CostOS™ Estimating 2008

CostOS Tutorial
07/03/2007
(date of last revision)

Copyright © NOMITECH 2007. All rights reserved.


No part of this document may be reproduced in any form without written permission of the copyright holder.
nomitech

Contents
INTRODUCTION…………………………………………………………………………………………………3
A. OVERVIEW OF THE PROJECT…………………………………………………………………………..3
B. CREATING A NEW PROJECT..…………………………………………………………………………..4
C. CREATING THE GROUP CODES LIST..………………………………………………………………..4
D. CREATING THE BOQ (BILL OF QUANTITIES) TABLE..……………………………………………..5
E. ADDING RESOURCES TO THE DATABASE…………...……………………………………………..6
F. COST ESTIMATING THE BOQ ITEMS…………………………………………………………………11
G. DEFINING THE GENERAL EXPENSES OF THE PROJECT ……………………………………….13
H. RUNNING PROJECT REPORTS……………………………….……………………………………….13

Confidential Page 2 7/3/2007


nomitech

Introduction

The following example is a real project of a three store building in Kifisia, Athens Greece. The rates
have been slightly changed and are not to be taken into account when estimating, for obvious
reasons. The estimator should be aware of the local circumstances and methods of construction when
estimating.

A. Overview of the Project

The project is a three store residential building with basement and roof located at the northern suburbs
of Athens. The following pictures show the 3D Model of the project.

Front View 1 Front View 2

Back View 1 Back View 2

Note: If you have downloaded the 30 day trial version of CostOS Estimating, this example’s database
is preloaded. If you wish to create a Blank New Database and re-enter all data provided in this
example you can do so by clicking anywhere in the ‘Database View’ and in the import database button

. When asked input demo as the Password. In the next screen tick on the Create New Blank
Database check box and input your preferred username and password. If you wish to move back to

the ‘preloaded’ database you can import the file located at C:\Program Files\CostOS Estimating
2008\Example\Example.zdb using username: demo and password: demo.

Confidential Page 3 7/3/2007


nomitech

B. Creating a New Project

After opening CostOS go to File >> New to create a new Project. Fill in the textboxes of the dialog that
opens with the following data:
Name: Athens Project
Description: Residential three store building located in Kifisia, Athens, with basement and roof
And click on the next button. At the following dialog specify the following data, which will be used for
statistical purposes:
Project Type: Construction
Subcategory: Residency
Basement Size: 148m2
Main Site Size: 360m2 (the area of the apartments plus the stairs and the lift)
Tick on the Add default expenses tickbox to load the predefined expenses list that comes with
CostOS.
Click on the next button. At the following screen give the name of the Contractor and its Initials and
browse to its logo by clicking at the set logo button. Click on the next button to give some details
about the client. Give the following details:
Name: Nano
Client budget: 500,000
State, Province: Attica
Project Location: Athens
Construction Duration (months): 18
Submission Date: 5/2/07
Click on the next button to give some details about the Energy Unit Prices:
Diesel: 0.95 (€/lt)
Petrol: 1.09
Electricity: 0.10
Other Energy: 0.50
Lubricates: 1.50
Tick on the Use these Energy Prices button.
Click on the next button to set the currency you will be working on:
Currency: EU Euro
Decimal Scale: 2
Divider Scale: 32
Rounding Mode: Round Half up
Click on the Finish Button, to complete the creation of the New Project.
When done, go to File>>Save Project to specify the location where the project will be saved.

C. Creating the Group Codes List

The Group codes are used to sum up your cost. Thus, they are usually the Cost Centers of your
company. They may however be some codes that you want to use to group the tasks you have to
estimate.
At the Database View (lower left part of your Screen) click on the Group Codes 2 icon. (The Group
Code 1 is usually used for the Master format codes). Click on the add button of the tool palette at the
lower right corner of the screen and fill in the following Data:
Groupcode: 0000
Title: DEMOLITION AND STRUCTURE MOVING
Click on the Add button.
Again, click on the add button at the lower right corner, and fill in the following data:
Groupcode: 0010
Title: Demolition
Click on the add button and click again on the add button at the lower right corner to add the following
entry:
Groupcode: 0050
Title: Structure Moving

Confidential Page 4 7/3/2007


nomitech

Click on the add button.


Spend two or three minutes to insert all the following data on the Group Codes 2 Table:

Group Code Title


0100 DEMOLITION AND STRUCTURE MOVING
0110 Demolition
0150 Structure Moving
0200 SOIL RELATED WORKS
0300 CONCRETE
0400 BRICKWORK
0500 PLASTER
0600 FLOORS
0700 DRYWALLS
0800 WOOD
0900 METAL
1000 ALUMINUMS
1100 GLASS
1200 PAINTING
1300 STAINLESS STEEL
1400 ISOLATION
1500 SPECIAL MATERIALS

D. Creating the BOQ (Bill of Quantities) Table

At the Project View (upper left part of your screen) click on the Bill Of Quantities under the Athens
Project. The right part of the screen changes to the Bill Of Quantities Screen. Now click on the Add
button at the toolbox at the lower right corner. On the window that pops up fill in the following data:

Title: Demolition and Structure Removal of Old Building


Unit: PCS
Quantity: 1
Group Code 2: (click on the three points button and select) 0100 Demolition and Structure
Moving
Surface Type: Basement
Description: Demolition of an old two store building. The Demolition Engineer should be
responsible for the safety measures.

Click on the Add button to add the entry on the BOQ Table

Repeat the procedure described above to add the following BOQ Items:

Code Title Unit Calc. Type Prod Qty G.C.2 Surf.


. Type
10 Demolition and PCS Productivity 1 1 0100 Bsmnt
Structure Removal of
Old Building
20 Excavation in Soil M3 Productivity 40 1000 0200 Bsmnt
30 C5/10 Concrete over M3 Productivity 1 24 0300 Bsmnt
soil
40 Reinforced Concrete M3 Productivity 1 238 0300 Bsmnt
C20/25 for
Foundation
Construction
50 Steel Reinforcement KG Productivity 1 8000 0300 Bsmnt

Confidential Page 5 7/3/2007


nomitech

S500s for Foundation


Construction
60 Reinforced concrete M3 Productivity 1 100 0300 Bsmnt
C20/25 for Columns
and Slab
Construction of
Basement
70 Steel Reinforcement KG Productivity 1 20000 0300 Bsmnt
S500s for Columns
and Slab
Construction of
Basement
80 Reinforced concrete M3 Productivity 1 225 0300 Sup.
C20/25 for Columns
and Slab
Construction of
Superstructure
90 Steel Reinforcement KG Productivity 1 31500 0300 Sup.
S500s for Columns
and Slab
Construction of
Superstructure
100 Brick work of outer M2 Productivity 1 475 0400 Sup.
walls
110 Brick work of inner M2 Productivity 1 270 0400 Sup.
walls
120 Outside Plaster M2 Productivity 1 555 0500 Sup.
Coating
130 Plaster Coating of M2 Productivity 1 1825 0500 Sup.
inner walls
140 Tile installation M2 Productivity 1 730 0600 Sup.

E. Adding Resources to the Database

CostOS Professional comes with a predefined cost database which you will find very useful especially
if you plan to use your own construction equipment. The equipment resources of the database are the
result of many years of experience and study.
Now, let’s input some required data on the database to estimate the project.

On the Database View (lower left part of the screen), click on the Projects. We will add a code for the
project we are estimating, in order to know that the resource rates we will input refer to this project.

Click on the add button (lower right corner). On the window that pops up, assign the following
values:
Project Code: 0100
Title: ATHENS PROJECT
Click on the add button.

Now on the Database View (lower left part of the screen), select Subcontractors. Click on the View All
button at the Toolbar at the lower right corner to see if there are any Subcontractors already defined

on the database. Click on the Add button to add a new Subcontractor. On the window that pops
up fill in the following data:
Title: Demolition and structure removal of Old Building
State/Province: Attica
Unit: PCS
Rate: 13000

Confidential Page 6 7/3/2007


nomitech

Group Code 2: 0100 – Demolition and Structure Moving


Performance: 8
Project: 0100 - ATHENS PROJECT
Company: Tolis Demolitions Ltd
Contact Person: Tolis
Phone Number: +30 210 6395865
E-mail: tolis@tolisdemolitions.com

Click on the add button. Repeat the steps described above to add the following subcontractors, too.

Title: Concrete Formwork Construction and Pouring


Unit: M3
Rate: 70
Insurance Rate: 20
Group Code 2: 0200 – Concrete
Performance: 10
Project: 0100 - ATHENS PROJECT
Company: Apostolos Hatzisimeon
Contact Person: Apostolos
Phone Number: +30 210 6395865
E-mail: tolis@nomitech.com

Title: Concrete C5/10 Pouring on Soil


Unit: M3
Rate: 40
Insurance Rate: 20
Group Code 2: 0200 – Concrete
Performance: 10
Project: 0100 - ATHENS PROJECT
Company: Apostolos Hatzisimeon
Contact Person: Apostolos
Phone Number: +30 210 6395865
E-mail: tolis@nomitech.com

Title: Rebar Cutting, Curving and Installation


Unit: KG
Rate: 0.18
Insurance Rate: 0.10
Group Code 2: 0200 – Concrete
Performance: 10
Project: 0100 - ATHENS PROJECT
Company: Apostolos Hatzisimeon
Contact Person: Apostolos
Phone Number: +30 210 6395865
E-mail: tolis@nomitech.com

Title: Brick work of outer walls


Unit: M2
Rate: 8
Insurance Rate: 2
Group Code 2: 0300 – Brick Work
Performance: 10
Project: 0100 - ATHENS PROJECT
Company: Hani Michael Ltd
Contact Person: Hani
Phone Number: +30 6977966625
E-mail: -

After adding the “Brick work” entry to the Subcontractor Table, select it (click once on it) and then click

Confidential Page 7 7/3/2007


nomitech

on the Copy button of the main toolbar. Click on the Paste button to Paste it on the
Subcontractor Table. Now double click on the pasted entry and change the following data, marked
bold.

Title: Brick work of inner walls


Unit: M2
Rate: 5
Insurance Rate: 1.8
Group Code 2: 0300 – Brick Work
Performance: 10
Project: 0100 - ATHENS PROJECT
Company: Hani Michael Ltd
Contact Person: Hani
Phone Number: +30 6977966625
E-mail: -

Click on the Update button and then on the Done button. Having done so, click again on the Paste

button to paste the “Brick work” entry, you copied before. Double click on the Pasted entry and
change the following data:

Title: Plaster Coating


Unit: M2
Rate: 4
Insurance Rate: 1
Group Code 2: 0500 – Plaster
Performance: 10
Project: 0100 - ATHENS PROJECT
Company: Hani Michael Ltd
Contact Person: Hani
Phone Number: +30 6977966625
E-mail: -

Click Update and Done. Repeat the Paste function and edit the pasted entry as follows:

Title: Tile Setting


Unit: M2
Rate: 8
Insurance Rate: 2.2
Group Code 2: 0600 – Floors
Performance: 10
Project: 0100 - ATHENS PROJECT
Company: Hani Michael Ltd
Contact Person: Hani
Phone Number: +30 6977966625
E-mail: -

Click Update and Done. Repeat the Paste function for last time and edit the pasted entry as follows:

Title: Cement Mortar over Concrete Slab


Unit: M2
Rate: 3
Insurance Rate: 2.2
Group Code 2: 0600 – Floors
Performance: 10
Project: 0100 - ATHENS PROJECT
Company: Hani Michael Ltd

Confidential Page 8 7/3/2007


nomitech

Contact Person: Hani


Phone Number: +30 6977966625
E-mail: -

If you have already noticed, the country is left as USA for all entries. We will now change the country
of all entries to Greece. To do so, double click on one entry e.g. Tile setting, and scroll down to see
the Country field. Select GREECE at the drop down menu and click on Update and Done.
Right click on the headers of the Subcontractor Table and select Country in order to show the Country
column on the Table.

Click on the GREECE cell and press the Ctrl button of your keyboard. Without leaving the Ctrl button
select the rest of the Subcontractor entries and press the right button of your mouse. On the window
that pops up select “Update 8 entries of Column ‘Country’ with value GR”

Now we will add the required Materials on the Database. On the Database view, (lower left part of the

screen) select Materials. Click on the View All, and then on the Add button. Fill in the
following data on the window that pops up:

Title: Concrete C5/10


State Province: Attica
Country: Greece
Unit: M3
Rate: 48
Group Code 2: 0300-Concrete
Project: 0100 - ATHENS PROJECT

Now copy and paste the above entry. Double click on the pasted entry and change the title to
Concrete C20/25, and the Rate to 52.

Repeat the above procedure to add the following entries as well:

Title Unit Rate


Steel Reinforcement S500s KG 0.53
Bricks and mortar for single brickwork M2 3
Bricks and mortar for double brickwork M2 6

Confidential Page 9 7/3/2007


nomitech

Plaster coating M2 3
Granite tiles 30 x 30cm M2 12
Glue for Granite Tiles KG 0.40
Cement Mortar over Slab and Below Tiles M2 3

Having finished with the above entries we will now add the suppliers of the materials. On the database
view select Suppliers. Click on the Add button and add the following data on the window that opens:

Title: Interbeton SA
State/Province: Attica
Contact Person: Spathis
Group Code 2: 0300 – CONCRETE
Country: GREECE

Click on the Add button to add the Supplier. Now, to assign the materials to the Supplier, first click on
the Materials Tab, next to the Description Tab, and then on the add button as shown below:

2
1

On the window that pops up click on the View All button. Press the Ctrl button and Select Concrete
C5/10 and Concrete C20/25. Click on the Select button to assign the Materials to the Supplier.

We will now enter two Equipment entries and two Labor resource entries. On the Database View
select Equipment and click on the Add button.

Fill in the following data:

Title: Excavator
Model: 330CL
Make: CAT
Unit: HOUR
Fuel Type: DIESEL
Fuel Consumption: 29.06
Lubricates Rate: 2.4
Spare Parts Rate: 6.78

Click once on the Depreciation Rate and then on the More button, to open the Depreciation
Calculator. Give the following values:
Initial Acquisition Price: 120000
Salvage Value: 5000
Interest Rate: 0.065
Depreciation Years: 8
Occupation Hrs/Mth: 175
Occupational factor: 0.73

Confidential Page 10 7/3/2007


nomitech

Click on the Next button and select “Caterpillar” as a Method of Depreciation Calculation. Click on the
Finish button to Exit the Depreciation Calculator. Click on the Add button. Now repeat the above steps
to enter the following Equipment:

Title: Truck
Model: 41.413 (8x4)
Make: MAN
Unit: HOUR
Fuel Type: DIESEL
Fuel Consumption: 21.22
Depreciation Rate: 4.52
Lubricates Rate: 2.4
Tires Rate: 0.98
Spare Parts Rate: 2.78

After you have finished entering the above equipment entries, select Labor on the Database View and
click on the Add button. Fill in the following Data:

Title: Operator
State/Province: Attica
Unit: HOUR
Rate: 12.50
Insurance Rate: 3.2
Project: 0100 – ATHENS PROJECT
City: Athens
Country: GREECE

Copy and paste the above entry and then edit the pasted entry as follows:

Title: Truck Driver


Rate: 10.12
Insurance Rate: 2.4

We have all the data we need to estimate the Project on the Database.

F. Cost Estimating the BOQ Items

Select Bill Of Quantities, under the Athens Project, at the Project View. Click the View All button
to see all the BOQ Items. Click once on the first BOQ Item “Demolition and Structure Removal of Old
Building”. Click on the Subcontractors Tab and then on the add button above the Tabs, as shown on
the following picture:

2
1

On the window that pops up click on the View All button and select the “Demolition and Structure

Confidential Page 11 7/3/2007


nomitech

Removal” entry from the Database. Click the Select button. The first BOQ Item is estimated.

We will now estimate the “Excavation in Soil” BOQ Item. Select the Item by clicking once on it. Click
then on the Equipment Tab and on the Add button over the Tabs. On the window that opens click on
the view all button and while keeping the Ctrl button pressed select the “Excavator CAT 330CL” and
the “Truck MAN 8x4”. Click on the Select button. The above equipment entries appear on the BOQ
Items resources screen.
Select the Truck and double click on its Factors. On the window that opens type the number 2 in the
Value of “Factor 1” and click the Update and Done button. We did this because we are going to use
two trucks while excavating.
After the above, click on the Labors Tab and then on the add button above the Tabs. Again click on
the View All button and while keeping the Ctrl button pressed select the “Operator” and the “Truck
Driver”. Click the Select button.
We need two Drivers for the two Trucks we assigned before. Thus, select the Truck Driver at the BOQ
Items Resources and double click on its factors. Give the number 2 as value for Factor one.

As you may have noticed while entering the “Excavation in Soil” BOQ Item, we assigned 40 for
Productivity. This means that with the CAT330 and the two trucks we can excavate 40M3/HOUR. We
will change now the productivity to 50M3/HOUR, please note the differences in the cost rate of the

BOQ Item. To do so, select the “Excavation in Soil” BOQ Item and click on the Edit button. On
the window that opens specify 50 for the value of Productivity and click on the Update and Done
Button.
We will now estimate the “C5/10 Concrete over Soil”. Select it at the BOQ Item and click on the

Subcontractors Tab. Click on the Add button over the Tabs and click on the View All button at
the window that opens. Select the “Concrete C5/10 Pouring on Soil” and click the Select button.
Next, click on the Materials Tab. Click on the Add button over the Tabs and click on the View All

button at the window that opens. Select the “Concrete C5/10” and click the Select button.
Notice the Rate and the Total Cost of the BOQ Item. They should be 108 and 2592 respectively.
Continue estimating the rest of the BOQ Items according to the following Table:

BOQ Item Subcontractor Material


Reinforced Concrete C20/25 for Concrete Formwork Concrete C20/25
Foundation Construction Construction and Pouring
Steel Reinforcement S500s for Rebar Cutting, Curving and Steel Reinforcement
Foundation Construction Installation S500s
Reinforced concrete C20/25 for Concrete Formwork Concrete C20/25
Columns and Slab Construction Construction and Pouring
of Basement
Steel Reinforcement S500s for Rebar Cutting, Curving and Steel Reinforcement
Columns and Slab Construction Installation S500s
of Basement
Reinforced concrete C20/25 for Concrete Formwork Concrete C20/25
Columns and Slab Construction Construction and Pouring
of Superstructure
Steel Reinforcement S500s for Rebar Cutting, Curving and Steel Reinforcement
Columns and Slab Construction Installation S500s
of Superstructure
Brick work of outer walls Brick work of outer walls Bricks and mortar for
single brickwork
Brick work of inner walls Brick work of inner walls Bricks and mortar for
double brickwork
Outside Plaster Coating Plaster Coating Plaster Coating
Plaster Coating of inner walls Plaster Coating Plaster Coating
Tile installation 1. Tile setting 1. Granite tiles 30 x 30cm
2.Cement Mortar over 2. Glue for Granite Tiles
Concrete Slab 3.Cement Mortar over

Confidential Page 12 7/3/2007


nomitech

Slab and Below Tiles

On the last BOQ Item (Tile installation) we are going to assign some factors on its materials. On the
BOQ Items Resources screen select the Materials Tab and double click on the “Granite tiles
30x30cm”. On the window that opens specify 1.05 for Factor 2, click Update and Done. This means
that 5% of the tiles is destroyed or lost at the installation.
Now double click on the “Glue for Granite Tiles”. On the window that opens specify 6 for Factor1 click
Update and Done. This means that we need 6KGS of glue for one square meter of Tiles.

G. Defining the General Expenses of the Project

At the Project View (upper left part of the screen) select General Expenses under the Athens Project.
We will now add some employees to the project. Make sure the Salaries Tab at the lower part of the
screen is selected. Click on the Add button and type Project Manager at the Description. Double
click on the Gross Salary and type 4,000 for his salary. Then double click on the months and type 20,
for the months he will be working on the project. Notice that the Project Manager’s compensation for
firing him after the project is finished, is automatically calculated to 8,000 based on European Law. Off
course you can double click on it and change the compensation value. Notice also the Factor which is
set to 1.17. This is the result of 14/12 which is two additional salaries that are usually given to
employees as a bonus. You can change the default value of 1.17 at the Project Properties.
Repeat the above procedure to add a Supervisor who gets 3,000 for gross salary and who will be
working on the Project for 16 months.

We will now add some expenses. Click on the Expenses Tab at the lower part of the screen. Select
the 1.2 Expense: “Site Connection to Electricity Provider (connection and networking only)” and click

on the Edit button. On the window that opens double click on the Misc. R. (Misc. Rate) cell and
type 400. Double click on the Quantity and type 1. Double click on the percent and type 100. Click on
the Ok button.
The project is quite small and located near the central offices. As such we are not going to set any site
offices. We are going to make though some transportation expenses from the office to the site. Click
on the Expense 2.12 “Miscellaneous Personnel Expenses (Business Trips, Visas, etc)” and then on

the Edit button. At the window that opens click on the Add button and type 2.12.3 for the code of
the new expense. Double click on the Description cell and type “Daily trips from office to site”. Select
month as a unit and type 300 for Misc R. and 20 for Months. Click the OK button.

We will now add some factors that are used on top of the Direct Cost of the Project. Click on the
Factors Tab at the lower part of the screen. You will notice that you can run three different scenarios
as far as the factors are concerned. This is basically used to run three different profitability scenarios.
Double click on the Risk and Profit cell of Case 2 and type 10. Repeat on the Risk and Profit cell of
case 3 and type 20.
We are going to insure the project, thus type 1.4 for all the cases at the Insurance Row.

H. Running Project Reports

At the Project View (upper left part of the screen) select Bill Of Quantities under the Athens Project.

Click on the View All button and then go to File >> Print Preview at the main menu. On the
“Select Report” window that opens press the Ctrl button and select all the reports except from those
that mention Group Code 1 and the Consumables Report. Click on the select button and wait a few
seconds. A whole bunch of report opens. Spend a few seconds on each one of them to understand
the data they provide you.

CostOS has a very powerful and dynamic reporting system. The last means that the data you show on
your screen, the way you sort, filter and format it is picked up when creating reports.

Confidential Page 13 7/3/2007


nomitech

Nomitech can also create custom reports for you!

For more information on using the product please refer to CostOS manuals or the advanced tutorials
shipped with CostOS Professional.