in level. Details are Standard nosings for new works cast into the deck within the area of in the system.
indicated in Figure 3. have an aspect ratio of nominally the joint.
2:1 in width to depth. When using
nosings of the same depth as The channel is not usually required
surfacing, the appropriate width when the expansion joint is at the
will depend on the joint type, class high end of the bridge deck.
of road and extent of trafficking
but never less than an aspect ratio
of 1.25:1 width to depth, if in our
doubt please contact our Technical
and Advisory Service. 05
USL Britflex BEJ
BridgeCare Expansion Joints
Stitch welding
(intermitent)
&IGURE
&IGURE D
Nosing recessed
and to match
kerb face
W D
Plan
Resin
nosing
07
USL Britflex BEJ
BridgeCare Expansion Joints
iv viii x xiv
Installation
A '
ENERAL STEPS IN THE vi) All exposed surfaces should be xi) The polyureide resin is batched xvii) The resin mortar will cure
INSTALLATION OF THE k"%*l dried before priming, by using from calibrated jugs of the after two to three hours at
%XPANSION *OINT compressed air and/or hot air two components and mixed approximately 70°C. It is
depending upon the weather with a powered paddle until then allowed to cool before
i) The two resin components conditions. homogeneous and streak free. the spacer splates, hangers
are warmed in oil jacketed and polystyrene shuttering
gas/diesel fired heaters and vii) If hydraulic relief is specified, xii) The resin mortar is batched by are removed.
maintained at 65° - 85°C prime beneath the position of first pre-heating one 20kg bag xviii) The sections of joints in the
the drainage channel with a mix of aggregate to approximately verges/central reserve are
ii) The width is marked out on of the two resin components. 70°C in a powered mixer. One installed in a similar manner.
the asphalt surfacing and saw (See section xi). The channel is batch of the resin compound
cut to provide a trench in the fixed with masonry nails into the (see (xi)) is then added and xix) The elastomeric insert is
carriageway. The trench width surfacing and protected from mixed until homogeneous. installed using compression
will depend on the selected the resin ingress with masking tongs into the carrier rails.
nosing width, type of joint and tape. The flexible discharge xiii) If required a measure of
the required gap setting. tube is then fitted at the low ‘Aerosil’ may be added xx) If specified, any kerb cover,
end of the channel and towards the end of the mixing footway or parapet plates
iii) The surfacing or the existing routed appropriately. cycle to stiffen up the mix for are fitted.
failed joint is broken out and placing in steeply graded areas.
removed. viii) The polystyrene shutter is
cut to size and placed in the xiv) The resin mortar is placed
iv) The concrete deck and any expansion gap, ensuring it is into the prepared trench in the
previously formed recess in the firmly in the gap. The complete carriageway and trowelled flush
verge/central reserve is lightly trench is then primed with the with the rails and surfacing.
scabbled and/or wire brushed resin mix (See section xi).
and substandard asphalt/ xv) Apply an anti skid aggregated
concrete removed. ix) The carrier rails are cut and scatter to the resin mortar prior
welded to suit any general to full cure.
v) All loose arisings and any changes in level or direction.
standing water are removed xvi) Once a suitable length of joint
with compressed air. x) The rails are positioned on has been poured curing hoods
spacer plates of the selected may be erected over the joint
size, attached to the hangers/ and hot air applied.
strongbacks, positioned over
the expansion gap and set for
line and level.
08
xv xix
Installation
B 7
EATHER AND 4EMPERATURE C 4
IME LAG AFTER COMPLETION D /THER .OTES
#RITERIA AND BEFORE OPENING TO TRAFüC
When the ‘BEJ’ system is
The polyureide resin may be Once the resin mortar bonded to steel, this should
installed in temperatures of has cured the elastomeric be prepared by grit blasting
up to 50°C. It is not affected element can be inserted and or mechanically abrading just
by freezing, but care must be the joint opened to traffic. prior to the priming operation.
taken to ensure the substrate During phased working the
is frost free and sufficiently joint can be opened to traffic The ‘BEJ’ insert should be
dry before the priming stage. after curing with or without protected from white-lining
the elastomeric element in materials, e.g. with sand.
Once the exposed surfaces place to suit the sequence
have been primed, the joint of installation and minimise
is effectively sealed. At traffic disruption.
temperatures below 5°C the
resin will be dormant until
heat is applied. At warmer
temperatures, the resin will
cure unaided.
09
USL Britflex BEJ
BridgeCare Expansion Joints
10
11
www.usluk.com