Professional Documents
Culture Documents
net/publication/307857650
CITATIONS READS
0 1,523
1 author:
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
Tandem Offloading Simulation study at Risk Bow tie Approach Analysis in Floating Production Storage and Offloading (FPSO) Vessel System View project
Identify Assess, Select, Define and Execute - GHG and Energy Management View project
All content following this page was uploaded by Prakash Bahadur Thapa on 06 September 2016.
Abstract
The facility study is double-bank two-stage (HP and LP), two-phase liquid/gas
separation at Crude flows through the inlet manifold. At the inlet manifold, it is
directed to one of the headers or the test header for well testing.
Gas from the Surge vessel (0.3 barg) is collected by use of gas ejector, boosted
to 2.5 barg, commingled with the gas from LP separator and fed into the 1st stage
of the AG Compressor.
Gas from the HP separator (10 – 12 barg) is let down to LP pressure (2.5 - 3.5
barg), commingled with LP gas and fed into 1 st stage of the AG Compressor. The
associated gas streams are compressed to a final discharge pressure of 120
barg as follows:
The objective of this study is to establish the production capacity limit of the gas plant
and hence ensure its technical and operational safety integrity. The study will be:
Establish design, operating capacities for all process, utility and ancilliary
equipment specified in the Gas facility.
Confirm technical integrity and HSE fit for all process/utility units in this
facility.
The facility study is double-bank two-stage (HP and LP), two-phase liquid/gas
separation at Crude flows to the station through the inlet manifold. At the inlet
manifold, it is directed to one of the headers or the test header for well testing.
Gas from the Surge vessel (0.3 barg) is collected by use of gas ejector, boosted
to 2.5 barg, commingled with the gas from LP separator and fed into the 1st stage
of the AG Compressor.
Gas from the HP separator (10 – 12 barg) is let down to LP pressure (2.5 - 3.5
barg), commingled with LP gas and fed into 1 st stage of the AG Compressor. The
associated gas streams are compressed to a final discharge pressure of 120
barg as follows:
The discharge from the compressor will be tied into the Manifold.
3.0 METHODOLOGY
The inlet to the Gas Compressor skid consists of a manifold of the HP gas
header, LP gas header and the Surge Vessel gas outlet line (via the Ejector),
leading to a common compressor inlet header.
The compressor inlet piping is rated ANSI 150 (230psig maximum allowable
working pressure at 200 ). Details of the various headers are listed in the table
below:
The erosional velocity criteria given in API PR 14E was used as the basis of
assessment for limits of safe flow velocities in the header to the 1st stage
compressor inlet scrubber. Liquid carry-over of 300 bbls/d (4% of Flow station
gross liquid production) is assumed.
Ve = C/(ρm )^0.5
Applying the above criteria, the threshold erosional velocity for the compressor
inlet piping was found to be 63.63 m/s. Operating flow velocity in header was
calculated to be 13.43 m/s Therefore the specified operating velocity is within
limits of erosional velocity and the header is not under erosion risk.
The operating envelope for the header in terms of flow throughput based on
erosional velocity limit is presented in Appendix 1. It shows that flow through the
header at the specified operating conditions does not result in a throughput
constraint and that the two-phase flow in the header (at the operating point) is
within the envelope.
5.0 Compressor
6.0 SEPARATORS
The basic information of the separators in the Gas Compression train is given in
table 7.1.1 below. Integrated system operating envelope for the separators with
the associated ancillary units - nozzles, relief and control valves – are presented
in appendix XX.
Table 6.1.1 Separators Summary Data
ST nd rd
Vessel Data 1 Stage Suction 2 Stage Suction 3 Stage Suction 4th Stage Suction Discharge Fuel Gas KO
Scrubber Scrubber Scrubber Scrubber Scrubber Vessel
Size 914mm ID and 660mm ID and 559mm ID and 1575mm 457mm ID and 406mm ID and 324mm ID and
3294mm T/T 1676mm T/T T/T 1473mm T/T 1346mm T/T 2150mm T/T
Internals Wire mesh, Vortex Wire mesh, Vortex Wire mesh, Vortex Wire mesh, Vortex Wire mesh, Vortex Wire mesh, Vortex
Breaker Breaker Breaker Breaker Breaker Breaker
Inlet Device Schoepentoeter Half open pipe Half open pipe Half open pipe Half open pipe Half open pipe
Nozzles 8” Inlet, 8” gas outlet, 6” Inlet, 6” gas outlet, 2” 4” Inlet, 4” gas outlet, 2” 4” Inlet, 4” gas outlet, 3” Inlet, 3” gas 3” Inlet, 2” gas
2” liquid outlet liquid outlet liquid outlet 2” liquid outlet outlet, 2” liquid outlet outlet, 2” liquid outlet
Operating Pressure 2.5 barg 6.9 barg 17.6 barg 47.5 barg 120 barg 4.5 barg
Operating 37 49 49 49 49 25
Temperature
The gas handling capacity of the separator is based on the minimum vessel
cross sectional area required for gas flow.
AG,min is the cross-sectional area above the highest liquid level. (m2)
Based on the above relation, the maximum allowable gas flowrate was calculated
for each of the gas scrubbers in the Gas Compressor train as well as the fuel gas
knock out vessel. The maximum allowable gas handling capacities for the
vessels are presented in Table 7.1.2 below.
Scrubber Stage Max Allowable Gas Flow Rate Max Liquid Rate
The equation above is based on Stokes law and in practice, bubbles larger than
200μm are assumed to be able to escape. Based on the above equations, the
liquid handling capacities of the scrubbers was found to be in the range 1183 -
14217 bbls/d.
This is based on the momentum criteria of the nozzle inlet devices which is
dependent on maximum flowrates. The criterion shall satisfy:
For schoepentoeter:
Where:
These criteria were used to test the suitability or otherwise of the inlet nozzle to
the scrubbers. Results of capacity checks for the vessels inlet nozzles are
summarises in Table 7.2.3 below. It shows that the nozzles capacities meet the
criteria.
This also is derived from the momentum criteria and given as follows:
Where:
The vessels gas outlet nozzles also satisfy the criteria as adequately sized and
therefore can handle the expected flows (Table 7.2.3).
As shown in the Table 7.2.3 above, the liquid outlet velocities in the nozzles are
in the range 0 - 0.002m/s and the liquid capacity (QL, max) is 1,102 bpd which
satisfies the criterion.
Details of specifications of the relief valves for the gas Solution facility are shown
in Table 7.1.1 below. Table of capacity checks on the Gas facility relief valves are
presented in Appendix XX. Generally, the relief valves are adequately sized for
the specified operating conditions.
Summary of the relief valves capacities rating result is shown in appendix 10 and table
below.
The table above shows that the relief valves are adequately sized for the
operating conditions. 7.1 FLARE CAPACITY
The flare system was rated based on API 521. The flare stack diameter is 16”
and the flare height is 20m. Using the above mentioned API standard, the
capacity at 0.5 Mach was found to be 55.9MMscfd. This is higher than the
operating point of 4.3Mmscfd.
8.0 CONCLUSION
Facility Operating envelop has been developed for the AG compression system
and associated process utility units. Calculations and analysis of the systems
operating envelop show that the design capacities of gathering, compression and
export equipment are adequate for the envisaged maximum operating capacities
based on the expected throughput gas supply.
The range, margin and limits of safe operating conditions for the main equipment
and integrated units are shown in the operating envelop. It can be shown that the
operating conditions as specified in the design documents are within the systems
envelope.
9.0 REFERENCES
APPENDIX
APPENDIX 1: AG COMPRESSOR INLET HEADER ENVELOPE
15.00
13.00
11.00
Gas Capacity, (MMSCFD)
9.00
7.00
5.00
3.00
1.00
-1.00 0 5000 10000 15000 20000 25000 30000 35000 40000 45000 50000
Liquid Capacity, blpd
SYSTEM CURVE
Flow (Mmscfd)
2 OPERATING CURVE
1200
1000
800
Power, kw
600
400
200
0
3.5 4 4.5 5 5.5 5.9
Flow, Mmscfd
40.00
35.00
30.00
Gas Capacity, MMSCFD
25.00
20.00
15.00
10.00
5.00
0.00
0 5000 10000 15000 20000 25000 30000 35000 40000 45000 50000
Liquid Capacity, blpd
Liquid Outlet Nozzle @1.5m/s LCV Capacity @ 80% Max Relief Capacity
APPENDIX 5: 2ND STAGE SUCTION SCRUBBER OPERATING ENVELOPE
40.00
35.00
30.00
Gas Capacity, MMSCFD
25.00
20.00
15.00
10.00
5.00
0.00
0 5000 10000 15000 20000 25000 30000 35000 40000 45000 50000
Liquid Capacity, blpd
Liquid Outlet Nozzle @1.5m/s LCV Capacity @ 80% Max Relief Capacity
3rd StageSuction Scrubber (V-2703) Operating Envelope
30
25
20
Gas Capacity, Mmscfd
15
10
0
0 10000 20000 30000 40000 50000 60000
Liquid Outlet Nozzle @1.5m/s LCV Capacity @ 80% Open Max Relief Capacity
4th Stage Suction Scrubber (V-2704) Operating Envelope
30.00
25.00
20.00
Gas Capacity, Mmscfd
15.00
10.00
5.00
18.00
16.00
14.00
12.00
Gas Capacity,Mmscfd
10.00
8.00
6.00
4.00
2.00
Vessel Gas Capacity Inlet Nozzle Vessel degassing Capacity Gas Outlet Nozzle
Liquid Outlet Nozzle @1m/s Operating Point Liquid Outlet Nozzle @1.5m/s LCV Capacity @ 80% Open
Fuel Gas Scrubber (V-4501) Operating Envelope
3.5
2.5
Gas Capacity, (Mmscfd)
1.5
0.5
0
0 10000 20000 30000 40000 50000 60000
Liquid Capacity ,( bpd)
Vessel Gas Capacity Gas Outlet Nozzle Inlet Nozzle Vessel degassing Capacity
27-PSV-
101 K-2701 2J3 234.8 731 3822.7 8,970 17.78 2.5 427.99 0.9932 0.548 1.287
27-PSV-
201 K-2702 1-1/2G3 713.3 738 3822.7 10,702 17.78 2.549 430.38 0.9852 0.180 0.503
27-PSV-
301 K-2703 1E2 1455 753 3813.3 8,602 17.78 2.667 435.95 0.9691 0.087 0.196
27-PSV-
401 K-2704 1-1/2D2 2176 738 3667.4 7,543 17.78 2.861 444.55 0.9417 0.053 0.11