Professional Documents
Culture Documents
00 28-Feb-17
SAIC NUMBER DATE APPROVED QR NUMBER
SAUDI ARAMCO INSPECTION CHECKLIST
Pipeline Inspection Prior to Welding of Temperature Tie-
SAIC-L-2115 29-Jun-17 PIPING-
In Weld Joint
PROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIME
SAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A REMARKS
No.
A General Requirements
The first string of a buried pipeline is placed in the trench and spot SAES-L-450
A2
backfilled (or tied into an anchor), during the hottest part of the day. Para. 15.5.1
SAES-L-450
A3 Subsequent strings are connected by temperature tie-in welds.
Para. 15.5.1
Welding surface is clean and free from oil, moisture, rust, scale,
sand, paint, metallic coatings or other foreign matter, at least 25 mm SAES-W-012
A7
of adjacent base metal prior to welding, including any such coatings Para. 10.3.1
on temporary attachments or supports
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A REMARKS
No.
At least two welders are used for pipelines greater than 16 inch SAES-W-012
A10
diameter, operating simultaneously and in opposite quadrants. Para. 10.7.1
Working clearance for welding is not less than 900 mm all around the SAES-W-012
A11
pipe. Para. 10.8
The actual tie-in temperature and the pipeline stations of the tie-ins SAES-L-450
A14
are recorded in the inspection record books. Para. 15.4
The hot pass is made while the pipe is still fully supported by the SAES-W-012
A15
sideboom tractor or supports. Para. 10.7.3
Each new string must be kept free of movement to prevent cracks in SAES-L-450
A16
the temperature tie-in welds. Para. 15.5.1
During the night and the cool periods of the day, there should be at
SAES-L-450
A17 least 900 m to 1200 m of pipe outside the trench to keep the S-curve
Para. 15.5.1
in sufficient tension to restrain the pipe already in the trench.
A string is always connected to each side of the anchor stub when SAES-L-450
B1
the work is stopped at the end of the day. Para. 15.8
C Buried Pipelines:
Each new string must be kept free of movement to prevent cracks in SAES-L-450
C3
the tie-in weld. Para. 15.5.1
The portion of the pipeline outside the trench shall be supported by SAES-L-450
C4
side booms holding the line in a gentle S-curve. Para. 15.5.2
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A REMARKS
No.
Spot backfilling (used to anchor to the line) may be completed at any SAES-L-450
C5
temperature but no closer than 1200 m from the free end of the tail. Para. 15.5.4
If spot backfilling closer to the free end is required, it shall be done SAES-L-450
C6
during the hottest part of the day. Para. 15.5.4
If the tie-in weld is made with the pipe in the trench (at tie-in
temperature) the string being tied in and the tail must be spot
SAES-L-450
C7 backfilled on the same day of the tie-in.
Para. 15.5.5
* NOTE: The spot backfilling shall not be closer than 24 meters from
the free end.
The strings which have been tied-in while resting on the skids or on
SAES-L-450
D2 the sand, are placed onto the supports by side booms, holding the
Para. 15.6.2
line in a gentle S-curve between supports and skids.
The pipeline that has been placed onto the supports has the top
SAES-L-450
D3 halves of ring girder supports or support straps, bolted in place on
Para. 15.6.2
the same day it is placed.
REMARKS:
REFERENCE DOCUMENTS:
1. SAES-L-450, Construction of On-Land and Near Shore Pipelines, (12 October 2015)
2. SAES-W-012, Welding Requirements for Pipelines, (10 August 2016)
3. SAES-H-200, Storage, Handling and Installation of Externally Coated Pipe, ( 7 February 2017)
REMARKS:
ITEM
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A REMARKS
No.
Name, Initials and Date: Name, Initials and Date: