SCOPE OF WORK

PROJECT: PROPOSED EXPANSION OF AVIONICS OFFICE


ITEM UNIT COST TOTAL COST
DESCRIPTION UNIT QTY GRAND TOTAL
NO. MATERIAL LABOR MATERIAL LABOR
2
A Demolition of Dry Wall Partition 35 m 3,821.15 133,740.12 133,740.12
B Dry Wall Partition 55 m2 3,889.34 213,913.56 213,913.56
Hardiflex 1/4" 34 shts 1,105.00 37,570.00 37,570.00
Metal Tracks (2 x 4 x 1.2mm) 10 pcs 845.00 8,450.00 8,450.00
Metal Studs (2 x 4 x 1.2mm) 21 pcs 845.00 17,745.00 17,745.00
Blind Rivets, 3/8 3000 pcs 1.95 5,850.00 5,850.00
Concrete Nail 3 kg 156.00 468.00 468.00
Channel Bar 4 x 7.25# 7 pcs 4,290.00 30,030.00 30,030.00
C Carpentry Works
Cabinets (ht of 3.5meters) 429 m2 290.80 124,753.48 124,753.48
Channels 2 x 3 x 2.0 mm 15 pcs 2,431.00 36,465.00 36,465.00
Tubular 1 x 2 x 1.0mm 79 pcs 455.00 35,945.00 35,945.00
Angle Bar 1 x 1 x 5mm 20 pcs 682.50 13,650.00 13,650.00
Plyboard 3/4" 50 shts 1,235.00 61,750.00 61,750.00
Expansion Bolt 180 pcs 45.50 8,190.00 8,190.00
Screw 4000 pcs 3.90 15,600.00 15,600.00
Welding Rod 5 box 2,860.00 14,300.00 14,300.00
Consumables 429 m2 155.27 66,612.00 66,612.00
Wall Mounted Cabinet (ht = 80cm) 83 m2 1,503.05 124,753.48 124,753.48
Plyboard 3/4" 21 shts 1,235.00 25,935.00 25,935.00
Plywood 1/4" 7 shts 468.00 3,276.00 3,276.00
Good Lumber 2 bd.ft. 2,100.80 4,201.60 4,201.60
Hinges 10 pcs 65.00 650.00 650.00
Stainless Handle 5 pcs 455.00 2,275.00 2,275.00
Consumables 83 m2 306.52 25,441.00 25,441.00
Wooden Table Counter (W = 65cm) 34 m2 3,669.22 124,753.48 124,753.48
Plyboard 3/4" 8 shts 1,235.00 9,880.00 9,880.00
Good Lumber 75 bd.ft. 97.50 7,312.50 7,312.50
Bolts and Screw 1 lot 5,200.00 5,200.00 5,200.00
Consumables 34 m2 402.62 13,689.00 13,689.00
D Doors and Windows
Transfer single swing door. Repair, Paint
4 m2 747.50 7,136.34 2,990.00 28,545.35 31,535.35
and Install Accs.
Supply and Installation of Swing Metal
2 m2 8,125.00 14,272.68 16,250.00 28,545.35 44,795.35
Door, 30cm x 210cm
2
Supply fixed glass, 80cm x 100cm 0.8 m 6,500.00 35,681.69 5,200.00 28,545.35 33,745.35
E Electrical Works 6 days 24,962.47 149,774.81 149,774.81
Rearranged of lights
Flourescent Bulb 2 pcs 1,105.00 2,210.00 2,210.00
2-Gang Switch 2 pcs 182.00 364.00 364.00
2-Gang Convenience Outlet 8 pcs 169.00 1,352.00 1,352.00
Internet Line and Outlet 4 pcs 325.00 1,300.00 1,300.00
Telephone Line and Outlet 1 pcs 260.00 260.00 260.00
Elec Conduits 1/2", 3/4" 20 pcs 1,040.00 20,800.00 20,800.00
Junction Box 2" x 4" 5 pcs 169.00 845.00 845.00
Utility Box 4" x 4" 5 pcs 234.00 1,170.00 1,170.00
3.5 mm2 THW Wire, Stranded 4 rolls 6,240.00 24,960.00 24,960.00
Electrical Tape 5 pcs 84.50 422.50 422.50
F Finish Floor 127 m2 548.04 69,601.37 69,601.37
Epoxy Rubberized Paint 14 gal 2,730.00 38,220.00 38,220.00
G Painting Works (Wall to Ceiling) 182 m2 822.94 149,774.81 149,774.81
Latex, Flat 5 gal 845.00 4,225.00 4,225.00
Latex, Semi Gloss 9 gal 845.00 7,605.00 7,605.00
Acri Color 9 gal 1,105.00 9,945.00 9,945.00
Enamel, Flatwall 5 gal 845.00 4,225.00 4,225.00
Paint Thinner 4 gal 468.00 1,872.00 1,872.00
Consumables 182 m2 56.43 10,270.00 10,270.00