BESTRODE SDN BHD

UNIT #2 MINOR OVERHAUL WORKS 2019

INSPECTION REPORT
EQUIPMENT/ TAG NO. : LOW PRESSURE HEATER 7
PMT NO. : SW PMT 4004

Table of Content
1.0 Visual Inspection Report
2.0 Final Inspection Report
3.0 UT Thickness Gauging (UTTG) Report
4.0 Magnetic Particle Inspection (MPI) /
Dye Penentrant Test (DPT)
5.0 DOSH Repir Procedure
6.0 Dosh Repair Report
7.0 Radiographic (RT) Testing Report
8.0 Box Up Certificate
9.0 Equipment Drawing
BESTRODE SDN BHD

EQUIPMENT BOX UP CERTIFICATE


EQUIPMENT/ TAG NO. : LOW PRESSURE HEATER 7
PMT NO. : SW PMT 4004
ITEM DESCRIPTION : UNIT #2 MINOR OVERHAUL WORKS 2019

1. It is hereby certified that the equipment referenced has been inspected, tested and accepted
in accordance with the attached acceptable records and other documents.

2. All the works in the equipment have been completed and complied
with all engineering standard and required procedure.

3. This is to certify that the equipment is ready for box up

INSPECTED BY NAME SIGNATURE DATE TIME


Bestrode SB

MPG

DOSH/ 3rd Party


BESTRODE SDN BHD

VISUAL INSPECTION REPORT


EQ./ TAG NO. : LOW PRESSURE HEATER 7 Report No. : BR/MPG/VI-06
PMT NO. : SW PMT 4004 Date : 5/02/2019
Project : UNIT #2 MINOR OVERHAUL WORKS 2019 Page :

Finding Recommendation
External External
1. Nameplate securely attached 1. Nil
2. No significant mechanical damage - Channel & 2. Nil
Nozzle
3. No significant pitting, corrosion & erosion after 3. Secure all bolt and nut, clean and apply anti seize
insulation removed - Head
4. No significant coating failure except few small spot 4. Touch-up paint

Internal Internal
1. Internal floating head and tubesheet face observed 1. The internal surface vessel, gasket surface &
with red residue oxidation partition plate should be mechanically cleaning
2. No solid particle or residue observed in inlet and 2. Cleaning
outlet nozzle
3. Gasket surface - gasket residue left, no erosion, 3. Cleaning
corrosion and pitting observed
4. Observed crack on partion plate 4. To do NDT (MPI) to identify defect

Remarks
1. Procedure to establish to carry out crack repair on partition plate

PREPARED BY REVIEWED BY VERIFIED

Name : Name : Name :


Date : Date : Date :
BESTRODE SDN BHD

ATTACHMENT/ EQUIPMENT PICTURE


EQ./ TAG NO. : LOW PRESSURE HEATER 7 Report No. : BR/MPG/VI-06
PMT NO. : SW PMT 4004 Date : 5/02/2019
Project : UNIT #2 MINOR OVERHAUL WORKS 2019 Page :

1.0 - Equipment before dismantling

2.0 - Channel after dismantle

3.0 Equipment Nameplate


3.0 - Nameplate

4.0 Tubesheet

5.0 Piping Inlet - Tube side

6.0 Partition plate - Channel

Remarks :