3. PREDIMENSIONAMIENTO:
VIGAS:
a. Principales
h = L / 12 b=h/2
h = 5.30 / 12 b = 0.50 / 2
h = 0.44 = 0.45=0.50m b = 0.25=0.30m
b. Secundarias
h = L / 14 b=h/2
h = 3.70 / 14 b = 0.30 / 2
h = 0.26 = 0.30m b = 0.15 = 0.25m (Por Norma E.030)
COLUMNAS:
Por la base de la viga se considerará columnas de 0.30 x 0.30m
LOSA:
e = L / 25 e = L / 25
e = 5.30 / 25 e = 3.70 / 25
e = 0.21m e = 0.15m
4. MODELAMIENTO EN ETABS:
PRIMERO ABRIMOS ETABS
1. File
New Model…
2. Define
Section Properties => Frame Sections…
TABLA => Frame Properties
Add New Property…
2. Define
Section Properties => Wall Sections…
TABLA => Wall Properties
Add New Property…
APARECERÁ LO SIGUIENTE:
APARECERÁ LO SIGUIENTE:
SE MODIFICA LOS APOYO A EMPOTRADO Y SE CREAN LOS DIAFRAGMAS
SELECCIONAMOS LA LOSA POR PAÑOS
VERIFICAMOS QUE ESTE EN: One Story
3. Assign
Shell => Diaphragms…
METRADO DE CARGAS
LOSA
o CARGA MUERTA
4. Select
Shell => Select => Properties => Slab Sections…
Y SELECCIONAMOS LA LOSA QUE PREDIMENSIONAMOS: LOSA ALIG 0.20M
Select
Close
o CARGA MUERTA
Get Previous Selections (Ctrl+J): SE SELECCIONA LO ANTERIORMENTE