You are on page 1of 28

PROJECT TITLE: KALAR KAHAR

DATE OF BOQ: 22/07/2017


LOCATION: KALAR KAHAR
CLIENT:
REVISION: 0

BILL OF QUANTIT

Dimensions
Sr No Descriptions of Items Nos
Length
A FOUNDATIONS
1 P.C.C (1:2:4) for footings of Coloumns
1.1 F1 2 7.5
1.2 F2 2 10
1.3 F3 7 10
1.4 F4 3 15
1.5 F5 1 25
1 Total P.C.C (1:2:4) for footings of Coloumns
2 P.C.C (1:2:4) for footing beams 1 390
Sub Total 1 & 2
3 App Steel for footings of coloumns
4 App Steel for footing beams
Sub Total 3 & 4

B GROUND FLOOR
App Excavation 1 52
1 App earth filling 1 52
2 Brick ballast for terrazo floor 1 48
3 P.C.C (1:2:4) for terrazo floor 1 48
4 Mortar (1:3) for floor tile 1 48
5 Area for floor tile 1 52
6 Vertical Coloumns
6.1 P.C.C (1:2:4) for C1 13 1.5
6.2 P.C.C (1:2:4) forC2 7 1.25
6.3 Steel for vertical coloumns
7 Floor Beams
7.1 P.C.C (1:2:4) for floor beams 1 390
7.2 App Steel for floor beams
8 Slab
8.1 P.C.C (1:2:4) for slabs 1 52
8.2 App Steel for slabs
9 Brick Work
9.1 Brick work in floors 1 400
9.2 Deductions for openings 1 33
9.3 Remaining
10 Mortar
10.1 Mortar (1:5) For brick work
10.2 Mortar (1:4) for plastering walls 2 400
10.3 Mortar (1:4) for plastering roof 1 48
10.4 Deductions for openings (1:4) 2 33
10.5 Remaining (1:4) for walls
B TOTAL FOR GROUND FLOOR
1 Brick Work (1:5)
2 Mortar (1:3) for floor tile
3 Mortar (1:4) for plastering walls
4 Mortar (1:4) for plastering ceiling
5 Mortar (1:5) For brick work
6 P.C.C (1:2:4)
7 Steel
8 App earth filling
9 Brick ballast for terrazo floor
10 Area for floor tile
11 App Excavation

C FIRST FLOOR
1 Brick ballast for terrazo floor 1 48
2 P.C.C (1:2:4) for terrazo floor 1 48
3 Mortar (1:3) for floor tile 1 48
4 Area for floor tile 1 52
5 Vertical Coloumns
5.1 P.C.C (1:2:4) for C1 13 1.5
5.2 P.C.C (1:2:4) forC2 7 1.25
5.3 Steel for vertical coloumns
6 Floor Beams
6.1 P.C.C (1:2:4) for floor beams 1 390
6.2 App Steel for floor beams
7 Slab
7.1 P.C.C (1:2:4) for slabs 1 52
7.2 App Steel for slabs
8 Brick Work
8.1 Brick work in floors 1 400
8.2 Deductions for openings 1 33
8.3 Remaining
9 Mortar
9.1 Mortar (1:5) For brick work
9.2 Mortar (1:4) for plastering walls 2 400
9.3 Mortar (1:4) for plastering roof 1 48
9.4 Deductions for openings (1:4) 2 33
9.5 Remaining (1:4) for walls
C TOTAL FOR FIRST FLOOR
1 Brick Work (1:5)
2 Mortar (1:3) for floor tile
3 Mortar (1:4) for plastering walls
4 Mortar (1:4) for plastering ceiling
5 Mortar (1:5) For brick work
6 P.C.C (1:2:4)
7 Steel
8 Brick ballast for terrazo floor
9 Area for floor tile

D SECOND FLOOR
1 Brick ballast for terrazo floor 1 48
2 P.C.C (1:2:4) for terrazo floor 1 48
3 Mortar (1:3) for floor tile 1 48
4 Area for floor tile 1 52
5 Vertical Coloumns
5.1 P.C.C (1:2:4) for C1 13 1.5
5.2 P.C.C (1:2:4) forC2 7 1.25
5.3 Steel for vertical coloumns
6 Floor Beams
6.1 P.C.C (1:2:4) for floor beams 1 390
6.2 App Steel for floor beams
7 Slab
7.1 P.C.C (1:2:4) for slabs 1 52
7.2 App Steel for slabs
8 Brick Work
8.1 Brick work in floors 1 400
8.2 Deductions for openings 1 33
8.3 Remaining
9 Mortar
9.1 Mortar (1:5) For brick work
9.2 Mortar (1:4) for plastering walls 2 400
9.3 Mortar (1:4) for plastering roof 1 48
9.4 Deductions for openings (1:4) 2 33
9.5 Remaining (1:4) for walls
D TOTAL FOR SECOND FLOOR
1 Brick Work (1:5)
2 Mortar (1:3) for floor tile
3 Mortar (1:4) for plastering walls
4 Mortar (1:4) for plastering ceiling
5 Mortar (1:5) For brick work
6 P.C.C (1:2:4)
7 Steel
8 Brick ballast for terrazo floor
9 Area for floor tile

E TOP ROOF
1 Area for bitumen coating 1 52
2 Area for polythene sheet 2 52
3 Area for thermopore sheet 1 52
4 Area for brick tiles 1 52
5 soil and mud 1 52
6 Grout (1:3) over brick tiles 1 52
7 Brick work in parapet walls 1 170
9 Mortar (1:4) For brick work parapet walls
10 Mortar (1:4) for plastering parapet walls 2 170
E TOTAL FOR TOP ROOF
1 Brick Work (1:4)
2 Mortar (1:3) for grout
3 Mortar (1:4) brick work parapet walls
4 Mortar (1:4) for plastering parapet walls
5 Area for bitumen coating
6 Area for polythene sheet
7 Area for thermopore sheet
8 Area for brick tiles
9 soil and mud

F Over head water tank


1 P.C.C (1:2:4) 1 60
2 App Steel

GRAND TOTAL
1 Brick Work (1:5)
2 Brick Work (1:4) parapet walls
3 Mortar (1:3) for floor tiles
4 Mortar (1:3) for grout top roof
5 Mortar (1:4) for plastering walls
6 Mortar (1:4) for plastering ceiling
7 Mortar (1:4) for brick work parapet walls
8 Mortar (1:5) for brick work
9 P.C.C (1:2:4)
10 Steel
11 Brick ballast for terrazo floor
12 Area for floor tile
13 App earth filling
14 Area for bitumen coating
15 Area for polythene sheet
16 Area for thermopore sheet
17 Area for brick tiles
18 soil and mud
19 App Excavation
20 App Paint

3 P.C.C (1:2:4) for Vertical Coloumns


3.1 C1 13 1.5
3.2 C2 7 1.25
App Steel for vertical coloumns

P.C.C (1:2:4) for floor beams 3 390


App Steel for floor beams

P.C.C (1:2:4) for slabs 3 52


App Steel for slabs

P.C.C (1:2:4) for terrazo floor 3 48

P.C.C (1:2:4) for Stair Case 1 43


App Steel for stair case

P.C.C (1:2:4) for doors and windows lintels 1 125


App Steel for lintels

Brick ballast for terrazo floor 3 48


Area for floor tile 3 52
Mortar (1:3) for floor tile 3 48

Brick work in floors 3 400


Brick work in parapet walls 1 170
Deductions for openings 1 100
remaining

Mortar (1:5) For brick work


Mortar (1:4) for plastering walls 6 400
Mortar (1:4) for plastering roof 3 48
Deductions for openings 2 100
Remaining

Area for bitumen coating 1 52


Area for polythene sheet 2 52
Area for thermopore sheet 1 52
Area for soil and mud 1 52
Area for brick tiles 1 52
Grout (1:3) over brick tiles 1 52
LAR KAHAR
22/07/2017
LAR KAHAR

L OF QUANTITIES

Dimensions
Quantity Unit Rate Amount Remarks
width height
TIONS

5.5 0.83 68.475 Cf


6 0.83 99.6 Cf
8 0.83 464.8 Cf
10 0.83 373.5 Cf
14 0.83 290.5 Cf
1296.875 Cf
1 1 390 Cf
1686.875 Cf
3000 Kg
1600 Kg
4600 Kg

FLOOR
34 4 7072 Cf
34 3 5304 Cf
30 0.33 475.2 Cf
30 0.12 172.8 Cf
30 0.08 115.2 Cf
34 1768 Sf

1 18 351 cf
1 18 157.5 cf
2600 Kg

1 1.5 585 Cf
1450 Kg
34 0.42 742.56 Cf
1700 Kg

0.75 10 3000 Cf
3 7 693 Cf
2307 Cf

700 Cf
0.06 10 480 Cf
30 0.06 86.4 Cf
0.06 7 27.72 Cf
452.28 Cf
UND FLOOR
2307 Cf
115.2 Cf
452.28 Cf
86.4 Cf
700 Cf
2009 Cf
5750 Kg
5304 Cf
475.2 Cf
1768 Sf
7072 Cf

OOR
30 0.33 475.2 Cf
30 0.12 172.8 Cf
30 0.08 115.2 Cf
34 1768 Sf

1 11 214.5 cf
1 11 96.25 cf
1500 Kg

1 1.5 585 Cf
1450 Kg

34 0.42 742.56 Cf
1700 Kg

0.75 10 3000 Cf
3 7 693 Cf
2307 Cf
700 Cf
0.06 10 480 Cf
30 0.06 86.4 Cf
0.06 7 27.72 Cf
452.28 Cf
RST FLOOR
2307 Cf
115.2 Cf
452.28 Cf
86.4 Cf
700 Cf
1811.11 Cf
4650 Kg
475.2 Cf
1768 Sf

LOOR
30 0.33 475.2 Cf
30 0.12 172.8 Cf
30 0.08 115.2 Cf
34 1768 Sf

1 11 214.5 cf
1 11 96.25 cf
1500 Kg

1 1.5 585 Cf
1450 Kg

34 0.42 742.56 Cf
1700 Kg

0.75 10 3000 Cf
3 7 693 Cf
2307 Cf

700 Cf
0.06 10 480 Cf
30 0.06 86.4 Cf
0.06 7 27.72 Cf
452.28 Cf
OND FLOOR
2307 Cf
115.2 Cf
452.28 Cf
86.4
700 Cf
1811.11 Cf
4650 Kg
475.2 Cf
1768 Sf

OOF
34 1768 Sf
34 3536 Sf
34 1768 Sf
34 1768 Sf
34 0.25 442 Cf
34 0.17 300.56 Cf
0.375 3.5 223.125 Cf
68 Cf
0.06 3.5 71.4 Cf
OP ROOF
223.125 Cf
300.56 Cf
68 Cf
71.4 Cf
1768 Sf
3536 Sf
1768 Sf
1768 Sf
442 Cf

ater tank
0.375 7 157.5 Cf
400 Kg

AL
6921 Cf
223.125 Cf
345.6 Cf
300.56 Cf
1428.24 Cf
259.2 Cf
68 Cf
2100 Cf
7475.455 Cf
20050 Kg
1425.6 Cf
5304 Cf
5304 Cf
1768 Sf
3536 Sf
1768 Sf
1768 Sf
442 Cf
7072 Cf
30000 Sf

1 40 780 cf
1 40 350 cf
7200 Kg

1 1.5 1755 Cf
5500 Kg

34 0.42 2227.68 Cf
5500 Kg

30 0.12 518.4 Cf

3 0.29 37.41 Cf
120 Kg

0.75 0.5 46.875 Cf


120 Kg

30 0.33 1425.6 Cf
34 5304 Sf
30 0.08 345.6 Cf

0.75 10 9000 Cf
0.375 3.5 223.125 Cf
3 7 2100 Cf
7125 Cf

2100 Cf
0.06 10 1440 Cf
30 0.06 259.2 Cf
0.06 7 84 Cf
1616 Cf

34 1768 Sf
34 3536 Sf
34 1768 Sf
34 0.25 442 Cf
34 1768 Sf
34 0.17 300.56 Cf
PROJECT TITLE:
DATE OF BOQ:
LOCATION:
CLIENT:
REVISION:

Sr No Material

Brick Work (1:5) super


1 structure

2 Brick Work (1:4) parapet walls

3 Plastering (1:4) walls

4 Plastering (1:4) ceiling

5 Mortar (1:3) for floor tiles

6 Mortar (1:3) for roof grout

7 P.C.C (1:2:4)

8 Steel
9 Brick ballast for terrazo floor

10 Area for floor tile

11 App earth filling

12 Bitumen coating

13 Polythene sheet

14 Thermopore sheet

15 Brick tiles

16 Soil and mud

17 Excavation

18 Paint

Termite Proofing (foundatins


19 and ground floor)

20 TOTAL
KALAR KAHAR
22/07/2017
KALAR KAHAR

Descriptions/Details Quantity Unit Bricks Cement


(Nos) (Bags)
Provide and lay first class brickwork in super structre in 1:5
cement sand mortar including raking out joints in the 6921 Cf 98105 280
same mortar, curing as shown on dawings and as specified.

Provide and lay first class brickwork in super structre in 1:4


cement sand mortar including raking out joints in the 223 Cf 3163 11
same mortar, curing as shown on dawings and as specified.

Supply, make, apply and cure 19mm thick smooth finished


plaster in 1:4 cement sand mortar, smooth finished with steel 1428 Cf 290
trowel on internal walls as shown in the drawings including
curing etc; complete in all respect.

Supply, make, apply and cure 19mm thick smooth finished


plaster in 1:4 cement sand mortar, smooth finished with steel 259 Cf 53
trowel on internal walls as shown in the drawings including
curing etc; complete in all respect.
Apply 25 mm thick cement sand (1:3) mortar over 37.5 mm thick 346 Cf 88
P.C.C (1:2:4) for proper laying of tiles.
Apply cement sand (1:3) grout over brick tiles for proper bond 301 Cf 76
between brick tiles.

Provide and lay structural cement concrete (1:2:4) of 3000 psi


cylinder crushing strength at 28 days using O.P. Cement, Chenab 7475 Cf 1316
sand and Sargodha crush stone including formwork and its
removal, placing, compacting, finishingand curingcomplete in all
respects (including screening and washing of stone aggregate)
but excluding the cost of reinforcement as perSpecifications.

Provide and fix steel reinforcement Grade 60 deformed 20050 Kg


steel bars conforming to ASTM A-615, including cleaning, cutting,
bending, placing, binding etc., including provision and cost of
spacers and binder wire, cost of chairs, over-laps not shown on
drawings etc., in any kind of R.C.C works as specified.
Provide 100 mm thick brick ballast of over burnt bricks with size 1426 Cf
of stone from 37.5 mm to 62.5 mm floor base.

Provide and lay glazed ceramic tiles flooring comprising


62.5 mm thick P.C.C. 1:2:4 screed, 25 mm thick 1:3 cement sand 5304 Sf
mortar bed under-coat and 300mm x 300m(matt finish) best
quality imported tiles or approved equivalent with skirting 100
mm, color will be selected from samples at the time of
construction, as per Specifications.

Structural backfill in foundations with approved suitable


excavated soil from BOQ Item 1.4.1 including breaking clods, 5304 Cf
dressing watering, compacting mechanicaly in layers not
exceeding 225mm thick depth to 95% Modification Proctor Dry
Density (MPD) from any lead and any lif compacted as per
Specification and as per approval of the Engineer.
Apply 2 coats of hot bitumen over RCC slab of specified grade 1768 Sf
and specifications.
3536 Sf
Lay one layer of polythene sheet 500 SWG over bitumen layers.

Lay 50mm thick "Diamond Jumbolon-Board" over polythene 1768 Sf


sheet and lay one more layer of polythene sheet 500 SWG.
Lay brick tiles over mud mortar as per specifications. 1768 Sf
Lay 75 mm to 100 mm mud clay with proper slope as per 442 Cf
required.

Structural excavation in soil above sub soil water level


for levelling and grading of walls and columns 7072 Cf
foundation as shown in drawings and Specifications and
as per approval of the Engineer.

Provide and apply one coat of primer Dulux Primeon of ICI or


Berger or Kansai Paint make (or approved equal) and 3 to 4 coats
(as may be approved to have the required finish) of Special 25000 Sf
Plastic Emulsion Paint ICI or Berger or Kansai Paint make as per
Specifications and approved shade, and as per sample by the
Engineer.

Provide and apply antitermite treatment to foundation


bed & vertical sides of excavation and under floors resting on 4500 Sf
ground, using the indicated insecticide emulsion below, applied
as specified by the manufacturer.

TOTAL 101268 2114


Materials
Sand Aggregate Steel Brick tiles Floor Tiles Earth filling Brick Ballast Bitumen
(Cft) (Cft) (Kg) (Sft) (Sft) (Sft) (Cft) (Sft)

1750

54

1451

263

329

286

3289 6578

20050
1425.6

5304

5304

1768

1768

5619 6578 20050 1768 5304 5304 1426 1768


Materials
Polythene Sheet Thermopore Sheet Mud and Soil Excavation Paint Termite Proofing
(Sft) (Sft) (Cft) (Cft) (Sft) (Sft)
3536

1768

442

7072

25000

4500

3536 1768 442 7072 25000 4500


Sanitary Sewerage Electrification Bricks Cement Sand Aggregate Steel Brick tiles
(Bags) (Cft) (Nos) (Kg) (Sft)

8 540 30

8 540 30

540 30

540 30

540 30

540 30

540 30 65

540 30 80
7
Market Rate (Rs)
Floor Tiles Earth filling Brick Ballast Bitumen Polythene Sheet Thermopore Sheet Mud Clay
(Sft) (Sft) (Cft) (Sft) (Sft) (Sft) (Cft)
30

75

20

3.5

37

2
Percurement Cost
Excavation Paint Termite Proofing Sanitary Sewerage Electrification
(Cft) (Sft) (Sft) (Rs)

988541

32810

200251

36342

57278

49813

1236739

1604000
42768

397800

37128

35360

12376

65416

12376
884

2.5 17680

20 500000

7.5 33750

5361312
Cost for Unit

(Rs)

143

147

140

140

166

166

165

80
30

75

20

37

7
2

20

1006

You might also like