MISSION INFORMATION
COUNTRY Indonesia
Overall performance
Red: Rated less than 2: Unsatisfactory, needs major overhaul and immediate
attention by IDB
PROCESSING
Project Officer
Division Manager
Clearance
1
Project Implementation Assessment Report
ABBREVIATIONS
2
Project Implementation Assessment Report
EXECUTIVE SUMMARY
The Mission visited and met the local communities (VCCs, KSMs, Facilitators,
volunteers, Local Government, etc.) in three Kelurahan (urban villages) in West Java
(Bekasi and Bogor) on July 1, and three Kelurahan in Aceh on July 4, 2010, along
with staff and experts of the Executing Agency (MOPW), BAPPENAS and MOF.
3
Project Implementation Assessment Report
Overall, 82% (i.e. 4013 out of 4871) Kelurahan (Urban Villages) across the project
locations have finalized the 'Open-Menu' and are eagerly awaiting the disbursement
of funds to begin implementation, with the remaining expected to be completed by
July 2010.
Overall rating is Green due to the implementation process and the results both in
community level and local government level is satisfactory.
4
Project Implementation Assessment Report
PART - 1: BASIC PROJECT DATA (basic project information inputted into the
system soon after appraisal – remains constant.)
1. PROJECT KEYS
Country Indonesia
5
Project Implementation Assessment Report
Loan Istisna’a
Number of Extensions 0 0
6
Project Implementation Assessment Report
S#
Cost
A. Block Finance
Components
(Description)
6.217
2.171
B Capacity B
Development
C. Communication and Advocacy - 0.985 0.033 1.018
D. Monitoring and Evaluation - 0.239 - 0.239
E. Consultancy Services (incl. Facilitators) - 0.051 - 0.051
F. PMU - - 0.330 0.330
G. Start Up Workshop - 0.030 - 0.030
H. Familiarization with IDB Procedures and - 0.009 - 0.009
C Communic
Guidelines
I. Financial Auditing - 0.025 0.003 0.028
Total Base Cost 7.887 2.206 10.093
Contingencies (Physical & Price) - 0.789 0.221 1.009
Total Project Cost - 8.676 2.426 11.102
7
Project Implementation Assessment Report
- 1 ID Tk - 1.53
Financing Plan
US$ equivalent, million
Parties Terms
Amount Repayment Grace
Service Fee/Mark Up Guarantee
period Period
IDB 8.676 0.014 18 yrs 7 yrs
Government 2.427 0.24
0.48
Total 11.102 0.981 25 yrs -
8
Project Implementation Assessment Report
9
Project Implementation Assessment Report
No. Name
A
B Signing of the F
10
Project Implementation Assessment Report
1 Setting up of PMUs
Baseline &
OCs NMC Comm
2 Procurement of Consultants Facilitator & City
Coord.
3 Training/Capacity Building
10 Project Completion
LOAN
ISTISNA'A
11
Project Implementation Assessment Report
(USD) (USD)
12
Project Implementation Assessment Report
13
Narrative Summary Performance Target
Goal:
1. Reduction of poverty in 14 Project
1. 5-10% Implementation
Increase Assessment
in the Gross Income level ofReport
the 14
Provinces of Indonesia Provinces, 5 years after project completion (pc)
Purpose:
1. Improve the socio-economic 1. At least 1/3 of 4,871 urban villages (Kelurahans)
conditions of the population of targeted by the project graduate from the list of
111 districts within the project 'less-developed areas', 2 years after pc
area, especially women and the 1a. All 4,871 Kelurahans provided with at least 20%
poorest of key necessary infrastructure (access roads,
1a. Improve the physical and water & sanitation, schools, health centres,
social infrastructure in the markets, etc) , 1 year after pc
target areas 1b(i). At least 20% of the vulnerable/ dependant in
1.b Contribute to the social target villages have access to basic needs, and
security of the percentage of orphans receiving scholarships
vulnerable/dependant in the graduate from secondary school, 2 years after pc
communities 1c(i). Direct employment for 2.4 million people (50%
1.c Facilitate economic growth women) and indirect employment for 5.0 million
and livelihood development people from the target population, 1 year after pc
1c(ii). Trade volume in the project area increases by
10%, 1 year after pc
1c(iii). Skilled jobs and micro-enterprises increases by
15%, 2 years after pc
2(i). At least 3000 sustainable self-help groups
operating within the communities and at least USD
2. Build the capacity and skills of 2.5 million worth of micro-credit provided to the
the communities and local communities, 2 years after pc
institutions 2(ii) The Institutional Capacity of the MOPW and
Local Govt. is strengthened to manage and
implement Community Empowerment and
Development programs, after pc
Outputs:
This table will apply for the first “project launch” mission; should remain same for
following PIARs.
Ratings (1-4)1
1 PIU/PMU
1
Please refer to Annex I “the Performance Rating Scale “ for definition of ratings
15
Project Implementation Assessment Report
PHYSICAL PROGRESS
Overall physical progress is generally satisfactory with the procurement processes for certain consultancy
assignments to be expedited.
Component Implementation Status Issues/Recommendation
1. Block Finance 1. 78,2% of Block Finance has already 1. 21,8% of Block Finances began
been disbursed and utilized by the disbursing in April 2010 and 100%
community with 100% physical physical completion is expected by March
completion by March 2010 2011
2. Consultancy Services
2.a. Facilicators and city coordinators
2. a. –
have established in May 2009
b. NMC will be established in July b. NMC assignment awaiting clearance of
2010 revised Draft Contract by IDB. To be
mobilized by July 2010
c. OCs have been established in Jan c.-
2010
d. – Awaiting clearance of 1st phase of
d. Baseline contract is waiting for consultant qualification evaluation by IDB.
3. Capacity Building and selection consultants clearances To be procured by August 2010
Institutional Development for IDB
3. a.Advanced training for KSM
strengthening, Livelihood development
3.a. Awareness activities and Basic have not been completed since EA is
and intermediate Training at awaiting for the NMC mobilization
community and local government
level have been implemented and b. there is a proposal to utilize balance of
4. Communication and are satisfactory contingencies for printing material costs,
Advocacy b. There is no no budget for printing once all major activities are completed.
material for training modules and
kits/media socialization. 4. To expedite the procurement, the
5. Monitoring & Evaluation consultant to be procured through
(MDGs) 4. TOR and Procurement process Consultant Qualification method of
under preparation Evaluation
6. PMU 5.- IDB is facing delays in procurement and
5. The Procurement is underway by is seeking alternative ways of undertaking
IDB the assignment.
7. Start Up Workshops 6. Increase the capacity of PIUs at local
6. PMUs and PIUs established at levels to improve coordination and
16
Project Implementation Assessment Report
8. Familiarization Visit to IDB 7. This Activities already included in 7. This start-up/ orientation workshop is
HQ NMC Contract and will be held after intended to serve as awareness of the ICDD
mobilization of NMC project to national stakeholders
9. Financial Auditing
8. Already done 8. Already done
10. Contingencies
9. in the process audit by BPKP 9. Report will be submitted by September
(national audit) 2010
10. Some funds of the Loan 10. Used some of the contingencies for
Contingencies have been utilized consultancy
17
Project Implementation Assessment Report
18
Project Implementation Assessment Report
Adherence to Cost
Components Total Estimated Cost at Actual Cost (cumulative) Variation Highlight the main findings,
Appraisal up To This Mission (%) any issues and suggested
remedial actions
Total IDB GOI Total IDB GOI Follow-up By By
actions when whom
A. Block Finance 88.911 56.91 32.00 46.15 20.3 Completed
1 0 by 2010
B. Capacity Building and Institutional 5.599 5.599 -
Development
C. Communication and Advocacy 0.100 0.100 - 0
D. Monitoring and Evaluation 0.100 0.100 - 0
E. Consultancy Services (incl. 29.571 19.71 9.857 5.12 11.1
Facilitators) 4 54
19
Project Implementation Assessment Report
Services :
20
Project Implementation Assessment Report
21
Project Implementation Assessment Report
22
Project Implementation Assessment Report
COUNTERPART FUNDING
2
Partners Counterpart disbursements Rating Recommendations to improve the
rating
0–4
Average score 4
2
Please refer to Annex I “the Performance Rating Scale “ for definition of ratings
23
Project Implementation Assessment Report
Planned %
Actual
SampleGraph showingCumulative
Disbursem Variance
Disbursemen
ent
Year t
US$
US$ million
million
2010 33 60 - -100%
n
50
40
30
20 24
Project Implementation Assessment Report
MONITORING SYSTEM
Please review and rate the monitoring system of Rating 3 Recommendations to improve the
the project to date since the effectiveness date (or 0–4 rating
last mission). This Last Follow-up By whom and
mission mission actions when
Rate Rate
Improve M&E By EA,
M&E framework in place that outlines performance framework, Advisory and
indicators and methods of data collection for each 3 3 strengthening NMC
indicator, when and by whom using new
applications for
data collection
Need updated By EA,
Base line data is available or defined 3 3 information and Advisory and
verification Baseline
Consultant
Need regular By EA, NMC,
training, esp. to OC and City
Dedicated staffs to run the system available 3.5 3 increase Coordinator
competency on
running M&E
system
Reporting and By EA and NMC
Regular reporting about the progress towards results and
2.75 3 updating of MIS
the problems during implementation system needs
improvement
M&E system used by the executing agency, the Bank and Not yet accessed
3.5 4
other stakeholders by IDB
3
Please refer to Annex I “the Performance Rating Scale “ for definition of ratings
25
Project Implementation Assessment Report
(If a results framework was established at appraisal, fill in the table below, otherwise provide brief
narrative)
4
Please refer to Annex I “the Performance Rating Scale “ for definition of ratings
26
Project Implementation Assessment Report
3. Community 3.All villages submit 4871 4866 Expedite VCC contin VCCs &
needs identified final 'Open menus', Villages Villages facilitation ues commu
and prioritized which are accepted -nities
4 3
in Open Menus by the
communities, by
month 6-8
4. Block 1.Block Finances 4871 Partial 21,8% of Block April VCCs &
Finances released in three Villages disbursem Finances will untill commu
disbursed to tranches of 30% ent made be disbursed Dec -nities
all target (upon final approval to 4866 and utilized by 2010
Kelurahans of Open Menus), kelurahan the community
50% (upon 20% . 3805
3 3
progress) and 20% kelurahan
(upon 60% have
progress) to be 100%
disbursed physical
completely by 2010 completio
n
5. All Kelurahan- 1.All villages 4871 3805 21,8% of the April VCCs &
level implement and Villages kelurahan Open Menu will untill commu
community complete the have be completed Dec -nities
projects activities described complete 2010
3 -
completed in the Open Menus d 100%
by 2012 open
menu
activities
6. Self-Help 3000 SGHs 3000 Although 4 - only about July Advisor
Groups established and SGHs in 106.277 10.000 SGHs untill NMC,
formed and trained, 36 months 4871 KSMs have got the Dec Nationa
active after project start Villages have on the job 2010 l
been training Trainer
establishe related with s, OCs
d, the admi-nistration and
number of for book Facilita
sustainabl keeping . rs
e, Incresing
KSMs/SHG the SGHs
27
Project Implementation Assessment Report
s is capacity about
17,575 livelihood,
economic economic
SGHs/KSM development
with and syariah
99167 system
members
7. Project well- Capable and Month 1.PMU 1.M & E will be July PMU &
coordinated, efficient PMUs and 10 estabishe handle by 2010 IDB
recorded, Consultants d on Jan IDB team
monitored established and 09 2.Communicati
and operational at 2.Local on &
supervised National, Provincial PIU Advocacy
and District levels establishe will be
by month 4, d on Jun integreted in
Monitoring and 09 NMC
Evaluation (M&E) 3. Contract
Specialist in place Facilictrs
by month 10 & city
3 -
cord.
establishe
d on May
09
4.NMC will
be esta-
blished on
July 2010
5.OCs
establishe
d on Jan
10
8. Capacity 4. Total 14598 3 3 Continuous July IDB,
Building participants/ members training and untill PMU,
community training from 4866 need Dec Advisor
VCCs strangthen the 2010 y&
318831 moduls related NMC
28
Project Implementation Assessment Report
Guidance Note: This table is to be filled when applicable, e.g. when a project is at a stage when results
have started to emerge.
29
Project Implementation Assessment Report
30
Project Implementation Assessment Report
under ICDD
phase2. The
project intends to
mitigate this risk
by piloting the
concept to poverty
programs
managed and
implemented by
the Ministry of
Public Works, since
it is the
implementing
agency under the
project
Lack of There is a risk that
Commitment and the capacity of
Capacity of Local local government
Government to is not sufficient to
support community support PNPM
Programs programs at the
Kelurahan level
and to ensure that
they are aligned
with broader city
investment and
physical planning.
Under the
proposed project
funds will be
available to
provide capacity
building to local
governments.
32
Project Implementation Assessment Report
Average score 2
Rate 4 – almost zero risk; Rate 3 – low risk; Rate 2 – risky; Rate 1 – high risk; Rate 0 – very high risk
33
Project Implementation Assessment Report
34
Item Issue Follow-up Action Responsible Current Status
1. Block Finance In EA monitoring • MOF and IDB to sign IDB 100% of Kelurahan have
(Istisna’a) status, 4013 (82%) Agreement and IDB to finished the Open Menu
Disbursement Kelurahan have now disburse Project Implementation
MOPW Assessment
and 78.2% of block Report
finished the open • Review Community finance has been
menu, but it’s only Plan based on disbursed and these
(75.6%) that were infrastructure, social 78.2% kelurahan have
included for and econ. activities achieved 100% physical
preparation of first • Review Community completion
Istisna’a disbursement. Plan based on
The Total amount of handling of the
Istisna’a to be impact earthquake in
disbursed first is about West Sumatera
Rp 507,65 M or US$ • Disburse Istisna’a to
46,15 million BKM account
• Disburse and utilize
Block Grant to
Community (KSM)
2. Consultant a. Delay in NMC o Submission Shortlist MOPW
Services (Incl. procurement of NMC
Facilitators) o Submission technical Procurement is complete
evaluation of NMC and awaiting clearance of
o Sub mission final draft contract for signing
evaluation and of contract and
contract clearance of mobilization
NMC
o Mobilization of NMC
b. Delay of OCs • Approval of Revised MOF
All OCs have been
Mobilization National Budget
mobilized by January 2010
• Mobilization of OCs
c. Mobilization of Done
facilitators Team and
done
City Coordinator team
3. Training and a. Training of • Serial Discussions, Advisory & IDB Although a draft version
Awareness Livelihood, Pro Poor, workshops and Team was prepared by EA &
Program and Economic Growth studies to understand advisory consultant, there
for Facilitators in and finalize the will be a completed
Intermediate/ Advanced curriculum content for curriculum enhancement
Locations Training of Livelihood Advisory & IDB during Phase-II of the
(KSMs will be active and Economic Growth team project.
when the revolving • Training of Trainers NMC and OCs
Fund has been for NMC and OC’s supervised by
disburshed to BKM, on related with Advisory 35
March or April 2010) Livelihood Facilitator & City
• Training of City Cord.
Project Implementation Assessment Report
RECOMMENDATIONS AND FOLLOW-UP ACTIONS (Summarize below key findings and recommendations)
b. The Budget is only for • Budget allocation for the July 2010 Advisory, CB
Training activities in Basic printing material of training NMC and &
and Intermediate location, modules in basic and IDB
but there is no budget for intermediate locations
printing material of
modules
c. The Budget is only for • Budget allocation for the Kits August 2010 Advisory, CB
Socialization and and Media Socializations in NMC and &
awareness activities basic and intermediate IDB
locations
4. a. Communication and The Procurement Process Will Sept 2010 MOPW & IDB
Communication Advocacy activities at be finalized
and Advocacy community and local
government level has
been done but with small
support of kits and media
b. Maximize impactful Arrange the communication Oct 2010 Advisory,
activities at national level and advocacy at national level NMC and &
(TV, national newspaper, etc) IDB
5. Monitoring Procurement of Firm to • Finalizing the August 2010 for MOPW & IDB
and Evaluation Handle Baseline Study procurement process. procurement
(MDGs) and Mid Term Review is • Using MIS existing as
still going on basis of baseline data until
the firm/ individual
consultant of M&E is
mobilized to verify/update
data
6. Project The PMU was established Support the capacity of PMU May-July 2010 Advisory,
Management at national, provincial and at all level to provide social MOPW
Units (PMU) city level since February and technical assistance to
2009 until now the communities and local
government
7. Start-up Plan the structure and a. Workshop of Review and Sept 2010 Advisory,
Workshops scope of the Start-up develop ICDD program design PMU, MOPW
Workshops due to wide (Preparation of Program) & IDB
coverage. To be done in
close coordination with
IDB FR
37
Project Implementation Assessment Report
38
SUGGESTED ANNEXES (As required)
3. Organizational structure
8. Aide Memoire
9. Action Letter
SUMMARY OF PROJECT COST5
S#
A Block Financ
B Capacity Bui
5
C Communicati
Add footnote for any component for which financing plan has been modified, e.g. additional financing, cancellation, project
scope changes, etc.
- Specialist fi
ANNEX I: PERFORMANCE RATING SCALE
Overall Assessment
The overall assessment would be the simple un-weighted average of
scores for all indicators, under each criteria/sub-criteria. This will be
determined by adding all rating scores and dividing the total by the
number of component indicators. The numerical average will then be
converted into descriptive ratings as follows:
Highly Satisfactory (HS) 3< R≤ 4
Satisfactory (S) 2<R≤ 3
Partially Satisfactory (PS) 1<R≤ 2
Unsatisfactory (US) 0.5<R≤1
Highly Unsatisfactory (HUS) 0<R≤0.5
ANNEX 2
Detailed Financing Plan
IDB PNPM - Integrated Community Driven Development Project, Indonesia
Amounts in USD Millions
S# Items IDB % IDB Total IDB % GOI GOI % Total
Istisna'a Loan
A Block Finance 56.911 56.911 64% 32.000 36% 88.911
B Capacity Building and Institutional Development 5.599 5.599 100% 5.599
C Communication and Advocacy
- Specialist firm 0.050 0.050 0.050
- Documentation and Audio/Visual Expenses 0.050 0.050 0.050
Sub-Total 0.100 0.100 100% 0.100
D Monitoring and Evaluation (MDGs)
- Specialist 0.090 ♦ 0.090 ♦
- Baseline Study (incl. socio-economic survey) 0.050 0.050 0.050
- Mid-Term Evaluation and Final Assessment 0.050 0.050 0.050
Sub-Total 0.100 0.100 100% 0.100
E Consultancy Services (incl. Facilitators)
- National Management Consultant 0.483 0.376 0.859 0.430 1.289
- Oversight Consultant (Provincial level Consultant) 3.086 2.400 5.486 2.743 8.229
- City Coordinators (District level Consulant) 1.713 1.028 2.741 1.371 4.112
- Facilitators 5.807 4.958 10.765 6.611 17.376
Sub-Total 11.089 8.762 19.851 64% 11.154 36% 31.005
F Project Management Unit (PMU) 2.000 100% 2.000
G Start-up Workshops 0.075 0.075 100% 0.075
H Familiarization with IDB procedures and guidelines 0.025 0.025 100% 0.025
I Financial Auditing 0.100 100% 0.100
Base Cost 68.000 14.661 82.661 65% 45.254 35% 127.915
J Contingencies (total 8% Physical & Price for all components except A and E) 0.339 0.339 0.339
Grand Total 68.000 15.000 83.000 65% 45.254 35% 128.254
The Block Finance will be utilized for Infrastructure, Social and Economic activities based on the priority needs of the communities reflected in the 'open menus'
Full-fledged modular-based training and awareness raising activities on social mobilization, community empowerment and building of pro-poor institutions
♦ This specialist will be financed by IDB outside the project cost
ANNEX 3: IDB Loan Fund Withdrawal Recapitulation - PNPM 2009 (as per first quartal of
F.y. 2010)
FamiliarizationwithIDB
7 25.000,00 235.000.000 - - - - -
procedures andguidelines