Professional Documents
Culture Documents
net/publication/224184605
CITATIONS READS
3 683
3 authors:
A. Kladas
National Technical University of Athens
267 PUBLICATIONS 2,410 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Eleftherios I. Amoiralis on 14 February 2014.
Φ
Abstract – Owing to deregulation, privatization and transformers in distribution networks is realized through a
competition, estimating financial benefits of electrical power proper economic evaluation method. The proposed method
system projects is becoming increasingly important. In other involves the incorporation of the discounted cost of
words, it is necessary to ensure that a project is profitable. In transformer losses to their economic evaluation, similarly to
this work, a real-life example of a detailed analysis for the least-
cost choice of a transformer is carried out, showing how the the TOC method, providing the ability to take into account
higher price of a facility can be traded against its operational variable energy cost during the transformer operating
cost over its life span. lifetime. Therefore, different loss cost during peak and off
peak load hours can be used for the overall energy loss cost
Index Terms-- Distribution transformers, Power system calculation, instead of a mean energy loss cost value that is
economics. usually adopted in the TOC method. The method is applied
in real-life study cases and sensitivity analysis is carried out,
I. INTRODUCTION yielding detailed results of the substantial overall economic
parts of a power system (power station and lines are the II. TRANSFORMER ECONOMIC EVALUATION
remaining elements). For power generation projects most
expenditure, in the form of operational cost, i.e. fuel and so A. Input Data of the Study Case
on, as well as income occur after commissioning. Such In this section, a real-life example of a detailed analysis
future financial flows will take place during different times for the least-cost choice of a transformer is presented. It
and circumstances. Correspondingly, these will have shows how the higher price of a facility can be traded against
different value of money than flows occurring during project its operational cost over its life span. The example considers
evaluation. Thus, the time value of money and the choice of two offers for distribution transformers. Different
a proper discount rate are highly important for capital transformer designs can be developed to meet the
intensive long-life projects with large operational cost, like requirements of a particular transformer specification. These
those of an electrical power system. designs will have varying amounts of core steel and copper
Since transformers constitute some of key energy- or aluminum conductors with differing no-load and load
consuming products in power systems (contributing to both losses. The lowest cost design that meets all the applicable
variable and fixed network losses), the cost-effective performance standards and requirements is generally
potential from the selection of improved energy efficiency referred to as the standard efficiency design [11]. In the
during the installation of new transformers or the retrofitting examined case study. the first transformer offer is the
of existing transformers can result to significant benefits for standard efficiency design, corresponding to lower bid price
electric utilities [1]-[3]. This trend is also enhanced by the but higher losses. The two transformer offers have the
recent developments in transformer technology, able to technical characteristics presented in Table I.
provide high efficient designs at a non restricting
manufacturing cost. The decision as to whether to purchase a TABLE I
low-cost, inefficient transformer or a more expensive, TRANSFORMER TECHNICAL SPECIFICATIONS
energy-efficient transformer, is primarily an economic one Transformer Size Bid Price No load losses Load losses
[4]. A common practice used for determining the cost- (kVA) (€) (kW) (kW)
effectiveness of distribution transformers is based on the Offer A 1000 9074 1.1 9
total owning cost (TOC) method, where TOC is equal to the Offer B 1000 11362 0.94 7.6
sum of transformer-purchasing price plus the cost of
transformer losses throughout the transformer lifetime [5]. The transformers are assumed to be loaded at 50% of full
Different implementations of the TOC method are load at the first year, and each year there is 3.7% increase of
encountered in the relevant bibliography, adopted by electric the load. Fig. 1 illustrates the transformer load factor
utilities [6]-[8] or industrial and commercial transformer variation during the study period. In this study case, the
users [9],[10]. expected life of the project is 30 years and a discount rate of
In the present paper, an assessment of the benefits 6% is considered.
resulting from the installation of energy efficient In order to choose the least-cost solution it is required to
consider the total cost of the project over its expected life
Φ
E. I. Amoiralis is with the Department of Production Engineering & span. This includes the bid price of the two transformers plus
Management, Technical University of Crete, GR-73100, Chania, Greece (e- their discounted cost of losses, i.e. no load losses and load
mail: eamir@tee.gr).
M. A. Tsili and A. G. Kladas are with the Faculty of Electrical & losses. It is assumed that reliability of the transformers will
Computer Engineering, National Technical University of Athens, GR- be the same as well as their maintenance cost. For the sake
15780, Athens, Greece (e-mail: mtsili@central.ntua.gr, of simplicity, these were ignored from the comparison. The
kladasel@central.ntua.gr).
10
8 well as the annual energy corresponding to off-peak load
6 losses, LLop (kWh), are computed as follows:
4
2
LLp = 2.25 kW ⋅16h ⋅ 365 ⋅ 0.522 = 6853 kWh
0
LLop = 2.25 kW ⋅ 8h ⋅ 365 ⋅ 0.522 = 3426 kWh
0 5 10 15 20 25 30
study period (years)
Therefore, the energy corresponding to the total losses,
Fig. 3. Annuity factor variation, based on the input data of Table I. i.e. load losses and no load losses, of peak (TLp in kWh) and
off-peak rate (TLop in kWh), are given based on the
C. Economic evaluation of offer A
following equations:
Costs of no load losses and load losses are calculated at n
the peak (16 hours) and off-peak rate (8 hours). TLp = ∑[ ( LLp (i) + NLLp (i) ) ⋅
Since no load losses are constant through the study i =1 (4)
period, the annual energies corresponding to peak and off-
peak no load losses values, NLLp and NLLop respectively, are ( annuity factor (i) − annuity factor (i −1) ) ]
computed as follows:
NLLp = 1.1kW ⋅16h ⋅ 365 = 6424 kWh n
TLop = ∑[ ( NLL op (i) + LLop (i) ) ⋅
NLLop = 1.1 kW ⋅ 8h ⋅ 365 = 3212 kWh i =1 (5)
In order to compute the energy corresponding to the peak ( annuity factor (i) − annuity factor (i −1) ) ]
and off-peak load losses values, transformer loading per year where the index i refers to the current year of the study (i.e.
should be taken into account. To be more precise, based on NLLop(3) is the energy corresponding to off-peak no load
Table II, the annual energy losses corresponding to peak and losses of the third year), and annuity factor (-1) is equal to
off-peak load losses for Offer A are calculated (Table IV). zero.
Using eq. (4) and eq. (5), we get:
TABLE IV
ANNUAL ENERGY CORRESPONDING TO LOAD LOSSES OF OFFER A TLp = 157655kWh and TLop = 315309kWh
Year Annual energy Annual energy The cost of losses of peak (CLp in €) and off-peak rate
corresponding to corresponding to off-
(CLop in €) are:
peak load losses peak load losses (kWh)
(kWh) CLp = 315309kWh ⋅ 0.087euros / kWh ⇒
1 6853 3426
2 7341 3670
CLp = 27432euros
3 7863 3932 and
4 8423 4212 CLop = 157655kWh ⋅ 0.043euros / kWh ⇒
5 9023 4512
6 9666 4833 CLop = 6779euros
7 10355 5177 Thus, the total cost of offer A is the summation of the
8 11092 5546 cost of losses (peak and off peak rate) and the price of the
9 11882 5941 transformer A, namely:
10 12728 6364 Offer A cos t = CLp + CLop + Bid Pr ice ⇒
11 13635 6818
12 14606 7303 Offer A cos t = 27432 + 6779 + 9074 ⇒
13 15647 7823
Offer A cos t = 43285euros
14 16761 8380
15 17955 8977 D. Economic evaluation of offer B
16 19234 9617 Costs of no load losses and load losses are calculated at
17 20603 10302 the peak (16 hours) and off-peak rate (8 hours).
Since no load losses are constant through the study CLp = 267154kWh ⋅ 0.087euros / kWh ⇒
period, the annual energies corresponding to peak and off-
peak no load losses values, NLLp and NLLop respectively, are CLp = 23242euros
computed as follows: and
NLLp = 0.94 kW ⋅16h ⋅ 365 = 5490 kWh CLop = 133577kWh ⋅ 0.043euros / kWh ⇒
NLLop = 0.94kW ⋅ 8h ⋅ 365 = 2745 kWh CLop = 5744euros
In In order to compute the energy corresponding to the Thus, the total cost of offer B is the summation of the cost
peak and off-peak load losses values, transformer loading of losses (peak and off peak rate) and the price of the
per year should be taken into account. As in the case of Offer transformer B, namely:
A, based on Table II, the annual energy losses corresponding
to peak and off-peak load losses for Offer B are calculated
Offer B cos t = CLp + CLop + Bid Pr ice ⇒
(Table V). Offer B cos t = 23242 + 5744 + 11362 ⇒
TABLE V
ANNUAL ENERGY CORRESPONDING TO LOAD LOSSES OF OFFER B Offer B cos t = 40348euros
Year Annual energy Annual energy For the above analysis it is clear that the life span cost of
corresponding to peak corresponding to off- the first alternative Offer A is 43285€, while that of Offer B
load losses (kWh) peak load losses (kWh) is 40348€. These values correspond to a difference of 7.3%
1 5787 2893 between the cost of Offer A and Offer B. Fig. 4 presents the
2 6199 3099 participation of bid price and peak and off-peak rate loss
3 6640 3320 costs in the overall costs of the two offers.
4 7113 3557 Cost of off-peak rate losses (€)
5 7620 3810 50000 Cost of peak rate losses (€)
Bid price (€)
6 8163 4081 45000
7 8744 4372 40000 6779
8 9367 4683 35000
5744
9 10034 5017
30000
10 10748 5374
Cost (€)
10 2007.
[11] N. Haggerty, T. Malone, J. Crouse, “Applying high efficiency
transformers,” IEEE Industry Applications Magazine, vol. 4, no. 6, pp.
0
50-56, Nov. 1998.
-20 -15 -10 -5 0 5 10 15 20 [12] Hellenic Transmission System Operator. Load, System Marginal Price
-10 and Interconnection Data. Available:
http://www.desmie.gr/content/values_xls.asp?lang=1.
-20 [13] W. G. Sullivan, E. M. Wicks, and J. T. Luxhoj, Engineering Economy.
Prentice Hall, 13th edn., 2006.
-30
V. BIOGRAPHIES
-40
Parameters variation (%) Eleftherios I. Amoiralis was born in Greece, in 1980. He received the
Diploma in Production and Management Engineering, the M.Sc. in
Fig. 5. Sensitivity Analysis.
Industrial Engineering, and the Ph.D. degree in the field of Electric Power
Systems from the Technical University of Crete (TUC), Greece, in 2004,
III. CONCLUSIONS 2005, and 2008, respectively. From 2005 to present, he is with Schneider
Electric AE as a freelancer. In 2001 and 2002, he has worked as an intern at
In the present article, the importance and the potentials to the Public Power Cooperation, of Greece. Since 2004, he has been occupied
improve power systems efficiency through the installation of as research associate in many research projects. His current research
energy efficient transformers was investigated. The analysis interests include transformer cost evaluation, energy-efficient transformers,
optimal transformer sizing, transformer design optimization as well as
was performed through proper transformer economic artificial intelligence. Dr. Amoiralis is member of IEEE and the Technical
evaluation methods, taking into account the energy loss Chamber of Greece.
consumption and its daily price fluctuation, revealing new
Marina A. Tsili was born in Greece, in 1976. She received the Diploma in
aspects that must be taken into account during the definition Electrical and Computer Engineering in 2001 and the Ph.D. degree in 2005
of the transformer purchasing policy of electric utilities. The from the National Technical University of Athens, Greece. From 2005 to
main conclusions of the study can be summarized as 2006 she worked for the Distribution Division of the Public Power
Corporation of Greece, in high and medium voltage substation studies. In
follows: i) investment to low efficiency decreases the initial 2007, she joined the Hellenic Transmission System Operator as a power
capital cost, but results to higher energy costs during the systems engineer. Her research interests include transformer and electric
transformer lifetime, yielding transformers with low machine modeling as well as analysis of generating units by renewable
energy sources. She is a member of IEEE and the Technical Chamber of
manufacturing cost non-profitable in the long term, ii) the Greece.
choice of the most profitable among transformers with high
degrees of efficiency must be based on the optimum balance Antonios G. Kladas was born in Greece, in 1959. He received the Diploma
between the initial purchasing cost and the energy savings in Electrical Engineering from the Aristotle University of Thessaloniki,
through the transformer lifetime. The proposed analysis can Greece in 1982 and the DEA and Ph.D. degrees in 1983 and 1987,
respectively from the University of Pierre and Marie Curie (Paris 6), France.
be easily expanded to take into account different scenarios of He served as Associate Assistant in the University of Pierre and Marie
energy pricing and loading variation (according to the Curie from 1984-1989. During the period 1991-1996 he joined the Public
conditions that occur during winter or summer season and Power Corporation of Greece, where he was engaged in the System Studies
Department. Since 1996 he joined the Department of Electrical and
the type of the served load) and investigate their effect on the Computer Engineering of the National Technical University of Athens
profit from the installation of high efficiency transformers. (NTUA), where he is now Professor. His research interests include
transformer and electric machine modeling and design as well as analysis of
generating units by renewable energy sources and industrial drives.
IV. REFERENCES
[1] Leonardo Energy, “Analysis of insufficient regulatory incentives for
investments into electric networks. An update,” Final Report
submitted to European Copper Institute (ECI), KEMA, Bonn, January
2009.