You are on page 1of 157

Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,

Beautification & Lighting Project

Vitti Sthapati Brindo Ltd. Page 1


June 20, 2017
VITTISTHAPATI
BRINDO LTD.
27/A Sangshad Avenue
Ref: VITTI/NCC/2017/11 Dhaka-1215,
Bangladesh

T: 880 2 8143471
To F: 880 2 8143470
Superintending Engineer, E: directors@vitti.com.bd
vittibd@gmail.com
Narayanganj City Corporation,
Nagar Bhaban, 10, Bangabandhu Road,
Narayanganj

Subject: Submission of Draft Final Traffic Impact Assessment Report on Baburail


Canal Beautification Project.

PROJECT: Restoration/Rehabilitation of Baburail Canal with Landscaping,


Beautification and Lighting.

Dear Sir

As per review we have incorporated all related works in accordance with the comments from
LGED for the Baburail Canal Restoration/Rehabilitation Project. We are submitting the Draft
Final Traffic Impact Assessment Report.

Attached please find the Draft Final Traffic Impact Assessment Report appropriate for your
kind review and approval.

Thanking you

_________________
Md. Ishtiaque Zahir
Architect Director

Enclosed:
1. Draft Final Traffic Impact Assessment Report - 1 Set

CC for Information:
1. Mayor, Narayanganj City Corporation.
2. CEO, Narayanganj City Corporation.
3. Executive Engr. Narayanganj City Corporation.
4. Urban Planner, Narayanganj City Corporation.
Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

TABLE OF CONTENTS
Table of Contents ............................................................................................................ 1
List of Tables ................................................................................................................... 5
List of Figures .................................................................................................................. 7
Abbreviations .................................................................................................................. 9
Executive summary ....................................................................................................... 12
Chapter 1: Introduction ................................................................................................. 17
1.1 Background ........................................................................................................... 17
1.2 Project Introduction ................................................................................................ 18
1.3 Objectives of the Project ........................................................................................ 20
1.4 Project Cost ........................................................................................................... 20
Source: Prepared by Consultants ................................................................................ 20
1.4 Need for Social Impact Assessment ...................................................................... 21
1.5 Objectives of the Study .......................................................................................... 21
1.6 Scope of SIA Study ................................................................................................ 22
1.7 SIA Team............................................................................................................... 23
1.8 Structure of the SIA Report .................................................................................... 23
Chapter 2: Study Approach and Methodology ............................................................ 25
2.1 Phase – I: Pre Survey Activities ............................................................................. 26
2.1.1 Collection and Review of Project Literature ...................................................................... 26
2.1.2 Rapid Reconnaissance Survey to Familiarize Field Activities .......................................... 26
2.1.3 Scoping and other Pre Survey Activities ........................................................................... 26
2.2 Phase II: Survey Activities ..................................................................................... 26
2.2.1 Socio-economic Household Survey of Project Affected Area........................................... 26
2.2 Qualitative Data Collection................................................................................................... 28
2.3 Review of Legal Policy Provisions and Implementation Capacity ....................................... 28
Chapter 3: Legal and Policy Framework ...................................................................... 31
3.1 National Legislation ............................................................................................... 31
3.1.1 Constitutional Provisions................................................................................................... 31
3.1.2 The Acquisition and Requisition of Immovable Property Ordinance, 1982 ...................... 31
3.1.3 Constitution Right of the Small Ethnic Communities ........................................................ 32
3.1.4 Other Relevant Acts, Laws and Rules in Bangladesh ...................................................... 32
3.2 Applicable World Bank Safeguards ........................................................................ 33
Chapter 4: Project Impacts and Inventory ................................................................... 36
4.1 Background ........................................................................................................... 36
4.2 Project Impacts ...................................................................................................... 36

Vitti Sthapati Brindo Ltd. Page 2


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Chapter 5: Socio-Economic Profile .............................................................................. 40


5.1 Socio-economic Information of Respondents ......................................................... 40
5.2 Migration Status of the Respondents ..................................................................... 48
5.3 WASH Status of the Household of the Respondents ............................................. 50
5.4 Environmental and Waste Management Condition in the Area .............................. 59
5.5 Social attachments, Facilities and Problems .......................................................... 63
Chapter 6: Institutional and Implementation Structure............................................... 68
6.1 Institution Related to Policy, Planning, M&E of the Project ................................ 68
6.2 Main Project Implementation Organization –NCC .............................................. 70
Chapter 7: Stakeholder Analysis .................................................................................. 73
7.1 Introduction ............................................................................................................ 73
7.2 Stakeholders at Different Levels ............................................................................ 73
7.3 Stakeholder Analysis ............................................................................................. 74
7.3.1 Political Organization ........................................................................................................ 75
7.3.2 Development ..................................................................................................................... 76
7.3.3 Administration, Security, Law and Order .......................................................................... 76
7.3.4 Peoples Issue & Human Rights ........................................................................................ 77
7.4 Beneficiaries/ Stakeholders Expectations .............................................................. 77
7.4.1 Overall Issues Emerged During Public Consultations ...................................................... 78
7.5 Information Disclosure Process ............................................................................. 80
7.6 Access to Information ............................................................................................ 81
Chapter 8: Impact Assessment .................................................................................... 86
8.1 Introduction ............................................................................................................ 86
8.2 Positive Impacts..................................................................................................... 86
8.3 Adverse Impacts .................................................................................................... 87
8.4: Major Risks and Assumptions ............................................................................... 90
8.4.1 Risks ................................................................................................................................. 90
8.4.2 Assumptions ..................................................................................................................... 90
8.4.3 Significance of Risk Assumptions ..................................................................................... 90
Chapter 9: Overall Issues of Significance and Management ...................................... 92
9.1 Issues of Significance ............................................................................................ 92
9.1.1 Issues to be addressed by the Project.............................................................................. 92
9.2.2 Issues that are project Scope ........................................................................................... 92
9.2 Social Management Plan ....................................................................................... 92
9.2.1 Resettlement Action Plan.................................................................................................. 92
9.2.2 Livelihood Related ............................................................................................................ 94
9.2.3 Inclusion and Equity ...................................................................................................... 94
9.2.4 Gender Minorities /Vulnerabilities ..................................................................................... 94

Vitti Sthapati Brindo Ltd. Page 3


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

9. 3 Ethnic Groups and Person with Disability.............................................................. 98


9.4 Stakeholders Engagement ..................................................................................... 99
9.5 Transparency and Accountability ....................................................................... 100
9.7 Capacity Support and Capacity Building .............................................................. 103
Chapter 10: Grievance Redress Mechanism ............................................................. 105
10.1 Grievance Redress Mechanism ......................................................................... 105
Chapter 11: Monitoring and Evaluation ..................................................................... 110
11.1 Introduction ........................................................................................................ 110
11.2 Monitoring and Evaluation Framework ............................................................... 110
11.2.1 Sample Design and Monitor ......................................................................................... 110
11.2.2 Measurable Indicators................................................................................................... 111
11.3 Impact Evaluation .............................................................................................. 113
11.3.1 Resettlement Monitoring and Social Evaluation Forms ................................................ 115
11.4 Computerized Management Information System (CMIS) ................................... 116
11.4.1 Budget Plan for CMIS ................................................................................................... 117
11.3 Monitoring and Evaluation Budget ..................................................................... 118
Chapter 12: Budget ..................................................................................................... 120
12.1 Budgetary Requirements for Social Management .............................................. 120
12.2 Overall Social Management Budget ................................................................... 120
Annexure ...................................................................................................................... 121
Annex-A: Data Tables_ Socio-economic Profile of the Respondents...................... 122
Annex-B: Survey Questionnaire ................................................................................. 142

Vitti Sthapati Brindo Ltd. Page 4


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

LIST OF TABLES
Table 1: Cost Abstract of Shitalakhya-Dhaleshwari River Connecting Canal Beautification
Project in Narayanganj City Corporation .......................................................................... 20

Table 2: Sample Size Distribution among the Respondent Sub-Segments for Quantitative
Survey ............................................................................................................................. 27

Table 3: Summary Characteristics of the Inventory of Baburail Canal Restoration Project


........................................................................................................................................ 36

Table 4: Age of the Respondents .................................................................................... 40

Table 5: Marital Status of the Respondents ..................................................................... 41

Table 6: Educational status of the Respondents .............................................................. 41

Table 7: Occupation of the Respondents ......................................................................... 43

Table 8: Roles and Responsibilities for SMF Implementation .......................................... 69

Table 9: Manpower of Narayanganj City Corporation (NCC)............................................ 70

Table 10: Comments and Suggestion from FGDs and KIIs.............................................. 77

Table 11: Opinions of Participants in Public Consultation Meeting (Tuesday), 11 April 2017
........................................................................................................................................ 78

Table 12: Proposed Plan for Future Public Consultations ................................................ 81

Table 13: Participants in Public Consultation Meeting (Tuesday), 11 April 2017 ............. 82

Table 14: Positive Impact of the project from KII, FGD .................................................... 86

Table 15: Possible benefits / good impacts when the project will complete ...................... 87

Table 16: Possible problems or adverse impacts when the project will complete ............. 87

Table 17: Possible problems during implementation of the Project .................................. 88

Table 18: Types of Adverse Impact and Mitigation Measures .......................................... 88

Table 19: Tentative SMP Implementation Schedule ........................................................ 93

Table 20: Budget for Gender Action Plan ........................................................................ 98

Table 21: Approximate Budget for the Head Consultant (TK) ........................................ 102

Table 22: Approximate Budget for the Assistant Consultant and NGO Worker (TK) ...... 102

Table 23: Budget for Capacity Building .......................................................................... 103

Vitti Sthapati Brindo Ltd. Page 5


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Table 24: Monitoring Indicators for the GRC .................................................................. 108

Table 25: Monitoring Framework for Proposed Project .................................................. 110

Table 26: Proposed Monitoring Indicators ..................................................................... 112

Table 27: Potential Monitoring Indicators ....................................................................... 112

Table 28: Monthly Progress Report Format for Social/Resettlement Monitoring ............ 115

Table 29: Budget for CMIS ............................................................................................ 117

Table 30: Proposed Budget for Monitoring and Evaluation ............................................ 118

Table 31. Budget for Social Mitigation ........................................................................... 120

Vitti Sthapati Brindo Ltd. Page 6


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

LIST OF FIGURES
Figure 1: Location of Narayanganj District ....................................................................... 19

Figure 2: Location Map of Proposed Beautification Project .............................................. 19

Figure 3: Location of the Proposed Project ...................................................................... 25

Figure 4: Baburail Canal Catchment Area for the SIA Survey .......................................... 29

Figure 5: Sex Distribution of the Respondents ................................................................. 40

Figure 6: Religion of the Respondents ............................................................................. 42

Figure 7: Race of the Respondents ................................................................................. 43

Figure 8: Ownership of the Households ........................................................................... 44

Figure 9: Type of Houses of the Area .............................................................................. 45

Figure 10: Total Area of the Floor of the Houses ............................................................. 45

Figure 11: Monthly Expenditure of the Respondents ....................................................... 46

Figure 12: Monthly Income of the Households ................................................................. 47

Figure 13: Households Saving at Present ........................................................................ 47

Figure 14: HH Loan at All Present ................................................................................... 48

Figure 15: Duration of Staying in the Present Residence ................................................. 48

Figure 16: Household Migration from the Area ................................................................ 49

Figure 17: Migration Status of the Respondents from Area.............................................. 49

Figure 18: Main Sources of Drinking Water for HH .......................................................... 50

Figure 19: Alternative Sources of Drinking Water ............................................................ 51

Figure 20: Main Sources of Cooking Water ..................................................................... 51

Figure 21: Alternative Sources of Cooking Water ............................................................ 52

Figure 22: Main Sources of Water for Bathing and Washing ............................................ 52

Figure 23: Alternative Sources of Water for bathing and Washing ................................... 53

Figure 24: Main Sources of Water for Latrine .................................................................. 53

Vitti Sthapati Brindo Ltd. Page 7


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Figure 25: Alternative Sources of Latrine Water .............................................................. 54

Figure 26: Types of Latrine Using by the Respondents.................................................... 54

Figure 27: Destination of Latrine Water ........................................................................... 55

Figure 28: Condition of the Latrines of HH ....................................................................... 56

Figure 29: Observed Status of the Latrines...................................................................... 56

Figure 30: Children under 5 or Disabled Who Can Not Use Latrine ................................. 57

Figure 31: Dispose of the Excreta .................................................................................... 58

Figure 32: Drainage Connection of HH ............................................................................ 59

Figure 33: Pathway of Rain or Waste Water .................................................................... 59

Figure 34: Water Logging Problems of the HH ................................................................ 60

Figure 35: Duration of Water Logging in a Year ............................................................... 60

Figure 36: Disposal of Kitchen Waste .............................................................................. 61

Figure 37: Air pollution Status of the Area ....................................................................... 62

Figure 38: Sound Pollution Status of the Area ................................................................. 62

Figure 39: Types of Membership of the Respondents ...................................................... 63

Figure 40: Play Grounds or Facilities for the Children ...................................................... 63

Figure 41: Open Space of Parks for the Residents to Walk or Socialize .......................... 64

Figure 42: Facilities for the Residents to Enjoy Cultural Events, Movie, Drama ............... 65

Figure 43: Drug Addiction Problem of the Area................................................................ 65

Figure 44: Security Related Problem in the Area ............................................................. 66

Figure 45: Percentage of People who are Socially Connected to Each Other .................. 66

Figure 46: Stakeholder Analysis of the Project ................................................................ 74

Figure 47: GRC Organogram......................................................................................... 106

Figure 48: Proposed CMIS model .................................................................................. 117

Vitti Sthapati Brindo Ltd. Page 8


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

ABBREVIATIONS
ARIPO Acquisition and Requisition of Immovable Property Ordinance of 1982
BAPA Bangladesh Poribesh Andolon
BAL Bangladesh Awami League
BBS Bangladesh Bureau of Statistics
BWDB Bangladesh Water Development Board
BJP Bangladesh Jatiya Party
BNP Bangladesh Nationalist Party
CSR Corporate Social Responsibility
COI Corridor of Impact
CUL Compensation Under the Law
CSC Construction Supervision Consultants
DC District Commissioner
DWDB Dhaka Water Development Board
EMP Environmental Management Plan
EMF Environmental Management Framework
EIA Environmental Impact Assessment
FGD Focus Group Discussion
GAP Gender Action Plan
GRC Grievance Redress Committee
GTL Grant to cover temporary loss of income
HH Household
HCG House Construction Grant
HDA Homestead Development Allowance
IEE Initial Environmental Evaluation
IGA Income Generating Activities
IDA International Development Association
IPDP Indigenous People’s Development Plan
KII Key Informant Interview
LGED Local Government and Engineering Department
MOL Ministry of Land
M&E Monitoring and evaluation
NCC Narayanganj City Corporation
NGO Non-Government Organization
OPs Operational Policies
PAPs Project Affected Persons
PAHs Project Affected Households
PD Project Director
PRA Participatory Rural Appraisal
PIU Project Implementation Unit
PAVC Property Assessment and Valuation Committee
PM Project Manager
RAP Resettlement Action Plan
RP Resettlement Plan
RRA Rapid Rural Appraisal

Vitti Sthapati Brindo Ltd. Page 9


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

RS Resettlement Site
RU Resettlement Unit
SIA Social Impact Assessment
SMF Social Management Framework
SMP Social Management Plan
SP Superintendent of Police
STD Sexually Transmitted Disease
STG Structure Transfer Grant
TOR Terms of Reference
UNO Upazila Nirbahi Officer
TL Team Leader
VNR Vested and Non-Resident Property
WB World Bank

Vitti Sthapati Brindo Ltd. Page 10


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Executive Summary

Vitti Sthapati Brindo Ltd. Page 11


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

EXECUTIVE SUMMARY
A. Introduction

The Knight Foundation’s “Soul of the Community” research found that three main qualities
attach people to place: 1) Social offerings, such as entertainment venues and places to
meet, 2) Openness, i.e. how welcoming a place is, and 3) The area’s aesthetics, e.g. its
physical beauty and green spaces. City beautification is an important step in creating a
city that feels safe and cohesive. The beautification and restoration of Baburail canal
project will be a visionary of unique urban and waterways project initiated by Narayanganj
City Corporation. Baburail canal was one of the crucial waterway that was an important
route to carry goods and products to the city heart, because it connect Shitalakhya and
Dhaleshwari River through the Narayanganj District. The channel is now disconnected
from the river Shitalakhya at east by filling it with earth. Now the canal is dying day by day
as the illegal occupiers every day construct shops interrupting its water flow, and also
used for solid and liquid waste dumping including sewerage.

Due to increasing demand of Narayanganj city dwellers and to reopen the old waterway of
this canal, Mayor of NCC, Dr. Selina Hayat Ivy, aimed in 2011 to restore the Canals to full
navigation in the interests of conservation, biodiversity and local quality of life, and to use
the restoration as a catalyst for wider social, economic and environmental regeneration in
areas neighboring the canal. Moreover, conservation of the waterway heritage and
ecology by restoration and beautification canals is also important for significant social and
economic regeneration, which will make a substantial contribution to local community
development and quality of life by increasing opportunities for recreational and amenity
use of the canal and their immediate environs.

B. Policy, Legal Administrative and Regulatory Framework

The policy framework and entitlements for the Project Affected Persons (PAPs) are based
on national law, Acquisition and Requisition of Immovable Property Ordinance of 1982
(ARIPO) and WB’s (OP4.12) Safeguard Guideline’s on resettlement.

Deputy Commissioner (DC) is empowered to permanently acquire or temporarily acquire


of property and eligible compensate to the Project Affected Person (PAP). DC assesses
the level of compensation, taking into consideration factors such as land transactions in
the locality over the past 12 months. The amendments to the ARIPO in 1993 increased
the amount of the premium for compulsory acquisition from 25 to 50% on the assessed
value of the property. The 1994 amendment provides provision for payment of crop
compensation to tenants. The ARIPO does not cover compensation for loss of wage
income; it also does not cover losses of non-titled persons (Sharecropper, squatters,
encroachers, etc.) aside from crop losses to tenants. However, due to various reasons,
actually legal compensation does not cover the market price of acquired land.

As per WB OP4.12, policy guidelines will have to be ensured for the interest of the project
level and project authority/ requiring body will reinstate the socio economic condition of
project-affected person (PAPs).

Vitti Sthapati Brindo Ltd. Page 12


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

C. Social Impact Assessment

Both qualitative and quantitative method were used to assess the social impact of the
project as well as to make a plan for social mitigation of adverse impacts of the project. A
quantitative survey was conducted to collect 384 respondents’ data by using electronic
semi-structure questionnaire. Moreover, for qualitative data 5 FGDs and 13 KIIs also done
to get the details of social impacts and mitigation mechanisms of the project.

Total 349 structure are identified as project affected structure that will be removed for
canal restoration. The most of the structures are business shops (73%); whereas 15
percent of the structures are houses and 9% of the structures are bridge and rest of are
the social organization (3%). Among the structures one-half of are not paved (48%),
whereas 40% of are semi paved structure and only 12% of the structures are paved.
However, 53% structures are found illegally occupied and established in the project area
whereas 26% of structures are situated in NCC place. Moreover, only 18 % structures are
establish on lease areas taken from government and only 3% structures are legally own
by the local people.

It must be admitted first that the findings from the individuals and groups are quite
consistent and excepting a few from among the directly affected and the poor, all were
found highly enthusiastic and confident about successful and timely completion of the
Project. The positive image and absolute authority of the Mayor of NCC appeared to be
instrumental for this. Even those few who had different views and concerns also
expressed their confidence on the Mayor for the final decision.

The respondents recalled that the Baburail canal was quite alive 30-40 years back and
was connected to the two rivers Dhaleswari and Shitalakhya. The respondents also
recalled that the water quality was good; cargo/jute boats and launch used to move
through the channel, they bathed in the water and different river fish were caught by the
fishermen. They also identified the factors/reasons for gradual turning of the canal to the
present state as well as the responsible acts and actors. Less water flow in the rivers,
dumping of solid waste on the canal bank, illegal occupants and encroachers of the area
close to the politicians, lack of dependence on the canal route, and lack of public
awareness and pressure etc. were categorically mentioned by the respondents. However,
it should mention that restoration of waterway is a ultimate dream and would be addressed
through some other large project when water quality of these two rivers will improve.

As mentioned above, only a small segment of the respondents raised some doubts and
concerns about the success of the project. Again, some suggestions were also noted from
the FGDs and KIIs. The researchers feel that some of those are worth mentioning for the
sponsors, planners and implementers of the project to take care in finalizing their design
and implementation plan. However, some of the concerns already solved the concerned
authorities. While the individual reports describe them, the following are some of the
commonly cited ones:

1. Lack of clarity and confusion exist about the authority of the project, especially in
the union Parishad area. Some raised question whether the quality of the work in
two areas would be identical or not.

Vitti Sthapati Brindo Ltd. Page 13


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

2. Questions are raise whether the canal will be able to link the two rivers or not? If
not, would there be water in the canal year round? In that case, would not this be
called a successful project?
3. Some poor people probably will lose their earning opportunity and/or residence
due to the project especially in the extended beautification component. How much
they will be compensated for their loss. However, the project will create income
opportunities for poor through creating jobs during construction and after
construction employments in restaurants and fast food shop etc.
4. Lot of hassles and environmental pollution may take place during the
implementation of the project. How much care and attention could be expected
from the implementers on these.
5. Some expressed their concern about generating stated benefit due to poor
management after completion of the project. Some of them demanded involvement
of people in the project maintenance.
6. To keep the canal water free from pollution, the respondents emphasized on the
need for very careful management/discharge of solid waste, waste water and
sewage.
7. Some poor people felt that this type of project would not benefit them. It will help
the landowners of the project neighboring areas and the rich.
8. A few skeptic participants also said that the project might enhance or invite social
crimes like prostitution (return of Taanbazar) and drug addiction in new form.
9. Many of the respondents suggested for establishing good public toilets in suitable
places and some proposed to have drinking water supply for all, as the project will
attract many people.

D. Social Mitigation Plan

To eradicate the adverse impacts of the project and ensuring the resettlement of PARs
and establishing the livelihood of PARs, social mitigation plan would adopted. Both SMP
and Resettlement Plan will be implemented under establishing a resettlement unit (RU)
during construction period and it will be converted to Social Development Unit/CSR
department during post project period. RP will be implemented by hiring an implementing
NGO for 06 months’ period. There will be a provision monitoring, social and livelihood
specialist with RU for the project period. NGO will prepare a monthly and final report
regarding the completion of RP and SMP. Tentative budget of the SMP is 47.90 Million
Taka. RAP will deal only resettlement issues, so SMP will not include any resettlement
issues. The details of RAP is given in a separate report.

During public consultation, all concerned urged to ensure proper compensation on land
and structure and suggested alternative livelihood program for project affected households
(near 400) (PAHs). In case of SMP, some issues have been given priority for the
increasing efforts of improving living standard of project area people. For sustainable
development, livelihood skill is to be generalized among the project area population.
Moreover, Some other social issues are prevalent in the area, viz: gender issues, wage
discrimination, child labor, child and women persecution, moral degradation, addiction,
gender discrimination, unhealthy sanitation, unhealthy harmful food preservation and
distribution in the hotel and restaurant, AIDS & STD diseases among migrants and
construction workers may spread in the area. Training and workshops will also be

Vitti Sthapati Brindo Ltd. Page 14


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

arranged to aware about these issues for the community people of the area. In addition,
special capacity building training will be arranged for women of PARs families.

E. Conclusion

Monitoring and evaluation including external evaluation system will be functioned


throughout the project period to ensure project transparency, success and sustainability.
The exposure and/or close interaction of the SIA consultants with senior persons in Vitti,
NCC, LGED, and WB have led them to believe that the project authorities are going to
take adequate measures in addressing almost all the concerns and suggestions in their
design, implementation and post project management plan of the mega project. However,
these are not full proof. The NCC and the beneficiaries at large must remain vigilant to act
timely while problems occur in order to take the pride from such a dream project and
sustain the benefit from it.

Vitti Sthapati Brindo Ltd. Page 15


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Chapter 1: Introduction

Vitti Sthapati Brindo Ltd. Page 16


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

CHAPTER 1: INTRODUCTION
1.1 Background
There are hundreds of rivers and canals in Bangladesh with a large network of navigation
routes. Transportation through waterways has always been a natural, environment friendly
and relatively cheap mode of transport. Inland waterways have become the very important
mode not only for maintaining transport link between various remote parts of the country; it
is a means of transporting export-import cargo as well. Over the decades, the navigability
during dry season in many rivers and canals of the country has been deteriorating
because of morphological processes and for withdrawal of water from the rivers beyond
the border and within the country. Illegal occupation and poor or no maintenance of inland
waterways has further aggravated the navigability.

Narayanganj, the oldest and the most prominent river port of Bangladesh, grew into a
prominent place of trade and commerce, which will become important in generating its
own economic and demographic pull in the southeast district and will be the dominant city
adjacent to Dhaka due to national policy on equal development as well as the economic
growth of the country and due to benefit of proposed Padma bridge & Jatrabari flyover.
Rivers and canals of Narayanganj has been playing a significant role to the sustainable
development of this city. There are a few rivers and rivulets flowing through the district.
Among those the Shitalakhya, the Dhaleshwari, the Buriganga, the Balu and the Meghna
are important. Those are non-tidal and navigable throughout the year. They have been
playing a vital role in the economy of the district as they facilitate irrigation, drainage, and
water supply of the area. Among them all, Baburail canal was one of the crucial waterway
once that was an important route to carry goods and products to the city heart, because it
connect Shitalakhya and Dhaleshwari river through the Narayanganj District. The canal is
now disconnected from the river Shitalakhya at east by filling it with earth. Now the canal
is dying day by day as the illegal occupiers every day construct shops interrupting its
water flow, and also used for solid and liquid waste dumping including sewerage.

Due to increasing demand of Narayanganj city dwellers and to reopen the old waterway of
this canal, Mayor of NCC, Dr. Selina Hayat Ivy, aims in 2011 is to restore the Canals to full
navigation in the interests of conservation, biodiversity and local quality of life, and to use
the restoration as a catalyst for wider social, economic and environmental regeneration in
areas neighboring the canal. Moreover, conservation of the waterway heritage and
ecology by restoration and beautification canals is also important for significant social and
economic regeneration, which will make a substantial contribution to local community
development and quality of life by increasing opportunities for recreational and amenity
use of the canal and their immediate environs. In addition, public spaces that are clean,
that have places to sit down, and that are close to trees, flowers and outdoor art make us
feel happier, relaxed and safer. Beautification enhancements provide benefits for
businesses, residents and tourists. Research has demonstrated that businesses that are
located in areas with beautification elements have higher foot traffic and sales.

Vitti Sthapati Brindo Ltd. Page 17


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

1.2 Project Introduction


Narayanganj city is a historical place of the country. The city is of great importance from
the commercial & industrial point of view. Several rivers are there in and around the city
namely the Shitalakhya, the Balu, the Dhaleshwari and the Buriganga rivers. There are
several internal canals also in it. As such, it has a unique natural landscaping. The River
Shitalakhya bisects the city into two parts and it is flowing through the elongated direction
of it and the river Dhaleshwari is flowing at the western part of the city corporation. The
Buriganga and the Balu are contributing the Dhaleshwari and the Shitalakhya respectively
from the up. Most of the internal canals have been encroached by the nearby habitants
and have become too much polluted because of the sewage disposal and to some extent
by the industrial pollutants. It has become very essential for restoration of all these canals
to get rid of further environmental degradation and to make the city a beautiful and
habitable one.

Aside from the obvious aesthetic benefits, studies indicate that beautification, including
landscaping of waterbody, can help drivers reduce stress, frustration, and aggression,
while helping maintain safe environment. Implementing simple, cost‐effective
beautification projects can enhance communities and improve quality of life for residents
and travelers. The proposed Baburail Canal Beautification and Restoration Project is an
ambitious plan at present to restore to full navigation of two historic inland waterways, the
Shitalakhya-Dhaleshwari River connecting Canal. The existing Baburail canal with most of
its part filled up with earth, dumping garbage and sewage pit, which cause nuisance and
foul odors. There are also four other canals carries household wastewater and rainwater
enter into the Baburail canal.

Finally, all the wastewater carries through Baburail canal and discharge to the
Dhaleshwari River. At present NCC intend and taken initiative to restore the Baburail canal
only connecting Shitalakhya and Dhaleshwari River. Other canals also restore
subsequently. However, the canal connection with the two rivers without cleaning its water
will spoil the aim of the project and will not improvement of the environment and quality of
life of the area. Shitalakhya and Dhaleshwari river water is highly contaminated with huge
volume of industrial waste and the water quality is degrading day by day. At this moment,
the canal water should be protected from the contaminated river water by installing sluice
gate at the both end of the river. In future when both of the river water will be cleaned and
become non-contaminated, then the sluice gates can be opened for flow. The canal
restoration and beautification along with appropriate conservation of the environment as
well as ensuring the recreation and amusement for all age group of city dwellers.

Vitti Sthapati Brindo Ltd. Page 18


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Figure 1: Location of Narayanganj District

Asia Bangladesh Narayanganj


District

Figure 2: Location Map of Proposed Beautification Project

Vitti Sthapati Brindo Ltd. Page 19


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

1.3 Objectives of the Project


The project objectives has been broadly categorized as following:

1. To ensure that the project is Environmentally & Socially Feasible on the proposed
location;
2. To restoration of this canal will reconnect Dhaleshwari -Shitalakhya river in future,
thus improving water flow, quality of water and surrounding environment and slope
protection with proper Navigation of boating through the canal;
3. To restore the legacy of prime business hub through shops and assisted the local
business;
4. To restore the bridges and culverts connecting the both sides of Canal;
5. To restore the Gymkhana Lake, slope protection, amusement facilities, assorted
urban recreation spaces to make life comfortable and environmentally viable;
6. To understand the Traffic impacts on the surrounding road networks and
transportation facilities after the proposed development;
7. To Save the valuable land from land grabbers and improve this encroached area
as an open space/ breathing place for retention area of water for avoiding artificial
water logging within the City Corporation.

1.4 Project Cost


Table 1: Cost Abstract of Shitalakhya-Dhaleshwari River Connecting Canal
Beautification Project in Narayanganj City Corporation

SL Description Unit Quantity Rate Amount in Taka

A Development Cost
1 Demolition Works Item 1.00 4,023,633.75 4,023,633.75
2 Lake Reshaping Works rm 2,803.50 35,925.00 100,715,737.50
3 Protection Works (Slope,Canal rm 5,607.00 124,469.61 697,901,103.27
Bank, Adjacent road and
structure)
4 Ghat sqm 3,900.00 16,425.00 64,057,500.00
5 Footpath, bicycle track, seating rm 5,607.00 10,836.55 60,760,535.85
etc.
6 Landscaping rm 5,607.00 1,445.17 8,103,068.19
7 Road widenning and upgradation sqm 10,740.00 10,000.00 107,400,000.00
Total 1,042,961,578.56
B Basic services cost
1 Drainage rm 5,607.00 34,784.00 195,033,888.00
2 Electrical and lighting works rm 5,607.00 15,500.00 86,908,500.00
Total 281,942,388.00
C Equipments and plants
1 Baily Bridges sqm 800.00 80,015.49 64,012,392.00
2 Bridge sqm 348.00 135,000.00 46,980,000.00

Vitti Sthapati Brindo Ltd. Page 20


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

3 Over pass sqm 10,850.00 112,370.00 1,219,214,500.00


4 Folded floating deck Each 1.00 5,000,000.00 5,000,000.00
5 Viewing deck sqm 370.00 80,000.00 29,600,000.00
6 Water control device Each 5.00 7,500,000.00 37,500,000.00
Total 1,402,306,892.00
D Security system (CCTV, IT
Kiosk)
1 Security system LS 1.00 15,000,000.00 15,000,000.00
2 WI FI Kiosk sqm 325.00 45,000.00 14,625,000.00
Total 29,625,000.00
E Social and Environmental LS 1.00 51,445,749.00 51,445,749.00
mitigation cost
Total 51,445,749.00
Total (A+B+C+D+E) 2,808,281,607.56
5% contingency 140,414,080.38
Total 3,000,141,436.93

Source: Prepared by Consultants

1.4 Need for Social Impact Assessment


Social Impact Assessment includes the processes of analyzing, monitoring and managing
the intended and unintended social consequences, both positive and negative, of planned
interventions (policies, programs, plans, projects) and any social change processes
invoked by those interventions. Its primary purpose is to bring about a more sustainable
and equitable biophysical and human environment.

The objective of SIA is to ensure that development maximizes its benefits and minimizes
its costs, especially those costs borne by people (including those in other places and in
the future). Costs and benefits may not be measurable or quantifiable and are often not
adequately taken into account by decision-makers, regulatory authorities and developers.
By identifying impacts in advance: (1) better decisions can be made about which
interventions should proceed and how they should proceed; and (2) mitigation measures
can be implemented to minimize the harm and maximize the benefits from a specific
planned intervention or related activity.

SIA also helped in enhancing the project benefits to poor and vulnerable people while
minimizing or mitigating concerns, risks and adverse impacts. Further, as the project
implementation entails a large number other social issues such as influx of labor during
construction and others, a systematic assessment provided the basis to prepare a Social
Management Plan.

1.5 Objectives of the Study


The main objective of the study is to ensure that the project addresses the adverse
impacts on the livelihood of the people and that nobody is left worse off after implementing

Vitti Sthapati Brindo Ltd. Page 21


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

RAP and those affected have access to project benefits, both during project construction
as well as operation. Specifically, the objectives of the study are:

1. To carry out a socio-economic, cultural and political/institutional analysis to identify


the project stakeholders and social issues associated with the project;
2. To assess the extent of asset loss and undertake the census of potential project
affected people;
3. To identify likely occurrence of STD and HIV/AIDS resulting from the influx of
outside laborers and others and develop a strategy to reduce their incidence; and
4. To develop a consultation framework for participatory planning and implementation
of proposed mitigation plan.

1.6 Scope of SIA Study


a) The study began with the identification of social issues and stakeholders and
communities, including socially and economically disadvantaged communities. The
focus of SIA was on identifying local population likely to be affected by the project
either directly or indirectly and undertake census survey.
b) The scope of the study in particular included the following:
c) Identifying key social issues associated with the proposed project and specifies the
project’s social development outcomes;
d) Assessing potential social and economic impacts both during the construction
phase and in the operation phase;
e) Reviewing policies, regulations and other provisions that related to resettlement
and rehabilitation of project affected people and other social issues;
f) Social screening of various project components and likely impacts in terms of land
taking (loss of houses, livelihood, etc.), and resultant involuntary resettlement and
provide inputs (in terms of magnitude of impacts and likely costs for mitigation) in
preparing appropriate mitigation plans;
g) Screen the social development issues in the project area and its vicinity and design
the social services that may be provided by the project in order to improve the
quality of life and achieve the projects economic and social goals;
h) Update the profile of the population and available infrastructure facilities for
services in the project affected area;
i) Based on the assessment of potential social and economic impacts establish
criteria that will assist in the formulation of strategies; to the extent possible
maximize project benefits to the local population and minimize adverse impacts of
the project interventions on the affected communities;
j) Inform, consult and carry out dialogues with the project stakeholders on matters
relating to project design, objectives, and implementation and provide specific
recommendations to avoid/minimize high social risks;
k) Screen the social development issues in the project area and its vicinity and
accordingly design the social services that have to be provided by the project in
order to improve the quality of life;
l) Assess the impact of influx of construction workers and others (both during civil
works and during operation of the project) on the incidence of HIV/AIDS and other
diseases and develop a strategy to control them.

Vitti Sthapati Brindo Ltd. Page 22


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

1.7 SIA Team


Vitti Sthapati Brindo Limited has prepared this report under the guidance and support of

 Mohidul Hoque Khan, Team Leader (TL)


 Md. Khalid Hasan, Social Assessment Specialist cum Deputy Team Leader (DTL)
 Md. Izazul Haque, Geography and GIS Specialist
 Asif Hasan, Research Manager
 Ashraful Haque Khan, Data Analyst
 Tahmina Bintay Younos, Assistant Researcher
 Maliha Mohiuddin, Assistant Researcher
 Md. Shakhawat Hossain, Assistant Researcher

1.8 Structure of the SIA Report


 Chapter 1 presents the background information of the Project including scope and
objectives of the SIA study.
 Chapter 2 presents study approach and methodology applicable for this Project.
 Chapter 3 presents discuss the legal and policy framework related to SIA.
 Chapter 4 presents project impacts and inventory.
 Chapter 5 describes the socio-economic profile of the study areas.
 Chapter 6 presents institutional and implementation structure of the project.
 Chapter 7 discuss on stakeholder analysis.
 Chapter 8 describes impact assessment of the project.
 Chapter 9 describes major risks and assumptions.
 Chapter 10 presents overall issues of significance and management.
 Chapter 11 presents grievance redress mechanism.
 Chapter 12 discuss on monitoring and evaluation.
 Chapter 13 presents budget for SMP.

Vitti Sthapati Brindo Ltd. Page 23


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Chapter 2: Study Approach and


Methodology

Vitti Sthapati Brindo Ltd. Page 24


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

CHAPTER 2: STUDY APPROACH AND


METHODOLOGY
Approach and methodology mainly consist of quantitative and qualitative tools and
techniques. The study was conducted in two phases.

Figure 3: Location of the Proposed Project

Source: Modified by Consultants

Vitti Sthapati Brindo Ltd. Page 25


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

2.1 Phase – I: Pre Survey Activities

2.1.1 Collection and Review of Project Literature


This phase intends to familiarize with the concerned and important stakeholders to identify
and collect the available literature and to scope the activities. This involved two pronged
approach (a) discussions with Project Implementing authorities and other concerned. b)
Collection of available relevant project literature. Consultations were held with concerned
revenue officials to establish the ownership of land. Literature review and consultations
formed the basis for identification of key stakeholders.

2.1.2 Rapid Reconnaissance Survey to Familiarize Field


Activities
Following to the review and consultations, rapid preliminary field visits were conducted as
part of ground trothing exercise. This provided the basis for field research preparation and
helped in testing the questionnaires and checklists.

2.1.3 Scoping and other Pre Survey Activities


Both the review and rapid reconnaissance survey helped in finalizing the study
instruments and inception report detailing the final methodology and work plan.

2.2 Phase II: Survey Activities

2.2.1 Socio-economic Household Survey of Project Affected


Area

2.2.1.1 Survey design and Sample Size

A total 384 respondent’s survey was done within the 0.5 km (See Figure:4) distance from
the bank of Baburail canal. At first, the holding numbers of the HHs were collected, and
then respondents were selected randomly from the randomly selected HHs. The sample
size was calculated by using Rao soft sample size calculator, where margin of error was
5%, confidence interval was 95%, population Narayanganj city corporation was 7,09,381
(source: www.ncc.org.bd) and response distribution was 50%. The quantitative data were
collected electronically using semi-structured questionnaire.

The survey has assessed the impacts of the project, the socio-economic conditions, and
living standards of affected persons due to the project implementation. The following were
collected during the survey:

Vitti Sthapati Brindo Ltd. Page 26


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

 Socio economic conditions of the affected persons


 Family structure and number of family members
 Literacy levels and health
 Occupation type and income levels
 Loss of immovable assets due to the project by type and degree of loss
 Accessibility to the community resources
 Perceived income restoration measures
 Willingness to participate in the project
 Possible positive impacts of project
 Possible adverse impacts of the project etc.

Table 2: Sample Size Distribution among the Respondent Sub-Segments for


Quantitative Survey

Description Frequency Percent (%) Total (%)


NCC 193 50.3
Major Area 100
Union Parishad 191 49.7
Male 192 50.0
Gender 100
Female 192 50.0
North 228 59.4
North or South side of canal 100
South 156 40.6
High 106 27.6
Socio-economic Medium 140 36.5 100
Low 138 35.9
Total 384 100.0
Source: Data Analysis

2.2.1.2 Data editing, coding and Data processing

The survey data was downloaded from the server instantly after the survey was completed
to get the first database. After coding the open-ended responses, and doing a rigorous
checking by trained staff members in the office, the clean database was prepared. The
study team members then processed the data to get the total set of tables.

2.2.1.3 Analytical approach

The collected data was tabulated and analyzed using quantitative technique
disaggregated by district, PNGO, nature of beneficiary (primary Vs. secondary) and
gender of the respondents by using, SPSS 22, Microsoft Excel 2016 and Windows Visio
2016 software.

2.2.1.4 Ethical Issues, Privacy and Confidentiality

The respondents were informed clearly that the information they provided during the
interview would be kept strictly confidential. The interview was held under conditions

Vitti Sthapati Brindo Ltd. Page 27


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

where in the respondent felt most comfortable in responding openly. In addition, their
identity was not linked to the study at any point of time or stages of the study. The study
registered oral consent from all interviewees.

2.2 Qualitative Data Collection


Five FGDs and thirteen KIIs were conducted in the project catchment area (half a km on
both sides of the Baburail canal) to have increased understanding of the social impacts
due to the Project over the questionnaire survey findings, which have been conducted
among 384 households in the same area. The FGDs were conducted among male &
female (3+2), NCC & UP area (3+2) and low & moderate-income residents (3+2). The KIIs
were conducted among ward councilor, NGO manager, CBO leader, journalist, teachers,
businessperson, religious leaders, cultural leaders etc. Detail checklists for FGD and KII
were developed in Bangla. Four skilled and qualified field researchers were collect the
qualitative data. Digital recorders were used in conducting KIIs and in-depth interviews
whenever it is possible; otherwise, detail notes had been kept. Digitally recorded data
were transcribed and coded for analysis.

2.3 Review of Legal Policy Provisions and Implementation


Capacity
Relevant national and state legislations and regulations were reviewed. To study
implementation arrangements and its capacity in delivering the R&R services verification
of these arrangements and in-depth interviews with authorities were conducted.

Vitti Sthapati Brindo Ltd. Page 28


Social Impact Assessment of Baburail Canal Restoration Project

Figure 4: Baburail Canal Catchment Area for the SIA Survey

Source: Prepared by Consultants


Vitti Sthapati Brindo Ltd. Page 29
Social Impact Assessment of Baburail Canal Restoration Project

Chapter 3: Legal and Policy Frame Work

Vitti Sthapati Brindo Ltd. Page 30


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

CHAPTER 3: LEGAL AND POLICY FRAMEWORK


3.1 National Legislation
The following is the review of the relevant national legislation, regulatory and policy
instrument and some international ones. The proponent of the project will conduct its
infrastructural and operational activities in compliance with applicable Bangladeshi and
international legislation and agreements. A comprehensive review of the legal and
institutional framework within which the environmental and social assessment is to be
carried out.

3.1.1 Constitutional Provisions


The fundamental rights under the Constitution indicate the general guidelines for a policy
on resettlement/rehabilitation of citizens adversely affected (whatever be the mechanism)
due to any activity of the State. Article 40 of the constitution states categorically that every
citizen has the right to practice any lawful occupation which implies that anything impeding
such right (a) should not be done or (b) there should be supplementary measures to
compensate the losses faced by the citizen. Resettlement and rehabilitation of adversely
affected people due to infrastructure projects very clearly falls within this requirement for
supplementary measures. However, as per Article 42, sub-clause 2, no law with provision
of compensation for acquisition of land can be challenged in a court on the ground that
such compensation has been inadequate. However, under World Bank OP 4.12
Involuntary Resettlement, every affected person will have access to a project specific
Grievance Redress Mechanism for dispute resolution before the matter moved to the
courts. The project proponents as well as the Bank will review complaints, the resolution
process and the outcome. Until the dispute is resolved the funds for the disputed asset
must be held in an escrow account (top-up payments due from the project agency can be
held until the project closes; the amount placed with the DC may be held for 10 years or
more if necessary).

3.1.2 The Acquisition and Requisition of Immovable Property


Ordinance, 1982
The policy framework and entitlements for the Project Affected Persons (PAPs) are based
on national law, Acquisition and Requisition of Immovable Property Ordinance of
1982(ARIPO) and WB’s (OP4.12) Safeguard Guideline’s on resettlement.

Deputy Commissioner (DC) is empowered to permanently acquire or temporarily acquire


of property and eligible compensate to the Project Affected Person (PAP). DC assesses
the level of compensation, taking into consideration factors such as land transactions in
the locality over the past 12 months. The amendments to the ARIPO in 1993 increased
the amount of the premium for compulsory acquisition from 25 to 50% on the assessed
value of the property. The 1994 amendment provides provision for payment of crop
compensation to tenants. The ARIPO does not cover compensation for loss of wage

Vitti Sthapati Brindo Ltd. Page 31


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

income; it also does not cover losses of non-titled persons (Sharecropper, squatters,
encroachers, etc.) aside from crop losses to tenants. However, due to various reasons,
actually legal compensation does not cover the market price of acquired land.

The Deputy Commissioner (DC) processes land acquisition under the Ordinance and pays
compensation to the legal owners of the acquired land. The Ministry of Lands (MOL) is
authorized to deal with land acquisition through the DCs. Khash (government owned land)
lands should be acquired first when a project acquires both Khash and private land. If a
project acquires only Khash, the land will be transferred through an inter-ministerial
meeting following the preparation of acquisition proposal submitted to Deputy
Commissioner (DC) or Ministry of Land (MOL).

3.1.3 Constitution Right of the Small Ethnic Communities


There is no special commitment regarding small ethnic communities. However, under
Article-19 of constitution declares quality of opportunity of the all citizen of the country.
Under the article-9, (1) the state shall endeavor to ensure equality of opportunity to all
citizens; (2) The state shall adopt effective measures to remove social and economic
inequality between man and man to ensure the equitable distribution of wealth among
citizens, and of opportunities in order to attain a uniform level economic development
throughout the republic. This section is a safety ethnic community.

3.1.4 Other Relevant Acts, Laws and Rules in Bangladesh


Other legislation relevant to the proposed Project are listed below:

Water Act 2013 is based on the National Water Policy, and designed for integrated
development, management, extraction, distribution, usage, protection and conservation of
water resources in Bangladesh. The project activities will influence the water quality
positively.

Protection and Conservation of Fish Act (1950) provides power to the government to make
and apply rules to protect fisheries; prohibit or regulate erection and use of fixed engines;
and construction of temporary or permanent weirs, dams, bunds, embankments and other
structures. The Act prohibits destruction of fish by explosives, guns, and bows in inland or
coastal areas; and destruction of fish by poisoning, pollution, or effluents. The Act
prescribes the seasons during which fishing is allowed, prohibits fishing during spawning
periods, and specifies officials having authority to detect breaches of this Act.

The Bangladesh Labor Act, 2006 provides the guidance of employer’s extent of
responsibility and workmen’s extent of right to get compensation in case of injury by
accident while working.

Inland Shipping Ordinance 1976 and Inland Shipping (Amendment) Act 1990 deals with
the administration, registration, competency and pollution control, etc., of inland water
transport.

Vitti Sthapati Brindo Ltd. Page 32


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

The Government of Bangladesh under MOL has prepared a national policy on involuntary
resettlement though formally not accepted, which sets out that the rights of those
displaced by development projects shall be fully respected, and persons being displaced
shall be treated with dignity and assisted in such a way that safeguards their welfare and
livelihoods irrespective of title, non-title, gender, and ethnicity. The Policy on involuntary
resettlement recognizes that:

 All those displaced involuntarily by projects impacts like eviction must be resettled
and rehabilitated in a productive and sustainable manner. People who are resettled
must be able, through their own efforts and/or with support as may be required, to
restore or improve upon their level of living within a reasonable period, at least pre
project condition.
 Cash compensation shall be paid in development projects at replacement value to
those displaced for land and other assets acquired based on established prior
ownership and/or user rights. In addition to cash compensation and resettlement, a
benefit sharing will be considered where feasible. iv. Cultural and customary rights
of people displaced by projects are to be protected, particularly those belonging to
Adivasi’s (indigenous people) and ethnic minorities.
 Gender equality and equity in all stages and processes of resettlement and
rehabilitation will be fully respected.
 Displaced persons will be informed and consulted in a transparent manner,
including formal disclosure of project impacts and mitigation measures.
 Vulnerable groups, including landless, poor women headed households, physically
challenged people, elderly and those falling below the nationally defined poverty
line (by the government) displaced by project impacts, are entitled to additional
benefits and assistance in a manner that addresses their specific needs related to
socio-economic vulnerability.
 Similarly, displaced persons and/or businesses on government-leased land will be
eligible for compensation for loss of access to land and sites.
 The right to compensation, resettlement and livelihood restoration shall not lapse
or end with the conclusion of implementation of a project and shall remain an
obligation of the owner of the project until fulfilled even beyond project completion.

The draft Policy was submitted to the Government in November 2007. It has been
approved by the Ministry of Land on 01 January 2008 and is placed before the Cabinet
later in February 2008. After cabinet approval, the Government will undertake further work
towards legislative changes to safeguard resettlement rights by law.

3.2 Applicable World Bank Safeguards


As per WB OP4.12, policy guidelines will have to be ensured for the interest of the project
level and project authority/ requiring body will reinstate the socio economic condition of
project-affected person (PAPs).

 Involuntary resettlement should be avoided where feasible, or minimized, exploring


all viable alternative project designs

Vitti Sthapati Brindo Ltd. Page 33


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

 Where it is not feasible to avoid resettlement, resettlement activities should be


conceived and executed as sustainable development programs, providing
sufficient investment resources to enable the persons displaced by the project to
share in project benefits. Displaced persons should be meaningfully consulted and
should have opportunities to participate in planning and implementing resettlement
programs.
 Displaced persons should be assisted in their efforts to improve their livelihoods
and standards of living or at least to restore them, in real terms, to pre-
displacement levels or to levels prevailing prior to the beginning of project
implementation, whichever is higher.

Vitti Sthapati Brindo Ltd. Page 34


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Chapter 4: Project Impacts and Inventory

Vitti Sthapati Brindo Ltd. Page 35


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

CHAPTER 4: PROJECT IMPACTS AND


INVENTORY
4.1 Background
A structured electronic questionnaire was used to collect detailed information on affected
property and to document impacts on private assets, incomes and livelihood for a full
understanding of impacts. The objective of the survey was to generate an inventory of
social impacts on the people affected by the project, type of property, ownership of
property, type of impact and its magnitude and details of affected property. The major
findings and magnitude of impacts are discussed in the following sections.

4.2 Project Impacts


The table 3 shows the summary characteristics of the inventory of Baburail canal
restoration project.

Table 3: Summary Characteristics of the Inventory of Baburail Canal Restoration


Project

SL. Characteristics of The Inventory


1 Installation Number
Taanbazar Pool 7
Rk Mitra Road 71
Mondol Para 48
Heart Foundation to Baburail Mosque 74
Baburail Mosque to Munshiganj Highway 149
Total 349
2 Family Structure of PARs Number
Male 652
Female 705
Children 438
Total 1795
3 Economy Taka
Total Monthly Income 99,92,500
Monthly Income from Installation 44,92,200
Total Value of Installation 130,58,9837
4 Land (Sq. ft.)
Land Area 95,690
Installation Area 90,809
5 Occupation of the PARs Percent
Business 78
Service 14
others 8
Total 100

Vitti Sthapati Brindo Ltd. Page 36


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

SL. Characteristics of The Inventory


6 Major Installation Percent
Bridge 9
Business 73
House 15
Social Organization 3
Total 100
7 Building Materials of Installation Percent
Not Paved 48
Paved 12
Semi Paved 40
Total 100
8 Ownership/Tenancy Percent
Lease from NCC 26
Lease from Other Govt. Authority 18
Legal Own 3
Illegal Occupied 53
Total 100

4.2.1 Land Requirement and Acquisition


The proposed Baburail Canal Restoration project, the land is needed for using in different
purposes. The acquisition of land will have a drastic impact on the livelihood of the
community people. In most cases, it will make the people homeless, unemployed and also
landless. Every effort has been made to keep the land requirements away from the human
resettlement and private property. After the planning, the amount of land requirement is
minimum. Moreover, the acquisition of the private land was avoided in the restoration of
the project.

4.2.2 Impact on Installations


Due to acquisition of land, 349 Installations are likely to be damaged at NCC and Union
Parishad. Owners of all identified properties are the legal titleholders. In here, 149
structures were belong to Baburail Mosque to Munshiganj Highway whereas 74 structures
were belong to Heart Foundation to Baburail Mosque,71 structures were belong to Rk
Mitra road, 48 structures were belong to Mondol para and 7 structures were belong to
Taanbazar Pool.

The most 73 % of the installation were business organization where as 15% of the
installation were house. Only 9% of the installation were bridge and the lowest 3% of the
installation were social organization. Moreover, 48% of the building were not paved in the
affected structures whereas 40% of the building were semi paved and 12% of the building
were not paved.

Vitti Sthapati Brindo Ltd. Page 37


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

4.2.3 Impacts on Population


The total people of the PARs of the area is 1795. Among them, 705 were females, 652
were males and 438 were children. No ethnic people are affected by the proposed project.

4.2.4 Impacts on Economy


The total value of installation is 130,58,9837 Taka. The total monthly income of the PARs
is 99, 92,500 Taka and the monthly income from installation is 44, 92,200 Taka. Moreover,
among the PARs, The most 78% of the people were businessperson whereas 14% of the
people are service holder and 8% of the people were doing other works.

4.2.5 Impact on Ownership


Among the affected installation, the most (56%) structures were illegally occupied whereas
26% structures had ownership on the land leases from NCC. Moreover, 18% structures
had ownership on land leases from other government authority. Only 3 % of the structures
were legally owned.

The details of PARs is presented in the RAP report.

Vitti Sthapati Brindo Ltd. Page 38


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Chapter 5: Socio-Economic Profile

Vitti Sthapati Brindo Ltd. Page 39


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

CHAPTER 5: SOCIO-ECONOMIC PROFILE


5.1 Socio-economic Information of Respondents
Figure 5: Sex Distribution of the Respondents

Figure 5 indicates the sex distribution of the respondents. In the household survey, half of
the respondents is female and half of male. Moreover, in the south side canal 56.1%
respondents are male compared to north side only 44.3% male. In the same way, 55.7%
respondents are female in north side compared to south side 43.6% female.

Table 4: Age of the Respondents

Age (Years) Major Area Total Total


NCC Union Parishad Male Female
Male Female Male Female
16-20 2.4 5.5 2.8 2.4 2.6 4.1 3.4
21-25 3.6 17.3 6.6 9.4 5.3 13.8 9.6
26-35 20.5 38.2 17 41.2 18.5 39.5 29.2
36-45 27.7 23.6 22.6 25.9 24.9 24.6 24.7
46-60 33.7 11.8 38.7 18.8 36.5 14.9 25.5
60+ 12 3.6 12.3 2.4 12.2 3.1 7.6
Total N= 83 110 106 85 189 195 384

Vitti Sthapati Brindo Ltd. Page 40


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Total Avg. age 45 35 45 37 45 36 41

The mean age of the respondents is 41 years. The mean age of male respondents is
higher than the mean age of female respondents. Moreover, in both NCC and Union
Parishad areas, the most of the male respondents are in between 46 to 60 years old
whereas, the most of the female respondents are in between 26 to 35 years old (Table 4).

Table 5: Marital Status of the Respondents

Major Area Total Total


Type NCC Union Parishad Male Female
Male Female Male Female
Unmarried 9.6 1.8 9.4 9.5 1 5.2
Married 88 87.3 88.7 88.2 88.4 87.7 88
Widow/widower 2.4 6.4 1.9 9.4 2.1 7.7 4.9
Separated/Deserted 4.5 2.4 3.6 1.8
Total 83 110 106 85 189 195 384

Source: Field Survey,2017

The marital status of the respondents has been shown on Table 5. More than one third of
total respondents is 88% married followed by unmarried members 5.2%, widowed
members is 4.9%, divorced and separated is 1.8%. Both in terms of married and
unmarried member, the male is higher in number compared to female.

Table 6: Educational status of the Respondents

Major Area Total Total


Education NCC Union Parishad Male Female
Male Female Male Female
No class 27.7 30.9 11.3 30.6 18.5 30.8 24.7
Class 1 0.9 2.4 1.5 0.8
Class 2 2.4 1.8 2.8 1.2 2.6 1.5 2.1
Class 3 4.8 3.6 4.7 2.4 4.8 3.1 3.9
Class 4 1.2 6.4 0.9 7.1 1.1 6.7 3.9
Class 5 16.9 16.4 18.9 15.3 18 15.9 16.9
Class 6 3.6 3.6 2.8 2.4 3.2 3.1 3.1
Class 7 6 8.2 1.9 8.2 3.7 8.2 6
Class 8 7.2 5.5 10.4 5.9 9 5.6 7.3
Class 9 3.6 5.5 5.7 8.2 4.8 6.7 5.7
SSC pass 7.2 3.6 14.2 5.9 11.1 4.6 7.8
HSC pass 10.8 4.5 14.2 3.5 12.7 4.1 8.3
Graduate 6 5.5 6.6 3.5 6.3 4.6 5.5
Masters or above 2.4 3.6 2.8 3.5 2.6 3.6 3.1
Madrassa 0.9 0.5 0.3
Vocational Institute 1.9 1.1 0.5

Vitti Sthapati Brindo Ltd. Page 41


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Total N=Eligible >5 age child 83 110 106 85 189 195 384
Source: Field Survey,2017

Most of the respondents (25 percent) have no formal education in the project area and
one- fourth of the respondents have only class 1 to 5 education. The percent of
uneducated male is significantly higher than the percent of uneducated male respondents.
The percent of uneducated respondents are higher in NCC than in Upazila parishad
areas. Only 8 percent of the respondents have a graduate degree (Table 6).

Figure 6: Religion of the Respondents

Source: Field Survey,2017

Figure 6 represents the religion of the respondents who are living within 0.5 km of Baburail
Canal. The figure shows that 90.6% of the respondents are Muslim in the north side of the
canal on the other hand 88% of the respondents are Muslim in the south side of the canal.
It also shows 9.4% of the respondents are Hindu in the north side of the canal whereas
12% of the respondents are Hindu in the south side of the canal. Further it also presents
that the most (89.3%) of the respondents are Muslim and the only 10.7% of the religion of
the respondents are Hindu in the study area (Annex A, Table 101).

Vitti Sthapati Brindo Ltd. Page 42


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Table 7: Occupation of the Respondents

Major Area Total Total


Occupation NCC Union Parishad Male Female
Male Female Male Female
Student (no work) 2.4 1.8 4.7 3.7 1 2.3
Housewife 81.8 85.9 83.6 42.4
Emigrant 0.9 0.5 0.3
Unskilled labor / House maid 7.2 7.3 2.8 1.2 4.8 4.6 4.7
Rickshaw / Van/ Cart puller 3.6 1.9 2.6 1.3
Service/ Garment worker 30.1 5.5 22.6 5.9 25.9 5.6 15.6
Skilled labor/ Driver 8.4 0.9 7.5 7.9 0.5 4.2
Small Business/ Vendor 24.1 2.7 32.1 5.9 28.6 4.1 16.1
Medium Business 14.5 11.3 12.7 6.3
Unemployed 1.2 4.7 3.2 1.6
Retired/ Old person 6 11.3 1.2 9 0.5 4.7
Unable to work/ Disable 1.2 0.5 0.3
Teacher 1.2 0.5 0.3
Total (N=) 83 110 106 85 189 195 384

Table 7 shows the occupations of the respondents. Among female respondents, most of
them are housewife and 5.6 percent are garment workers. In male respondents, 28
percent are small businessperson or vendor and another 26 percent male respondent’s
main occupation is garment works.

Figure 7: Race of the Respondents

Race of the Respondents


99.6 100 99.7
Percentage

0.4 0.3

North South Total

Bengali Ethnic/ Adivasi

Source: Field Survey,2017

Figure 7 represents the race of the respondents who are living within 0.5 km of Baburail
Canal. The figure displays that the most 99.6% of the respondents are Bengali and only
one of the respondents are Ethnic people, who are not direct affected people of this
project, lived in the north side of the canal. However, 100% of the respondents are Bengali
lived in the south side of the canal (Annex A, Table 102).

Vitti Sthapati Brindo Ltd. Page 43


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Figure 8: Ownership of the Households

Ownership of the Households


50.3 49.7 47.1
44.6 40.9
Percentage

31.6
23.8
12

NCC Union Parishad Total


Ownership

Live at own land Live on rent House built on Govt. land

Source: Field Survey,2017

Figure 8 depicts the graphical representation of ownership of the dwelling houses of the
respondents. It shows that one half (44.6%) of the respondents live on rent houses, 31.6%
of the respondents are living at their own houses and also 23.8% of the respondents’
houses are built their houses on the government land in the NCC. In Union Parishad, one
of the half (50.3%) of the respondents live at their own houses and 49.7% of the
respondents are living on rent. For total respondents, the most percentage (47.1%) of the
respondents are living on rent where as 40.9% of the respondents are living at their own
house whereas the low percentage (12%) of the respondents’ houses are built on
government land (Annex A, Table 103).

Vitti Sthapati Brindo Ltd. Page 44


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Figure 9: Type of Houses of the Area

Type of Houses of the Area

Shanty/ Jhupri 1

Bamboo/Tin/ Earthen houses' weakly built 4.2


Types

Bamboo/Tin/ Earthen houses' well built 10.9

Brick and cement (floor/partial) 38.5

Brick and cement (all) 45.3

Percentage

Source: Field Survey,2017

Figure 9 depicts the graphical representation of type of houses of the respondents. It


shows that 45.3% of the respondents’ houses construct by all over brick and cement
where as 38.5% of respondents’ houses partially construct by brick and cement. It has
seen from the figure that the lowest percentage (1%) of the houses are constructed by
shanty /jhupri (Annex A, Table 104).

Figure 10: Total Area of the Floor of the Houses

Source: Field Survey,2017

Figure 10 represents the area of the floor of the houses. It shows in the figure that the
most (28.1%) of the respondents are using 151-300 sq. ft. household floor whereas in
NCC 33.2% of the respondents and in union parishad 23% of the respondents are using

Vitti Sthapati Brindo Ltd. Page 45


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

the same size. Moreover, the second highest (25%) of the respondents are using 301-500
sq.ft floor whereas in NCC 27.5% of the respondents and in union parishad 22.5% of the
respondents are using the same size .(Annex A, Table 105 ).

Figure 11: Monthly Expenditure of the Respondents

Source: Field Survey,2017

Figure 11 shows the average monthly expenditure of the household of the respondents. It
shows that one third (32.3%) of the respondents average monthly expense is Tk 10001-
150000 where as 27.3% of the respondents average monthly expense Is up to Tk 10000.
Moreover, the figure shows that the lowest percentage (8.3%) of the respondent’s average
monthly expense is Tk 20001-25000 (Annex A, Table 106).

Vitti Sthapati Brindo Ltd. Page 46


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Figure 12: Monthly Income of the Households

Source: Field Survey,2017

Figure 12 denotes the monthly income of the households. It shows in the figure that the
most (28.4%) of the respondents average monthly income is Tk 10001-15000 where as
24.5% of the respondents average monthly income is Tk 25000+. It has seen from the
figure that the lowest percentage (10.9%) of the respondents’ average monthly income is
Tk 20001-25000 (Annex A, Table 107).

Figure 13: Households Saving at Present

Source: Field Survey,2017

Figure 13 denotes the HH saving at all present. It shows that the most (54.9%) of the
respondents have no any HH savings where as 11.7% of the respondents have saved up
to Tk 3001-15000 HH savings. The lowest (4.2%) of the respondents have saved Tk
50001- 100000 HH savings (Annex A, Table 108).

Vitti Sthapati Brindo Ltd. Page 47


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Figure 14: HH Loan at All Present

Source: Field Survey,2017

Figure 14 denotes the HH loan at all present. It shows in the figure that the most (71.9%)
of the respondents have taken no any HH loan where as 2.6% of the respondents do not
know anything. In the second highest (7.6%) of the respondents have taken loan up to Tk
20000 (Annex A, Table 109).

5.2 Migration Status of the Respondents


Figure 15: Duration of Staying in the Present Residence

Duration of Staying in the Present Residence


55.5
Percentage

15.1 13
4.4 5.7 6.3

Upto 60 61-120 121-180 181-300 300+ Since


months months months months months birth
Time

Source: Field Survey,2017

Figure 15 represents the duration of staying in the present residence within half a
kilometer from Baburail Canal. The figure shows that the most (55.5%) of the respondents
have been living in that area since birth where as 15.1% of the respondent are staying
from 61 to 120 months. It has seen from the figure that the lowest percentage (4.4%) of
the respondents are staying up to 60 months (Annex A, Table 201).

Vitti Sthapati Brindo Ltd. Page 48


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Figure 16: Household Migration from the Area

Source: Field Survey,2017

Figure 16 illustrates the graphical representation of household migration from other area. It
shows that one half (53.5%) of the respondents have not migrated and (46.5%) of the
respondents have migrated in the north side of the canal. It shows that one half (56.4%)
of the respondents have not migrated and (43.6%) of the respondents have migrated in
the south side of the canal It has seen from the figure that the 45.3 % of the respondents
have migrated from other areas (Annex A, Table 202).

Figure 17: Migration Status of the Respondents from Area

Source: Field Survey,2017

Figure 17 illustrates the graphical representation of households’ migration from other area.
The figure shows that most 75% of the male respondents are migrated from district other
than Narayanganj, 16.3 % of the male respondents are migrated from other union around
the city and 8.8% of the male respondents are migrated from other Upazila of
Narayanganj. The figure shows that most 75.5% of the female respondents are migrated

Vitti Sthapati Brindo Ltd. Page 49


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

from district other than Narayanganj, 12.8 % of the female respondents are migrated from
other union around the city and 11.7% of the female respondents are migrated from other
Upazila of Narayanganj. It shows that most (75.3%) of the respondents have migrated
from district other than Narayanganj whereas 14.4 % of the respondents have migrated
from other union around the city. It has seen from the figure that the lowest 45.3 % of the
respondents have migrated from other areas (Annex A, Table 203).

5.3 WASH Status of the Household of the Respondents


Figure 18: Main Sources of Drinking Water for HH

Source: Field Survey,2017

Figure 18 represents the main sources of the drinking water who are living within 0.5 km of
Baburail Canal. The figure displays that the most 55.2% of the respondents are drinking
water from tube well and the lowest 7% of the respondents are drinking water from tube
well (Annex A, Table 301).

Vitti Sthapati Brindo Ltd. Page 50


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Figure 19: Alternative Sources of Drinking Water

Source: Field Survey,2017

Figure 19 represents the alternative sources of the drinking water who are living within 0.5
km of Baburail Canal. The figure displays that the most 80.5% of the respondents have no
any secondary alternative water source and the lowest 2.9 % of the respondents are
drinking water from using tube well (manual) and supply water (Annex A, Table 302).

Figure 20: Main Sources of Cooking Water

Source: Field Survey,2017

Vitti Sthapati Brindo Ltd. Page 51


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Figure 20 represents the main sources of the cooking water who are living within 0.5 km of
Baburail Canal. The figure displays that the most 51.3% of the respondents are using
water for cooking from tube well with overhead tank and the lowest 0.8% of the
respondents are using water for cooking from secondary source (Annex A, Table 303).

Figure 21: Alternative Sources of Cooking Water

Source: Field Survey,2017

Figure 21 represents the alternative sources of the cooking water who are living within 0.5
km of Baburail Canal. The figure displays that the most 80.2% of the respondents are not
using any alternative secondary water source for cooking tube well and the lowest 2.6% of
the respondents are using alternative water source by using tube well (manual) and supply
water (Annex A, Table 304).

Figure 22: Main Sources of Water for Bathing and Washing

Source: Field Survey,2017

Vitti Sthapati Brindo Ltd. Page 52


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Figure 22 represents the main sources of the water for bathing and washing clothes. The
figure displays that the most 45.8% of the respondents are using water for bathing and
washing clothes from tube well with overhead tank and the lowest 0.8% of the
respondents are not using water from any secondary source. (Annex A, Table 305).

Figure 23: Alternative Sources of Water for bathing and Washing

Source: Field Survey,2017

Figure 23 represents the alternative source of the water for bathing and washing clothes.
The figure displays that the most 76.3% of the respondents are not using water for bathing
and washing clothes from any alternative secondary source and the lowest 1.8% of the
respondents are using alternative sources by supply water (Annex A, Table 306).

Figure 24: Main Sources of Water for Latrine

Main Sources of Water for Latrine

No secondary source 1.3


Surface water (River/canal/Pond/ lake/ditch) 3.4
Source

Tube well (manual) 5.7


Tube well with overhead tank 45.3
Supply water (Not connected to HH) 16.7
Supply water (Connected to HH) 27.6

Percentage

Source: Field Survey,2017

Vitti Sthapati Brindo Ltd. Page 53


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Figure 24 represents the main sources of the water for latrine. The figure displays that the
most 45.3% of the respondents are using water for latrine from tube well with overhead
tank and the lowest 1.3% of the respondents are not using water for latrine from any
secondary source (Annex A, Table 307).

Figure 25: Alternative Sources of Latrine Water

Source: Field Survey,2017

Figure 25 represents the alternative sources of the water for latrine. The figure displays
that the most 81.5% of the respondents are not using water for latrine clothes from any
alternative secondary source and the lowest 1% of the respondents are using alternative
sources by surface water (Annex A, Table 308).

Figure 26: Types of Latrine Using by the Respondents

Source : Field Survey,2017

Vitti Sthapati Brindo Ltd. Page 54


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Figure 26 represents the types of latrine using by the respondents. The figure displays that
the most 38.3 %of the respondents are using well-built latrine connected with drain and
the lowest 0.3% of the respondents are using ring slab latrine with flap (Annex A, table
309).

Figure 27: Destination of Latrine Water

Destination of Latrine Water


To the Khal To other place
88.5 87.3
81.5
Percentage

18.5
11.5 12.7

North South Total


Flow of water
Source: Field Survey,2017

Figure 27 represents the destination of the latrine water. The figure shows that 88.5% of
the respondents said that the flow of latrine water goes to the canal and 11.5 % of the
respondents said that the flow of latrine water goes to the other place in the north side of
the canal. In the same graph, it has shown that 81.5% of the respondents said that the
flow of latrine water goes to the canal and 18.5% of the respondents said that the flow of
latrine water goes to using the other place. It has shown that the most (87.3%) of the
respondents said that the flow of latrine water goes to the canal and the only 12.7% of the
respondents said that the flow of latrine water goes to the other place (Annex A, Table
310).

Vitti Sthapati Brindo Ltd. Page 55


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Figure 28: Condition of the Latrines of HH

Condition of the Latrines of HH

57.2 54.8
51.3
48
43.6
40.5
Percentage

North
South
Total

2.3 0.7 1.6

Good Moderate Bad


Condition

Source: Field Survey,2017

Figure 28 represents the condition of the latrines. The figure shows that 57.2% of the
respondents said that the condition of the latrine is good in the north side of the canal,
51.3 % of the respondents said that the condition of the latrine is good in the south side of
the canal and total 54.8% of the respondents said that the condition of the latrine is good
condition. In the same graph it has shown that 0.7% of the respondents said that the
condition of the latrine is bad in the south side of the canal, 2.3 % of the respondents said
that the condition of the latrine is bad in the north side of the canal and total 1.6% of the
respondents said that the condition of the latrine is bad condition (Annex A, Figure 311).

Figure 29: Observed Status of the Latrines

Source: Field Survey,2017

Vitti Sthapati Brindo Ltd. Page 56


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Figure 29 illustrates the graphical representation of observed status of the latrines. The
figure shows that most 56.2% of the female respondents said that the situation of the
latrines is hygienic and 43.8% of the female respondents are said the situation of the
latrines is unhygienic. In the same figure shows the most 74.3% of the male respondents
said that the situation of the latrines is hygienic and 25.7% of the male said that the
situation of the latrines is unhygienic. The most 58.8% of the respondents said the
situation of the latrines are unhygienic and 41.2% of the respondents said the situation of
the latrines are hygienic (Annex A, table 312).

Figure 30: Children under 5 or Disabled Who Can Not Use Latrine

Source: Field Survey,2017

Figure 30 portrays the graphical representation of under 5 or disable member in the


households who cannot use latrine. It shows that (35.3%) of the respondents said that the
children under 5 or disabled member cannot use latrine and 20.9% of the respondent said
that the children under 5 or disabled member can use latrine (Annex A, table 313).

Vitti Sthapati Brindo Ltd. Page 57


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Figure 31: Dispose of the Excreta

Source: Field Survey, 2017

Figure 31 represents the dispose of the excreta of the HH. The figure displays that the
most 65.4% of the respondents said that they dispose the excreta in latrine whereas
12.8% of the respondents said they dispose the excreta in drain or open space. In the
same graph, it has shown that the lowest 1.3% of the respondents dispose the excreta in
no specific place (Annex A, Table 314).

Vitti Sthapati Brindo Ltd. Page 58


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

5.4 Environmental and Waste Management Condition in the


Area
Figure 32: Drainage Connection of HH

Source: Field Survey, 2017

Figure 32 represents the drainage connection among the household of the respondents. It
shows that existing drainage connection are almost surface drain of that area. As 33.3% of
the respondents in north, 54.5% respondents from south and 31.3% respondents in total
agreed with the statement that there were surface drainage connection (Annex A, Table
401).

Figure 33: Pathway of Rain or Waste Water

Source : Field Survey,2017

Vitti Sthapati Brindo Ltd. Page 59


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Figure 33 shows the pathway of rain or wastewater of the HH. It presents that 27.6% of
the respondents said that the water goes to outside through pipes while most of the
(46.9%) respondents said that the water goes direct to Baburail canal though pipes. Only
a few respondents are agreed that less amount stagnates around the community (Annex
A, Table 402).

Figure 34: Water Logging Problems of the HH

Source: Field Survey,2017

Figure 34 shows the percentage of water logging problem among the households. Most of
the respondents (82.4%) said that they did not face any water logging problem in
Narayanganj City Corporation. In addition, 91.1% of the respondent from Union Parishad
said so. While a few 13.3% of the respondent among the total respondent said, they faced
water logging problem (Annex A, Table 403).

Figure 35: Duration of Water Logging in a Year

Vitti Sthapati Brindo Ltd. Page 60


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Source: Field Survey,2017

Figure 35 shows the duration of water logging in year of the area. According to NCC
respondents, half (50%) of them in NCC said that they faced water logging problem for at
least 5 to 10 days. While 35.29% of them said that, they faced water logging problem for
at least 5 to 10 days (Annex A, Table 404).

Figure 36: Disposal of Kitchen Waste

Source: Field Survey,2017

Figure 36 shows the system, which is used for disposal of kitchen waste of the HH. Most
of the respondents around 41.4% said that the kitchen waste were thrown to the canal.
Only 4.9% of the respondents said that they disposed those waste to specific dustbin.
(Annex A, Table 405)

Vitti Sthapati Brindo Ltd. Page 61


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Figure 37: Air pollution Status of the Area

Air pollution Status of the Area


44.3 42.4
39.7
36.8 34.9
32.1
Percentage

28.2
22.7
18.9

North South Total


Yes, high Yes, some No

Source: Field Survey,2017

Figure 37 shows the percentage of facing Air Pollution in the project area. In North side
44.3% of the respondents said that they faced some air pollution in their area, while 18.9%
of them said they are in highly air-polluted area (Annex A, Table 406).

Figure 38: Sound Pollution Status of the Area

Sound Pollution Status of the Area


51.8
Percentage

34.9

13.3

Yes, high Yes, some No


Source: Field Survey, 2017

Figure 38 shows sound pollution percentage according to respondents’ response. Here


more than half of the respondent (51.8%) said that there were no existing sound pollution
problem. While rest of them respond yes about sound pollution (Annex A, Table 407).

Vitti Sthapati Brindo Ltd. Page 62


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

5.5 Social attachments, Facilities and Problems


Figure 39: Types of Membership of the Respondents

Source: Field Survey,2017

Figure 39 represents the types of membership among the respondents. Among the
respondents, 91.7% are not member of any organization. While a few 0.8% of the
respondents are the active member of the political party (Annex A, Table 501).

Figure 40: Play Grounds or Facilities for the Children

Source: Field Survey,2017

Vitti Sthapati Brindo Ltd. Page 63


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Figure 40 represents the playgrounds or facilities for the children to play in the field. It
shows the playgrounds proportion is not at all around 95.8% respondents from Union
Parishad, 68.9% respondents from NCC area and the total percentage shows 82.3%
(Annex A, Table 502).

Figure 41: Open Space of Parks for the Residents to Walk or Socialize

Source: Field Survey,2017

Figure 41 illustrates the open space of parks for the residents to walk or socialize. In this
figure, 96.9% respondent of Union Parishad said there are no open space park whereas
2.6% people of Union Parishad said inadequate and 2.5% respondents people agreed.
(Annex A, Table 503)

Vitti Sthapati Brindo Ltd. Page 64


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Figure 42: Facilities for the Residents to Enjoy Cultural Events, Movie, Drama

Source: Field Survey,2017

Figure 42 displays facilities for the residents to enjoy cultural events, movie, and drama. In
the figure where 90.6% female respondents said there are no facilities for cultural events,
movie, drama although 9.4% female respondents said about inadequate facilities and no
one said yes about there are no any facilities (Annex A, Table 504).

Figure 43: Drug Addiction Problem of the Area

Source: Field Survey,2017

Figure 43 represents about the serious problems of drug addiction. It displays the
percentage of very serious 17.1% in north side, 10.3% in south area and the total is about
14.1%. Whereas 42.3% south people said, this is serious and 25.4% of north people and
32.3% is about total people (Annex A, Table 505).

Vitti Sthapati Brindo Ltd. Page 65


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Figure 44: Security Related Problem in the Area

Source : Field Survey,2017

Figure 44 shows the percentage of security related problems in the area. According to
NCC areas’ 48.7%, respondents said medium. It has also shown in Union Parishad 36.6%
respondents said medium and the total is about 42.7%. In the same graph shown that
7.3% respondents of NCC said security problem is very low, 27.7% is from Union
Parishad and the total is about 17.4% (Annex A, Table 506).

Figure 45: Percentage of People who are Socially Connected to Each Other

Source : Field Survey,2017

Figure 45 reflects how much people are socially connected to each other. The figure
displays that the high 37.8% of the respondents from south area said they are connected,
27.2% from north area and the total is 31.5%. On the same graph the medium 61.5% from
south area, 62.3 from north area and 62 is the total (Annex A, Table 507).

Vitti Sthapati Brindo Ltd. Page 66


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Chapter 6: Institutional and


Implementation Structure

Vitti Sthapati Brindo Ltd. Page 67


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

CHAPTER 6: INSTITUTIONAL AND


IMPLEMENTATION STRUCTURE
6.1 Institution Related to Policy, Planning, M&E of the
Project
In order to implement Social management, NCC needs a stronger institutional
management unit. So that, the existing institutional arrangement of NCC needs to be
reviewed.

The Project Implementation Unit (PIU) that will be established within NCC will lead the
Project implementation. The PIU will be responsible for procurement of consultants for
carrying out the SIA. The PIU will be headed by the Project Director (PD). The PIU will
consists of an Environment and Social (E&S) monitoring Cell with qualified staff. This E&S
Cell will assist the PIU on issues related to environmental and social management and
oversee the Construction Supervision Consultant (CSC) and contractors and will compile
quarterly monitoring reports on SMP compliance, to be sent to the Project Director and
also shared with the World Bank, throughout the construction period. The E&S Cell will
also provide trainings to the NCC field personnel responsible for monitoring of social
compliance during both construction and O&M phases of the project. In addition, NCC will
recruit a SMP Implementation Specialist or hire an NGO in the entire proposed NCC
project, who will be responsible for overseeing the social mitigation measures during
operation and maintenance period. Moreover, the project authority will establish RU during
construction period and it will be converted to a Corporate Social Responsibility (CSR) /
Social Development Cell during post construction period for mitigating future social and
resettlement impact including any pending resettlement issues, headed by a Deputy
Director as Project Manager (PM) under the guidance of Project Director (PD).

The E&S Cell will have adequate numbers of environmental and social
scientists/specialists and maintain coordination and liaison with CSC for effective SMP
implementation. Similarly, the CSC will also have environmental and social monitors who
will supervise and monitor the contractors for effective SMP implementation. The
contractors in turn will also have supervisors who will ensure SMP implementation during
construction activities and will assign to develop necessary detailed SMP plans as per this
SMP, and oversee their implementation during construction.

The PIU will also engage an independent organization to carry out external monitoring
and evaluation on implementation of RAP; however, this component will not involve
monitoring and evaluation of EMP due to limited nature of impacts. The roles and
responsibilities of PIU and its consultants are presented in Table 8.

Vitti Sthapati Brindo Ltd. Page 68


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Table 8: Roles and Responsibilities for SMF Implementation

Organizations Responsibilities
PIU/NCC  Ensure that all project activities are well managed and coordinated.
 Recruitment of consultants for SIA & RAP
 Procurement of works and goods.
 Payment of compensation to the project affecters
 Recruitment and supervision of Construction Supervision
Consultants (CSC)
 Recruitment and supervision of external monitor and independent
Panel of Experts
 Carry out environmental assessment of projects in Component in
compliance with the World Bank and Government of Bangladesh
requirements

E&S Cell within  Responsible for assisting PD with developing TORs and hiring of
PIU/ NCC consultants to carry out any required environmental assessment
work for subprojects and also for preparatory studies in
Component, reviewing consultant deliverables related to
environmental assessment, reviewing bid documents for inclusion
of SMP measures, supervising construction activities, producing
periodic monitoring reports,
 Ensuring inclusion of SMP in bidding documents
 Providing training on SMP principles and requirements to CSC,
contractors, NCC field staff, and others as needed to ensure
effective implementation of SMP
 Supervising CSC for the implementation of SMP
 Closely coordinate with other concerned agencies, local
governments and communities to support implementation of SMP
 Preparation of progress reports on implementation of SMP.
 Ensure effective implementation of SMP components not directly
tasked to the contractor including components dealing with
indirect, induced and cumulative effects, as well as operations and
maintenance stage plans and measures.
 Commissioning and oversight/review of consultant reports for
SIAs/SMPs to be developed for the subcomponents of the Project
 Ensure compliance of the studies on Component comply with
World Bank and Government of Bangladesh requirements.
 Responsible for developing standard environmental code of
practices during operation stage of Canal

SIA Consultants  Carrying out SIA studies in compliance with the GoB and World
Bank guidelines
 Preparing RAP for inclusion in the bid documents

CSC  Supervise civil works, ensuring compliance with all design


parameters including quality requirements
 Supervising contractors for SMP and EMP implementation
 Prepare monthly reports and submit to PIU
 CSC will have dedicated environmental and social staff

Vitti Sthapati Brindo Ltd. Page 69


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Contractor/NGOs Responsible for implementation of mitigation and monitoring measures


proposed in the SMP
M&E Consultant External Monitoring and evaluation of Resettlement Action Plan

6.2 Main Project Implementation Organization –NCC


Narayanganj Municipality was established on 8 September 1876 to control an area of 4.5
square miles with a population of 27,876. The city was commissioned as an urban
administrative unit in British period. During 1766, on 5 May, 2011 former Narayanganj,
Siddirganj and Kadamrasul municipalities are upgraded as Narayanganj City Corporation
to take care of the development needs of this city and to ensure necessary citizen services
according to commitment of Hon’ble Prime Minister Sheikh Hasina. Dr. Salina Hayat Ivy
was the first elected Mayor as well as current Mayor of NCC.

Hierarchy: The Mayor is the head of NCC. He will assist by member development and
member finance and administration and some other part time members. The structure of
administration of NCC is given below in the following table.

Table 9: Manpower of Narayanganj City Corporation (NCC)

SI Post Name Total


Posts
1 Mayor 1
2 Mayor officials 4
3 Chief Executive Officer 3
4 Administration Department (Secretary’s Office) 3
5 Counselor’s Staff 54
6 ICT and Computer 3
7 Central Record Room Section 3
8 Law Section 5
9 Administration Section 10
10 Security Section 11
11 Central Reserve Section 4
12 Communication Section 81
13 Magistrate Section 3
14 Communication Section 4
15 Revenue and Taxation Department 6
16 Assets Department 16
17 Social Welfare Department 17
18 Accounting Department 14
19 Engineering Department 3
20 Architecture Department 14
21 Electricity Department 14
22 Health and Family Planning Department 5
23 Waste Management Department 3
24 NCC’s Each Regional Office Post 168

Vitti Sthapati Brindo Ltd. Page 70


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Total 449

Work force: Dr. Salina Hayat Ivy is foremost of the Naryanganj City Coporation. Total 449
employees are working in NCC with 1st class to 4th class.

Key strengths and Weakness of NCC: NCC is one of the important city corporation in
Bangladesh for its economic zones. Dr. Salina Hayat Ivy have visionary leadership for
developing newly shaped Narayanganj City Corporation. The mayor very much concerned
issues like environment, employment, health and safety. She has tried to ensure
transparency in every official activities of NCC. NCC is not sufficient with his official’s and
employees; they need more work force for agitating more development projects. The
income of NCC is not sufficient, its need more fund and donor organization to contribute
the development works.

Issues for Considerations: Key issues the sustainability of the proposed project
regarding funding, income and facilities management.

Capacity Building: For capacity building NCC should recruit more efficient engineers and
others officials. They also need sever capacity building trainings and workshops.

Vitti Sthapati Brindo Ltd. Page 71


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Chapter 7: Stakeholder Analysis

Vitti Sthapati Brindo Ltd. Page 72


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

CHAPTER 7: STAKEHOLDER ANALYSIS


7.1 Introduction
During the development of PP and other documents, meetings and consultations with the
public had already taken place to disseminate information on the project activities among
the project-affected peoples (PAPs) and other stakeholders of this project. The
consultation approach was based on a combination of Formal and Informal meetings,
Focus Group Discussions (FGDs), Key Informant Interview (KII) with the local peoples,
local elite and businessperson, teachers, women group, local NGOs, Narayanganj Press
Club, Ward Councilors and other Govt. organizations. The formal meetings were held
through prior notice, appointment and invitation including all the PAPs and households,
district administration, local administration and other stakeholders in the affected area.
The basis for selecting the stakeholders was based on the following criteria:

 Identifying the project affected people


 Identify the government agencies connected with the project
 Identify local elites and academicians for their view on the project
 Identify the closed households or commercial institutions of the project site, make
them aware about the impacts of the project, and noted their concerns and
reporting.
 Identify the local NGOs working in the area

One large public consultation meeting, which included affected peoples, representatives
from the project areas, district and local administration, as well as other community
peoples including prominent locals, lawyers, journalists, academicians and Narayanganj
City Corporation (NCC), was held in NCC auditorium on 11 April 2017. Meeting minutes
of the consultation with the stakeholders are shown in the later part of the annexure.

7.2 Stakeholders at Different Levels


This section presents the main stakeholders of the project area. NCC, LGED and DWDB
are the main development stakeholders. Political organizations are also playing a vital role
as a major part of stakeholders. Whether upholding security, law enforcement agencies,
Narayanganj press club, Narayanganj motor labor union are correspondingly one of the
imperative stakeholders.

Vitti Sthapati Brindo Ltd. Page 73


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

7.3 Stakeholder Analysis


Figure 46 illustrates the detailed roles and responsibilities of different stakeholders in the
target project area.

Figure 46: Stakeholder Analysis of the Project

Political Organization Administration, Revenue,


Security, Law and Order
_Awami League (AL)
_Bangladesh Natioanlist Party
(BNP)
_Regional Political Parties _Deputy Commissioner (DC)
Including Leftist _Superintendent of police (SP)
_Bangladesh Jatiya Party (BJP) _Upazilla Nirbahi Officer (UNO)

Mayor of Narayanganj
City Corporation

Peoples Issue & Human


Development
Rights
_Local NGOs
_Narayanganj City Corporation (NCC) _Grassroots Communities
_Local Government Engineering _Local Elites & Business Community
Department (LGED) _Bangladesh Poribesh Andolon
_Dhaka Water Development Board (BAPA)
(DWDB) _Narayanganj Motor Labor Union
_TLCC
_WC

Vitti Sthapati Brindo Ltd. Page 74


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

7.3.1 Political Organization


Bangladesh Awami League (BAL): BAL is one of the oldest and major political parties in
Bangladesh. They played leading role to achieve the independence of Bangladesh,
presently it is the country’s governing political party. Honorable prime minister of
Bangladesh, Sheikh Hasina is the chief leader of the ruling party. However, as the ruling
party and the highest decision making authority (government) of the state, Bangladesh
Awami League can play a vital role in the project. The local AL subdivision can watch after
or facilitate good governance through detailed participation, visible precision, contestation,
responsibility and innovation for the best implementation and outcome of the project.
Moreover, monitoring the opposite political party should be another concern.

Bangladesh Jatiya Party (BJP): Bangladesh Jatiya Party (BJP) is the present opposition
party of Bangladesh. Currently Rowshan Ershad is the opposition leader and Hossain
Mohammad Ershad is the chairman and founder of BJP. As an opposition party, they
should speak as an alternative of government. They would give total support to
accomplish this project flawlessly. However, their role is very important for the project
expansion. They will give total sustenance for keeping decent atmosphere in the project
area.

Bangladesh Nationalist Party (BNP): Bangladesh Nationalist Party (BNP) is another


major political party of Bangladesh. BNP should speak is in the target project territory and
should be in charge of challenging the strategies of the government's policies and creating
different arrangements where suitable or relevant to offer. However, most importantly they
should not make or support any sort of political unrest and make the peaceful community
worsen in the project area.

Regional Political Parties including Leftist: Other political parties should be concerned
about the big picture and what is happening for the greater development. Helping by
providing with the best support and with the relevant recommendation for the project.

Vitti Sthapati Brindo Ltd. Page 75


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

7.3.2 Development
Narayanganj City Corporation (NCC): Once people called Narayanganj the Dundee of
the east for the significance of jute business. On 5 May 2011, Narayanganj Pouroshova
was moved up to City Corporation. It was framed involving Narayanganj town, Siddirganj
municipal territory and Kadamrasul municipality. Newly shaped Narayanganj City
Corporation is 72.43 sq. km (counting Shitalakkha River) with 7,09,381. It comprises of 27
wards including 9 save seats for women. After dissolving the Siddirganj municipality, its
nine wards (1 to 9) have been announced as wards 1 to 9 of NCC. Many industry &
garments factory stand here and day-by-day it is increasing rapidly because of
Narayanganj city is very close to the capital city of Dhaka. NCC will play the leading role to
implement the project in cooperation with LGED.

Local Government and Engineering Department (LGED): LGED is one of the largest
trusted public organizations of Peoples Republic of Bangladesh under Local Government,
Rural Development and Co-operatives (LGRD). It was established in 1960. LGED works
for development of transportation structures in rural areas and to provide technical support
to the rural and the urban local government institutions, planning and execution of
infrastructure development projects in the rural and urban areas to expand communication
and transport network, job creation, and poverty reduction. LGED will enhance the socio-
economic condition of the community through supply of infrastructures at local level and
capacity building of the stakeholders. LGED will play the monitoring, implementation and
supervision role with NCC in this project.

Dhaka Water Development Board (DWBD): DWDB is a government organization, which


is dealing the water resources development and management. DWDB is working under on
Bangladesh Water Development Board (BWDB). The major objectives of DWDB is to
control the flow of both surface water including rivers, waterways and ground water in
Dhaka District.

7.3.3 Administration, Security, Law and Order


Bangladesh Poribesh Andolon (BAPA): BAPA was launched in 2000 to create a
nationwide movement to protect Bangladesh’s environment. BAPA is general platform for
citizens and organizations concerned with the environment. BAPA, acting as an
organization against any kind of environmental degradation, is trying to create a broad-
based citizen’s movement for protection and progress of environment in Bangladesh.

Vitti Sthapati Brindo Ltd. Page 76


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Local NGOs play a very crucial character to implement this project. The local NGOs of
Narayanganj would support to demonstrate of the project plan through relationship
building with people. Nearby local elites and businessperson would no damage and
prescribe important recommendations. On the other hand, grassroots communities can
build appreciative of the project plan, facilitate the project, and complain appropriately to
the authority.

7.3.4 Peoples Issue & Human Rights


Deputy Commissioner (DC) of Narayanganj would be the prime personnel to monitor the
holistic law implementation and under his jurisdiction, Upazila Nirbahi Officer (UNO) of
Narayanganj Sadar Upazila, Superintendent of Police (SP) of Narayanganj District would
monitor the holistic law implementation. Armed forces and would be in the duty of keeping
holistic peace and keep the area free from any kind of un-wanted disturbances and
unrests. Moreover, TLCC and WC will give their support in the project by monitoring and
positive criticism of the overall works.

7.4 Beneficiaries/ Stakeholders Expectations


The stakeholders are very much concerned about this project. Improvement of the
facilities in project area is the main expectation from the stakeholders. Nearby livelihood
and land losers claim for compensation at the affected land and structure.

Table 10: Comments and Suggestion from FGDs and KIIs

Date Participants Comments and Suggestion

th th
KIIs 11 to 20 Local people of Effective compensation should be given those are really
April, 2017 Narayanganj, affected by this project.
Income opportunities should be create who lost his jobs due
to this project.
PAPs
This project will increase the beauty of city.
There should be excellent quality of drainage system.
Economic activities will rise for the project.
Environment pollution will be reduced.
The canal will be an entertainment center.
Once again, connection will be made between two rivers.
Development of Narayanganj city and rural areas will be
increased.
Local shop and local trade will be improved.
The city will be neat and clean.
Both sides have wide road to walk along the sidewalk.
th th
FGDs 11 to 20 Local people Construction materials should be better. Maintenance
April, 2017 (Male Group, should be regularly.
Women Group, There should be complain box.
Both side drainage should be arranged.
Kashipur Union
There should be a billboard which will focus Baburail Canal
Parishad, NCC history.
Slum, NCC Canal water should utilize for both cooking and bathing.
Areas) The construction materials should be in accurate place.
For maintenance Baburail Canal people should recruit from
Narayanganj, then this will create some employment in the

Vitti Sthapati Brindo Ltd. Page 77


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

area.
The water of the canal should clean.
The both side road has to be widened.
The old tradition will be returned in the Narayanganj.
In the canal, the water is to be throughout the year.
To arrange planting trees in the both side of canal.
There should be arranged sweet water supply in the canal
bank.

7.4.1 Overall Issues Emerged During Public Consultations


Table 11 presents the comments and expectations of stakeholder during public
consultation on SIA that was held on 11 April 2017.

Table 11: Opinions of Participants in Public Consultation Meeting (Tuesday), 11


April 2017

Personal Question Answer of the Meeting


Information
Sl. Question Reply/ Response

01 Nuruddin Ahmed Can we make an Auto-stand Vitti: To provide a sustainable solution to


President for the Padel Chalito Autos? transport problem we thought about
Narayanganj Bashi promoting Public Transport like Buses. There
Shong Gothon is a grid given in the action area plan. We will
01726670692 widen the roads up to 7m. Then buses will
start running on these roads. It will be an
environment friendly solution.
02 Advo. AB Siddique How to manage the waste Vitti: Solid waste will be dumped outside the
President materials that accumulate city about 30 km away, this process will be
BAPA beside the drains? He also indicated in tender processing. A monitoring
01742820442 asked where to dump these cell will be formed and local people will
wastes? monitor the work. There will be fixed dustbins
beside Gymkhana Lake.

03 Obaidullah Have the consultants Vitti: Yes, we have. If there appears any kind
Ex-Panel Mayor considered the existence of of obstacle in the utility lines, then it will be
gas line and WASA line removed. There will be walkways beside the
(Utility Lines) during the water bodies. Project’s social survey is
designing/planning? He ongoing and the decision for road
added that will the Utility connectivity will be taken after the findings
lines be interrupted/ from the social and traffic surveys are
disturbed by the received.
development works? He
again asked would there be
any walkway/ road beside
the canal if all the private
bridges were demolished?
04 Nazmul Alam When the project will start Vitti: The project is already running and total
Councilor and what is the total duration duration of the project is about 2 years.

Vitti Sthapati Brindo Ltd. Page 78


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

16 No. Ward, of the project? Hopefully, within 2019 the whole project will
Narayanganj be completed.
05 Abdus Salam Will the Canal be filled with Vitti: Three internal canals are also
President water ever (as consultant connected to Baburail canal and their
Narayanganj Press proposed dams/sluice gate)? polluted water should not contaminate
Club Baburail canal. We are thinking about
01552329422 providing either Rubber Dam or any other
kind of Dam whichever seems suitable to
save Baburail’s water.
It is noteworthy that, the underground water
level is in good condition and water level will
always be 4.5 m from the bed level of the
Canal.
06 Is there any provision of Vitti: Thanks for your suggestion. We will try
potable water? He added to incorporate it in our plan and designs.
that is there provision of There is provision for public toilet in
maintenance of trees. He Gymkhana Lake but due to lack of space,
also asked is there any there is no provision for public toilet in
provision of Public Toilet? Baburail Canal. We shall try to incorporate
the clubhouse for the provision of Public
Toilet.
07 Afzal Hossain Is there any provision of Vitti: We are not treating the Lake water. We
General Secretary water treatment plant, after will preserve the rainwater in it, which will be
Narayanganj Press provision of dams will this clean. We are putting dams so that this clean
Club turn Baburail Canal into a water does not get mixed with the polluted
afzalhossainpouty@g pond? Last, he asked would water that comes from river branches.
mail.com this water body be pollution
01913535383 free?

08 Abdur Rahman Liton Will there be any Vitti: Honorable Mayor has got some creative
Secretary resettlement plan of the ideas about the resettlement and that will
Shop Owners union settlements along R.K. Mitro definitely happen.
01711339914 road? He added that we
have shifted our shops in our
own initiatives for the
betterment of the project.
09 Sharifuddin Shobuj Will there be any Mayor: I will try to work for the development
Narayanganj Press development of other Lakes, works along Shitalakkha River to Dhaleswari
Club bridges outside the River.
0191339822 Narayanganj City Vitti: Honorable Mayor has taken the
Corporation area (From ownership of working in the Union Level by
Dhaleswari to Shitalakkha developing partnership with LGED. In
River)? Is it possible to come Bangladesh LGED is the only Engineering
to NCC office directly from Department to work with Union Parishad.
Chasara by rickshaw? ***Some person wanted all of the Survey
Data of TIA and SIA. Nevertheless, he was
assured that these data are confidential so
those will not be provided. However, the
entire planning of Baburail Khal Project will
be available online within very short time.

Vitti Sthapati Brindo Ltd. Page 79


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

10 Ranjit Kumar Das Will there be any kutcha Mayor: Kutcha Bazar is unhygienic.
SM Malik Road Bazar (Organic food store) Therefore, modern Grocery stores
01714404364 inside the plan? (He was (Departmental store) will come to the area
concerned because famous instead. However, if people still want a
Kutcha bazar of traditional Kutcha bazar (Organ food store)
Meenabazar/Boubazar was then I will try to think of it. There is no
being demolished) provision for Kutcha bazar along the canal
because of environmental concern.
11 Mizanur Rahman Is there any preparation of Vitti: We have thought of creating a
Tulu public toilet in the plan? How recreational space surrounding the water
Businessman many and where? bodies. In Gymkhana, lake there will be 2
Rk Mitra Road public toilets. However, as per your concern
01711537228 we will try to make arrangements for drinking
water beside the water bodies also.
12 Md. Shofiuddin How long is this project Vitti and Mayor: It has been two years of this
Prodhan going to take to become a project. We have already started the work for
Councilor reality? Can we bring segment one. One tender is passed. Now it
14 No. Ward, Shitalakkha River inside the is time for the other segments. Eventually,
Narayanganj realm of this project? (He the end of 2018 or the beginning of 2019 will
01713015143 also wants that river to be do the project.
pollution free)
Vitti: We all want to save Shitalakkha. This is
now a national problem. If government wants
to do it, then it might be possible to save our
rivers. We have to find it out from the Rainfall
data. We considered the increase of traffic
flow in the project. We have to check it back
in our TIA. DAP is ongoing. Therefore, plan
for a building will not pass if it does not have
a road that is 7m wide.

Concluding Notes of Mayor: In conclusion note Mayor expressed her gratitude to all for
attending in the meeting and making it successful. She informed the audience that a
portion (package-1) of the project is already on going and tender for package-2 will be
prepared very soon. Narayanganj is a city of Canal and Rivers and connected by seven
rivers directly and indirectly. Government is now taking positive initiatives to save the
rivers and agricultural land with proper law and order. Mayor has an agenda to save the
playground, doing tree plantation and she has already given directions to new elected
councilors to provide her with a list of canals and water bodies that need to be restored.

7.5 Information Disclosure Process


Public disclosure is a continuous process. NCC has initiated the process through the
beginning of the project development. During the project preparation process, NCC
undertook several Stakeholder Consultations. The public consultations conducted to date

Vitti Sthapati Brindo Ltd. Page 80


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

have thoroughly covered the issues related to environmental and social issues, which
allowed all proposed measures to be developed with sufficient input from the affected
stakeholders, using the mechanism of participatory, inclusive and informed consultation.
The methodology used for the disclosure process was as follows:
i) A 100% questionnaire-based census (inventory) was carried out on the PAPs during
which
Information on the project activities was disseminated and the nature of impact and
compensation issues were discussed.
ii) During the sample-based socio-economic survey, which had covered 384 households
within the impact zones, dissemination of information on the project activities was also
taken and information disclosure carried out.
During consultations and engagement process with people in the Project locality, NCC
field staff explained impacts and benefits of the Project, payment of required
compensation for the damage and measures taken by the Project to avoid public utilities
and community infrastructure such as schools, roads, common property resources etc.
2.5. Plan for further consultation and community participation during Project
implementation
The proposed plan for future public consultations is as follows:

Table 12: Proposed Plan for Future Public Consultations

1 Detailed/Check Public Meeting and individual affected household survey In every six
survey will be carried out as per the monitoring programme. The month
survey will be focused on compensation, rehabilitation and
community development programme related to the
different Project components
2 Construction Localized group meetings, Distribution of information Throughout
Phase leaflets and brochures, Public display construction
period
3 Operations Information brochures, Operation field offices in the Continuous
Phase affected localities, Monitoring and providing response to during Project
public enquiries, Press releases operations

7.6 Access to Information


The EIA, SIA and RAP reports will be disclosed in the NCC website. Consultation
workshops were held on 11th April 17 at NCC auditorium to share and disclose the some
findings of the SIA report. Invitations were sent to relevant stakeholders including local
government officials and local community. The documents will also be sent to the World
Bank info shop. The executive summaries of EIA, SIA and RAP documents will also be
translated and made available to the local communities by placing them at NCC offices.

Vitti Sthapati Brindo Ltd. Page 81


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Table 13: Participants in Public Consultation Meeting (Tuesday), 11 April 2017

Picture-1: Welcome notes by Honorable Mayor Picture-2: Detail Presentation of the Project

Picture-3: Women’s’ Participation Picture-4: Discussion Participation by Chief


Guest

Picture-5: List of Project Affected People Picture-6: Poster for the Public Consultation

Vitti Sthapati Brindo Ltd. Page 82


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Discussion Session by Project Affected People

Picture-7: Mr.Nuruddin Ahamed (President, Picture-8: Advo. AB Siddique (President, BAPA)


Narayanganjbashi Sangathan)

Picture-9: Mr. Obaidullah (Ex-Panel Mayor) Picture-10: Sharifuddin Shobuj (General


Secretary, Narayanganj Press Club)

Picture-11: Mr.Ranjeet Kumar Das ( S M Mallick Picture-12: Mr.Tarik Babu( General Secretary,
Road) BAPA)

Vitti Sthapati Brindo Ltd. Page 83


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Picture-13: Mr.Safiuddin Prodhan (14 No Ward Picture-14: Mr.Najmul Alam (16 No Ward
Councilor) Councilor)

Picture-15: Mr.Abdus Salam (President, Picture-16: Mr.Afzal Hossain (General


Narayanganj Press Club) Secretary, Narayanganj Press Club)

Picture-17: Mr.Mizanur Rahman Tulu (Businesman, Picture-18: Mr.Abdur Rahman Liton (General
R K Mitra Road) Secretary, Shop Owners Union)

Vitti Sthapati Brindo Ltd. Page 84


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Chapter 8: Impact Assessment

Vitti Sthapati Brindo Ltd. Page 85


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

CHAPTER 8: IMPACT ASSESSMENT


8.1 Introduction
In this section, probable impacts of the project are identified and described. The project
has some critical issues such as land acquisition, shop owners and structure losers have
been identified in the project site. During survey, some livelihood impact has been
identified and these will be solved by giving them full compensation. No indigenous
community, residents on vulnerable has been identified as affected. In the following
paragraph and tables, project’s impacts and probable mitigation measures has been
presented.

8.2 Positive Impacts


The future of the project is very prospective. Planned urbanization and employment
generation are expected to be increased in the project area. After development of the
project, in new site with new facilities will be intensified both socially and economically.
The table 9 represents the probable positive impacts of this project. The majority people
say when the project will be developed this project bring benefits for them. People of
project area also think that their income opportunities for both poor and local people will
increase because NCC will give them compensation and employment in Govt. and Private
sector, by this way local people will engage in the study area. In addition, environment of
the project areas will be more clean and free from pollution. That place can be used as
both tourist and recreational place area. Moreover, local people think that they will be
happier than before because opportunities of local people, businessman, transport sector,
environment, and investment will increase.

Table 14: Positive Impact of the project from KII, FGD

SL Types of Impact Positive Impacts


01 Income opportunities for the poor Affected people will get compensation.
and local people Employment in Govt. and Private sector will increase.
Local people will engage to work the project.
House rent will increase.
Land value will increase

02 Income opportunities for the Trade and business will increase.


businessman Communication system will be more improved.
Infrastructures will be developed.

03 Transport Sector The traffic will reduce.


Transport workers will get more income.
The roads will more wide.
Water Transport system will be added.

04 Tourism and Recreation The city will be an amusement center.


People will take fresh breath when the project will be
accomplished.
There will be created playground.

Vitti Sthapati Brindo Ltd. Page 86


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

05 Environment Environmental pollution will be reduced.


Area will be clean and free from waste dumping.
The canal will have clean water and the water flow will
upsurge.
06 Investment Govt. and private investment will increase.
Source: Qualitative Data Analysis

Table 15 shows the percentage of possible benefits/good impacts of this project. The
highest 96.4% people claim yes that the area will be attractive where 16.1% people
opposed with the statement. Area will be clean free from waste dumping were agreed by
the 95.3% and here a few 4.7% people disagreed. While 85.6% of the respondent think
that air quality will improve, 14.3% do not think so. It also represents the 72.9% people
admit in income opportunity will increase when the project will be completed and 27.1%
deny these possible benefits.

Table 15: Possible benefits / good impacts when the project will complete

SL Possible Benefits / Good Impacts Percent of


Respondents
Yes No
01 Land value will increase/Developers will be attracted 83.1 16.9
02 Income opportunity will increase 72.9 27.1
03 Area will be clean free from waste dumping 95.3 4.7
05 Area will be attractive 96.4 3.6
06 Area will be free from water logging 81 19
07 Improve water transport system 73.2 26.8
08 Improve the overall environment of the area 90.4 9.6
09 Air quality will improve 85.6 14.3
10 Ample green space will be available for recreation 86.9 13

8.3 Adverse Impacts


The table 16 represents the possible problems or adverse impacts when the project will be
completed. Significantly, 84.9% people said yes on the house rent will increase/low
income people will be ousted and 15.1% said no. It is also representing the response
19.1% claimed yes on traditional values will tilt/disappear and 81% opposed with the
statement.

Table 16: Possible problems or adverse impacts when the project will complete

SL Types of Adverse Impact Percent of


Respondents
Yes No
01 House rent will increase/ Low income people will be ousted 84.9 15.1
02 The area will be much crowded, Become congested 70.6 29.4
03 Migrants will take over the locals 49.2 50.8
04 Traditional values will tilt / disappear 19.1 81
05 Social crime will increase 31.2 68.8
06 Public health concerns will raise 27.1 72.9
Source: Field Survey Data

Vitti Sthapati Brindo Ltd. Page 87


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Possible problems during implementation of the project reflects on the table 17. Most of
the people (84.6%) agreed that communication across the canal will be disrupted and
15.45 did not agreed. It also reflecting 32.6% said yes on the education of children will be
disturbed and 67.4% deny this possible problem.

Table 17: Possible problems during implementation of the Project

SL Possible problems during implementation of the Project Percent of


Respondents
Yes No
01 Noise pollution will Increase 60.7 39.3
02 Air pollution will Increase 65.4 34.6
03 Too many laborers/ outside people will crowd the area 58.3 41.7
04 Many people will lose their income 67.4 32.6
05 The education of children will be disturbed 32.6 67.4
06 There will be interruption in business due to massive work 61 39.1
07 May need to leave the place during implementation 51.3 48.7
08 Communication across the canal will be disrupted 84.6 15.4
09 Will face problem in disposing waste water and solid waste 80.4 19.5
disposal in the canal
10 Waste water and sewage disposal in the Khal will be 75.8 24.8
restricted
Source: Field Survey Data

There are some adverse impacts can also be seen in the project area. The key types of
adverse impacts are representing in table 18, which are land acquisition, requisition from
local people, damaging road infrastructure for moving heavy vehicle, health related issues,
temporary loss of local community. Adverse impact for land acquisition would be
demolishing illegal construction building, which were situated in the canal bank where
mitigation measures might be compensation, provided by NCC. Relocation of shops and
business will affect adversely on employment opportunity, here creating alternative income
facilities and arranging income-generating activities (IGA) with new strategies training by
NGOs will work as mitigation measures. Water borne, airborne, STD diseases may
increase due to constriction, migration of workers etc. will increase health related risks
where mitigation measures should be increasing health services in the area, raising
awareness and information campaign on time with the help of NGOs and other related
organizations.

Table 18: Types of Adverse Impact and Mitigation Measures

SL Type of Adverse Impact Mitigation Measures Implementing Authority


Impact
01. Land Demolishing illegal NCC will provide primary 1. Narayanganj City
Acquisition construction building compensation. NCC will carry Corporation
which were situated in out feasibility study of the land 2. NGO as
the canal bank. acquisition. implementation
agency
Land Dumping center may Contractor with supervision of
02. Requisition be needed for the the NCC will hire the land as 1. Contractor
construction materials market price. If the land has 2. NCC will ensure
but it has not yet crops then the crop value will be proper

Vitti Sthapati Brindo Ltd. Page 88


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

finalized. provided and determined by compensation


NCC.
Demolition of Removal of business Replacement cost of structures 1. Narayanganj City
03. existing structure and other immovable builds Corporation
business items will be provided at current
structure market price of the same
building materials plus the
current cost of labor to build
them.
1.Primary Compensation by
NCC
04. Employment Temporary Negative Persons who are employed in 1. NCC will ensure
opportunity impact on income the affected businesses being proper
sources will be operated on private or public compensation
occurred due to lands. 2. Contractor
relocate shops and 3. Skill training by
business. 1.Creating alternative income NGO
facilities
2. Cash grant will be provided
by NCC
3. Arrange training by NGOs on
income generating activities
(IGA) with new strategies.
4. PAPs and Local people
should be given priority to the
construction work of the port. It
is also provided job facilities for
the local people.
05. Road May be damaged due Future support from the project 1. NCC
infrastructure to movement of heavy authority will be 2. Construction
vehicle. given if any damage will occur Contractor
in future during project
implementation. Authority
should reinstate it timely and
give support for the
maintenance.

07. Health related Water borne Authority should support and 1. NCC
issues airborne, STD increase health services in the 2. NGO
diseases may area.
increase due to ,
constriction, migration
of workers etc.
08. Drug Addiction Drug Addiction may Raising awareness and 1. NCC
and AIDS etc. increase due to information campaign is 2. NGO
migration of workers needed on time with the help of
NGOs.
09. Livelihood Temporary livelihood Authority should allocate of 1. NCC
will be affected for commercial spaces and/or 2. NGO
the existing compensation for project
shopkeepers and affected shopkeepers and
employees businessman.

10. Loss of Temporary loss of Authority should provide job the 1. NCC
Income of the income in the people who are affected in this 2. NGO
community community project.
Short technical trainings should
be arranged for
PAPs and their families.

Vitti Sthapati Brindo Ltd. Page 89


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

8.4: Major Risks and Assumptions

8.4.1 Risks
Major risks of the present project are the land acquisition and livelihood loss of the project
affected people and livelihood restoration of the project-affected person. Other risk is solid
waste and liquid waste management of the project area. So, this issue should be handled
carefully.

8.4.2 Assumptions
In many cases, people are unable to regain business or livelihoods due to the price hike of
land and business place and discontinuation of livelihoods may occur due to the project.
On the other hand, they have to spent illegal money for collecting compensation from NCC
office. Many PAPs, due to lack of up to date legal document are failed to collect money.
Therefore, this is very important to consider these factors very seriously so that the PARs
are getting enough space for restoration their livelihoods.

8.4.3 Significance of Risk Assumptions


In recent years, due to several projects, people were victimized and violently evicted
against land acquisition and for proper compensation. In addition, they straggle a lot to
start a new jobs. Therefore, this is very important to reinstate PAPs in previous socio
economic condition as well as to ensure their livelihoods.

Vitti Sthapati Brindo Ltd. Page 90


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Chapter 9: Overall Issues of


Significance and Management

Vitti Sthapati Brindo Ltd. Page 91


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

CHAPTER 9: OVERALL ISSUES OF


SIGNIFICANCE AND MANAGEMENT
9.1 Issues of Significance
In the following sections significant social and project related issues have been discussed
regarding restoration of Baburail canal.

Main issues of the significance are as follows:

• Land Acquisition
• Compensation at the rate of full replacement cost
• Livelihood restoration of project affected persons
• Mitigation of social Issues
• Ensure connectivity social, economic and communications
• Ensure environment quality and pollution free water of the canal

9.1.1 Issues to be addressed by the Project


 Land Acquisition
 Compensation at the rate of full replacement cost
 Livelihood restoration of project person
 Mitigation of social Issues

9.2.2 Issues that are project Scope


The main scope of work is to prepare a social management plan (SMP) and preparation
RAP.

9.2 Social Management Plan


A social management plan has been developed for mitigating social issues in the project
area. A time bound implementation schedule has been proposed in the following table.
The SMP has both resettlement and purely social issues. A separate RAP has also been
prepared.

9.2.1 Resettlement Action Plan


Total affected land is 3.5 km long and 15-30 m wide in different sections connecting
Shitalakkha River at the East and Dhaleswari River at the West. A resettlement action
plan has been developed and total resettlement budget is Tk. 130589837.

Vitti Sthapati Brindo Ltd. Page 92


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping, Beautification & Lighting Project

Table 19: Tentative SMP Implementation Schedule

Months 1 Up to
July,
2019
Serial Items 1 2 3 4 5 6 7 8 9 10 11 12
1 Socio Economic Survey
2 Preparation IEE,EIA,SMP
3 Joint Verification/Video Filming by NCC and LGED
office
4 Land Acquisition & Requisition
4.1 Serving Section-3,6,7 notice from NCC office
4.2 Starting of Payment of Compensation
5 Set UP CSR Unit of NCC
6 NGO/IA Recruitment
8 Information Campaign
9 Payment of Additional Grant
10 Raising Awareness
10.1 Health Awareness, drug addiction,STD, HIV/ AID etc
10.2 Awareness against social Degradation, human
traffcking, gender discrimination, wage discrimination,
child labour, begging, early marrige, dowry, smoking
etc
11 Skill Training
12.0 Monthly Monitoring Report
12.1 Final SMP Progress Report

Vitti Sthapati Brindo Ltd. Page 93


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

9.2.2 Livelihood Related


Among all affected persons, approximately half of the PARs lost their main occupations
due to this project.

9.2.3 Inclusion and Equity


In preparing SMP and RAP, inclusion of all sorts of people, community, PAPs and
stakeholders are given importance. Equity and justice has given priority.

9.2.4 Gender Minorities /Vulnerabilities


Bangladesh is a highly patriarchal society. For this fact, the men control over labor, choice
of marriage partner, income, assets and affairs of livelihood. There is a strong cultural
preference for males over females in the male dominated scenario of Bangladesh, which
exacerbates an imbalance society. From fathers to husbands to sons, women are
dependent on men throughout their lives. Moreover, gender studies focus on women. It
happens because the position of women in the society is unfavorable in every aspect.
Women are more vulnerable than men because of their lack of control over the means of
production, restricted mobility, limited facilities for education and jobs. It is not only poverty
that plays a hand in gender inequities but also the intricate connection of social and
cultural influence the practices. Gender inequities not only effects on girls and women but
also on boys and men.

9.2.4.1 Present Women Status in the Project Area

Project area of Baburail Canal is not different from this situation. During census and field
survey of the project area, no any female headed and handicapped people are identified
from the affected people. In the project area women of both Muslim and Hindu community
are living in a conservative society. A majority of women in the surrounding project area
(not exactly acquired area) are housewives from poor community people. Their
educational levels are comparatively low and so, access to technical skills education is
constrained by poverty and other mobility related issues. Most of the women live in their
husbands’ houses and are exclusively dependent on cash incomes generated by the
family from employment. Only a few families own Land and supplementary incomes from
agricultural activities are limited. Their knowledge and awareness on external issues such
as HIV/AIDS is quite remote. Their vulnerabilities are reasonably high in physical and
sexual abuse, domestic violence and other forms of insecurities.

9.2.4.2 Possible areas of Women Involvement

The following proposals are made to involve Women at various levels of the Project.
Women can work as managers during project implementation. The project can hire a local
NGO to implement the RAP. It is proposed that NGO must fulfill the following conditions:

Vitti Sthapati Brindo Ltd.


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

 The NGO must propose at least one women as part of the key personnel; the
proposed Women Key Person shall be available to work at site at least 50% of
duration as the contract.
 The NGO will depute a technical/ professional team to work at the site, which will
consist at last 30% of Women members. Junior support Personnel and
administrative staff will not have considered as technical/ Professional.
 Income generating program will be designed to ensure women a reliable income
by engaging in activities. Taking into account the availability of resources and the
type of enterprises that they are already engaged in.
 Capacity enhancing assistance will be provided for improving the access of
women to skills training for off-farm employment such as tailoring, weaving,
cutting, embroidery, handicaps’, hair cutting, beautification and processing of
locally produced products.
 Social awareness campaigns and training opportunities will be organized to
increase Women’s in regulation into social and economic mainstream.
 Project will strength Women’s community based and non-governmental
organizations by providing training and advisory supports once during construction
period.
 Prepare the skill development Plan for the women.
 Develop monitoring and evaluation system for the gender development activities.
 Provide support for getting loan from financial institutions.
 Preparing a periodical report and activities undertaken for the welfare of Women.

9.2.4.3 Gender Action Plan

The gender action plan will be mainstreaming some important issues from national to
grass root level. This action plan will be eliminating gender inequities. In the context of
present situation, the government as well as the civil society can play vital roles regarding
women development. Some of the following measures are:

 Offering high level education


 Increasing women employment
 Involving them in active politics and social activities
 Arranging social protection programs
 Generating awareness among parents
 Giving scholarships to the girls
 Spreading awareness against child abuse and violence
 Stopping sex identification and abortions
 Social welfare developments by politicians
 Promoting campaign through NGOs to eradicate Gender Inequality
 Increasing women's share of seats in National Parliament and local government
bodies
 Combat violence against children, adolescences and women
 Guarantee women's and girls’ property and inheritance rights
 Guarantee reproductive health and rights

Vitti Sthapati Brindo Ltd.


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

The overall objective of Gender Action Plan (GAP) can improve the wellbeing of women
who are living in the proposed project areas. The three specific objectives of GAP are
given below:

 To avoid adverse impacts on women around the project area.


 To facilitate economic benefits to women during project construction period.
 To support the processes of improving the socio-economic conditions of women.
The first objectives call for exploring the strategies and mechanisms for avoiding or
minimizing adverse effects and impacts of project constructions on the properties,
livelihoods of women and their families. Furthermore, it focuses on adopting appropriate
measures to avoid any harmful effects on women and girls during project construction
period such as insecurities and harassments from construction workers, disturbances to
routine life, and damages to their properties and livelihoods.

The second objective endeavors to identify and provide economic benefits to women and
their families during project construction period. Employment opportunities for women
would be limited in project construction work as such work is largely male-centered in
Bangladesh. In addition, the social cultural norms in Bangladesh may not prescribe
women engaging in construction work along with men in many cases. However, women of
poor families may opt for such employment in the construction work as the work
opportunities available. Employment opportunities for male members from the poor and
vulnerable families could also be provide. It will help to generate incomes by those
employees, which will indirectly benefit the female members of their families.
Opportunities for women to run small tea stalls or selling food parcels can also be
promoted.

The third objective focuses on networking with development agencies, other industrial and
commercial establishments in the area. It will persuade them to implement suitable
programs and activities that enhance the socio-economic conditions of women, girls and
their families. In brief, NCC will ensure following action during construction period for
women.

 Engage affected and vulnerable women in construction work if they are interested.
 Include 25% women as construction workers.
 Separate sheds for women workers by ensuring their privacy and security.
 Separate hygienic and safe toilet facilities inside the camp and construction sites.
 Provide working dress with helmet, gumboot for workers,
 Maintain same wage rate for man and woman.
 Provide healthy food facilities near working site with subsidized rate.
 Ensure crest for women worker with child near camp and working sites.
 Ensure first Aid facilities and mobile hospitals near working site in emergency
cases.
 Provide transport between working sites and camps.
 Not engage women labor at night
 Ensure safe drinking water.
 Build awareness about STD diseases, HIV/AIDS.
 Build awareness against child and women trafficking and drug abuse.
 Ensure payment through bank.

Vitti Sthapati Brindo Ltd.


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Vitti Sthapati Brindo Ltd.


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Table 20: Budget for Gender Action Plan

Serial Description No/Nos Days for Man Monthly Cost/ Total (Tk)
training month Unit Cost (Tk)

1 Campaign on Creating 4 1 100000 400000


Awareness about women’s
right and Leadership
Training
2 Campaign on Health related 4 1 100000 400000
issues like AIDS and STD

3 Campaign on WASH 3 1 150000 450000


4 Workshop on Property right 1 1 100000 100000

5 Workshop on Skill 2 1 150000 300000


development

6 Gender Specialist 1 12 100000 1200000

7 Environment and Health 1 12 100000 1200000


Specialist
8 Training Specialist 1 12 100000 1200000
9 Training for 200 women.

Group-A (Cutting and 50 90 1000000 3000000


Tailoring)

Group B (Embroidery and 50 90 1000000 3000000


Weaving)

Group C (Handicrafts) 50 90 1000000 3000000

Group D (Hair cutting and


beautification) 50 90 1000000 3000000

10 Bill board 4 100000 400000


11 Leaflet & poster, booklet 1000 100 100000
12 Campaign for Clean 4 1 100000 400000
Environment
Sub Total 23,550,000
5% Administrative cost 1177500
5% Incidental cost 1177500
20% Contingency 4710000
Total 30,615,000

9. 3 Ethnic Groups and Person with Disability


No indigenous people or person with disability was identified as project affected person.
Therefore, no need for Indigenous people plans.

Vitti Sthapati Brindo Ltd.


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

9.4 Stakeholders Engagement


Stakeholder engagement is the process by which an organization involves people who
may be affected by the decisions it makes or can influence the implementation of its
decisions. They may support or oppose the decisions, be influential in the organization or
within the community in which it operates, hold relevant official positions or be affected in
the long term.

Stakeholder engagement is a key part of corporate social responsibility (CSR) companies


engages their stakeholders in dialogue to find out what social and environmental issues
matter most to them about their performance in order to improve decision-making and
accountability. Engaging stakeholders is a requirement of the Global Reporting Initiative, a
network-based organization with sustainability reporting framework that is widely used
around the world.

Involving stakeholders in decision-making processes is not confined corporate social


responsibility (CSR) processes. It's a tool used by mature private and public sector
organizations, especially when they want to develop understanding and agree to solutions
on complex issues or issues of concern.

An underlying principle of stakeholder engagement is that stakeholders have the chance


to influence the decision-making process. This differentiates stakeholder engagement
from communications processes that seek to issue a message or influence groups to
agree with a decision that is already made.

"Stakeholder Engagement: A Road map to meaningful engagement" describes seven


core values for the practices of gaining meaningful participation of which perhaps the
three most critical are:

 Stakeholders should have a say in decisions about actions that could affect their
lives or essential environment for life.
 Stakeholder participation includes the promise that stakeholders’ contribution will
influence the decision
 Stakeholder participation seeks input from participants in designing how they
participate

The practitioners in stakeholder engagement are often businesses, non-governmental


Organization (NGOs), labor organizations, trade and industry organizations, governments,
and financial institutions.

As a part of stakeholder’s engagement, SMP and RAP has a proposal of engagement


NGO during implementing period and public consultation during feasibility stage and
PAPs will have to engage in construction and lump sum budget for social development of
community for future development and risk management of social issues.

Vitti Sthapati Brindo Ltd.


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

9.5 Transparency and Accountability


The success of project work depends on the ability of all affected parties to express their
concerns freely. That is why WB has high standards of stakeholder engagement—to
ensure that clients achieve the best possible development outcomes. Bank’s country
strategies and projects are based on dialogue with stakeholders, including civil society.
World Bank Group President, Jim Yong Kim, has committed to incorporate beneficiary
feedback in 100 percent of World Bank financed projects by 2018. Therefore, the ability to
help eliminate poverty and improve livelihoods would be severely compromised without
space for civil society to help shape development in their countries.

Environmental and social safeguard policies are designed to prevent and mitigate harm to
people and the environment because of Bank Group-supported operations. Those who
feel they have been negatively affected by WBG projects have access to robust and
independent grievance mechanisms and to bodies, such as the World Bank Inspection
Panel and the IFC Compliance Advisor/Ombudsman, able to hold WBG institutions to
account. Therefore, the ability to help eliminate poverty and improve livelihoods would be
severely compromised without space for civil society to help shape development in their
countries. When allegations of reprisal are brought to our attention, we work within the
scope of our mandate with appropriate parties to try to address them. Where links
between reprisals and WBG-financed projects can be established, Bank has taken action
as documented by past cases and will continue to do so.

World Bank has strong policies and mechanisms that address many concerns raised by
human rights advocacy groups and civil society, and Bank is open to dialogue on
improvements and values the perspectives these groups bring. Bank will continue to work
with them towards our shared goal of strengthening protections for people in the countries
in where Bank work. Regarding the above context, SMP and RAP have proposal of
raising participatory approach for project-affected person and concerned stakeholders.

The objectives of the Accountability Mechanism will be to provide an independent and


effective forum for people adversely affected by WB-assisted projects to voice their
concerns and seek solutions to their problems, and to request compliance review of the
alleged noncompliance by WB with its operational policies and procedures that may have
caused, or is likely to cause, them direct and material harm. As a WB Accountability
Mechanism (AM), project transparency, an independent forum for people adversely
affected by WB assisted projects where they can voice their concerns and seek solutions
to their problems and request a review of alleged noncompliance by WB with its
operational policies and procedures. They are:

 Two or more adversely affected people


 AP authorize representative
 NGO – Board members
 Write a letter/ email/ fax in any official or national language to
 Complaint Receiving Officer at WB HQ and Resident Mission office

Vitti Sthapati Brindo Ltd.


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Any time during project’s life one can complain but no more than 2 years after project
closing date

The World Bank Group has several accountability mechanisms designed to enable civil
society and people to voice their concerns regarding projects supported by the Bank.

 A cornerstone of our work on investment projects is helping to ensure strong


protections for the world’s poorest and most vulnerable people and for the
environment. The World Bank’s current policies – often called “safeguards” –
require borrowing governments to address certain environmental and social risks
in order to receive Bank funding for development projects.
 The World Bank is in the process of reviewing, updating and strengthening its
environmental and social safeguards. The proposed framework emphasizes the
Bank’s commitment to core values, including respect for individual dignity,
transparency, accountability, consultation, participation, and non-discrimination.
 The World Bank has also just introduced a new Grievance Redress Service
(GRS), to address complaints related to World Bank projects. Through this service,
individuals and communities that may be directly and adversely affected by a
World Bank-financed project can bring their concerns directly to the attention of
World Bank management. The GRS ensures that complaints are being promptly
reviewed and addressed by the responsible units in the World Bank. The objective
is to make the World Bank more accessible for project-affected communities and
to help ensure faster and better resolution of project-related complaints.
 The Inspection Panel (IPN) is the Bank’s independent accountability mechanism
for people and communities who believe that they have been, or are likely to be
adversely affected by a World Bank-funded project.
 However, it is suggested for setting up an ‘independent monitoring panel’ within
the project. This proposed panel will make mission report every 4 months in the
1st year and subsequently twice (1 in every 6 months) a year for the remaining
period of the project’s implementation headed by an independent monitoring
consultant with support staff. Project authority will take necessary action regarding
this.
 Meaningful Public Consultation and Disclosure Requirements is also a part of
accountability. The Bank reaffirms its recognition and endorsement of the
fundamental importance of transparency and accountability to the development
process. Accordingly, it is Bank’s policy to be open about its activities and to
welcome and seek out opportunities to explain its work to the widest possible
audience.
 The RPF, EMF and other reports will be disclosed in country (on NCC website and
in hard copy in locally accessible locations in the project area CC, UP, Pouroshava
and Upazila including NCC offices at the existing terminals) and sent to WB Info
Shop.
 The IPN was created in 1993 by the World Bank Board of Executive Directors, as
a three-member body, in an important step to increase the transparency and
accountability in Bank operations. The IPN provides independent investigation,
subject to Board approval, to determine whether harm has occurred from
noncompliance with Bank Policy in connection with the implementation of a project

Vitti Sthapati Brindo Ltd.


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

financed by the World Bank. The IPN is the first body of its kind to give voice to
private citizens in an international development context.

However, as required, an independent monitory panel was asked for the project. In this
panel, there will be a chief consultant, two assistant of the consultant and one NGO
worker. The team will be working as long as the work is going on. At first year, they will
make report every four months. From second year, they will be making reports every six
months. This will be continued until the end of the project.

An approximate budget for the first two years is given below:

Table 21: Approximate Budget for the Head Consultant (TK)

Budget for the Head Consultant:

st
1 Year- (3 times Monitoring in a year):
Description Unit Visit Unit Cost in Total Cost in
Taka Taka
Independent Remuneration 1 3 200,000 600,000
Consultant for one week
(for one week) Transport 1 3 250,000 750,000
Conveyance and
Logistic
1st Year total 1,350,000

2nd Year – Till the project ends (2 times monitoring per Year):

Description Unit Visit Unit Cost in Total Cost in


Taka Taka
Independent Remuneration 1 2 220,000 440,000
Consultant for one week
(for one week) Travel and Local 1 2 270,000 540,000
Hospitalities
nd
Per Year (From 2 Year) 980,000

Table 22: Approximate Budget for the Assistant Consultant and NGO Worker (TK)

Budget for the Assistant of Consultant:


st
1 Year (3 times Monitoring):
Description Unit Visit Unit Cost in Total Cost in
Taka Taka
Assistant of the Remuneration 2 3 75,000 450,000
consultant for one week
(for one week) Transport 2 3 25,000 150,000
Conveyance and
Logistic
1st Year total 600,000
2nd Year – Till the project ends (2 times monitoring per Year):
Description Unit Visit Unit Cost in Total Cost in
Taka Taka

Vitti Sthapati Brindo Ltd.


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Assistant of the
Remuneration 2 2 90,000 360,000
consultant for one week
(for one week) Transport 2 2 40,000 160,000
Conveyance and
Logistic
nd
Per Year (From 2 Year) 520,000
Budget for the NGO worker:
st
1 Year (3 times Monitoring):
Description Unit Visit Unit Cost in Total Cost in
Taka Taka
NGO worker Remuneration 1 3 50,000 150,000
(for one week) for one week
Transport 1 3 20,000 60,000
Conveyance and
Logistic
1st Year total 210,000
2nd Year – Till the project ends (2 times per Year):
Description Unit Visit Unit Cost in Total Cost in
Taka Taka
NGO worker Remuneration 1 2 60,000 120,000
(for one week) for one week
Transport 1 2 30,000 60,000
Conveyance and
Logistic
nd
Per Year (From 2 Year) 180,000
Grand Total (For the First Two Years) Tk. 38, 40
In Words: Thirty Eight Lacks Forty Thousand Only
9.7 Capacity Support and Capacity Building
Capacity support program will be for affected person and project community. Capacity
building support for NCC official for mitigating social resettlement issues, construction etc.
The training of NCC will be for strengthening and institution building. It is proposed here,
25 officials NCC, 350 (one family member of project affected person) and 200 from project
community below poverty line will award capacity building training. PAPs and community
training will be mainly for technical and social issues. NCC will also arrange short training
and workshop for social resettlement issues and investment potential.

Table 23: Budget for Capacity Building

SI Description No Days for Man Monthly Total


Training month Costt (Tk)

1 Capacity Building Specialist 1 12 100000 1200000


2 Training Specialist 1 12 1200000
3 Capacity Building training (NCC 575 15 10000 5750000
official 25 +PAPs Family Member- 350,
and 200 from community household
member below poverty regarding
various issues)
Total 8150000

Vitti Sthapati Brindo Ltd.


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Chapter 10: Grievance Redress


Mechanism

Vitti Sthapati Brindo Ltd.


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

CHAPTER 10: GRIEVANCE REDRESS


MECHANISM
10.1 Grievance Redress Mechanism
The objective of a grievance procedure is to ensure all comments and complaints from
any project stakeholder, including local/regional authorities, residents of nearby residential
areas, NCC employees and other interested parties, are acknowledged and responded to
within a reasonable timeframe.

NCC will accept all comments and complaints associated with the project. The comments
and complaints will be summarized and listed in a Complaints/Comments Log Book. Any
person or organization may send comments and/or complaints in person or via post, email
or facsimile using the contact information.

All comments and complaints will be responded to either verbally or in writing, in


accordance with preferred method of communication specified by the complaint in the
Comments and Complaints Form. All grievances will be registered and acknowledged
within 5 days and responded to within 20 working days. The PAPs/community can appeal
the decision of the GRC in the appropriate court of law, which mainly depends on the
nature of the grievance. NCC will keep a grievance log and report on grievance
management, as part of half-yearly project progress reports, available at NCC website
and NGO office.

The redress committee will be formed with at least seven members. The committee will
solve the grievances, which have been raised by the PAPs and Project community. The
members of the committee are Mayor of NCC or Representative of NCC (1), NGO
representative (1), LGED representative (1), Affected persons’ representatives (2),
Teacher from local educational institute (1), Representative of civil society (1), and
Female Word Councilor (1). From the affected persons’ representatives, one will be a
male and the other one be female. The Grievance Redress committee (GRC) headed by
an officer of Resettlement Unit (RU)/Social Development Unit of project area equivalent to
Assistant Director in the NCC.

The committee will receive the application from the affected stakeholders about their
grievances and they will solve the grievances every month other than disputes relating to
ownership rights under the court of law. The GRC will review grievances involving all
resettlement benefits, relocation, other assistance and social issues.

Vitti Sthapati Brindo Ltd.


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Figure 47: GRC Organogram

NCC

NGO

GRC

Mayor/ Representative Head of Project/


Representative Representative Representative Female Word
Representative of Civil Society Representative
from LA (1) from NGO (1) from PARs (2) Councilor (1)
of NCC (1) (1) of LGED (1)

Male (1) Female (1)

The GRM will directly focus on and seek to resolve complaints (and requests for
information or clarification) that pertain to outputs, activities and processes undertaken by
the Project, i.e., those which (i) are described in the Project Implementation Manual; (ii)
are funded through the Project (including counterpart funds); and (iii) are carried out by
staff or consultants of the organization, or by their partners and sub-contractors, directly or
indirectly supporting the project. It is envisaged that such cases would fall under (but are
not limited to) the following categories:

 request for information, comment or suggestion, e.g., request for clarification as to


the delay in reimbursing expenses of participants in a given training event;
 violation of rights or non-performance of obligations, e.g., complaint by consultant
or firm whose contract is suspended as a result of presumed poor performance or
non-delivery of agreed-upon outputs;
 grievances or offenses involving a violation of law, e.g., allegations of corruption;
and
 complaints against project staff, members of project committees, consultants, and
subcontractors involved in project implementation

GRM will be implemented in two phases: 1) Phase 1 to support safeguards


implementation, 2) Phase two of GRM will cover all components and overall project
implementation. A formal grievance redress process for phase two will be outlined in the

Vitti Sthapati Brindo Ltd.


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

project‘s operation manual and a protocol will be set up and distributed to project staff and
implementers. The project level protocol will build on experience of the initial GRM
protocol, which supports implementation of the safeguards explained below.

Phase One –GRM under Safeguard Issues

 Receive compliant through the toll free number.


 Register Case no. by issuing a complaint number to the complainant; Date and
channel of receipt, name of complainant, nature of the complaint, gender, father or
husband’s name and complete address.
 Nature of complaint should be clearly addressed (e.g., loss of land/property or
entitlements)
 Forward the complaint to the concerned person immediately via SMS.
 Within five days complain will be examined, resolved and reported.
 If not resolved within five days, SMS alert is sent out by the system to senior
management.
 Complaint will be investigated and resolved within seven days from the date of
receiving the complaint.
 Confirmation will be received from complainant on grievance redress and ticket
number closed.
 Monthly reports will be generated from the system that provides feedback to
improve the process of implementation of RPE.

Phase Two – Establishment of implementation Arrangements for setting up project level


GRM.

 Experience from the phase 1 of GRM implemented to support social and


environment safeguards will be used to extend the protocol and inform the project
wide GRM.
 PIU needs to identify groups of users that are likely to use the GRM and assess
the resources- human, financial and technological.
 PIU needs to develop standard operating procedure and flowcharts to define how
GRS involves within the project’s operating structures.
 The whole procedure should be monitored and reported on time.
 The whole process will be overseen by NCC Mayor.

The representatives of the affected areas will do face to face communication with the
affected people of the community. It will also help the affected females to talk about their
hurdles with the female representative from the community. The whole procedure should
be kept confidential between the representatives from the community and the affected
people. It is noted that the GRC will provide claimants with the assurance that grievances
will be resolved satisfactorily without any cost. GRC will also assist the transfer of
resettlement entitlements.

Grievance procedure will not replace existing legal process available to the affected
people and will not infringe on claimants' right to access existing legal procedures. It will
seek to resolve issues promptly and fairly to expedite the receipt of entitlements and

Vitti Sthapati Brindo Ltd.


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

assistance will be provided without expensive restoration cost and time consuming legal
actions.

Some of the monitoring indicators for the GRC are given below:

Table 24: Monitoring Indicators for the GRC

SL. Monitoring R & R Action Grievances redress


No. indicators Indicators
1 Physical - No. of PAHs paid compensation for - No. of grievances registered
progress acquisition of private properties; at GRC;
- No. of PAHs provided R & R - No. of project level
assistance; grievances meeting;
- No. of Women PAPs received - Location of GRC meetings;
livelihood training ;
2 Income - Reinvestment of compensation by the - No. of PAPs expressing
Restoration PAPs; satisfaction at GRC resolution
- No. of PAPs with new employment in firms of judgments given,
opportunities after receiving training timeliness, impartiality, etc.
support;
- No. of Women groups formed for
income generation;
3 Financial - Compensation paid for houses - No. of court cases registered
Progress including assistance towards registration
charges and taxes;
- Compensation paid for acquiring other
assets from private owner;
- Expenditure on non-qualified impacts
4 Implementati - No. of Women PAPs got employment
on of gender training’
development - No. of Women developed;
plan - No. of Women PAPs provided jobs in
the project activities;
- No. of Women PAPs received loan for
sell employment
- No. of Women PAPs participated in
consultations by NGO.

Vitti Sthapati Brindo Ltd.


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Chapter 11: Monitoring and


Evaluation

Vitti Sthapati Brindo Ltd.


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

CHAPTER 11: MONITORING AND EVALUATION


11.1 Introduction
Monitoring can be defined as the ongoing process by which stakeholders obtain regular
feedback on the progress being made towards achieving their goals and objectives. On
the other hand, Evaluation is a rigorous and independent assessment of either completed
or ongoing activities to determine the extent to which they are achieving stated objectives
and contributing to decision-making. The overall objective of a monitoring and evaluation
(ME) programme is to monitor, assess and report on the effectiveness of the
implementation of project activities resettlement, and particularly the application of
mitigation measures. This includes land acquisition, payment of compensation, and
physical progress with land resettlement and rehabilitation activities, effectiveness of
consultation and participation, and the sustainability of livelihood restoration efforts.

11.2 Monitoring and Evaluation Framework

11.2.1 Sample Design and Monitor


Social Management, Resettlement and Monitoring Framework for Restoration of
Shitalakkha-Dhaleswari River Connecting Baburail Canal Beautification project.

Table 25: Monitoring Framework for Proposed Project

Design Performance Data Sources Reporting


Targets/Indicators Mechanisms Assumptions and Risks
Summary
1.Impact By 2019: For all indicators for social Assumption:
Land Acquisition, 1.All payments of and resettlement issues: Donor’s commitment to
Compensation Compensation Annual reports of monthly, improving the payment
and other Social including additional quarterly, and annual y mechanism in NCC
Issues grants is to be reporting system to be ensured office.
completed for NGO and Resettlement Unit
2. Awareness of NCC Risks:
Program of Social 1. Starting timely
issues implementation RAP
and payment of NCC
office.
2. Some PAPs will not
get money due to
malpractices from NCC
offices
3. Increase social crimes
and increase STD
disease and HIV/AIDs

Vitti Sthapati Brindo Ltd.


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Outcome By end of project For all indicators: Assumption:


Improved access (2019) % increase Annual reports of Annual Capacity building
to efficient reports of monthly, quarterly, activities for NCC
manpower and Number of and annually reporting system Risks:
activities NCC households will be to be ensured for NGO and 1. Construction of
compensated and Resettlement Unit of NCC ancillary
rehabilitated (xx% of facilities for
new beneficiaries NCC
are from poor 2. Land loss not
households; xx% of regained
female-headed 3. Livelihood loss
households not reinstated
in service area
benefitted, their
income and social
status will be
uplifted)
Activities with Milestones Inputs

Output 1: Resettlement rehabilitation WB: $xxx million


1. NGO recruitment by ___ (Date) 1. Consulting services (xxx PMs): $xxx million
2. Mobilize design and supervision consultant 2. Civil works: $xxx million
by ___ 3. Equipment: $xxx million
3. Award all contracts by ___ 4. Training: $xxx million
4. Complete construction, repair and 5. Contingencies: $xxx million
rehabilitation by __
5. Complete all construction and commission Government (if any): $xxx million
all facilities by ___
6. Personnel (xxx PMs): $xxx million
6. Payment of land in NCC office by___
7. Transport and logistics: $xxx million
7. Payment additional grant of NCC
by_______ 8. Operating expenses: $xxx million

11.2.2 Measurable Indicators


There are some monitoring indicators are presented here. NGO will use suitable
monitoring indicators for reporting, monthly, quarterly, annually and post implementation
evaluation report.

Vitti Sthapati Brindo Ltd.


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Table 26: Proposed Monitoring Indicators

Monitoring Indicators
• Payment of compensation and entitlements before replacement
• Time taken for land acquisition
• Number of grievances registered and resolved
• Number of court cases
• Land Purchase amount
• Income patterns
• Land holding status
• Income from land
• Changes in occupations
• Housing status (area, floor, walls, roof, etc.)
• Length of rural roads (connectivity to nearest land ports)
• Journey time
• No. of training programs conducted
• No. of personnel trained
• Trainees’ understanding of the training content
• Achievement of learning objectives
• Adherence to contract conditions and standards (housing,
sanitation, crèches, use of local labor, equal wages to men and
women, avoidance of child labor, etc.)
• Absence of inconvenience and nuisance during implementation
• Adherence to SMP/RAP provisions/ guidelines during sub-project
preparation and implementation
• No Accidents
• No Women trafficking

Tables 27 indicates the Potential Monitoring Indicators related to this project.

Table 27: Potential Monitoring Indicators

Monitoring Monitoring Indicators


Issues
1. Budget and • Have all resettlement staff been appointed and mobilized for field
Timeframe and office work on schedule?
• Has capacity building and training activities been completed on
schedule?
• Are resettlement implementation activities being done as per agreed
implementation plan?
• Are funds for resettlement being allocated to resettlement agencies
on time?
• Have resettlement offices received the allocated funds?
• Have funds been disbursed according to Entitlement Matrix of RP.
• Has all the land made encumbrance free and handed over to the
contractor in time for project implementation?

Vitti Sthapati Brindo Ltd.


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Monitoring Monitoring Indicators


Issues
2. Delivery of DP • Have all APs received entitlements according to quantity and
Entitlements categories of loss set out in the entitlement matrix?
• How many affected households have land titles?
• How many affected households are relocated and built their new
structures at new location?
• Are income and livelihood restoration program activities being
implemented as planned?
• Have affected businesses received entitled benefits?
• Have the APs losing their eroded land received proper
compensation?
• Have the squatters, encroachers been displaced due to the project,
been compensated?
• Have the community structures been compensated and rebuilt at
new site?
3. Consultation, • Have resettlement information brochures/leaflets been prepared and
Grievances and distributed?
Special • Have consultations taken place as scheduled including meetings,
Issues groups, community activities?
• Have any DP used the grievance redress procedures?
• What grievances were raised?
• What were the outcomes?
Monitoring Monitoring Indicators
Issues
• Have grievances and resolutions been documented?
• Have any cases been taken to court?
• Have conflicts been resolved?
4. Benefit • What changes have occurred in patterns of occupation compared to
Monitoring the pre-project situation?
• What changes have occurred in income and expenditure patterns
compared to pre-project situation?
• Have APs income kept pace with these changes?
• What changes have occurred for vulnerable groups?

11.3 Impact Evaluation


Monitoring & Evaluation is an important task for measuring the periodic progress of
activities under resettlement program. Impact evaluation is also an important task. This
helps to identify the constraints and bottlenecks in the progress as well as future impacts
to determine remedial measures. Implementing Social management and resettlement
being a complex nature of task, it needs development and establishment of Computerized
Management Information System (CMIS). The main objective of the CMIS is to provide
the management of the project with an efficient tool for better planning and control of
different project tasks. Therefore, NCC will develop a computerized management
information system in monitoring social and resettlement work. Software will be developed
for CMIS. The authority will appoint experienced system analyst, programmer for this. All
sorts of social issues and resettlement information, land acquisition, Entitlement Person
(EP) file including all information and entitlements, pre and post-acquisition and requisition
information of resettlement will be provided for CMIS. Socio economic background of the
concerned affected persons and project community will be recorded for ready reference.
The authority will arrange necessary step in this connection for proper and successful
resettlement and social development. The major input in to the system will be:

Vitti Sthapati Brindo Ltd.


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

 Affected household data


 Land acquisition data
 Data on losses
 Resettlement entitlement and delivery data
 Resettlement monitoring and evaluation data
 Other management related data

Monitoring and evaluation (M&E) are critical for ensuring effective implementation of the
RAP and achievement of the set targets. Resettlement monitoring is a continuous process
of data collection, dialogue with the various stakeholders, analysis & reporting and
feedback to management to enable timely adjustment of implementation procedures and
entitlements, if required.

The monitoring will commence with the commencement of the Project implementation and
shall continue throughout the implementation of the Project. At the implementation period,
field officials will design a format for monthly resettlement/SMP monitoring and data
collection. NCC will prepare a post-resettlement/social evaluation report at the end of the
Project activity. The report should provide evidence whether adverse effects of the project
have been mitigated adequately or at least pre-project standard of living and income have
been restored because of the RAP/SMP implementation.

Some monitoring indicators are given below. This might help as proper guideline for
implementation and monitoring of RAP/SMP. In addition to that, NCC will appoint
Monitoring and Evaluation Specialist for further developing indicators and format for
further needs or may reshuffle from the changed needs for efficient implementation of
RAP.

The GRC, implementing agency or NGO, NCC RU/Social Development Unit and
Accounts section will develop standard reporting formats and reports will be submitted on
a monthly basis highlighting constraints and suggestion for implementation of SMP/RAP.
RU/ Social Development Unit will arrange monthly review meeting with assistance of
Implementing Agency NGO for identifying the problems and proper suggestions will be
given to the implementing NGO and minutes will be sent to the concerned persons and
higher authority. For smooth implementation of the affected person’s problem, project
community GRC will have a direct contact with the field.

The NGO or implementing agency, executing the program will monitor PAPs participation
in the vocational training and other economic rehabilitation program. Records will be
maintained about their attendance and the payments. Post resettlement socio economic
survey for evaluation will be carried out based on a TOR to be developed by a
resettlement/ social development expert engaged by NCC .The survey document will be
the final project document. The implementing NGO will develop Computerized
Management Monitoring System and will supply to the NCC and implementing NGO and
NCC will preserve the data.

Implementation of the RAP/SMP will be monitored regularly. A Computerized


Management Information System (CMIS) will be established to provide integrity of data
records, better planning and decision-making, improved resettlement services, problem

Vitti Sthapati Brindo Ltd.


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

detection on resettlement issues, and project expenses and implementation within limits
and schedules. The CMIS will provide household files for PAPs containing losses and
entitlement, scheduled monitoring reports, progress reports, and financial reports. The
Project Management Office (PMO) i.e. RU will establish a quarterly monitoring system
involving staff of the NGO staff. The PMO will prepare progress reports on all aspects of
land acquisition and resettlement activities. The report contains progress made in RAP
implementation with particular attention to compliance with the principles and matrix set
out in the plan. (NCC will hire Independent auditors acceptable to World Bank (WB) to
carry out external monitoring of the resettlement operations within two months of loan
effective date. The External monitor’s report will be submitted simultaneously to the NCC
and WB regularly. The monitoring consultant will be selected within three months of loan
approval. Monitoring will be carried out every year during project implementation.

For efficient implementation and management of the RAP/SMP, some review work is
needed. This will be internal and external. The authority will produce monthly and
quarterly reports for monitoring the progress. NCC will engage efficient consultant from
outside for total review of the project after the implementation period. At the same time,
WB and other stakeholders may arrange separate study to monitor the implementation of
RAP/SMP. NCC will carry out a midterm internal evaluation for the affected person at the
implementation period. Following formats are proposed to use the progress monitoring. In
addition to following formats internal Monitoring Specialist, Resettlement Specialist may
develop other formats or may change following formats if justified.

11.3.1 Resettlement Monitoring and Social Evaluation Forms


Table 28 shows the proposed Monthly Progress Report Format for Social/Resettlement
Monitoring of the project.

Table 28: Monthly Progress Report Format for Social/Resettlement Monitoring

Reporting Month: …………………


Sl. Component Progress
No. Unit Completed Cumulative During Status &
Completed
Total % Achievement Reporting Remarks
Month
1. Resettlement Preparation:
1.1 Identification of PAPs No.
1.2 Group Meeting with PAPs, No.
1.3 Distribution of Compensation for
Tk.
Structures
1.4 Compensation for crop/tree Tk.
2. Payment of Compensation
2.1 Land (agriculture/homestead) Tk.
2.2 Compensation for Structures Tk.
2.3 Compensation for Crop/tree Tk.
3. Relocation and Income Restoration Activities
3.1 Relocation of Households No.
3.2 Payment of Transfer Grant Tk.

Vitti Sthapati Brindo Ltd.


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

3.3 Income Restoration Grant Tk.


Social Issues
Accident
Awareness meeting HIV/AIDS
Capacity Building Training
Awareness meeting child and
women Trafficking
Awareness meeting Gender
Issue
Awareness meeting Drug
Addiction

Public consultation is a very important aspect for monitoring purpose and it is a


continuous process. Resettlement Unit (RU)/ Social Development Unit of NCC will use
this format for reporting public consultation in their monthly and quarterly progress report.
NGO or implementing agency will submit it to the RU/Social Development Unit and to the
WB.

11.4 Computerized Management Information System (CMIS)


Monitoring and Evaluation is a huge task for measuring the intermittent advancement of
activities under resettlement program. Impact evaluation is also an imperative task. This
distinguishes the constraints and bottlenecks in the development and future impacts to
decide and modify remedial measures. Actualizing Social management and resettlement
being a complex characteristic of the task, it needs improvement and foundation of
Computerized Management Information System (CMIS). The prime concern of the CMIS
is to give the administration a project with an effective tool for better arranging and
controlling of different tasks assigned.

In this way, NCC will build up a computerized information system in checking social and
resettlement work. Software will be developed for CMIS. The relevant authority will
designate experienced system expert or analyst and a programmer for this. A wide range
of social issues and resettlement data, acquisition of land, entitlement person (EP)
document including all data and designations, pre and post-obtaining and requisition data
of resettlement will be accommodated in CMIS. Financial background of the concerned
victims and targeted project community will be recorded. Moreover, for the implementation
of an automated Computerized Management Information System (CMIS) for the
accomplishment of stated task and data record, a budget will be needed. The budget draft
would require the following issues for implementing a Computerized Management
Information System CMIS:

1. Purchasing equipment:
_Computers
_A central Server (Network Hub)
_Printers Furniture
2. Transportation to the office
3. Configuring the network
4. Software development

Vitti Sthapati Brindo Ltd.


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

5. Appointing of experienced system analyst

Figure 48: Proposed CMIS model

Source: Microsoft XP Network Support

11.4.1 Budget Plan for CMIS


The budget plan for CMIS is given below.

Table 29: Budget for CMIS

No Description Unit Quantity Rate (Tk.) Amount (Tk.)

1 PC (Full set desktop computer); Dell each 4 52000 208000


OptiPlex 3040 MT 6th Gen i5-6500 or
equivalent
2 Computer Server; Model: Dell Power Edge each 1 525000 525000
R720 E5-2650 2.6GHz Enterprise or
equivalent
3 Printer (Centrally shared); Model: HP Color each 1 35000 35000
LaserJet Pro MFP M177fw or equivalent
4 Furniture and decoration (including all each 4 tables, 8 90000 90000
necessary tables, chairs, shelves etc.) chairs, 2
shelves

5 Transportation Cost - - 20000 20000

6 Network configuration each 1 10000 10000

Vitti Sthapati Brindo Ltd.


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

7 Software Development each 1 100000 100000

8 Appointment of experienced system 1 person 24 months 40000 40000


analyst
9 Data manager 4 person 24 months 25000 240000

10 Maintenance cost each 24 months 15000 360000

11 Internet Line each 24 months 2000 48000

Sub total 1676000

5% Administrative cost 83800

5% Incidental cost 83800

20% Contingency 335200

Total 2178800

11.3 Monitoring and Evaluation Budget


Table 30 shows the budget needed for monitoring and Evaluation of the project.

Table 30: Proposed Budget for Monitoring and Evaluation

Serial Description No Man month Monthly cost (Tk) Total (Tk)

1 M & E specialist 1 24 100000 2400000


2 Baseline Survey 1 1500000
3 Post Project Evaluation 1 1500000
Total 5400000

Vitti Sthapati Brindo Ltd.


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Chapter 12: Budget

Vitti Sthapati Brindo Ltd.


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

CHAPTER 12: BUDGET


12.1 Budgetary Requirements for Social Management
Following budget has been proposed for the social action plan. Budget has been prepared
on the basis of Census, socio economic survey and the basis of wide range of pubic
consultation among the stakeholders. As there is separate resettlement plan (RP), this
cost has been excluded from the social management plan.

12.2 Overall Social Management Budget


Table 31. Budget for Social Mitigation

Serial Item Qty. Unit Cost (TK) Total (TK)


1 Awareness Building (arranging 10 10 x 100000 1000000
workshop), social issues, road
accidents etc.
2 Bill Board 10 10 x 200000 2000000
3 Poster, Booklet, Brochure for 5000 5000 x 50 lump 250000
resettlement and social issues sum
4 NGO lump sum 1500000
5 CSR activities on the basis of 20000000
participatory planning with
affected community, both affected
and non-affected specially for
poor and vulnerable and common
people (lump sum)
Subtotal 24750000
6 5% administrative cost of subtotal 1237500

7 5% Incidental cost of subtotal 1237500

8 Contingency 20% Subtotal 4950000


A. Sub-Total 32175000

B Sub Total Monitoring and 5400000


Evaluation Budget
C Sub Total Capacity Building 8150000
Budget
D Budget for CMIS 2178800

Grand Total 47903800

The total budget for social mitigation of the project is 47.90 Million taka only.

Vitti Sthapati Brindo Ltd.


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Annexure

Vitti Sthapati Brindo Ltd.


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping, Beautification & Lighting Project

ANNEX-A: DATA TABLES_ SOCIO-ECONOMIC PROFILE OF THE


RESPONDENTS
Table 101: Religion of the Respondent.
North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad

Islam 83.4 95.3 90.6 88 96.9 78.2 90.6 87.9 89.9 89.3
Hindu 16.6 4.7 9.4 12 3.1 21.8 9.4 12.1 10.1 10.7
% 100 100 100 100 100 100 100 100 100 100
Total
N= 193 191 192 192 228 156 106 140 138 384

Table 102: Race of the Respondent

North or South side of


Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad

Bengali 100 99.5 100 99.5 99.6 100 99.1 100 100 99.7
Ethnic/ Adivasi 0.5 0.5 0.4 0.9 0.3
% 100 100 100 100 100 100 100 100 100 100
Total
N= 193 191 192 192 228 156 106 140 138 384

Vitti Sthapati Brindo Ltd. Page 122


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping, Beautification & Lighting Project

Table 103: Ownership of the household


North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad

Live at own land 31.6 50.3 48.4 33.3 39.9 42.3 64.2 37.9 26.1 40.9
Live on rent 44.6 49.7 38.5 55.7 43.4 52.6 33 50.7 54.3 47.1
House built on Govt. land 23.8 13 10.9 16.7 5.1 2.8 11.4 19.6 12
% 100 100 100 100 100 100 100 100 100 100
Total
N= 193 191 192 192 228 156 106 140 138 384

Table 104: Type of House Construction


North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad

Brick and cement (all) 39.9 50.8 49.5 41.1 39 54.5 72.6 39.3 30.4 45.3
Brick and cement (floor/partial) 41.5 35.6 37.5 39.6 43 32.1 22.6 39.3 50 38.5
Bamboo/Tin/ Earthen house – well
built 8.8 13.1 7.8 14.1 12.7 8.3 4.7 13.6 13 10.9
Bamboo/Tin/ Earthen house –
weakly built 7.8 0.5 3.1 5.2 5.3 2.6 5.7 5.8 4.2
Shanty/ Jhupri 2.1 2.1 2.6 2.1 0.7 1
% 100 100 100 100 100 100 100 100 100 100
Total
N= 193 191 192 192 228 156 106 140 138 384

Vitti Sthapati Brindo Ltd. Page 123


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping, Beautification & Lighting Project

Table 105: Area of floor


North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad

Up to 150 sq.ft. 20.7 15.2 17.7 18.2 10.1 29.5 1.9 15.7 32.6 18
151-300 sq.ft. 33.2 23 26.6 29.7 29.8 25.6 1.9 42.9 33.3 28.1
301-500 sq.ft. 27.5 22.5 28.6 21.4 29.8 17.9 26.4 25.7 23.2 25
501-750 sq.ft. 9.3 16.8 14.1 12 15.4 9.6 22.6 11.4 7.2 13
751-1000 sq.ft. 4.1 9.9 4.7 9.4 6.6 7.7 16 3.6 3.6 7
1000+ sq.ft. 5.2 12.6 8.3 9.4 8.3 9.6 31.1 0.7 8.9
% 100 100 100 100 100 100 100 100 100 100
Total N= 193 191 192 192 228 156 106 140 138 384
Avg. 380 524 435 468 462 436 853 327 269 451

Table 106: Av. Monthly Expense


North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad
Up to Tk.10000 33.2 21.5 23.4 31.3 25 30.8 76.1 27.3
Tk.10001-15000 37.8 26.7 32.8 31.8 30.7 34.6 85 3.6 32.3
Tk.15001-20000 16.6 20.9 20.8 16.7 22.4 13.5 21.7 15 20.3 18.8
Tk.20001-25000 4.1 12.6 7.3 9.4 9.2 7.1 30.2 8.3
Tk.25000+ 8.3 18.3 15.6 10.9 12.7 14.1 48.1 13.3
% 100 100 100 100 100 100 100 100 100 100
Total
N= 193 191 192 192 228 156 106 140 138 384

Vitti Sthapati Brindo Ltd. Page 124


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping, Beautification & Lighting Project

Avg. 15380 19382 17953 16788 17708 16878 29465 14400 11094 17371
Table 107: Av. Monthly Income
North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad
Upto Tk.10000 14.5 12.6 9.4 17.7 17.5 7.7 37.7 13.5
Tk.10001-15000 34.2 22.5 32.3 24.5 28.1 28.8 43.6 34.8 28.4
Tk.15001-20000 22.8 22.5 22.4 22.9 21.5 24.4 1.9 40 21 22.7
Tk.20001-25000 10.9 11 10.9 10.9 11.4 10.3 25.5 5.7 5.1 10.9
Tk.25000+ 17.6 31.4 25 24 21.5 28.8 72.6 10.7 1.4 24.5
% 100 100 100 100 100 100 100 100 100 100
Total N= 193 191 192 192 228 156 106 140 138 384
Avg. 20540 24194 22427 22288 20766 24683 38844 18544 13562 22357

Table 108: HH savings at present (all sources)


North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad
None 50.3 59.7 58.3 51.6 58.3 50 52.8 53.6 58 54.9
Upto Tk.3000 9.8 7.3 5.7 11.5 10.1 6.4 1.9 10 12.3 8.6
Tk.3001-15000 17.6 5.8 9.9 13.5 11 12.8 15.1 8.6 12.3 11.7
Tk.15001-50000 10.9 3.7 8.9 5.7 3.1 13.5 2.8 9.3 8.7 7.3
Tk.50001-100000 5.2 3.1 5.2 3.1 3.5 5.1 2.8 7.1 2.2 4.2
Tk.100000+ 5.7 7.9 5.2 8.3 3.5 11.5 15.1 5 2.2 6.8
Don't know 0.5 12.6 6.8 6.3 10.5 0.6 9.4 6.4 4.3 6.5
% 100 100 100 100 100 100 100 100 100 100
Total
N= 193 191 192 192 228 156 106 140 138 384
Vitti Sthapati Brindo Ltd. Page 125
Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping, Beautification & Lighting Project

Avg. 60725 922668 84745 604844 57059 657391 1E+06 81229 66183 4E+05
Table 109: HH loan at present (all sources)
North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad
None 73.6 70.2 72.9 70.8 68.4 76.9 69.8 70 75.4 71.9
Up to Tk.20000 7.8 7.3 6.8 8.3 8.8 5.8 5.7 8.6 8 7.6
Tk.20001-50000 11.4 5.2 6.3 10.4 9.2 7.1 5.7 9.3 9.4 8.3
Tk.50001-100000 4.1 2.6 3.1 3.6 3.9 2.6 2.8 4.3 2.9 3.4
Tk.100000+ 2.6 9.9 7.8 4.7 5.3 7.7 14.2 3.6 2.9 6.3
Don't know 0.5 4.7 3.1 2.1 4.4 1.9 4.3 1.4 2.6
% 100 100 100 100 100 100 100 100 100 100
Total N= 193 191 192 192 228 156 106 140 138 384
Avg. 91372 392802 368630 124348 137664.5 413552.2 6E+05 64250 79863 2E+05

Table 201: Duration of staying in the present residence or within half a kilometer from Baburail Canal.
North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad
Up to 60 months 6.2 2.6 4.2 4.7 3.9 5.1 1.9 2.1 8.7 4.4
61-120 months 13.5 16.8 11.5 18.8 10.5 21.8 8.5 17.9 17.4 15.1
121-180 months 3.1 8.4 4.2 7.3 5.3 6.4 7.5 5 5.1 5.7
181-300 months 10.4 15.7 12.5 13.5 11.8 14.7 10.4 18.6 9.4 13
300+ months 6.2 6.3 6.3 6.3 7.9 3.8 4.7 6.4 7.2 6.3
Since birth 60.6 50.3 61.5 49.5 60.5 48.1 67 50 52.2 55.5
% 100 100 100 100 100 100 100 100 100 100
Total
N= 193 191 192 192 228 156 106 140 138 384

Vitti Sthapati Brindo Ltd. Page 126


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping, Beautification & Lighting Project

Avg. 175.3 193.8 194.5 178.8 203.7 165.5 201.7 191.5 170.8 185.6

Table 202: Household migration from the area.


North or South side of
Major Area Gender Socio-economic
canal
Total
Union
Whether migrated in NCC Male Female North South High Medium Low
Parishad
Yes 46.6 44 41.7 49 46.5 43.6 29.2 52.1 50.7 45.3
No 53.4 56 58.3 51 53.5 56.4 70.8 47.9 49.3 54.7
% 100 100 100 100 100 100 100 100 100 100
Total
N= 193 191 192 192 228 156 106 140 138 384

Table 203: Migration from area


North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad
From other union around the City 5.6 23.8 16.3 12.8 15.1 13.2 16.1 16.4 11.4 14.4
From other upazila of Narayanganj 15.6 4.8 8.8 11.7 5.7 17.6 3.2 15.1 8.6 10.3
From district other than Narayanganj 78.9 71.4 75 75.5 79.2 69.1 80.6 68.5 80 75.3
% 100 100 100 100 100 100 100 100 100 100
Total
N= 90 84 80 94 106 68 31 73 70 174
Note: The residents who migrated from other districts named 27 different districts from all over the country

Vitti Sthapati Brindo Ltd. Page 127


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping, Beautification & Lighting Project

Table 301: Drinking water - Main source


North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad
Supply water (Connected to HH) 28 13.6 11.5 30.2 21.5 19.9 29.2 19.3 15.9 20.8
Supply water (Not connected to HH) 18.1 15.7 9.9 24 19.7 12.8 11.3 13.6 24.6 16.9
Tube well with overhead tank 45.6 64.9 69.8 40.6 49.1 64.1 53.8 58.6 52.9 55.2
Tube well (manual) 8.3 5.8 8.9 5.2 9.6 3.2 5.7 8.6 6.5 7
% 100 100 100 100 100 100 100 100 100 100
Total
N= 193 191 192 192 228 156 106 140 138 384

Table 302: Drinking water - Alternate source


North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad
Supply water (Connected to HH) 5.7 5.2 0.5 7.1 0.9 5 2.2 2.9
Supply water (Not connected to HH) 6.7 4.2 2.6 3.9 2.6 5 4.3 3.4
Tube well with overhead tank 20.9 19.3 1.6 4.8 18.6 20.8 5.7 7.2 10.4
Tube well (manual) 0.5 5.2 4.7 1 3.1 2.6 4.7 4.3 2.9
No secondary water source 87 73.8 66.7 94.3 88.2 69.2 73.6 80 86.2 80.5
% 100 100 100 100 100 100 100 100 100 100
Total
N= 193 191 192 192 228 156 106 140 138 384

Vitti Sthapati Brindo Ltd. Page 128


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping, Beautification & Lighting Project

Table 303: Cooking water - Main source


North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad
Supply water (Connected to HH) 34.7 13.1 15.6 32.3 22.4 26.3 29.2 25 18.8 24
Supply water (Not connected to HH) 18.1 17.8 10.9 25 21.9 12.2 11.3 17.1 23.9 18
Tube well with overhead tank 39.4 63.4 65.1 37.5 46.9 57.7 54.7 50 50 51.3
Tube well (manual) 6.2 5.8 7.8 4.2 8.3 2.6 4.7 7.1 5.8 6
8 1.6 0.5 1 0.4 1.3 0.7 1.4 0.8
% 100 100 100 100 100 100 100 100 100 100
Total
N= 193 191 192 192 228 156 106 140 138 384

Table 304: Cooking water - Alternate source


North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad
Supply water (Connected to HH) 4.7 0.5 4.7 0.5 0.9 5.1 0.9 3.6 2.9 2.6
Supply water (Not connected to HH) 5.2 1 3.6 2.6 4.4 1.3 3.6 5.1 3.1
Tube well with overhead tank 1.6 21.5 21.4 1.6 5.3 20.5 20.8 7.9 8 11.5
Tube well (manual) 0.5 4.7 4.2 1 3.1 1.9 4.7 3.6 2.6
No secondary water source 88.1 72.3 66.1 94.3 86.4 71.2 73.6 81.4 84.1 80.2
% 100 100 100 100 100 100 100 100 100 100
Total
N= 193 191 192 192 228 156 106 140 138 384

Vitti Sthapati Brindo Ltd. Page 129


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping, Beautification & Lighting Project

Table 305: Water for Bathing and washing clothes - Main source
North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad
Supply water (Connected to HH) 40.4 13.6 22.4 31.8 23.2 32.7 30.2 29.3 22.5 27.1
Supply water (Not connected to HH) 22.3 11.5 10.9 22.9 21.1 10.9 8.5 15.7 24.6 16.9
Tube well with overhead tank 26.4 65.4 54.7 37 41.7 51.9 55.7 43.6 40.6 45.8
Tube well (manual) 1 8.4 6.8 2.6 5.3 3.8 4.7 5.7 3.6 4.7
Surface water (River/canal/Pond/
lake/ditch) 9.3 4.7 4.7 7.9 5 8 4.7
8 0.5 1 0.5 1 0.9 0.6 0.9 0.7 0.7 0.8
% 100 100 100 100 100 100 100 100 100 100
Total
N= 193 191 192 192 228 156 106 140 138 384

Table 306: Water for Bathing and washing clothes - Alternate source
North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad
Supply water (Connected to HH) 2.6 1 2.6 1 0.9 3.2 1.9 2.1 1.4 1.8
Supply water (Not connected to HH) 2.1 1.6 1 2.6 2.2 1.3 1.9 1.4 2.2 1.8
Tube well with overhead tank 1 22 21.4 1.6 4.8 21.2 20.8 7.9 8 11.5
Tube well (manual) 0.5 4.7 4.2 1 3.1 1.9 4.7 2.9 0.7 2.6
Surface water (River/canal/Pond/
lake/ditch) 11.4 0.5 5.7 6.3 9.6 0.6 2.8 7.1 7.2 6
No secondary water source 82.4 70.2 65.1 87.5 79.4 71.8 67.9 78.6 80.4 76.3
% 100 100 100 100 100 100 100 100 100 100
Total
N= 193 191 192 192 228 156 106 140 138 384

Vitti Sthapati Brindo Ltd. Page 130


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping, Beautification & Lighting Project

Table 307: Water for Latrine use -Main source


North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad
Supply water (Connected to HH) 42 13.1 24 31.3 23.2 34 29.2 31.4 22.5 27.6
Supply water (Not connected to HH) 22.3 11 10.9 22.4 21.1 10.3 8.5 14.3 25.4 16.7
Tube well with overhead tank 25.9 64.9 54.2 36.5 41.7 50.6 54.7 42.9 40.6 45.3
Tube well (manual) 3.1 8.4 7.8 3.6 7 3.8 5.7 7.1 4.3 5.7
Surface water (River/canal/Pond/
lake/ditch) 6.2 0.5 2.6 4.2 5.3 0.6 3.6 5.8 3.4
8 0.5 2.1 0.5 2.1 1.8 0.6 1.9 0.7 1.4 1.3
% 100 100 100 100 100 100 100 100 100 100
Total
N= 193 191 192 192 228 156 106 140 138 384

Table 308: Water for Latrine use - Alternate source


North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad
Supply water (Connected to HH) 3.1 2.6 0.5 0.9 2.6 2.9 1.4 1.6
Supply water (Not connected to HH) 1.6 2.1 1 2.6 2.6 0.6 1.9 2.1 1.4 1.8
Tube well with overhead tank 1 22 21.4 1.6 4.8 21.2 20.8 8.6 7.2 11.5
Tube well (manual) 0.5 4.7 4.2 1 3.1 1.9 4.7 2.9 0.7 2.6
Surface water (River/canal/Pond/
lake/ditch) 2.1 0.5 1.6 1.8 0.9 1.4 0.7 1
No secondary water source 91.7 71.2 70.3 92.7 86.8 73.7 71.7 82.1 88.4 81.5
% 100 100 100 100 100 100 100 100 100 100
Total
N= 193 191 192 192 228 156 106 140 138 384

Vitti Sthapati Brindo Ltd. Page 131


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping, Beautification & Lighting Project

Table 309: Type of latrine using by the respondents


North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad
Latrine connected with sewage line 52.3 3.7 27.1 29.2 18.9 41.7 15.1 33.6 32.6 28.1
Latrine connected with septic tank 16.1 42.4 38.5 19.8 22.8 38.5 44.3 25.7 21 29.2
Ring-slab latrine with flap/water seal 0.5 0.5 0.4 0.7 0.3
Ring-slab latrine without flap/water seal 1 1 1.6 0.5 1.8 2.1 0.7 1
Pit latrine without cover/lid 1 1 0.9 0.9 0.7 0.5
Well-built latrine connected to
open/drain 27.5 49.2 30.7 45.8 52.6 17.3 38.7 35.7 40.6 38.3
Hanging/bucket latrine 1.6 0.5 1 1.3 1.4 0.7 0.8
No latrine/ Defecated open/ On drain 1 2.6 0.5 3.1 1.3 2.6 0.9 0.7 3.6 1.8
% 100 100 100 100 100 100 100 100 100 100
Total
N= 193 191 192 192 228 156 106 140 138 384

Table 310: The Flow of The Latrine Water


North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad
To the Khal 83.1 89.8 84.6 89.1 88.5 81.5 90.5 82.1 89.8 87.3
To other place 16.9 10.2 15.4 10.9 11.5 18.5 9.5 17.9 10.2 12.7
% 100 100 100 100 100 100 100 100 100 100
Total
N= 59 98 65 92 130 27 42 56 59 157

Vitti Sthapati Brindo Ltd. Page 132


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping, Beautification & Lighting Project

Table 311: Condition of the latrine.


North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad
Good 34.6 75.3 58.4 51.1 57.2 51.3 81.9 48.2 40.2 54.8
Moderate 64.4 22.6 40 47.3 40.5 48 18.1 48.9 58.3 43.6
Bad 1.1 2.2 1.6 1.6 2.3 0.7 2.9 1.5 1.6
% 100 100 100 100 100 100 100 100 100 100
Total
N= 188 186 190 184 222 152 105 137 132 374

Table 312: Observed Status of The Latrine


North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad
Hygienic 31.3 50.8 56.2 25.7 35.2 50 53.4 37.4 35.4 41.2
Unhygienic 68.7 49.2 43.8 74.3 64.8 50 46.6 62.6 64.6 58.8
% 100 100 100 100 100 100 100 100 100 100
Total
N= 179 185 185 179 216 148 103 131 130 364

Table 313: Children under 5 or Disabled Member Who Cannot Use Latrine
North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad
Yes 21.8 19.9 20.5 21.2 19.4 23 26.7 16.8 20.5 20.9
No 25.5 45.2 37.9 32.6 34.7 36.2 39 33.6 34.1 35.3
Not applicable 52.7 34.9 41.6 46.2 45.9 40.8 34.3 49.6 45.5 43.9
Total % 100 100 100 100 100 100 100 100 100 100

Vitti Sthapati Brindo Ltd. Page 133


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping, Beautification & Lighting Project

N= 188 186 190 184 222 152 105 137 132 374

Table 314: Dispose of the excreta


North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad
In latrine 51.2 81.1 56.4 74.4 65.1 65.7 89.3 56.5 48.1 65.4
At the garbage stack/ In the drain 19.5 2.7 10.3 12.8 18.6 2.9 3.6 17.4 14.8 11.5
No specific place 2.4 2.6 2.9 3.7 1.3
In drain/open space 17.1 8.1 15.4 10.3 11.6 14.3 3.6 13 22.2 12.8
In the Khal 9.8 8.1 15.4 2.6 4.7 14.3 3.6 13 11.1 9
% 100 100 100 100 100 100 100 100 100 100
Total
N= 41 37 39 39 43 35 28 23 27 78

Table 401- Drainage Connection to House


North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad
Yes, underground 27.5 26.2 25.5 28.1 25.4 28.8 29.2 28.6 23.2 26.8
Yes, surface drain 56 27.7 37.5 46.4 33.3 54.5 34 43.6 46.4 41.9
No 16.6 46.1 37 25.5 41.2 16.7 36.8 27.9 30.4 31.3
% 100 100 100 100 100 100 100 100 100 100
Total
N= 193 191 192 192 228 156 106 140 138 384

Vitti Sthapati Brindo Ltd. Page 134


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping, Beautification & Lighting Project

Table 402- Pathway of Rain or Waste Water


North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad
To outside ditch/canal thru pipes 40.9 14.1 26 29.2 15.4 45.5 28.3 29.3 25.4 27.6
To Khal through pipes 40.9 52.9 47.4 46.4 52.2 39.1 50.9 44.3 46.4 46.9
Naturally drained to the edges or
outside 17.6 30.4 25 22.9 29.8 15.4 20.8 23.6 26.8 24
Stagnates around the community 0.5 2.6 1.6 1.6 2.6 2.9 1.4 1.6
% 100 100 100 100 100 100 100 100 100 100
Total
N= 193 191 192 192 228 156 106 140 138 384

Table 403: Water Logging Problem


North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad
Yes 17.6 8.9 17.7 8.9 15.8 9.6 6.6 19.3 12.3 13.3
No 82.4 91.1 82.3 91.1 84.2 90.4 93.4 80.7 87.7 86.7
% 100 100 100 100 100 100 100 100 100 100
Total
N= 193 191 192 192 228 156 106 140 138 384

Vitti Sthapati Brindo Ltd. Page 135


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping, Beautification & Lighting Project

Table 404: Duration of Waterlogging


North or South side of
Major Area Gender canal Socio-economic
Union
NCC Parishad Male Female North South High Medium Low Total
Up to 4 days 58.8 20.6 17.6 27.8 42.9 22.2 5.9 19.6
5-10 days 50.0 41.2 52.9 35.3 36.1 73.3 28.6 51.9 47.1 47.1
11-20 days 35.3 23.5 23.5 22.2 26.7 28.6 11.1 41.2 23.5
21-30 days 14.7 2.9 23.5 13.9 14.8 5.9 9.8
Total % 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0 100.0
N= 34 17 34 17 36 15 7 27 17 51
Avg. 24.4 6.1 16.1 22.6 18.4 17.9 11.1 19.2 19.7 18.3

Table 405: Disposal of Kitchen Waste


North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad
Waste collectors collect from home 39.4 16.8 26.6 29.7 30.3 25 32.1 28.6 24.6 28.1
Disposed to specific dustbin 6.7 3.1 6.3 3.6 3.5 7.1 4.7 4.3 5.8 4.9
Thrown to the Khal 26.9 56 40.6 42.2 38.6 45.5 43.4 37.1 44.2 41.4
Thrown to any open place 26.9 24.1 26.6 24.5 27.6 22.4 19.8 30 25.4 25.5
% 100 100 100 100 100 100 100 100 100 100
Total
N= 193 191 192 192 228 156 106 140 138 384

Vitti Sthapati Brindo Ltd. Page 136


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping, Beautification & Lighting Project

Table 406: Air Pollution


North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad
Yes, high 29.5 15.7 30.2 15.1 18.9 28.2 22.6 20 25.4 22.7
Yes, some 51.8 33 44.3 40.6 44.3 39.7 32.1 50.7 42 42.4
No 18.7 51.3 25.5 44.3 36.8 32.1 45.3 29.3 32.6 34.9
% 100 100 100 100 100 100 100 100 100 100
Total
N= 193 191 192 192 228 156 106 140 138 384

Table 407: Sound Pollution


North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad
Yes, high 15 11.5 12.5 14.1 12.3 14.7 14.2 16.4 9.4 13.3
Yes, some 44 25.7 37 32.8 28.5 44.2 27.4 37.9 37.7 34.9
No 40.9 62.8 50.5 53.1 59.2 41 58.5 45.7 52.9 51.8
% 100 100 100 100 100 100 100 100 100 100
Total
N= 193 191 192 192 228 156 106 140 138 384

Vitti Sthapati Brindo Ltd. Page 137


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping, Beautification & Lighting Project

Table 501: Types of Membership


North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad
Political party 1.6 1.6 1.3 0.9 1.4 0.8
Professional organization 1 0.5 0.5 0.4 0.6 0.9 0.7 0.5
Social/ women organization 3.1 1 4.2 3.1 0.6 1.9 2.1 2.2 2.1
School committee 1 1 0.4 0.6 1.9 0.5
Mosque/ madrasa 0.5 7.3 7.8 3.5 4.5 8.5 2.9 1.4 3.9
Sports club 0.5 0.5 0.5 0.5 0.4 0.6 1.9 0.5
No member 93.3 90.1 84.4 99 90.8 92.9 84 94.3 94.9 91.7
% 100 100 100 100 100 100 100 100 100 100
Total
N= 193 191 192 192 228 156 106 140 138 384

Table 502: Play Ground Facilities for Children


North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad
Adequate 2.1 1 1 0.9 1.3 0.7 2.2 1
Inadequate 31.1 2.1 17.2 16.1 7.5 30.1 10.4 23.6 14.5 16.7
Not at all 68.9 95.8 81.8 82.8 91.7 68.6 89.6 75.7 83.3 82.3
% 100 100 100 100 100 100 100 100 100 100
Total
N= 193 191 192 192 228 156 106 140 138 384

Vitti Sthapati Brindo Ltd. Page 138


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping, Beautification & Lighting Project

Table 503: Open Space of Parks for the Residents to Walk or Socialize
North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad
Adequate 0.5 0.5 0.6 0.7 0.3
Inadequate 24.9 2.6 21.4 6.3 4.4 27.6 8.5 17.9 13.8 13.8
Not at all 75.1 96.9 78.1 93.8 95.6 71.8 91.5 82.1 85.5 85.9
% 100 100 100 100 100 100 100 100 100 100
Total
N= 193 191 192 192 228 156 106 140 138 384

Table 504: Facilities for the Residents to Enjoy Cultural Events, Movie, and Drama
North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad
Adequate 1 1 1.3 0.7 0.7 0.5
Inadequate 34.2 4.7 29.7 9.4 11.8 30.8 10.4 22.9 23.2 19.5
Not at all 64.8 95.3 69.3 90.6 88.2 67.9 89.6 76.4 76.1 79.9
% 100 100 100 100 100 100 100 100 100 100
Total
N= 193 191 192 192 228 156 106 140 138 384

Vitti Sthapati Brindo Ltd. Page 139


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping, Beautification & Lighting Project

Table 505: Drug Addiction Problem


North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad
Very serious 14.5 14.1 12.5 16.1 17.1 10.3 25.5 10 10.1 14.3
Serious 39.9 24.6 36.5 28.1 25.4 42.3 32.1 31.4 33.3 32.3
Medium 30.1 26.2 34.9 21.4 26.8 30.1 21.7 33.6 27.5 28.1
Low 10.9 12.6 7.3 16.1 13.2 9.6 10.4 11.4 13 11.7
Very low 4.7 22.5 8.9 18.2 17.5 7.7 10.4 13.6 15.9 13.5
% 100 100 100 100 100 100 100 100 100 100
Total
N= 193 191 192 192 228 156 106 140 138 384

Table 506: Security Related Problem


North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad
Very High 2.1 3.7 4.2 1.6 3.1 2.6 2.8 3.6 2.2 2.9
High 30.1 16.2 28.1 18.2 16.7 32.7 17.9 28.6 21.7 23.2
Medium 48.7 36.6 34.9 50.5 48.7 34 39.6 42.1 45.7 42.7
Low 11.9 15.7 9.4 18.2 15.8 10.9 16 12.1 13.8 13.8
Very low 7.3 27.7 23.4 11.5 15.8 19.9 23.6 13.6 16.7 17.4
% 100 100 100 100 100 100 100 100 100 100
Total
N= 193 191 192 192 228 156 106 140 138 384

Vitti Sthapati Brindo Ltd. Page 140


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping, Beautification & Lighting Project

Table 507: Percentage of People Who are Socially Connected to Each Other
North or South side of
Major Area Gender Socio-economic
canal
Total
Union
NCC Male Female North South High Medium Low
Parishad
High 32.1 30.9 31.3 31.8 27.2 37.8 34.9 34.3 26.1 31.5
Medium 66.8 57.1 62 62 62.3 61.5 59.4 59.3 66.7 62
Low 1 12 6.8 6.3 10.5 0.6 5.7 6.4 7.2 6.5
% 100 100 100 100 100 100 100 100 100 100
Total
N= 193 191 192 192 228 156 106 140 138 384

Vitti Sthapati Brindo Ltd. Page 141


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

ANNEX-B: SURVEY QUESTIONNAIRE


Social Impact Assessment on Restoration of
Baburail Khal, Narayanganj

Household Questionnaire

Greetings!

I am ...................................................., here on behalf of Narayanganj City Corporation assigned for


household survey for identifying social impacts of restoration of Baburail Khal through Narayanganj
City Corporation. I am member of the team of Vitti Consultants engaged by the City Corporation. We
will be interviewing various people living within half a kilometer on both sides of the Baburail Khal. The
information and opinion provided by the respondents will be useful for a better restoration of the Khal.
You are one of the randomly selected persons with whom we will talk. Hope you will cooperate with me
to allow interviewing you. Let me assure you that strict confidentiality will be maintained about the
information and opinion, which we receive from you. These will be used for research purpose only.
While interviewing, you will also have the option of not responding to a particular question. May I now
proceed with the interview, which may take about half an hour (maximum)?

1- Agreed  Proceed 2- Not interested  Thank and go to next respondent in the list.

Name

Sex
1 = Male, 2 = Female, 3 = Third Gender
Address
(Mahalla/ Road/ Landmark)

Ward #

NCC/ Union Parishad

GPS Code

Mobile number
Interview Time Starting: Ending:

Interviewer's pledge:
I do hereby pledge that I have filled out the questionnaire myself interviewing the person named and I
have tried to remain as neutral as possible in recording the information.

Interviewer's Name & ID Date


Supervisor's Name & ID Date

Vitti Sthapati Brindo Ltd. Page 142


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Household Member Matrix

Relation Age Sex Marita Educati Disabl Main Secondar


to HH l on e occupati y
head Male-1 Status on Occupati
Sl. (Round Female (highest on
Short Name
# (Code- ed -2 (Code class (Code
1) Year) -2) passed) -3) (Code- (Code-4)
4)

1 2 3 4 5 6 7 8 9
01
02
03
04
05
06
07
08
09
10
Tot
al

Relation to household head (Code-1) Marital status: (code-2) Disable: (code-


Household head 1 Daughter/son in-law 7 Unmarried 1 3)
Husband/wife 2 Brother/Sister-in-law……. Married 2 No .. 1
Son/daughter 3 8 Widow/widower 3 Physical .. 2
Brother/sister 4 Grandson/daughter.. 9 Divorced 4 Blind .. 3
Father/mother 5 Niece/Nephew Separated/Deserted. 5 Mental ... 4
Father/Mother in-law. 6 ………….10 Deaf/dumb ..5
Other relative
…………...11
Non-
relative……………...12
Main occupation: (Code-4)
Child (0-5 yrs) 1 Skilled labor/ Driver 8
Student (no work) 2 Small Business/ 9
Vendor
Housewife 3 Medium Business 10
Emigrant 4 Beggar 11
Unskilled laborer / House maid 5 Unemployed 12
Rickshaw/Van/ Cart puller 6 Retired/Old person 13
Service 7 Other (write) 14
……...............

Vitti Sthapati Brindo Ltd. Page 143


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Section 1: Socio-economic Information of Respondent Households

Q. # Question Answer Skip


101 Race Bengali 1
Ethnic/ Adivasi 2
102 Religion Islam 1
Hindu 2
Christian 3
Buddhist 4
Other ……………. 5
103 Ownership of the dwelling house Live on rent
1
Own house built on own land
2
Own house built on Govt./other’s
3
land
4
Other (write) ...........................
104 Type of house construction Brick and cement (all)
Brick and cement (part) 1
Bamboo/Tin/ Earthen house – 2
strong built 3
Bamboo/Tin/ Earthen house – 4
weak built 5
Shanty/ Jhupri 6
Other (write) .......................
Number of rooms in use
105 (exclude rooms rented or given sublet) No. of rooms: ..…..……

106 Total floor area in use: ……… sq.ft.


107 Average HH expenditure per month Tk. ……………..
Average HH income per month Tk. ……………..
108 (All members,)
109 HH savings at present (all sources) Tk. ……………..
110 HH loan at present (all sources) Tk. ……………..

Section-2: Migration

201 How long staying in the present ……….. months


residence or within half a kilometer from Since birth 99
Baburail Khal?
202 Migrated to the area or Not (Please tick) Yes 1
[Definition: Staying in the areas for last 3 No 2 >>2
months for permanent residence ] 05
203 If yes, migrated from where From other union around the City 1 >>2
From other upazila of 2 05
Narayanganj 3 >>2
From district other than 05
Narayanganj
204 Name of the District:
205 Would you have to migrate due to this Yes 1
project? No 2
206 If yes, Please specify the particular
reason(s)

Vitti Sthapati Brindo Ltd. Page 144


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Section-3: WaSH
A. Water use, all purposes
301 Interviewer: For each of the purpose of water use mentioned in the left column of the Table below,
please ask main and alternative sources of water and write the answer in the corresponding right
columns using source code below.
Main source Alternate
Purpose of water use (Code) source
(Code)
Drinking
Cooking
Bathing and washing clothes
Latrine use
Water source Code:
Supply water (Connected to HH) 1
Supply water (Not connected to HH) 2
Tube well with overhead tank 3
Tube well (manual) 4
Dug well (protected) 5
Dug well (unprotected) 6
Surface water (River/canal/Pond/ 7
lake/ditch) 8
Other (write)……………….

Q. # Question Answer Skip


302 What is the type of latrine that you and Latrine connected with sewage 1
the members of your household use? Latrine connected with septic tank 2
Ring-slab latrine with flap/water 3
seal 4
Ring-slab latrine without flap/water 5
seal 6
Pit latrine with cover/lid 7
Pit latrine without cover/lid 8 >>3
Well built latrine connected to 9 04a
open/drain >>4
Hanging/bucket latrine 01
No latrine/ Defecated open/ On
drain
Other (specify) ………………

303 (Ask and observe) To sewage line 1


Where do the latrine water/sludge/feces To septic tank 2
go? To the edge of the slum thru pipe 3
To drain/canal flowing through the 4
slum 5
To the Baburail Khal 6
Other (specify) ………………….

304 Super structure of the latrine Good 1


Moderate 2
Bad 3
304 Get photograph of the latrine, one inside and one outside
a
305 Observed status of the latrine Hygienic 1
(Water seal/ breakage/ leakage/ etc. ) Unhygienic 2

Vitti Sthapati Brindo Ltd. Page 145


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Q. # Question Answer Skip


306 Is there any children under 5 or disable Yes 1
member in this household who cannot No 2
use latrine?
307 If yes, In latrine 1
Where do you dispose off the excreta? At the garbage stack/ In the drain 2
No specific place 3
In drain/open space 4
In the Baburail Khal 5

Section-4: Environmental and Waste management

Q. # Question Answer Skip


401 Is there any drainage connection to your Yes, underground 1
house? Yes, surface drain 2 40
No 3 3
402 Where do the rain or wastewater go? To outside ditch/canal through 1
pipes 2
To Baburail Khal through pipes 3
Naturally drained to the edges or 4
outside
Stagnates around the community
Other (Specify) ………………

403 Do you face waterlogging at your house


any time of the year? Yes 1 40
No 2 5
404 How many months a year you face
waterlogging? ………….. Months
405 How are the kitchen wastes of yours HH Waste collectors collect from home 1
disposed off? Disposed to specific dustbin 2
Thrown to the Baburail Khal 3
Thrown to nearby ditch/ any place
Other (Specify) …………….

406 Do you face air pollution staying in your Yes, high 1


house? Yes, some 2
No 3
407 Do you face sound pollution staying in Yes, high 1
your house? Yes, some 2
No 3

Section-5: Social facilities and problems

501 Membership of any political party, Political party 1


professional organization, social organization, Professional organization 2
school committee, mosque, sports club etc.? Social/ women organization 3
School committee 4
[ FI: Please mark those apply ] Mosque/ madrasa 5
Sports club 6
Other ………….. 7
None 8
9

Vitti Sthapati Brindo Ltd. Page 146


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

501 If member, type of membership: General member 1


a Executive member 2
502 How much playgrounds or facilities in this Adequate 1
area for the children to play in the field? Inadequate 2
Not at all 3
503 How much open space of parks in this area Adequate 1
for the residents to walk or socialize? Inadequate 2
Not at all 3
504 How many facilities in this area for the Adequate 1
residents to enjoy cultural events, movie, Inadequate 2
drama etc? Not at all 3

505 In your opinion, how serious is the problem of Very serious 1


drug addiction in your area? Serious 2
Medium 3
Low 4
Very low 5

506 In your opinion, how much is the security Very High 1


related problem in your area? High 2
Medium 3
Low 4
Very low 5

507 In your opinion, how much people in your High 1


area are socially connected to each other? Medium 2
Low 3

Section-6: Questions related to Baburail Khal Project

6-A. General
01 How much do you know about the Very well 1
restoration and development of the Baburail Fairly well 2
Khal? Moderate 3
Little 4
[Ask supportive questions to assess on the Very little 5
spot]
602 What are the sources of your information on From Mayor 1
the Baburail Khal restoration? From Other NCC staff 2
members 3
From local leaders 4
From friends/ neighbors
Other (write) ……………..
603 Do you think this project will succeed? Sure 1
May or may not 2
No 3
604 Why do you think so? :
605 In your opinion, how much is the support of Very high 1
local people towards the project? High 2
Moderate 3
Low 4
Very low 5

Vitti Sthapati Brindo Ltd. Page 147


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

606 Do you know the plan how the Canal will be Yes 1
restored? No 2
607 Do you personally support the kind of Very much support 1
restoration that has been planned? Moderately support 2
No 3
608 Give reasons for your answer:

609 How do you suggest the restoration works to be In one dry season 1
completed? In two dry seasons 2
No idea 3

6-B. Possible problems that the people may face during implementation of the project
609 In your opinion, what are the major problems that the people may face during implementation
of the project? (Probe)
[FI: First circle the responses mentioned spontaneously in the ‘Unaided’ column. Then
mention rest of the listed responses one by one and ask whether that could also be a
problem. Circle those agreed in the ‘Aided’ column and others in the last column]
Responses Unaided, Aided, No
yes yes
a. Air pollution will Increase 1 2 3
b. Noise pollution will Increase 1 2 3
c. Too many laborers/ outside people will crowd the area 1 2 3
d. Many people will lose their income 1 2 3
e. The education of children will be disturbed 1 2 3
f. There will be interruption in business due to massive work 1 2 3
g. May need to leave the place during implementation 1 2 3
h. Communication across the khal will be disrupted
i. Solid waste disposal in the Khal will be restricted
j. Waste water and sewage disposal in the Khal will be
restricted
k. Other (write) ,,,,,,,,,,,,,,, 1 2 3
6-C. Possible benefits / good impacts when the project will complete
610 In your opinion, what are the major benefits that the people will enjoy once the project is
complete? (Probe)
[FI: First circle the responses mentioned spontaneously in the ‘Unaided’ column. Then
mention rest of the listed responses one by one and ask whether that could be a benefit.
Circle those agreed in the ‘Aided’ column and others in the last column]
Responses Unaided, Aided, yes No
yes
a. Land value will increase/ Developers will be 1 2 3
attracted
b. Income opportunity will increase 1 2 3
c. Area will be clean, free from waste dumping 1 2 3
d. Area will be attractive, beautified 1 2 3
e. Area will be free from water logging 1 2 3
f. Improve Water transport system 1 2 3
g. Improve the overall environment of the area 1 2 3
h. Air quality will improve, No bad smell 1 2 3
i. Ample green space will be availale for recreation 1 2 3
i. Other (write) ,,,,,,,,,,,,,,, 1 2 3
6-D. Possible problems or adverse impacts when the project will complete

Vitti Sthapati Brindo Ltd. Page 148


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

611 In your opinion, what are the major problems that the people may face once the
project is complete? (Probe)
[FI: First circle the responses mentioned spontaneously in the ‘Unaided’ column.
Then mention rest of the listed responses one by one and ask whether that could
be a problem. Circle those agreed in the ‘Aided’ column and others in the last
column]

Responses Unaided, Aided, No


yes yes
a. House rent will increase/ Low income people will be ousted 1 2 3
b. The area will be much crowded, Become congested 1 2 3
c. Migrants will take over the locals 1 2 3
d. Traditional values will tilt/disappear 1 2 3
e. Social crime will increase
f. Public health concerns will raise
e. Other (write) ,,,,,,,,,,,,,,, 1 2 3
h. Other (write) ,,,,,,,,,,,,,,, 1 2 3
612 Are you affected from restoration of Baburail Direct affected 1
canal? Not directly affected 2
613 How you will mitigate this problem? ……………………………………………………

614. Do you have any suggestion for the authorities in Baburail Khal Restoration project? Please
tell.
…………………………………………………………………………………………………
…………………………………………………………………………………………………

FI: Please examine the whole questionnaire to ensure that you have nothing more to ask. Then
thank the respondent for his/her cooperation to conclude your interview.

Vitti Sthapati Brindo Ltd. Page 149


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping, Beautification & Lighting Project

Vitti Sthapati Brindo Ltd. Page 150


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping, Beautification & Lighting Project

Photo Album (Existing Physical Condition)

Vitti Sthapati Brindo Ltd. Page 151


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping, Beautification & Lighting Project

Photo Album (Full Project after Restoring the Canal)

Vitti Sthapati Brindo Ltd. Page 152


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

Comments and Remarks on SIA Report

SI Topics Comments Remarks


1 Executive A. Introduction: As discussed at the Incorporated as per the comments
nd
Summary: Office of the PD, MGSP on 22 and the Title has been changed as
May, the sub project title may be the “Restoration/Rehabilitation of
changed in order to keep the sub Baburail Canal with Landscaping,
project in Environment Category Beautification & Lighting”
Yellow B. The project would need
restructuring with focus to
beautification instead of
highlighting restoration of water
flow of Baburail Canal. New title
may be "Narayanganj City East-
West Beautification Sub Project".
The word canal is avoided here.
The changed focus: will require
tremendous amount of rewriting
(Para 1, p13).

2 C. Social Impact i. Need some editing. We would i. Incorporated and corrected. This
Assessment: like to have soft copy of the SIA section has been discussed in
report, not now, but after Section 2.2: Phase II: Survey
modification as huge amount of Activities.
rewriting is involved. Then we shall
be able to edit in track change
mode. Interview of 384
respondents by structured
questionnaire is a qualitative
survey, the qualitative part is 5
FGDs and 13 Klls (para 1, p14).

ii. Para 2 (p14) notes that 53% ii. Incorporated and


structures are illegally established, corrected according to comments.
it requires mentioning- on whose
land? Khas/Railway/BWDB etc.

iii. Para 4 (P14) write a lot about


past glory of Baburail khal as a link
waterway between two rivers. iii. Incorporated and rewriting
While rewriting, it should mention according to comments
that restoration of waterway is a
dream and would be addressed
through some other large project
when water quality of Sitalakhya
and Dholeswari will improve. This
is far away from the scope of this
small sub project.

iv. After para 4 (p14) nine bullet iv. Here some ponts has
points noted some concerns which been addressed from FGD
sound negative but several of them findings & concern from the local
are already resolved. Authority of people. Point has been
NCC and adjoining UP on land is incorporated according to
no longer an issue. Bullet 3 comments.

Vitti Sthapati Brindo Ltd. Page 153


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

vaguely says that many poor


people will lose earning opportunity
without mentioning how many poor
people would lose earning and
how. Bullet 4 says about pollution
but does not mention what
pollution. Bullet 7 remarked that the
rich will benefit (may be for
increased value and rent of
property) and the poor will not
benefit. The sub project would also
benefit the poor for increased work
opportunity during construction and
after construction employment in
restaurant and fast food shop etc.
will increase.

3 D. Mitigation i. Para 1(p15) mentions budget of i. Detail discussed in


Plan: SMP implementation and that Resettlement Action Plan
resettlement would be dealt (RAP) Report
separately without putting any
budget under it.

ii. Para 2 (p15) suggests among


other things alternative livelihood
program for affected households. It
ii. Near 400 PAHs has been
mentioned. Detailed
does not say for how many project discuss in Chapter -8:
affected households such Impact Assessment and
livelihood program will be needed, RAP Report
definitely not all. Most would like
one-time compensation in cash.
This paragraph mentions large
number of social problems without
considering how the project would
negatively impact them. The
project is not likely to have any
negative impact on child marriage
and dowry. Labor influx may have
some influence on wage
discrimination and engagement of
child labor if not mitigated. Influx of
visitor

in the beautification sites may have


some effect on food safety,
sanitation, hygiene, sex work etc
but effective mitigation measures
can be taken.

4 E. Conclusion: Please include monitoring and Incorporated according to


evaluation including external comments
evaluation as means to enhance
implementation success and
sustainability.

Vitti Sthapati Brindo Ltd. Page 154


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

5 Chapter 1: i. Background and project i. Incorporated according to


Introduction introduction need rewriting for comments
restructuring
ii. Section 1.3 mixed up sub ii. Incorporated according to
project objective and SIA comments
objective this should limit to
sub project objectives
iii. Section 1.4 Title should be iii. Incorporated according to
Need for Social Impact comments
Assessment (the word impact
is missing). This section need
editing to be done later.

6 Chapter 2: Study Section 2.2.1.1 It need to clarify Incorporated according to


Approach and whether 384 sample respondents comments. Randomly selected
Methodology are all PAPs or include both PAP considering 0.5 km Impact zone.
and non-PAP households living
within half km distance (not radius)
from the canal banks. If all PAP
HHs how many are PAP HHs in
total? It is not clear how samples
were drawn. If PAP only from
census to sample using random
number table or if PAP and other
HHs by accidental or systematic
sampling etc.
7 Chapter 4: Table 3 reveals that data is taken Details information provide in RAP
from 1795 PAP HHs? Please report
provide in this Table average
income of PAP HHs, a distribution
by monthly income categories,
average value of installations,
average land of PAP HHs and
average area affected. Since illegal
occupants are 53% please mention
who owns the land (Khas/ Railway/
BWDB etc).
8 (Chapter 4 & 9), Resettlement Action Plan lacks Details information provide in RAP
enough information. There should report
be entitlement matrix for
compensation and assistance of
project affected person (PAP).
There should also be a detailed
budget for Resettlement Action
Plan. In 4.2.1 (page-37), it is stated
that the acquisition of the private
land was avoided but in 4.2.2, it is
observed that 349 installations are
likely to be damaged at NCC and
Union Parishad and owners of all
identified properties are legal title
holders. Both the statements are
apparently conflicting. Please
rewrite the text maintaining
consistency.
9 Chapter 7 MGSP, LGED is an important Incorporated according to the
stakeholder but its role is not well comments and followed the SIA

Vitti Sthapati Brindo Ltd. Page 155


Social Impact Assessment of Restoration/Rehabilitation of Baburail Canal with Landscaping,
Beautification & Lighting Project

defined. Moreover, TLCC, a citizen framework prepared by MGSP


committee, WC, ward level citizen project of LGED.
committee exist in Narayanganj
City Corporation but in the
stakeholder mapping, these
committees have not been
revealed.
10 Chapter 10 Grievance Redress Mechanism Incorporated according to the
(GRM) including its organogram comments and followed the SIA
should be consistent with MGSP, framework prepared by MGSP
LGED provided guideline. The project of LGED.
GRM is already outlined and ready
for dissemination, and check
whether GRC committee has been
formed or not (Please provide the
specific GRG compositions in the
updated report)
11 Chapter 5 the 0.4% of ethnic minorities was This issue has been solved
found. Please give the details e.g.
which community, number of the
HHs, source of income etc. of the
minorities.
12 General  Please reconfirm whether HHs -Detail discussed in RAP Report
of below poverty level (BPL)
and female headed household
were exist in the PAPs list.

 Please specify the "existing


and proposed widths & -Incorporated according to
lengths" of the canal as comments
specified in the design.
- Incorporated according to
 Please confirm with supporting comments
documents that whether NCC
or other government
departments is the owner of
the canal.

 No photograph of the sub


project is included in the report. -Incorporated according to
Please add the photographs of comments
different sections showing
canal view including users,
residents, shops, institutions
and environmental degradation
activities occurred along the
canal.

 There are mistakes in


mentioning figure number and -Checked and edited
subhead number. These
should be checked.

Vitti Sthapati Brindo Ltd. Page 156

You might also like