Arunkumar

From: Arunkumar [a.arunkumar@isgec.co.in]


Sent: 20 March 2019 11:33
To: 'Durairaj G'
Subject: RE: PENDING WORKS - ARUNKUMAR _Final

 
 
List updated.. pl. add your pending points also to fix priority 
 
 
1. Revised TG hall layout incorporating the Stub column details as per client comment 
2. Bought out indent for Monorail and chain pulley block‐22.03.2019 
3. PMDL document deletion and reason chart for upto march month(R0) 
4. Technical clearance for AC system –SK system‐19.03.2019 
5. Techncial clearance on BHEL safety valve offer Assam Petro chemicals‐15.03.2019 
6. Technical clearance for ventilation system–SK system‐19.03.2019 
7. Technical clearance for AC system –APC‐20.03.2019 
8. Technical clearance for ventilation system–APC‐20.03.2019 
9. Technical clearance on Revised FFS offer Technico‐20.03.2019 
10. Comments / Approval on ACC GA and PID to Enexio.‐01.03.2019 
11. Approval on STG GA to Siemens – 20.02.2019. 
12. Comments / approval on ACC CEP & Drain pump calculation to Enexio. 01.03.2019 
13. Comments on AOD of ACT to paharpur vendor – 09.03.2019.  
14. Comments / approval on STG PIDs to Siemens.‐14.03.2019 
15. Comments / approval on HMBD. 01.03.2019 
16. Comments / clearance on revised BOP Pumps GA drawing – 11.03.2019. 
17. Comments / approval on STG Drain qty calculation  
18. Approval/ comments on TG deck civil loading data dwg‐18.03.2019 
19.  Approval on EOT crane  Girder GA &Girder calculation to vendor. 
20. Customer over all layout Checking & comments if any 
21. Submission of Civil input drawing for Field MCC room with AHS compressor room. 
22. Submission of Ash silo GA input for Client submission 
23. Checking for puddle pipe for Auxiliary Cooling tower basin  
24. Drafting work inputs 
a. PID of Hot gas system (From customer TP to Boiler inlet)‐For customer submission‐ 
b. GA of duct assembly with  Duct support  from ABC chamber to Boiler inlet.  
c. Revised TG hall layout – Incorporating customer comments 
d. PID of TG vendor Excluded piping 
e. AHS compressed Air system PID‐ For customer submission & vendor DDE 
f. Atmospheric Tank GA and Fabrication drawing 
g. Civil input & Puddle details for Raw water storage tank 
h. Civil input for N‐pit water tank 
i. Civil input for Boiler blow down pit 
j. Cutout and insert plate details for TG building layout (0.0m,4.5m,9m and 14.5m lvl) as  
k. Insert plate details for the ESP / AHS MCC room. 
l. Structural input for OHT supporting structure. 
m. Structural input for warmup vent supporting structure. 
 
 
 
 
 
 
1
 
From: Durairaj G [mailto:durairaj@isgec.co.in]
Sent: 18 February 2019 16:52
To: 'Arunkumar'
Subject: RE: PENDING WORKS - ARUNKUMAR
 
List updated ….. 
 
27. Comments / clearance on efficient offer for FFS – 11.02.2019. 
28. Comments / clearance on inditech offer for DSH – 12.02.2019. 
29. Comments / clearance on Chemtrol offer for DSH – 12.02.2019. 
30. Comments / clearance on CIRCOR offer for DSH – 12.02.2019. 
31. Comments / approval on EOT crane GA drawings to vendor – 13.02.2019. 
32.  Comments / approval on BOP pumps AOD to vendor. 
33. Point wise reply to Consultant for the comments on BOP pumps GA – 13.02.2019. 
34. Comments on DSH offer from Emersion – 13.02.2019. 
35. Comments / clearance on Steam trap offer from Pennant – 14.02.2019. 
36. Comments / clearance on PR Accoustics offer for silencer – 14.02.2019. 
37.  Revised Power plant plot plan submission to client and consultant. 
38. Revised TG building layout submission to client and consultant. 
39. Submission of AHS documents (As applicable) to client and consultant – 15.02.2019. 
40. Comments on AHS AOD – 15.02.2019. 
41.  Comments / clearance on safety valves offer (REC007080 REV No : 00) – 15.02.2019. 
42. .  Comments / clearance on safety valves offer  (REC007088 REV No : 00 ) – 15.02.2019. 
43.  Reply to Project team regarding Pneumatic handling system for Radiant ash. 
 
 
 
From: Durairaj G [mailto:durairaj@isgec.co.in]
Sent: 11 February 2019 11:53
To: 'Arunkumar'
Subject: RE: PENDING WORKS - ARUNKUMAR
 
List updated….. 
 
14. Comments / clearance on steam traps offer from Uniklinger – 30.01.2019. 
15. Comments / clearance on strainer offer from Abirami – 30.01.2019. 
16. Comments / clearance on strainer offer from Procedyne – 01.02.2019. 
17.  POS for ACC. 
18.  Comments / approval on STG Hall layout submitted by Siemens – 04.02.2019. 
19.  POS for EOT crane. 
20. Comments / clearance on strainer offer from Kiwkflow – 08.02.2019. 
21.  Comments / approval on BOP Pumps AOD documents – 31.01.2019. 
22.  Bought out indent for IBR & Non IBR valves. 
23. Bought out indent for AHS Compressors (If it is excluded from AHS vendor scope). 
24. Bought out indent for DM tank. 
25. POS for AHS. 
26. POS for Compressed air system. 
 
 
 
From: Durairaj G [mailto:durairaj@isgec.co.in]
Sent: 22 January 2019 18:26
To: 'Arunkumar'
Subject: PENDING WORKS - ARUNKUMAR
 

2
Following are the current pending works needs to be attended. 
 
1. Revised plot plan submission to client. 
2. Revised TG building layout to client. 
3. Comments on DV equipments offer for AC. 
4. Comments on APC offer for AC. 
5. Comments on Confonomics offer for AC. 
6. Comments on Kelvin offer for ACC. 
7. Comments on RMEBS controls offer for SOV. 
8. Comments on AP cranes offer for EOT crane. 
9. C & I Process parameter inputs to C & I. 
10. Clearance on Effimax offer for ACC. 
11. Comments on technico offer for Fire fighting system. 
12. Comments / clearance on Effimax offer for Fire fighting system. 
13. Submission of STG PIDs to client and consultant. 
 