You are on page 1of 33

Chapter 17.

5
HOISTING SYSTEMS
F RED A. E DWARDS

17.5.1 INTRODUCTION
After a detailed technical feasibility study has indicated the
commercial viability of exploiting an ore body using under-
ground methods, an adequate planning and design process for
mine access should begin. Two general types of access should be
considered: (1) vertical to near-vertical shafts using hoists and
cable-suspended conveyances, or (2) horizontal or inclined open-
ings using rail, trucks, conveyors, or cable-operated conveyances.
Because a shaft often provides the most direct access over
the longest period of time, there is an advantage to designing a
shaft for maximum duty, consistent with economy. The current
trend in shaft design is to provide multipurpose shafts. These
shafts contain facilities for handling ore, waste, materials, per-
sonnel, services, manways, and ventilation.
During the process of identifying the purpose of the shaft, it
should be realized that once a shaft is excavated and equipped,
it cannot be enlarged easily in the future. Therefore, the shaft’s
initial and ultimate requirements must be defined during the
design phase.
This chapter presents the information and criteria necessary
to design or select a mine shaft hoisting system. Specific topics
such as hoist selection, hoist rope details, headframe design, shaft
furnishings and equipment, as well as shaft lining design, are
included in the discussion. Ramps and tunnels are dealt with in
a similar fashion in Chapters 17.4 and 24.1. Fig. 17.5.1. Shaft hoisting system.
A system is defined as a group of units so combined as to
form a whole and to operate in unison. Thus, when designing a
shaft hoisting system, one must consider not only each part of dip, plunge and depth of the ore body, and (3) hydrogeology of
the system separately but the interrelationships among the parts the strata to be penetrated. With the above information, the
of the system in its entirety. For the purpose of this discussion, engineer is in a position to prepare conceptual designs and order-
the shaft hoisting system has been divided into five main compo- of-magnitude cost estimates.
nents: (1) hoist, (2) conveyance, (3) rope, (4) shaft, and (5) Outside influences on the cost of any new project must be
headframe (Fig. 17.5.1). taken into account. These are (1) the geographic location of the
Following a description of each of the five main hoisting project, affecting cost of materials; (2) climatic conditions at the
components, a segment describing a systematic procedure that site, especially heavy rainfall, snow, extreme cold and high
can be used to design a shaft hoisting system is presented. winds; and (3) availability of skilled manpower to carry out the
work, noting labor relations in the area. While these items do
17.5.1.1 Design Parameters for Evaluating not generally affect the design considerations, they affect the
development costs for the access system.
Alternative Modes of Access After the above terms have been defined, trial calculations
and alternate designs can be considered. During this process, the
The first step in evaluating an access system for a mine is to
interrelationships among the major components of the system
determine the principal purpose of the opening. The opening
can be examined. Each trial design must be evaluated to ensure
could be used for production, service, ventilation, exploration,
that it meets the design objectives. These objectives are con-
development, or a combination of these. Next, duty requirements
cerned with capital costs, operating costs, dependability, effi-
for the opening must be established. Questions include: how
ciency, flexibility, suitability to the mining plan, and time to
much ore and waste? how many personnel? how much material
construct. This procedure of defining, examining alternate de-
and supplies? how much air?
signs, and conducting evaluations is continued until an optimum
With this information, the basic design parameters, includ-
solution is reached.
ing the size of the opening, configuration, ground support, and
inclination can be developed. This allows preliminary designs
and comparative capital and operating cost estimates to be made 17.5.2 SHAFT HOISTING SYSTEMS
between alternative systems.
Detailed cost analysis for the mine access cannot be carried In this chapter, the major components associated with verti-
out without additional design consideration involving the follow- cal to near-vertical shafts using hoists and cable-suspended con-
ing items: (1) geology of the ground to be excavated, (2) strike, veyances are described briefly. The term shaft hoisting system is

1646
HOISTING SYSTEMS 1647
used to describe collectively the openings and the equipment (1) by purpose, (2) by configuration, (3) by ground support, and
being considered. (4) by excavation method.
In addition to the five major hoisting components, Edwards SHAFT PURPOSE. One of the first items to be examined when
(1988) has identified an additional 277 subcomponents. The designing a shaft is to identify its intended purpose. When de-
number of subcomponents and their interrelationship with the fined by purpose, shafts usually fall into the following categories:
main components are indicative of the complexity involved with 1. Production: ore and waste handling.
the design of shaft hoisting systems. 2. Service: personnel and materials handling.
A brief description of each of the above main components is 3. Ventilation: upcast or downcast airflow.
now presented. In the following segments, information on the 4. Exploration: for defining mineral deposits.
design and technical considerations to be examined when select- 5. Escape: for emergency.
ing a particular component is presented in more detail. 6. Combinations of the above.
SHAFT CONFIGURATION. Shafts may be classified according
to their size and configuration. The most common shaft configu-
17.5.2.1 Hoists
rations for any size shaft are circular, rectangular, and elliptical.
There are two basic types of hoists in common use today. Size of a shaft can be small (32 to 160 ft2, or 3 to 15 m2), medium
These are the drum hoist in which the hoist rope is stored on the (160 to 2150 ft2, or 15 to 200 m2), or large ( > 2150 ft2, or 200
drum, and the friction hoist in which the rope passes over the m2), depending upon its service.
wheel during the hoisting cycle. Within each category there are SHAFT GROUND SUPPORT R EQUIREMENTS. Shafts may be
several variations. classified according to the type of ground support to be used to
Drum hoists are usually located at some distance from the maintain the stability of the shaft structure, for example, a timber
shaft and require a headframe and sheaves to center the hoisting shaft or concrete-lined shaft. Ground support applied to the shaft
ropes in the shaft compartment. Friction hoists may also be structure can be classified as temporary support or permanent
located directly over the shaft and, depending upon the wheel support. Ground support requirements are thoroughly discussed
diameter, may require deflection sheaves to center the rope in in Chapter 17.4.
the shaft compartment. SHAFT EXCAVATION METHODS. Shafts may be classified by
the excavation method used during construction. There are two
17.5.2.2 Conveyances types of excavation methods: conventional and bored. Conven-
tional shafts are excavated with standard drilling, blasting, and
Conveyances used in mining operations are classified ac- mucking methods, in combination with various methods of
cording to their use. Those for handling personnel and material ground support. They may be of any configuration or inclination.
are generally termed cages. Conveyances for handling broken Bored shafts are excavated using a mechanical shaft boring ma-
ore or coal and waste are termed skips. Combination skip-cages chine (SBM). Several boring methods are available. Most meth-
are used in some areas. A counterweight may also be considered ods remove cuttings from the collar of the hole. Some methods
a conveyance. drop cuttings from the machine into the mine. All bored shafts
are circular in configuration, with various methods of ground
17.5.2.3 Rope support. They may be of any inclination. Shaft excavation tech-
niques are discussed in Chapter 17.4 and Section 9.
When considering the complete shaft hoisting system, there
are three common uses for steel ropes, with a particular construc- 17.5.2.5 Headframe
tion applicable for each use. A list of ropes by use and most
common construction follows: Headframes may be constructed of wood, steel, or concrete.
They are generally divided into two types:
Rope Use Rope Construction A. With backlegs
1. A-frame
1. Hoist rope Round strand 2. Four-post
Flattened strand 3. Six-post
Locked coil 4. Other
2. Balance rope Non-rotating B. Tower
3. Guide and rubbing rope Half-locked coil 1. Ground-mounted hoist
2. Tower-mounted hoist
17.5.2.4 Shaft
Brucker (1975) has provided two definitions that can be 17.5.3 HOISTS
used to describe shafts for mining purposes: (1) a vertical, deep, Generally, the mine hoist selected and installed at a mine
restricted cross-section excavation, and (2) a vertical or inclined remains in position for the life of the operation. It is therefore
primary opening in rock that gives access to and serves various imperative that the proper hoist be selected. In order to select
levels of a mine. the proper hoist, it is important to understand the basic design
Primary openings can be further defined as those that are parameters, the various types of hoists available, and the relation-
considered to be permanent and require a high degree of safety. ship between the mine hoist and the other components of the
Although the above definitions can be used to describe any type hoisting system. Each major type of hoist is now considered
of shaft, they are somewhat general and do not provide sufficient separately (Fig. 17.5.2).
information to allow the design and construction of a shaft as a
useful structure for mining purposes.
There are several classifications that can be used to differenti-
17.5.3.1 Types of Hoist
ate shafts by type. For the purpose of this discussion, four com- SINGLE DRUM. The single drum hoist may be used for bal-
monly used classifications are presented. Shafts can be classified anced or unbalanced operation. When used for unbalanced
1648
D OUBLE D RUM , B OTH D RUMS C LUTCHED . The double
drum hoist with both drums clutched has the added feature
of allowing hoisting to continue in one compartment should
something happen to the other compartment. This is an excellent
feature if there is only one hoist available. This type of hoist is
also favored during shaft sinking operations.
MULTIPLE D RUM, BLAIR T YPE. With this type of hoist,
each conveyance is suspended from two hoist ropes that are each
coiled on a drum. The advantage of this is that smaller diameter
ropes and drums may be used. This type of hoist was developed
in South Africa. There are no Blair-type hoists in use in North
America. However, for very deep mines, they should be con-
sidered.
FRICTION H OIST , S INGLE R OPE , AND M ULTIROPE . The
Koepe or friction hoist was developed by Frederick Koepe in
1877. It consists of a wheel with a groove lined with friction
material to resist slippage. The hoist rope is not attached or
stored on the wheel. In early installations, the hoist was mounted
on the ground, and a single rope was wound around the drum
and over the headsheaves to the conveyances, in a balanced
arrangement. In addition, a tailrope of the same weight per unit
length as the headrope was suspended in the shaft below each
conveyance. Thus the only out-of-balance load was the payload.
As hoisting loads became larger, the number of headropes
and headsheaves increased to the point where it became more
practical to install the hoist in the headframe directly over the
shaft. In North America, many friction hoists are mounted in
this way. In order to bring the rope centers in line with the
Fig. 17.5.2. Arrangements of various hoists.
compartment centers, deflection sheaves must also be installed
in the headframe below the hoist.

hoisting, the cost of the electric drive becomes quite high for long
hoisting distances and high tonnages. This is because the motor
must have sufficient torque to handle the weight of the rope, 17.5.3.2 Comparison of Friction and Drum Hoists
conveyance, and payload.
In a balanced hoisting system, one rope winds off the drum A friction hoist system differs from a drum hoisting system
as the other winds on. When used with a skip or cage in balance in performance as well as components. Therefore, when at-
with a counterweight, a single drum hoist can service one or tempting to decide which type of hoist to use, it is necessary to
more levels since the location of the counterweight is not impor- compare the two complete systems rather than the two hoists
tant. When used with two skips in balance, the single drum hoist alone. In addition to comparing the total capital costs of the
is best used for single-level hoisting. Any rope adjustments to hoist, headframe, ropes, conveyances, and shaft, it is necessary
locate the conveyance must be done manually. For shallow shafts to consider operating costs, maintenance costs, reliability, power
with one layer of rope, no dividing of the drum is required. For supply system, local custom, and individual preference.
deeper shafts, the drum must be divided. Brucker (1975), Schulz (1973) and Tudhope (1973), among
DIVIDED SINGLE DRUM. This type of hoist is used for deeper others, have discussed drum hoist and friction hoist applications.
shafts with balanced hoisting when several layers of rope must The following general statements help distinguish between these
be stored on the drum. Peak horsepower is less than with unbal- two hoisting systems: (1) double-drum hoists are the preferred
anced hoisting because the skip weights are balanced. Since the hoist for shaft sinking; (2) double-drum hoists are the best choice
payload and weight of the rope is not balanced, the maximum for hoisting in two compartments from several levels; (3) drum-
unbalanced load occurs when the loaded conveyance is at the type hoists are best suited for high payloads from shallow depths;
bottom of the shaft.
(4) the limitation on a drum hoist employing a single rope is the
SPLIT D IFFERENTIAL D IAMETER D RUM. The third type of
ultimate strength of the rope, because large ropes are difficult to
single drum hoist available is the split differential diameter drum.
manufacture and handle; (5) the depth capacity of drum hoists
This type of hoist is used with a conveyance and counterweight
in balance. If the counterweight is wound on the smaller diameter can be extended by using two ropes per conveyance (Blair-type
drum, it moves less than the main conveyance, and rope adjust- hoist), and with this arrangement, Blair hoists can be used for
ment problems are reduced. depths exceeding those of either single-rope drum hoists or fric-
D OUBLE D RUM, ONE D RUM C LUTCHED. Although more tion hoists); (6) friction hoists with multiple ropes can carry a
expensive than a single drum hoist, the double drum hoist with higher payload and have a higher output in tons per hour than
one drum clutched has certain advantages. With this type of drum hoists within a range of depths from 1500 to 5000 ft (460
hoist, it is possible to make quick adjustments to the ropes due to 1520 m); (7) friction hoist mechanical operation is very simple,
to initial stretch. As a service hoist with cage and counterweight, has a low rotational inertia, and is less costly than a drum hoist;
this type of hoist can serve several levels efficiently. As a produc- (8) friction hoists have a lower peak power demand than drum
tion hoist with two skips, the ropes can be adjusted to maintain hoists with the same output; and (9) the friction hoist can operate
balanced hoisting at any level in a multilevel operation. on a relatively light power supply.
HOISTING SYSTEMS 1649
cal and mechanical braking systems, which must operate both
17.5.3.3 Hoist Component Considerations
under normal and emergency conditions.
When selecting (or comparing) hoists, the components to be Electric braking may be accomplished through regenerative
considered during the evaluation process include (1) drum, (2) braking, counter-torque braking, or dynamic braking. In regen-
bearings, (3) gearing, (4) brakes, (5) drive motor, and (6) control. erative breaking, the motor, when connected to a hoist operating
DRUM. For drum hoists, the drum must be designed to store on an overhauling load, performs as an induction generator,
the required length of rope, meet the statutory requirements developing braking torque and returning energy to the system.
concerning fleet angles and rope ratios, and must be sufficiently With counter-torque and dynamic breaking, there is no energy
strong to withstand bending and crushing forces. The design of returned to the system; instead, it is consumed and dissipated in
drums is well documented (Atkinson, 1973) but beyond the the secondary resistance as heat.
scope of this Handbook. When electric braking is used, and during normal operating
Drums may be plain faced or grooved. With plain-faced conditions, the mechanical brake serves two purposes. Firstly, it
drums, a section of the drum is unavailable for carrying live helps to slow down the drum after the speed has been greatly
turns of rope. However, with grooved drums, the entire face can reduced electrically, and secondly, it holds the drum at rest.
be utilized. Under these conditions, the mechanical brake does little work,
There are three types of drum grooving available: (1) helical, and its design and operating characteristics can be fairly simple
(2) parallel, and (3) Le Bus (or antisynchronous). Helical groov- and straightforward. Under emergency conditions, however, the
ing is a continuous spiral providing smooth winding with a single hoist must be stopped with the mechanical brake as quickly as
layer of rope. It can also be used with multilayer winding. Paral- possible, without damaging the hoist, brake, or conveyances.
lel grooving is made up of individual grooves evenly spaced over In North America, there are three main types of brakes used:
the drum width. This grooving is used for single layer winding (1) the jaw, (2) the parallel motion, and (3) disk brakes. Disk
only. Le Bus grooving is a combination of parallel and helical. It brakes are used mainly on friction hoists, whereas jaw and paral-
is deeper than helical and parallel grooves, thus providing better lel motion brakes may be used on both drum and friction hoists.
support. It is most suited for multilayer winding as it reduces With the “caliper-type” brakes, two shoes are pressed against
rope whip at the crossover points. the periphery of the brake drum through the pull of a single or
For friction hoists, the drum must be sized to meet statutory double draw bar acting through a series of linkages. The source
requirements for rope-to-drum ratios and must be wide enough of force can be a brake weight or a nest of springs. When not in
to carry the required number of ropes. use, the weight or springs are held open by a hydraulic oil
The tread of a friction hoist drum is lined with a friction cylinder. When the brakes are applied, oil flows from the cylinder
material to resist slippage. In the past, this material was wood to allow the force of the weight or springs to apply the brakes.
or leather. At present, polyurethane, PVC, or combination The control of this flow is extremely important, as it determines
blocks are used. the speed and amount of force to be applied.
BEARINGS. When there is a relative motion between two The use of disk brakes, particularly with friction hoists, has
members of a machine, one of which supports the other, the increased. Two types of disk brakes are used. In one type, the
supporting member is called a bearing. Bearings are classified brake is operated via a lever system and during emergency stops
into two general types: sliding bearings and roller bearings. Slid- via a falling weight. This is similar to conventional post brake
ing bearings are those in which the surfaces are in sliding contact, systems. With the other type of system, hydraulically operated,
and the supported member runs on a cylindrical, conical, or flat spring applied units are used. These units are mounted around
surface. Roller bearings have surfaces that are in rolling contact, the brake disk. The required number of units is determined by
and the supported member runs on hardened steel balls or rollers.
the total braking force required by the particular hoist. The
In some hoists, sliding bearings lined with babbitt are used
braking control unit is similar to that used in drum hoists. The
for the hoist drum shaft, pinions, and headsheaves. During oper-
advantages of disk brakes are their relatively small dimensions,
ation, the bearing surfaces are separated by an unbroken film of
light weight, and ease of replacement.
oil. Although sliding bearings are, in principle, the perfect type
CLUTCHES. Drum hoists used for unbalanced hoisting, or
of bearing, they are being replaced by roller bearings. The advan-
when operating from several levels, should have at least one of
tages of roller bearings are their low coefficient of friction, econ-
omy of space, simplicity of lubrication, practical elimination the drums clutch-connected to the drum shaft. With such a hoist,
of wear due to roller point contact, maintenance of accurate the clutched drum(s) is supported on the shaft through a sleeve
alignment, and their consistency in design and manufacture. For bushing and the clutch is used to transfer the motor torque to
a hoist, roller bearings having a rated life of 300,000 hours are the drum. In order to prevent the drum from rotating when it
generally selected. is unclutched, it is necessary that the clutch operating mecha-
GEARING. The hoist may be driven by either ac or dc electric nism and the drum brake be interlocked.
motors. Depending upon the hoisting speed, these motors may The clutch is operated through a two-, three-, or four-arm
be connected to the shaft directly or through a gear drive. Low- spider that is attached to the turning drum shaft. These arms are
speed motors may be connected directly; high-speed motors re- perpendicular to the shaft and are shifted parallel to the axis of
quire a gear reducer drive. the drum shaft. A clutch ring with matching teeth on its entire
With high-speed motors (300 to 900 rpm), power is transmit- periphery is bolted to the inside of the drum, and as the spider
ted from the motor to the hoist through coupling-connected is moved, these two sets of teeth are free to engage at any point
single or multiple-stop, helical gear reduction drives. Beerkircher on the circumference of the drum. Driving torque is then trans-
(1975) recognizes the following as consideration for the design mitted from the clutch to the drum through the bolts used to
and selection of a suitable gear drive: (1) size, type, speed, loca- hold the clutch ring to the drum flange.
tion, and number of motors; (2) size, type, speed, torque require- D RIVE MOTOR. Staley (1936) describes four methods of
ments, and location of hoist; (3) type of operating cycle; and (4) providing power to drive the hoist: (1) electric power, (2) steam,
physical restrictions. (3) compressed air, and (4) internal combustion engine. Electric
BRAKES. The braking system is required to decelerate, stop, power is by far the most common method and is the only one
and hold the hoist drum. This may be accomplished using electri- treated here.
1650 MINING ENGINEERING HANDBOOK
Table 17.5.1. Capital and Operating Cost Comparison controls). The mechanical portion of the hoist is designed to
Between M-G Set and Static Drive support the hoisting rope and its loads. The electrical portion of
the hoist is designed to provide sufficient torque to turn the drum
and raise or lower the rope, conveyance and payload.
In order to design and build a hoist, certain basic duty
information is required, namely, (1) hoisting distance, (2) pro-
duction rate (tons per hour), (3) maximum loads, and (4) types
of guides (wood, steel, rope). It can be shown that for a given
depth and production rate, there is an optimum load that results
in the lowest cost for the hoist.
Due to competition among suppliers and the tendency for
owners to purchase on the basis of lowest cost, it is possible that
the selected hoist will not have any excess capacity for the drum
and motor. This may mean that any change in the future, how-
ever slight, could not be accommodated. It is thus important that
the purchaser provide the supplier with the following additional
information: (1) ultimate use of shaft (men, materials, ventila-
tion, exploration, proposed phasing of expansion); (2) surface
The choice of electric motor drives lies between alternating- plant layout (type of headframe, bin location, etc.); (3) under-
current motors and direct-current motors, with direct current ground layout (levels, station, loading pocket); and (4) type of
being supplied from either a motor-generator (MG) set or from power distribution system available.
a silicon-controlled rectifier (SCR). The correct choice for a Although the complete detailed design of a hoist is not possi-
particular application is complex and requires advice from per- ble here, the following segments provide sufficient information
sons expert in this field. The principal factors to be considered to allow the reader to determine the best type of hoist for a
in selecting a motor are the mechanical configuration, electric particular set of conditions, together with some indication as to
power system, and economics. the power and current consumptions involved.
The ac motor has the advantage of having the lowest initial In order to determine the dimensions, capacity, and size of
cost and can use the power normally supplied. However, it has the mechanical components, the designer must determine certain
a higher starting torque and is difficult to automate. The ac basic criteria. These include:
motor generally requires a gear train to drive the hoist. 1. Hoisting speed, including acceleration, deceleration, and
The dc motor provides accurate and sensitive control, is maximum speed.
easily automated, and has a lower starting torque. The dc motor 2. Production rate, in tons per hour.
may be directly connected to the hoist, thus eliminating the gear 3. Maximum load to be hoisted.
drive and the space requirements of such a drive. 4. Hoisting distance.
The choice of power-conversion equipment is affected by the 5. Weight of payload and conveyances.
quality of the power system available, the ratio of the hoisting 6. Diameter of hoisting rope.
load (electrical) to the total plant load, and personal preference. After this information is determined, the designer can then
Table 17.5.1 shows an operating and cost comparison of motor- determine the capacity of the electric motor required to raise
generator sets and static drives for a mine hoist. and lower the loads in the required time.
HOIST CONTROL. Control systems are required to monitor The order in which the data should be generated is as follows:
the speed and location of each conveyance moving in the shaft. (1) duty cycle times, (2) hoisting rate, (3) payload and convey-
Whenever a conveyance exceeds a preselected, safe, speed- ance weight, (4) rope size, (5) drum dimensions, and (6) RMS
distance profile, the control systems initiates an action to prevent horsepower requirement.
the moving conveyance from striking a permanent obstruction These items are discussed in more detail in the following.
regardless of its speed or direction of travel. In addition, control DUTY CYCLE. The duty cycle describes the total time it takes
systems may be used to shut down equipment due to high op- to move a conveyance from the bottom of its wind to the top. It
erating temperatures, excess brake wear, rope slip, slack rope, is often depicted graphically as a time-speed diagram. In order
loss of power, etc. Discussion with hoist manufacturers reveals to be complete, the duty cycle must include periods of time
that the control systems for friction hoists are more numerous for initial creep, acceleration, full speed, deceleration, dumping,
and complex than for drum hoists. loading, and rest. The physical laws of uniformly accelerated
Because a full discussion of all of the systems (and their motion are used to determine the time required and the distance
variations) is beyond the scope of this presentation, it may be traveled once values for acceleration rate, final velocity, and
more useful to discuss the factors to be considered when re- shaft depth are known.
viewing various systems presented by suppliers. The three most The relationships between maximum speed, length of wind,
important factors to be considered, according to Eastcott (1977), and running time are summarized as follows (Fig. 17.5.3).
are (1) reliability, (2) simplicity, and (3) ease of adjustment. Accelerating time, seconds:

17.5.3.4 Hoist Selection


(17.5.1)
The size of a hoist is expressed by the drum dimensions,
horsepower rating of the motor, and rope pull. The following
segments show how these factors are calculated. Accelerating distance, ft or m:
Both drum hoists and friction hoists consist of two separate
machines, each of which must be designed to produce the desired
result. These types of machines are as follows: (1) mechanical (17.5.2)
(drum, drumshaft, gears, brakes), and (2) electrical (drive motor,
HOISTING SYSTEMS 1651
Friction Hoist (English units)
Cycle time = 0.359 L + 21.266
Friction Hoist (SI units)
Cycle time = 0.651 L + 22.294
The maximum velocities used above should not exceed the
following values for different types of guides:

Wood guides 35 ft/sec (10 m/s)


Steel guides 50 ft/sec (15.25 m/s)
Rope guides 70 ft/sec (20 m/s)

In addition, the designer should check any statutory restric-


tions on velocity and acceleration in the jurisdiction (country or
state) in which the hoisting system will operate.
P RODUCTION R ATE . The required production rate (or
Fig. 17.5.3. Time-speed diagram.
hoisting rate as it is sometimes termed) for a skip hoist is ex-
pressed in terms of the average tons per hour hoisted. If the mill
Decelerating time, seconds: operates on a different schedule to the mine, the production rate
must be adjusted to reflect the difference between hoisted tons
per day and milled tons per day. In addition, the moisture con-
(17.5.3) tent of the ore must be taken into consideration and included in
the quantity of material to be hoisted.
At this stage the concept of hoist utilization factor should
Decelerating distance, ft or m:
be introduced. In certain well-organized shafts, the utilization
factor can be as high as 0.92 but a more normal figure is 0.70.
(17.5.4) SKIP SIZE. After the cycle time and production rate are
known, the payload requirements for the skip are derived simply
as:
Full-speed time, seconds:
production rate production rate (tons/hr)
Payload p = =
(17.5.5) no. of trips/hr cycle time (s) × 3600 (s/hr)

Full-speed distance, ft or m: The approximate weight of the skip can be derived from one
of the following relationships:

(17.5.6) = 0.5 payload + 1500 in lb (17.5.8)

(0.5 payload + 680, in kg) (17.5.8a)


where a is acceleration in ft/s2 or m/s2, r is retardation in ft/
sec2 or m/s2, t1 is acceleration time in sec, t 2 is full speed time in
set, t3 is retardation time in sec, V is maximum speed in ft/sec or roughly, skip weight = payload.
or m/s, and L is length of wind in ft or m. Now if we call tr the Conveyance manufacturers should be consulted for more
time at rest (loading and dumping), accurate figures.
ROPE SIZE. After the weights of the payload and the convey-
Cycle time in seconds = t1 + t2 + t3 + tr ance are known, the correct size of rope can be selected by
applying the required (usually specified by statute) safety factor.
The type of rope must also be considered and is covered in more
(17.5.7) detail in 17.5.5.
For initial estimating purposes, the size of the rope required
may be selected by using the following relationships (de la Ver-
For initial estimating, the following assumptions may be gne, 1978).
used: 1. For a depth of 4500 ft (1370 m) or less:

(17.5.9)

(17.5.9a)
Substitution of the above values in Eq. 17.5.7 gives the total
cycle time for the hoisting operation:
Drum Hoist (English units) where W is rope weight in lb/ft or kg/m, P is payload in tons
Cycle time = 0.337 L + 21.388 or tonnes, s is mass of skip + mass of payload, Lu is maximum
Drum Hoist (SI units) rope length that can be suspended in ft or m, and Ls is Lu/5 in
Cycle time = 0.612 L + 22.439 ft or m.
1652 MINING ENGINEERING HANDBOOK
2. For depths greater than 4500 ft (1370 m):

(17.5.10)

(17.5.10a)

D RUM SIZE. Having determined the rope diameter, it is


possible to establish a hoist drum diameter. Minimum allowable
drum diameters are usually covered by legislation. In the United
States, drum and sheave diameters must be
1. Not less than 60 times the hoist rope diameter for slope
or inclined shaft applications.
2. Not less than 80 times the rope diameter if the hoist ropes
are 1 in. (25 mm) in diameter or greater, or not less than 60
times the rope diameter if the hoist ropes are less than 1 in. (25
mm) in diameter for vertical shaft applications.
3. Not less than 100 times the diameter for locked coil ropes.
For drum hoisting, the drum width and center to center
distance of the drums (for double drum hoists) must be calcu-
lated. The drum width may be determined from the following
equation:

(17.5.11)
Fig. 17.5.4. Horsepower constant (Anon., 1948). Conversion factor:
1 ft = 0.3048 m.
where capacity is length of rope to be stored in ft, W is drum
width in in., N is number of layers, D is drum diameter in in.,
and d is rope diameter in in. In SI units,

(17.5.11a)

where capacity is length of rope in meters, W is drum width in


cm, N is number of layers, D is drum diameter in mm, and d is (17.5.12a)
rope diameter in mm.
The center-to-center distance of the drums can be calculated Since the efficiency of the hoist varies according to depth, a
using the requirements for proper fleet angles (covered later) and graph has been developed from calculated data showing the
knowing the center-to-center distance of the hoisting compart- variation in the constant for different depths (Fig. 17.5.4).
ments being serviced. A more exact method of calculating the hoist motor horse-
In the case of tower-mounted friction hoists, the center-to- power is presented for both drum hoists and friction hoists as
center distance of the compartments must be equal to or less follows (Harmon, 1973).
than the drum diameter. If it is less, a deflector sheave must be Drum Hoist Horsepower Calculations— The equations
installed below the hoist wheel to deflect the ropes on one side needed to calculate horsepower at all points A through F, as
of the hoist into their correct position. In addition, the tail rope shown on the horsepower vs. time cycle graph in Fig. 17.5.5, are
also has a natural bending radius that must be considered. as follows (in English units only):
POWER REQUIREMENTS. After the duty cycle and rope size 1. Horsepower HP, required to accelerate the hoist system
have been determined, it is possible to calculate the hoist motor (motor inertia not included):
power requirements. A quick, approximate method follows.
(17.5.13)

where TSL is total suspended load and mass of hoist rotating


parts to be accelerated TSL = EEW (refer to Fig. 17.5.6) + SL
+ 2SW + 2R, SL is skip load, SW is skip weight, R is rope
weight, V is rope speed in fps, and Ta is total acceleration time
(i.e., ta to creep + ta from creep to full speed).
2. The horsepower HP, regenerated into the electrical power
system by suddenly decelerating is shown as a negative horse-
(17.5.12) power as it is created by energy pumped back into the power
system (all terms the same as in Eq. 17.5.13):
HOISTING SYSTEMS 1653
bottom when traveling at full speed at that particular point in
the shaft:

(17.5.15)

4. Running horsepower at the end of acceleration to full


speed:

(17.5.16)

where SLB is suspended load at shaft bottom =

5. Running horsepower at the end of full-speed-run period


and start of deceleration:

(17.5.17)
Fig. 17.5.5. Horsepower vs. time cycle, drum hoist (Harmon,
1973, p. 15-54).
where SLT is suspended load at shaft top =

6. Running horsepower at the end of deceleration:

(17.5.18)

7. The horsepower correction factor for motor and gearing


efficiency is less than 100%:

(17.5.19)

a. Peak accelerating horsepower of the hoist system:

(17.5.19a)

b. Full-speed horsepower at the end of acceleration period:

(17.5.19b)

c. Full-speed horsepower at the start of deceleration period:

(17.5.19c)

Fig. 17.5.6. Equivalent effective weight chart (EEW) (Harmon, 1973, d. Deceleration horsepower:
Fig. 15-39). Conversion factors: 1 ft = 0.3048 in., 1 lb = 0.4536 kg.

(17.5.19d)

(17.5.14) (1) Horsepower required to accelerate motor rotor (or ar-


mature):
where TR is total retard time, i.e., from full speed to creep speed
to stop. (17.5.20)
3. Running horsepower at the shaft bottom without acceler-
ation, that is, the horsepower to hoist a full skip load at the shaft
1654 MINING ENGINEERING HANDBOOK
(2) Horsepower required to decelerate motor rotor (or ar-
mature):

(17.5.21)

e. Total horsepower to accelerate the hoist system and mo-


tor rotor (or armature):

E = A + HP8 (17.5.19e)

f. Total horsepower to decelerate hoist system and motor


rotor (or armature):

F = D + HP9 (17.5.19f)

8. Finally, equations to calculate the RMS horsepower re-


quirement are as follows: Fig. 17.5.7. Horsepower vs. time cycle, Koepe hoist (Harmon,
a. dc motors: 1973, p. 15-54).

The equations used to calculate horsepower requirements at


all points (in English units only), A through E, as shown on the
(17.5.20a) horsepower vs. time cycle graph in Fig. 17.5.7, are as follows:
1. Acceleration horsepower:

b. ac motors:
(17.5.23)

where TSL = EEW + SL + 2SW + R, and R = (depth ×


rope weight) per ft × 2 × no. of ropes.
(17.5.20b) 2. Regeneration horsepower:

9. As a check on calculations, the following equation can be (17.5.24)


solved:
3. Running horsepower at shaft bottom:

(17.5.21)
(17.5.25)

4. Running horsepower at end of acceleration:

The relation should agree to within 1 or 2% with the RMS (17.5.26)


horsepower calculation. This check is simply an approximation
of the area under the horsepower vs. time-cycle diagram (Fig. The efficiency of the motor and drive system is greater than in
17.5.5) and represents work done, which is load times depth the drum hoist:
divided by 550 ft-lb/set-hp with an efficiency factor of 0.85
incorporated.
For unbalanced hoists, the only change is in the total sus-
pended load TSL. In this case,
5. Summary calculations:
TSL = EEW + SL + 1SW + 1R. (17.5.22) a. Acceleration peak of Fig. 17.5.7

Friction Hoist Horsepower Calculations—Horsepower calcu- (17.5.27a)


lations for friction hoists are similar to those for drum hoists but
a little simpler (several are identical). This is because the running b. Full-speed running horsepower:
horsepower after initial acceleration does not change as a result
of a constant rope weight (head rope plus tail rope) during travel (17.5.27b)
up the shaft.
HOISTING SYSTEMS 1655
c. Total retardation horsepower:

(17.5.27c)

(1) Running horsepower at end of full-speed run:

(17.5.28)

(2) Horsepower required to retard motor rotor:

(17.5.29)

d. Total horsepower to accelerate hoist and motor rotor:

(17.5.27d)

e. Total horsepower to retard hoist and motor rotor:

(17.5.27e)

6. RMS horsepower
a. dc motors:

(17.5.30a)

b. ac motors:

(17.5.30b)

The check for Eqs. 17.5.23 through 17.5.30b is the following:

Example 17.5.1. Drum Hoist Calculation (Harmon, 1973)


(in English units): Determine RMS hp of a hoist system using
an ac motor and hoisting two 10-ton skips in balance in a 1000-
ft shaft. Rope speed is 20 ft/sec. Skip-weight/skip-load ratio =
0.75. Acceleration rate is 2.0 ft/sec2; deceleration, 2.0 ft/sec2;
rest period is 10 sec. The hoist uses two l-in. dia. round-strand
ropes at 3.78 lb/ft. The hoist is a 15-ft dia. single-drum unit. The
hoist duty cycle, in seconds, is

1. Accelerate to creep ........................................................... 1.0


2. Creep at 2.0 ft/sec2 .......................................................... 2.0
3. Accelerate to full speed .................................................... 9.0
4. Travel at full speed........................................................... 39.4
5. Decelerate to creep speed................................................. 9.0
6. Creep at 2 ft/sec2 ............................................................. 4.0
7. Decelerate to stop ............................................................. 1.0
8. Rest (load and dump) .................................................... 10.0
1656 MINING ENGINEERING HANDBOOK

Check:

(17.5.21)

Then

Therefore, the check indicates that the solution will be accu-


rate to within 2%.
The RMS hp for the ac motor

or approximately 1000 hp or a difference of 1.78%, which is within the allowance of 1 to


Hence, for the skip load, skip weight, rope, and rope speed 2%; therefore, the solution is accurate.
used in this example, a 1000-hp ac motor would be sufficient for
this duty cycle.
Example 17.5.2. Friction Hoist Calculation (Harmon, 1973)
(in English units): Determine the RMS hp for an ac drive running
a friction hoist operating 5-ton skips in balance in a 1000-ft shaft
with the following given information:
Given: 1. Hoist uses four l-in. dia. F.S. ropes at 1.80 lb/ft
2. Rope speed = 20 fps
3. Wheel diameter = 10 ft
4. Skip-weight/skip-load ratio = 1.2 17.5.3.5 Number of Hoists Required
5. Duty cycle Ta = 10 sec
T F S = 39.75 sec Since most shafts are designed to be multipurpose (i.e., for
Tr = 8 sec ore, waste, personnel, materials), one of the first items to be
Rest = 10 sec considered is the number of hoists required to meet all the
HOISTING SYSTEMS 1657
hoisting requirements. The best approach is to list all require- Table 17.5.2. Hoisting Time Used For Maintenance and
ments, determining the daily hoisting time required for each. If Inspection of Shaft and Equipment
the total is more than 24 hours, two hoists must be employed;
Time
or if close to 24 hours, compromises made. The items to be Items (h) Remarks
included in the list are as follows: (1) number of ore hoisting
trips per day, (2) number of waste hoisting trips per day, (3) Shaft, conveyance & rope inspection & signal
number of material trips per day, (4) number of man trips per bell test Weekly
day, (5) time required for hoist, shaft, rope, and conveyance Sheave wheels inspection W eekly
Hoist inspection W eekly
inspections as required by law and good maintenance practices,
(6) time required for internal movement of personnel, and mate- TOTAL WEEKLY:
rials, and (7) idle time, per day, per week. Rope maintenance (lubrication) Monthly
After the number of trips has been determined, it is then TOTAL MONTHLY:
necessary to calculate the length of time or duty cycle for each Electromagnetic test to ropes and attachments Quarterly
trip (see 17.5.3.4). Drop test Quarterly
ORE HOISTING TIME. In order to determine the number of TOTAL QUARTERLY:
hours per day required to hoist ore, the following should be Note: If the above is interpreted as unavailability of the hoists for
known: (1) planned tonnage to be hoisted daily, and (2) produc- production hoisting, then the average time lost per day at the typical
tion rate for the skip hoist in tons per hour. This may be ex- hoisting facility can be taken as one hour.
pressed as follows:

time required for ore hoisting (hours/day)

daily ore production (tons/day)


= (17.5.32) federal or local authorities, vary for each country and jurisdic-
hoist production rate (tons/hour) tion, the following procedures are carried out on most hoisting
facilities:
WASTE HOISTING TIME. Waste hoisting time is calculated 1. Shaft and conveyance (including shaft signal) inspec-
in a similar manner as for ore hoisting. When calculating daily tion—once per week.
waste production, consideration should be given to using waste 2. Hoist (electrical and mechanical components) inspec-
underground as backfill as this will reduce the daily waste tion—once per week.
hoisting requirements: 3. Rope and rope attachments inspection—once per week.
4. Rope maintenance (including attachments)—once per
time required for waste hoisting (hours/day) month.
5. Electromagnetic test to ropes—once every three months.
6. Conveyance drop test—once every three months.
daily waste production (tons/day)
= (17.5.33) In order to allow maximum time for ore hoisting, it is normal
hoist production rate (tons/hour) practice at most major mines to carry out maintenance and
repairs of a major nature on the weekend when the requirements
MATERIALS AND SUPPLIES H OISTING T IME . In order to for lowering personnel and material is at a minimum, unless
determine the number of hours per day required to hoist materi- such repairs are deemed necessary for the safe running of the
als and supplies, the following information should be known: (1) facilities. However, statutory maintenance and inspections con-
number of material and supplies trips per day, and (2) hoist duty sume some of the time which would have been available other-
cycle, defined as the total time it takes for the hoist to move a wise for hoisting. For a typical mine, the average time lost for
conveyance from one elevation to the next: this activity can be approximated, as shown in Table 17.5.2.
INTERNAL HOISTING TIME. In some mining operations it is
time required for materials and supplies (hours/day) necessary to transfer personnel, materials, and equipment be-
tween levels using the shaft hoisting equipment. The work re-
N × T quired to carry out these tasks is termed internal hoisting, and
= (17.5.34)
3600 the time required to complete this type of hoisting can best
be obtained through personal experience or by discussion with
where N is number of material trips, and T is cycle time per trip operators of similar mines.
in sec. IDLE TIME: HOIST UTILIZATION. It is a fact that it is not
PERSONNEL HOISTING TIME. The projected daily employee possible to plan to operate 100% of the time and that some idle
requirement that must be lowered and raised through the time must be provided in any hoisting schedule. The amount of
hoisting facilities is either known or calculable. Using the daily time to be allowed is generally a matter of experience on the part
manpower data, the hoisting time required for transporting per- of the designer. However, the total operating time scheduled
sonnel to and from underground is calculated after determining during planning stages should not exceed 70% of the total op-
the cycle time, using Eq. 17.5.7. erating time available, that is, 16.8 hr/day (Harvey 1973a).
In estimating the cycle time, consideration is given to the The hoist utilization factor Hu is defined as:
following: (1) cage capacity, (2) number of working levels under-
ground to which personnel are to be transported, (3) hoisting No. of trips actually made in a month
Hu =
speed to the first level, then between each level to conform with No. of trips possible on the basis of cycle time
the mining regulations, (4) loading and unloading time (per (17.5.35)
level), and (5) idle time (per cycle).
MAINTENANCE AND INSPECTION TIME. Although statutory In certain exceptionally well-organized shafts, utilization
maintenance, inspections, and test requirements, as regulated by factors as high as 0.92 have been achieved, but a more reasonable
1658 MINING ENGINEERING HANDBOOK
figure of 0.70 should be adopted. With multipurpose hoists, the
utilization factor will be much lower.
SUMMARY. After the daily hoisting time for each of the
above time subcomponents has been calculated and a hoist utili-
zation factor estimated, a total daily hoisting time T can be
determined. If this total is greater than 24 hours, two (or more)
hoists are required:

(17.5.36)

where To is ore hoisting time, Tw is waste hoisting time, Ts is


materials hoisting time, T p is personnel hoisting time, T m is
maintenance hoisting time, Ti is internal hoisting time, and Hu
is hoist utilization factor.

17.5.4 SHAFT CONVEYANCES AND


ACCESSORIES
The most common shaft conveyances considered are skips,
cages, and counterweights. Accessories consist of loading pock-
ets, spill pockets, and arrestor gear.
Skips are used to hoist broken ore and waste from the mine.
Cages are used to raise and lower personnel, material, and equip-
ment. Counterweights may be used in balance with either skips
or cages. Loading pockets can improve the efficiency of hoisting
systems by ensuring that the optimum amount of material is fed
to the skip during each cycle. Arrestor gear is provided in the Fig. 17.5.8. Bottom dump skip, swing-out body (Penning,
headframe and shaft bottom for friction hoist systems to protect et al., 1977).
personnel, the hoist, and the conveyances in the event overtravel
occurs at the end of the hoisting cycle.
body to rotate around the shaft as the skip is being hoisted
17.5.4.1 Description of Skip Hoisting through the dump. The design of the tipping path is complex
Skipping, as described by Souter (1973), consists of filling, because the payload is being discharged as it moves along the
hoisting, dumping, and returning to be filled again. The ore and path. The horizontal and vertical forces to be considered, ac-
waste may be crushed or uncrushed, filling may be volumetric cording to Harvey (1973a), are dependent upon the rate at which
or by weight, and the operation may be manual or automatically the skip enters the dump, the inertia of the skip plus payload,
controlled. During filling, the skip is subjected to high dynamic the horizontal acceleration (which itself is dependent upon the
loads, and depending upon depth, a certain amount of rope angle of the tipping path), and the static forces.
stretch occurs. Although chairing of the skip is possible, this The advantages of Kimberley skips are (1) there is less shaft
practice can also result in higher impact loading, difficulties with spillage when handling fine or wet material, and (2) they handle
slack rope, and the danger of leaving the chairs in the shaft, larger pieces for a fixed cross-sectional area. The disadvantages
which could cause collision. are (1) the capacity is limited due to the height-to-width ratio,
In order to permit hoisting at high speeds, skips are guided (2) the payload ratio is usually lower particularly with sticky
as they travel in the shaft. Difficulties with guides due to mis- material that tends to build up in the bottom, (3) they generally
alignment or loosening generally result in lower hoisting speeds impose higher stresses on the headframe and bins, and (4) they
and, correspondingly, reduced production rates. require more headframe height to dump.
Skips may be dumped at any point in the shaft, although the SWING-OUT BODY. The swing-out body skip also consists of
most common location is in the headframe. Dumping is usually a bail frame, a shaft, and the skip body. In this case, the skip
accomplished by means of scrolls located at each side of the skip body is suspended from the shaft and the skip dumped by means
compartment at the dump. A roller on the side of the skip body of rollers mounted on each side (at the bottom) of the body,
(for swing-out body skips) or on the door (for fixed body skips) engaging a scroll and causing the body to pivot away from the
engages the scroll and causes the skip to be dumped. In the Sala- bail into the dump. At the same time, a discharge door, which
type skip, an air cylinder actuates the dump door. forms the bottom of the skip, opens and the material is dis-
charged (Fig. 17.5.8).
There are three common types of swing-out body skips.
17.5.4.2 Types of Skips
These are the Jeto, Saunders, and Rollamatic. The differences
There are three main types of skips in use today: (1) the among these three types is the mechanism involved with the
overturning, (2) the swing-out body, and (3) the fixed body. opening and closing of the door and the location of the door
OVERTURNING. The overturning or Kimberley skip consists hinge. Safety latches have been used on all three types. This is
of a bail frame, a shaft to support the skip, and the skip body to prevent the skip from opening in mid-shaft, particularly when
itself. The skip body rests on the shaft. The skip is dumped traveling empty.
through the action of a bull wheel, mounted on each side (at the For bottom-dumping skips in general, the cross-sectional
top) of the skip body, engaging a scroll and causing the skip area is partially determined by the size of material to be handled.
HOISTING SYSTEMS 1659
the door to swing open. In the Sala skip, the door is operated by
means of air cylinders mounted on the skip body. Compressed
air to operate the cylinders is provided through a yoke which is
permanently mounted in the headframe and picked up by the
skip as it enters the dump.
The cross-sectional area of fixed-body skips is determined
by the size of the material to be handled. Since fixed-body skips
can be built without a bail, the cross-sectional area of the skip
can be increased by 10 to 15% when compared to skips with a
bail for the same sized compartment.
The advantage of fixed-body skips are (1) the skip can load
and dump through the guides, (2) the skip has no bail, thus
allowing a larger cross-sectional area to be used for the skip
body (this can reduce the overall length of the skip for a given
capacity), (3) the only moving part is the door that forms its
own dump chute, (4) they are suitable for fixed or rope guides,
(5) a hinged floor at the top can convert the skip to a personnel
and materials cage, (6) the skip requires less travel distance to
open the door, (7) this type of skip places less stress on the
headframe, skip body, and ropes during the dumping operation,
and (8) there is less spillage at the door. The disadvantage of this
type of skip is that its bailess construction requires adequate
design and inspection during operation.

17.5.4.3 Skip Design Considerations


The process of skip design has been well documented by
Penning (1977). When selecting a particular skip, the compo-
nents to be considered during the evaluation process include (1)
design methods, (2) factors of safety, (3) body, (4) door, (5)
crosshead, (6) bail, (7) guide rollers, and (8) guide shoes.
DESIGN METHODS. Skip components may be designed on
the basis of experience and practice or through analytical meth-
Fig. 17.5.9. Bottom dump skip, fixed body (Penning et al., 1977). ods that define the loading being placed on the various compo-
nents of the skip. The types of loading to be considered are (1)
dynamic loading, caused by filling, hoisting, and dumping the
The door opening is sized to be at least three times the dimensions skip, and (2) static loading. Factors of safety are usually specified
of the largest piece to be handled. This is to prevent possible by legislation.
bridging. Other factors to be considered are the length of the BODY. The skip body is designed as a rectangular box with
skip, the available space, and the hoist rope center-to-center stiffeners. The type of material, its thickness, and the stiffener
distance. size and spacing are the variables to be examined. Particular
The advantages of swing-out body skips are (1) they have attention must be given to the area on the back side of the skip
more favorable payload ratio than the overturning type, (2) the that receives impact and abrasion from loading.
tipping path is less complex than for overturning skips, and (3) Skip bodies are usually lined with abrasion resistant (AR)
the dumping distance in the headframe is less than for overturn- material to increase its overall life. Two types of steel or elasto-
ing type. The disadvantages are (1) muck build up at the hinge meters have been used for skip liners. AR steels are members of
point in the door can prevent the door from closing and could the high-strength, low-alloy family of steels. Manganese steels
place large forces on the headframe scroll or skip body during are used because they have the ability to work-harden during
the closing cycle, (2) with wet material, there could be spillage service. Elastometers have the advantage of reduced weight,
or dribble from the door lip, and (3) the bottom door mechanism less ore sticking and buildup, corrosion resistance and ease of
is more complex than the fixed body type. handling during replacement.
FIXED-BODY. In fixed-body skips, the body of the skip re- The use of aluminum is also increasing, particularly in drum
mains fixed and does not move out of the confines of the skip hoist applications. Such skips have a lower mass and allow a
compartment during dumping. Instead, a door at the bottom of higher payload to be hoisted.
the body swings open to form a chute and allows the material D OORS. Both swing-out body and fixed-body skips have
to discharge into the dump bin. This type of skip may or may doors at the bottom of the skip. Doors must be designed to
not have a bail (Fig. 17.5.9). withstand the impact of large pieces falling on the floor during
There are several types of fixed-body skips. The most com- loading and the static loading of a full skip as well as abrasion
mon are the Rolla-Chute, the Arc-Door, and Sala-type skip. The during unloading.
difference among these types is the mechanism involved with the With swing-out body skips, the door is hinged at the back,
opening and closing of the door. In the Rolla-Chute skip, the and there are several problems associated with leakage paths
door is held closed by means of a door latch. When the skip between the door and the body. These door leakage problems
enters the headframe, a latch track releases the latch, allowing may be solved through the use of rubber sheets, flexible materi-
the door to open and the material to discharge. With the Arc- als, or special modification of plates at the door. Fixed-body skips
Door chute, a roller is mounted on each side of the door. When generally have fewer problems with leakage or door closure. One
the skip enters the skip dump, the roller engages a scroll, causing situation that may cause problems to both types exists when the
1660 MINING ENGINEERING HANDBOOK
skip is loaded on the side opposite the dump site. In this case, a fixed-body is preferred because it is faster operating, there are
vertical stop may be placed for the dump roller to react against. no large masses to be moved, and it can be easily automated.
Doors are made and lined with the same material as used in the The loading pocket is furnished with pneumatically or hy-
body. draulically controlled gates. The bottom of the loading pocket
CROSSHEAD. The crosshead fastens the bail to the rope. It is usually inclined at an angle of 60° or greater to ensure rapid
must be designed to take all the skip loads, including accelera- loading and complete clean out.
tion, impact and service factors. The location of the crosshead With balanced skip hoisting, two loading pockets are pro-
above the skip is particularly important during loading. It should vided, one for each skip.
not interfere with the flow of muck from the loading pocket. The SKIP FEED CHUTE. A feed chute is required to direct the
rope stretch in deep mines can be several feet and must be material from the measuring pocket to the skip. The angle of
considered. It can be calculated from the following relation: inclination of the feed chute is usually 60° or greater.
The clearance between the chute and the skip is approxi-
mately 3 in. (75 mm). It has been suggested that the ratio of the
chute discharge width to the skip width should not exceed 0.7
for skips up to 4.25 ft (1.3 m) wide and 0.8 for skips up to 6 ft
(1.8 m) wide. To reduce spillage, the sides of the chute should
be slightly converged at the lip.
(17.5.37) AUTOMATIC LOADING. Automatic loading of skips is used
to improve the efficiency of hoisting systems and to reduce labor
B AIL. During hoisting, the bail supports the body pivot, requirements. Efficiency is improved by ensuring that each skip
prevents the body from moving, and supports the door. At the receives the required load without overloading or underfilling.
dump, the bail is subjected to horizontal loading and supports Manpower is reduced when automatic loading is used in conjunc-
the door and is thus subjected to both bending and axial loading. tion with automatic hoisting. In order that automatic loading
GUIDE ROLLERS. The purpose of guide rollers is to keep the can be accomplished, a minimum of three control systems must
guide shoe off the guides. This in turn results in a smoother ride, be included (1) a means of measuring the weight and/or volume
reducing dynamic loading between the skip, guide, and buntons of material in the measuring pocket, (2) a means of opening and
during travelling. closing feed chutes to fill and empty the measuring pocket, and
When selecting guide rollers, there is usually a conflict be- (3) a logic system to ensure that the above operations are carried
tween a large-diameter tire, adequate shaft clearance, and the out in the correct sequence to prevent such systems failures as
cross section of the skip. Left unresolved, the final design usually double loading and dumping into an empty shaft. With auto-
results in a small-diameter tire. Such tires need frequent replace- matic hoisting, the logic system extends to the operation of the
ment. The range of tire sizes used are from 6 in. (152 mm) to 14 hoist.
in. (356 mm) in diameter. Tires are rated on a load-mile per hour
basis.
GUIDE SHOES. Guide shoes are used on vertical conveyances
17.5.4.5 Spill Pockets
to keep the main structure from being worn away by the guides. Despite the precautions taken to prevent spillage during the
They are considered as expendable items to be replaced when loading and dumping of the skips, a certain amount is inevitable
they are too worn for further use. Clearance between the guide below the loading pocket. This spillage may be confined to the
and guide shoe varies from ¼ to ½ in. (6.4 to 12.7 mm). Guide hoisting compartment by lining these compartments down to a
shoes can be made from many materials, such as cast iron, mild spill pocket. According to data collected by Souter (1973) from
steel, hardened steel, AR steel, brass, or bronze. The amount of a number of mines in South Africa, the amount of spillage,
wear to be expected is directly proportional to the load on the expressed as a percentage of tons hoisted, varied from 1.5 to 5 %.
guide shoe and inversely proportional to the hardness of the The larger amounts of spillage were associated with manually
softer material. operated systems handling uncrushed material.
There are two commonly used methods of handling spillage
17.5.4.4 Loading Pockets in modem hoisting systems. One method consists of installing
deflectors in the shaft below the underwind position of the skip.
At the loading pocket, ore and waste are transferred from These deflectors direct spillage into a pocket similar to the load-
the mine to the skip. The equipment and systems installed can ing pocket. The spillage pockets are then cleaned as required.
vary from simple manually operated to complex and automated. With drum hoisting, this system can be used at any elevation in
There are two basic types of loading systems available. These the shaft. With a friction hoist, the spillage pocket must be
involve measurement by weight or by volume. located below the tail rope loops, and a second conveyance such
The criteria to be considered in the design of all systems as the cage must be used to handle spill. The second method of
include (1) response time, (2) loading time, (3) accuracy of mea- handling spillage consists of developing a ramp from the lowest
suring devices, (4) operating and maintenance costs, and (5) elevation to the shaft bottom. In this system, any spillage falls
amount of spillage. directly to the shaft bottom, where it can be mucked out. Regard-
Although details can vary, each system has certain common less of the system used, particular care is required with friction
elements: (1) pocket chute with control gates, (2) measuring hoist systems to ensure that the tail ropes do not become entan-
pocket, and (3) skip feed chute with control gate. gled or affected by the build-up of spill in the shaft.
P OCKET C HUTES. Pocket chutes are generally fabricated
from steel with liners. They have an angle of inclination of 45 to
17.5.4.6 Cages
55°. Chute gates can be pneumatically or hydraulically controlled
and may be guillotine, ball and chain, or radial type. Cages are used primarily to handle personnel and materials
MEASURING POCKET. The measuring pocket construction is entering and exiting from the mine. In some instances, cages are
similar to that of the skip body. There are two types of fabricated used to hoist cars loaded with ore and waste. The design and
pockets available, the swing-out body and the fixed-body. The construction of cages are similar to those used for skips.
HOISTING SYSTEMS 1661
A cage is merely an enclosed box, opened by door(s), and ported by the conveyance as it travels through the arrestor zone.
suspended from a hoisting rope. The dimensions and capacity of these devices are located in the headframe and at the shaft bot-
the cage are determined by the quantity, volume, weight, and tom. They rely on friction between the device and the guides to
dimensions of the materials and/or items to be handled. decrease momentum.

17.5.4.7 Counterweights 17.5.5 ROPES


In some balanced hoisting systems, a counterweight may be
used with either a cage or skip. Since counterweights serve no The basic purpose of the hoisting rope is to connect the
conveyance to the hoist. It is selected primarily on the basis of
functional purpose other than to provide for balanced hoisting,
their dimensions are quite variable. They are usually designed safety, compatibility, life, and costs. Safety requirements when
hoisting personnel, or where persons may be endangered by
to fit the space available.
hoists and their appurtenances, are usually determined by legisla-
tion. The life of a rope is usually expressed as the number of
17.5.4.8 Safety Devices trips it will make; it is affected by rope construction, hoist and
In North America, different types of safety devices are used sheave dimensions, type of loading, shaft atmosphere, and main-
for drum hoists and friction hoists. tenance. Costs of initial purchase, maintenance, and costs of rope
DRUM HOIST. With drum hoists, both excessive overwind changing including lost production are normally considered. In
and rope breakage can occur. Of these two types of accidents, addition to hoisting ropes, the hoisting systems designer must be
rope breakage is considered the most serious, and provisions to concerned with balance ropes (for friction hoist application),
bring the conveyance to a safe stop in the event of a rope break guide ropes, rubbing ropes, and rope attachments.
is required by legislation. The type of rope construction commonly used for various
The most common safety device used is the safety dog. A hoisting applications are as follows:
pair of dogs is installed at the top of the conveyance at each
guide. During travel, the tension in the hoisting rope keeps the Rope Use Typical Rope Construction
dogs open. Should the rope break, or become slack, a large spring drum hoist ropes round strand—Lang lay flattened
and series of levers cause the dogs to penetrate the guide and flattened strand 6 × 27 FC
stop the conveyance. full locked coil
FRICTION H OIST. In multiple rope friction hoist installa- friction hoist rope locked coil
tions, the probability of all hoisting ropes breaking is small. flattened strand
Therefore, overtravel is considered to be more serious, and provi- balance ropes non-rotating 18 × 7 nylon core
sions to bring the conveyance to a safe stop in the event of non-rotating 34 × 7 nylon core
overtravel are required. guide and rubbing ropes half locked coil
The most common device used is arrestor gear, consisting of shaft sinking non-rotating 18 × 7 IWRC
steel frames supported in the hoisting compartment and trans- full locked coil
slings round strand 6 × 25 IWRC
In this segment, a general description of the various types
of ropes, plus the factors to be considered to ensure correct
application and selection, is presented.

17.5.5.1 Rope Construction


In the construction of most wire ropes, a number of individ-
ual wires are wound around a core to form a strand. The strands
are then wound around a core to form the rope. Fig. 17.5.10 is
an exploded view of a rope showing the components.
Some ropes are constructed without strands by winding con-
secutive layers of wire around the inner layers.
The factors to be considered in rope construction are (1) the
wire, (2) strands, (3) cores, and (4) lay. By varying these factors,
ropes with different characteristics can be constructed.
WIRE STRENGTHS AND PROPERTIES. Wire for manufactur-
ing wire rope is available with varying strengths up to 360,000
psi (2480 MPa). It is thus possible to manufacture ropes of
different strengths for the same diameter and the same construc-
tion. Generally speaking, as the wire strength increases, fatigue
life and rope life tend to decrease.
The most common wire used in mining is improved plow
grade 110/120. Wire is also available in different shapes with
round, full-lock and half-lock being the most common. Galva-
nized wire is available for wire ropes and should be considered
if ropes are being replaced due to corrosion.
STRANDS. Individual wires are twisted together to form
strands. There are four common types of strands: (1) round
strands, (2) triangular strands, (3) oval strands, and (4) flat
Fig. 17.5.10. Rope components (Anon., 1980a). strands.
1662 MINING ENGINEERING HANDBOOK

Fig. 17.5.11. Rope lay (Anon., 1980a). (a) Lang lay: wires and strands laid in same direction; (b) ordinary lay: wires and strands laid
in opposite directions.

CORES. The purpose of the core is to take the internal com- Regular lay ropes have the wires in the strands laid in such
pressive stresses. The largest of these stresses is due to the ten- a manner that the wire crowns run approximately parallel to the
dency of the rope to flatten when bent around a sheave or rope direction. Such ropes have good resistance to kinking and
thimble. twisting and are able to withstand considerable crushing and
Natural fiber cores (FC) such as sisal and hemp are suitable distortion. Regular lay should be used for slings and balance
for most applications. Synthetic fiber cores such as nylon and ropes.
polypropylene are used in conjunction with high-strength wires With Lang lay, the wires are on the diagonal of the strand
and in corrosive applications. and are exposed for a greater length. This arrangement gives
Independent wire rope cores (IWRC) are stronger than fiber greater abrasion resistance and a more flexible rope. Lang lay is
cores. They add to the strength of the rope and reduce the commonly used for hoisting ropes on drum hoists. Ropes with
stretch; fatigue life is reduced, however. this lay slide into position on a drum better than regular lay
LAY. The lay of a rope is the manner in which the wires are ropes. Because of the tendency to untwist, these ropes should
twisted into the strand and the strands are twisted into ropes. not be used with swivels or single-part hoisting without guides.
There are three properties used to describe lay: (1) length (or
pitch), (2) direction (right or left), and (3) type (regular or Lang).
17.5.5.2 Hoist Ropes
Fig. 17.5.11 illustrates the direction of lay for regular lay
and Lang lay, which are the usual lays used in mining ropes. The three types of ropes generally considered for hoisting
The lay length is the distance from one crown to the next of a ropes are round strand, flattened strand, and locked coil. Typical
particular wire. properties for these types of rope are given in Table 17.5.3.
Right lay is usually used unless special circumstances require ROUND STRAND ROPES. Round strand ropes consist of a
the use of left lay. Some drums are designed to take left-hand number of strands, each consisting of wires, wound around a
lay ropes and should be checked prior to purchasing. Fig. 17.5.12 core. The rope designation (e.g., 6 × 27 FC) indicates the num-
shows how to select the lay of the rope required for a drum. ber of strands (6) and the number of wires (27) per strand; FC
HOISTING SYSTEMS 1663

Fig. 17.5.12. Selection of correct direction of lay for a drum hoist (“Wire Rope Users Manual,” 2nd ed., Committee of Wire Rope
Producers, American Iron and Steel Institute, undated).

Table 17.5.3. General Wire Rope Data for Standard Tensile Wire, Nominal Breaking Load of 120 Long Tons/ln.2

stands for fiber core. The greater the number of wires in a strand, 2. The rope has a greater crushing strength and can be used
the greater the flexibility of the rope, but the smaller wires wear in multilayer winding.
faster and are more easily damaged. 3. The wire density in the rope is higher. Thus for the same
FLATTENED STRAND. The properties of round strand rope diameter, more steel area is available, and the rope has a higher
have been improved in flattened strand rope by making the strength.
strands triangular instead of round. The benefits of this are FULL LOCKED COIL. This type of rope is completely differ-
1. An increase in the number of wires in contact with the ent from both round and flattened strand rope. The center or
sheaves and drums increases the contact area, thereby reducing core of the locked coil rope consists of a concentrically laid strand
the pressure and lessening wear on ropes, sheaves, and drums. of round wires. Around this core lies one or more layers of
1664 MINING ENGINEERING HANDBOOK
shaped wires, the outer layer always being interlocking. The
shape of all shaped wires in a locked coil rope depends on the
rope diameter and its end use.
Locked coil rope construction has some very definite advan-
tages. In a locked coil rope, there is no initial twist in the rope
so the wires do not tend to untwist under load. Locked coil ropes
have a higher breaking strength than stranded rope for equal
diameter and for the same nominal strength grade. Because of
their smooth external surface, reduction in strength caused by
frictional wear on drums or pulleys is much lower. Also, because
of their design, locked coil ropes are less subject to rotation and
stretch than stranded ropes.

17.5.5.3 Rope Selection


For the initial selection, four requirements should be consid-
ered: (1) strength, (2) resistance to being fatigued, (3) abrasion
resistance, and (4) resistance to crushing or distortion. The
choice should be made after correctly estimating the relative
importance of each of the above requirements. Naturally,
strength is the overriding concern.
Design considerations should provide economical and effi-
cient rope service while maintaining the necessary degree of
safety to both personnel and equipment. These objectives are
best met by accepting the following guidelines:
1. Design the hoisting system with good rope life as an
objective.
2. Specify ropes to be compatible with the required factor
of safety to match the design of hoist, shaft, headframe, and
sheave.
3. Design rope storage and handling procedures.
4. Design correct rope installation procedures.
5. Design correct and adequate maintenance procedures.
6. Design and institute an inspection procedure. Fig. 17.5.13. Fleet angle calculation.
R OPE SELECTION FOR D RUM H OIST. This segment dis-
cusses the selection of the size of rope to meet operating condi-
tions for drum hoists for vertical and slope applications. In the
United States, the Code of Federal Regulations (CFR) (Anon., Drum and sheave tread diameters should be (1) not less than
1989) specifies minimum requirements for the following items 60 times the hoist rope diameter for slope or inclined shaft
that are relevant to drum hoisting: (1) factor of safety, (2) ratio applications, (2) not less than 80 times the hoist rope diameter
of drum/sheave diameter to rope diameter, and (3) fleet angles. if the hoist ropes are 1 in. (25 mm) in diameter or greater, or
An example calculation of hoist rope selection concludes this not less than 60 times the hoist rope diameter if the hoist ropes
discussion. are less than 1 in. (25 mm) in diameter for vertical shaft applica-
Factor of Safety—Mandatory requirements by the Mine tions, and (3) not less than 100 times the hoist rope diameter for
Safety and Health Administration (MSHA) are covered in CFR. locked coil ropes.
Sections 55/56/57.19-21 and 75/77.1431 for metal and non- Fleet Angles—The mandatory regulation (Anon., 1989)
metal open pit mines, sand, gravel and crushed stone operations, states, “Fleet angles on hoists installed after Nov. 15, 1979, shall
metal and nonmetal underground mines, and underground coal not be greater than ½° for smooth drums or 2° for grooved
mines, respectively, require the following minimum rope drums.” (CFR 56.19-37). However, to increase rope life manu-
strengths, where L is maximum suspended rope length in ft: facturers of hoist ropes commonly recommend a maximum fleet
angle of 1°20' and a minimum fleet angle of 0°30' to insure rope
winding drum ropes less than 3000 ft long: minimum rope will crossback and start a new layer without piling. Computa-
strength = static load × (7.0 – 0.001L). tions of optimum total fleet angle are given in ANSI M 11.1 (Fig.
(17.5.38) 17.5.13).
Size Calculation—The procedure for sizing a rope for a drum
winding drum ropes 3000 ft long or greater: minimum rope hoist consists of the following steps:
strength = static load × 4.0. Step 1. Tabulate operating conditions.
(17.5.39) Step 2. Calculate personnel load.
Step 3. Calculate load with conveyance at collar. (Note: US
practice only requires check of lowest level.)
Drum/Sheave Diameter—Mandatory requirements for Step 4. Calculate load with conveyance at lowest level.
drum and sheave diameters have now been removed from the Step 5. Select rope and check safety factor using ANSI
regulations, but insofar as the old regulations are still common M11.1 or CFR Title 30.
practice in the United States as well as Canada and Europe, they Step 6. Check other hoisting components.
are repeated here. Example 17.5.3. Given the following drum hoisting system:
HOISTING SYSTEMS 1665
Step 1. Assumed operating conditions. ponents of the hoisting system, the designer may decide to reduce
the weight or payload of the cage in order to use a smaller-
Height, collar to head sheave diameter rope with higher tensile-strength wire. Alternatively, a
Depth of lowest level decision may be made to use a larger-diameter rope and thus
Cage capacity increase rope life.
Cage capacity materials R OPE SELECTION FOR FRICTION H OIST. A friction hoist
Cage weight differs from a drum hoist in that the rope is not wound on and
Weight of rope attachment off the drum but passes around the drum, with the drum friction
providing the force necessary to move the rope. Friction hoists
may be mounted in the headframe tower directly over the shaft,
Select the proper hoisting rope and determine factors of safety or they may be mounted in a hoist house at ground level. The
SF. friction hoist drum is often referred to as a wheel.
Solution. A specific friction hoist application can have a number of
Step 2. Calculate man load. acceptable hoist rope/tail rope alternatives. As the selected num-
60 persons @ 200 lb = 12,000 lb ber of hoist ropes increases, their diameter can become smaller.
Step 3. Calculate load with conveyance at collar. This also means the hoist drum can have a smaller diameter,
(Not required in US practice.) which affects the center-to-center distance of the compartments.
Assume 1-1/2 in., 6 × 27 flattened strand rope. Table 17.5.3 Because of this, it is important that the hoisting system designer
shows the properties of this rope. ensure compatibility with the other components of the hoisting
Assume owner elects to employ factors of safety from 57.19a- system (i.e., shaft, headframe, conveyance).
21 of the CFR when hoisting materials. Regulations and other calculations and considerations in-
Thus suspended load is volved in rope selection for friction hoists are discussed here. An
example that considers factors of safety and other criteria is then
cage weight presented. When an overall hoisting system is designed by a hoist
pay load manufacturer, it is in the owner’s best interest to carefully check
rope attachments the proposal as there have been instances where undue emphasis
130 ft rope @ 3.95 lb/ft has been placed on the capital cost of the hoist at the expense of
Total: higher operating costs of the overall system. These trade-offs in
system selection must be carefully weighed.
Thus minimum breaking strength = suspended load × SF When determining a factor of safety for friction hoist ropes
required = 28,814 lb × (7 – 0.001 in North America, it is common practice to follow the Ontario
× 130) = 197,953 lb. (Canada) regulations:
Step 4. Calculate load with conveyance at lowest level.
factor of safety = 8.0 – 0.0005 d, but not less than 5.5
(17.5.40)
suspended loads
cage weight where d is maximum length of rope in feet
payload Ontario (Canada) regulations require the following factors
rope attachments of safety that may be used as guidance for other ropes in a
5130 ft of rope @ 3.95 lb/ft friction hoist installation:
Total:
1. Balance or Tail Ropes
Thus minimum breaking strength = 48,564 × 4
= 194,256 lb 2. Guide or Rubbing Ropes

Step 5. Select rope and check safety factor. 3. Bending Ratio. The required bending ratios are the same as
From steps 3 and 4 above, it can be seen that the loading for drum hoists. The bending ratio may exceed the regulatory
condition at the lowest level is critical, and that the minimum minimum but for locked coil construction does not normally
rope breaking strength required is 194,256 lb. exceed 140.
Referring to Table 17.5.3, it can be seen that 1½-in. diameter
6 × 27 flattened strand rope manufactured from 120 long tons/ Wire Rope Industries of Canada recommends the following
in.2 wire has an ultimate breaking strength of 235,000 lb. minimum bending ratios for locked coil ropes, although all such
For this rope the factors of safety are specifications have been removed from US CFR requirements:

Rope is therefore deemed satisfactory.


Step 6. Check with other hoisting components. In addition to the regulatory requirements for factor of
The designer would normally check hoist drum storage ca- safety, the following items should also be considered when select-
pacity and fleet angles at this stage as well as rope projected ing ropes for friction hoists: (1) T1 / T2 ratio, (2) drum tread, (3)
pressure on the drum grooving. After considering the other com- deflection sheaves, (4) differential rope loads, and (5) tail ropes.
1666 MINING ENGINEERING HANDBOOK
T1 / T2 Ratio—T1 / T2 ratio is the ratio of the static rope Hoisting Speed—There are no relationships attributable to
tensions on each side of the drum, where T1 is the weight of the effect of speed. However, as the speed of hoisting increases,
loaded conveyance plus weight of ropes, and T2 is the weight any inadequacies in the hoisting system are magnified.
of unloaded conveyance plus weight of ropes. The maximum Tail Ropes—In friction hoisting, the use of tail ropes makes
recommended value for a particularinstallation is a function of it possible to balance the head rope weight and achieve a lower
the coefficient of friction of the tread material, of the acceleration peak horsepower than for drum hoisting. However, the use of
and deceleration required, and of the angle of lap of the rope on tail ropes presents some additional problems that must be recog-
the drum. A typical maximum value of T1 / T2 is 1.5. This is also nized.
a concern for brake torque application. Should T1 / T2 become 1. Tail Rope Orientation
too high, the rope will slip on the drum; when this happens, the Any object falling down a mine shaft is affected by the
coefficient of friction drops and control is lost. There will also angular velocity of the earth and will move toward the east wall.
be tread damage due to friction temperature rise and abrasion. A tail rope behaves in a similar way. If the shaft compartments
Drum Treads—Selection of an appropriate tread material are arranged east— west, the tail rope loops will open and close
for the drum rope grooves and tread pressure are important. As freely. However, if the compartments are north and south, the
the rope passes over the drum, the load, and thus the strain in ropes could foul the separators at the shaft bottom. Thus, if tail
the rope changes. This change in strain tends to cause the rope ropes are used, then the orientation of compartments should be
to creep (as opposed to slip) on the drum. A resilient tread considered. The above described action results from a physical
material such as polyurethane tends to flow with the change in principle known as the Corioli effect and is a function of the
strain and reduce creep. hoist speed.
Typically, the average tread pressure (i.e., the sum of the 2. Tail Rope Loop Diameter
rope tensions/projected rope area on the drum) of 300 psi (2069 A natural loop diameter exists for each type of tail rope
kPa) with lock coil, 250 psi (1724 kPa) with flattened strand, depending upon its construction. This should coincide as closely
and 200 psi (1379 kPa) with round strand ropes on plastic treads as possible to the center-to-center distance of the conveyance.
will give good life. The bending ratio is defined as the natural bending diameter
Deflection Sheaves—Deflection sheaves are used when the divided by the rope size. It is possible to specify different rope
pitch circle diameter of the friction hoist pulley wheel (sitting construction and number of tail ropes to satisfy the loop diameter
above the shaft) is greater than the center-to-center distance of requirements.
the compartments. In addition to positioning the hoisting ropes,
the use of deflection sheaves has the advantage of increasing the Rope Construction Natural Bending Ratio
angle of contact of the ropes on the wheel, permitting a higher 34 × 7 Non-Rotating 46:l
T1 / T2 ratio before slippage will occur. 18 × 7 Non-Rotating 60:1
However, deflection sheaves have the disadvantage of requir- 6 × 7 Round Strand—Reg. Lay 90:1
ing additional torque during the hoisting cycle, increasing the
height of the headframe, and putting reverse bending into the 3. Tail Rope Loop Dividers
ropes, which can reduce their life. One rule of thumb used to According to Delorme (1977), to avoid mishap and possible
position the deflection sheaves is that the ropes traveling at full mechanical damage through entanglement, the balance rope loop
speed should take a minimum of 0.5 seconds to travel from the area should be well controlled in the sump. One method is by
constructing a loop divider. The balance ropes should be re-
drum to the deflection sheave. This rule, it has been claimed,
stricted quite closely in the direction of their lateral movement.
alleviates the fatigue problem due to reverse bending since it
Early contact with the dividers between individual ropes will
provides the requisite time for the rope strands and wires to
provide good control in the sump area and also assist in ensuring
adjust their position.
that adequate stability through the shaft is maintained. Longitu-
Differential Rope Loads—A great concern with multirope
dinal movement, on the other hand, should not overly be re-
friction hoists is the equalization of loads between the ropes. The
stricted. The dividers should be designed to avoid trapping any
two most common causes of differential loading are a difference material from spillage. Some operators have found that wire rope
in rope length or in circumferential lengths of each rope groove covered with rubber hose and placed in the same configuration
on the wheel. (as shown in Fig. 17.5.14) has proved most successful in this
Analysis of this problem and procedures to identify and connection. The elevation of the loop divider for good results is
correct the effects have been well covered in the technical litera- one loop diameter plus approximately 3 ft (0.9 m) above the
ture. In the initial design stage, it is important that steps be taken bottom of the loop. Some operators have placed such dividers at
to reduce its effects. Since there are no hard and fast rules, the several elevations in the sump area to ensure good control.
following rules of thumb have been developed in the industry: Calculation—The design of a friction hoisting system, in-
1. The ratio of rope lengths (skip in dump to hoist drum)/ cluding the selection of ropes, involves a knowledge of costs,
(skip at loading pocket to hoist drum) should be greater than shaft design, headframe design, and other factors beyond the
0.015. scope of this chapter. However, an example of rope selection is
2. The total number of revolutions of the drum on a trip presented based on previously mentioned technical considera-
should be less than 100. tions. The procedure involved in the analysis is as follows:
3. The number of ropes should be kept to a minimum. There Step 1. Tabulate data.
will be less difficulty maintaining equal tension on a four-rope Step 2. Calculate rope tensions.
hoist than on a six-rope hoist. In addition, a larger wheel will be Step 3. Check factor of safety of head ropes.
required for a four-rope drum having fewer revolutions per trip, Step 4. Check factor of safety of tail ropes.
lower rope bending stresses, and lower sensitivity to tension Step 5. Check bending ratio.
variations. This requirement may conflict with rope size choice, Step 6. Check T1 / T 2 ratio.
however. Step 7. Check tread bearing pressure.
4. Rope attachments should have both fine and coarse Step 8. Check loop diameter of tail rope.
length adjustment. Example 17.5.4. Given the following friction hoist system:
HOSTING SYSTEMS 1667
e) The difference between the hoisting distance (1921 ft) and the
suspended rope length (2122 ft) is 201 ft. We will assume 100 ft
of this is in the headframe and 101 ft is in the shaft bottom.
Select the proper hoisting rope and determine factors of
safety.
Solution.
Step 2. Calculate rope tensions.

Wt/ft of 6 head ropes = 6 × 7.8 = 46.8 lb/ft


Wt/ft of 4 tail ropes = 4 × 11.7 = 46.8 lb/ft

Note: It is rare that a perfect balance is achieved, but a close


match is desired.
The maximum rope tension T1 occurs with the loaded skip
at the dump.

T2 = Rope from loading pocket to drum


(1921 + 100) × 46.8
+ Skip weight
+ Tail ropes

Step 3. Check factor of safety of head ropes.

Fig. 17.5.14. Rope loop divider (Delorme, 1977).

Step 1. Assumed operating conditions. This exceeds the requirement of 6.0 (according to CFR 57.19-
21 and ANSI M11.1 standard for friction hoists at a depth of
a) Hoist wheel diameter approximately 2000 ft).
Step 4. Check factor of safety of tail ropes.
From the calculation of T1 the maximum weight of sus-
pended tail rope is 94,630 lb.
b) Suspended loads
Hoisting distance
Suspended ropes
Skip payload
Skip and rope attach-
ments

c) Head ropes This significantly exceeds any regulations. This can be expected
Type because the rope was selected on the basis of weight and not
strength.
Number Step 5. Check bending ratio.
Diameter
Ultimate strength
Weight/ft

d) Tail ropes
Type

Number
Diameter This meets the requirements for good practice according to rope
Ultimate strength manufacturers and some codes that apply.
Weight/ft Step 6. Check T1 / T2 ratio.
1668
amount of energy that can be absorbed. This is the reason why
the codes permit reduction in the factor of safety with longer
ropes.
2. When a hoisting system is being designed for balance
This is less than the 1.5 noted earlier as a typical maximum. The hoisting using two skips, the amount of stretch must be consid-
following should be borne in mind: ered when designing the overtravel allowance in the headframe.
1. There is no code requirement for T1 / T2. Under normal loading conditions, one skip will be positioned at
2. A workable T1 / T2 ratio is dependent on the coefficient of the loading pocket after the skip in the headframe has completed
friction of the actual drum tread material and head ropes used, dumping. If, however, a skip is not loaded, the stretch due to
as well as angle of contact. The latter considerations enter with the payload will not take place. Should the empty skip be hoisted
ground-mounted hoists that do not have as much contact as to the surface, it will be above the headframe dump (by the
tower-mounted usually do. amount of rope stretch that did not take place) when the lower
3. Manufacturers apply a factor of safety to actual coeff- skip is at the loading pocket. For example, a 10-ton (9-t) payload
cients of friction to determine the T1 / T2 for a particular appli- on a 4000-ft (1219-m) long 1-in. (38-mm) rope would cause a
cation. stretch of about 4 to 6 ft (1.2 to 1.8 m).
Step 7. Check tread bearing pressure. 3. Due to both the static and dynamic forces, the skip moves
down during loading. Unless this movement is considered in the
design of the loading pocket and the skip, considerable spillage
could occur.
4. The static and dynamic rope stretch at the loading pocket
must be considered in establishing the skip undertravel in the
shaft bottom.
The formula for rope stretch or elongation in ft (m) is

(17.5.41)

Again there is no code requirement for tread bearing pressure, where P is load in lb (kg), L is length of rope from the hoist to
and acceptable pressures depend on tread material and rope the loading point in ft (m), A is nominal rope cross-sectional area
construction. Varying the tread pressure changes the mainte- in in.2 (mm2), and E is a constant for a given rope construction in
nance costs but not the safety of the installation. lb/in.2 (Pa). E is analogous to Young’s modulus. It is determined
Step 8. Check loop diameter of the tailrope. experimentally by rope manufacturers and takes into consider-
ation the voids between the wires in the rope and the geometric
Tailrope size 2.625 in. change in the rope under load.
Tailrope construction 18 × 7 NR Values of E change as the rope stretches with use. Typical
Bending ratio 60:1 values are tabulated below:
Diameter of natural loop = 2.625 × 60 = 157.4

This is marginally less than the drum diameter and is therefore


satisfactory.
GUIDE AND R UBBING R OPES. Ropes used as guides and
rubbing ropes may be of locked coil or half locked coil construc-
tion. These ropes are manufactured with a core of concentrically
laid round wires covered with one or two layers of shaped wires.
The outer layer of locked coil construction is always composed
of interlocking wires of Z shape.
Some of the advantages of locked coil ropes as guides and
rubbing ropes are as follows: (1) their smooth surface reduces The amount of dynamic stretch that takes place is propor-
friction, (2) they have a greater degree of rigidity, and (3) they tional to the mass and velocity impact of rock feeding into the
have a higher breaking strength in relation to their diameter. skip. These factors may be controlled (to reduce stretch) through
ADDITIONAL R OPE SELECTION C ONSIDERATIONS. In addi- loading pocket design. Dynamic stretch is commonly taken as
tion to those factors covered in the previous sections, the follow- equal to the static stretch produced by the load weight.
ing four items of importance should be considered in order to Rope Torque—Stranded ropes have a tendency to untwist.
ensure that a particular hoisting rope will meet all of its hoisting In drum hoisting, the rope is fixed at the drum, and at the
requirements: (1) rope stretch, (2) rope torque, (3) rope harmon- conveyance the tendency to untwist is restrained by the guides
ics and vibrations, and (4) rope sag. These are discussed in the and shoes. Consequently torque is developed in the rope. The
following subsections. counter torque exerted by the conveyance tends to produce wear
Rope Stretch—When a skip is loaded at the loading pocket, on one side of the guides. When disconnecting the rope from the
the rope stretches. The amount of stretch, which has a static and conveyance, the torque is released, and a dangerous situation
dynamic component, has a number of significant consequences develops if the end of the rope is not restrained and spins out of
that must be considered in the design of the hoisting system. control.
These are as follows: Some mining companies are deliberately letting the torque
1. The rope acts as a spring and helps absorb impact loads. out of the rope when they take rope end samples for testing.
The longer the rope, the greater the stretch, and the greater the However, some experimental work, as reported by Dolan (1961),
HOISTING SYSTEMS 1669
has shown that by allowing a rope to rotate, ultimate strength Table 17.5.4. Minimum Ratio of Drum/Sheave Diameter
is lost. to Rope Diameter
One formula used for calculating the approximate amount
Minimum Tread Diameter
of torque in a rope is Rope Construction of Sheave or Drum

T = kPd (17.5.42)

where T is torque in ft-lb, P is load in lb, d is nominal diameter


of rope in in., and k = 11 × 10–3 ft/in. for Lang lay and = 7
× 10–3 ft/in. for regular lay.
Rope Harmonics and Vibrations—Vibrations in hoist ropes
can be observed as “yo-yo-ing” at the collar, and in the case of Note: Conditions may exist where further reduction may be neces-
sary. Under such conditions, service life would be affected and due
drum hoists as ropes whip between the hoist and the head sheave.
precautions should be exercised. If possible, the hoist/sheave manu-
The causes of these vibrations are (1) jerking operations such as facturer should be consulted for guidance. Note that the Jan. 24,
uneven braking, (2) the horizontal movement of the rope at the 1984, MSHA Standards do not define necessary D/d ratios.
crossover points on the drum, and (3) the vertical movement of
the rope at crossover points on the drum.
These vibrations cannot be avoided and normally do not
cause problems. However, there have been cases where the fre- 17.5.5.4 Rope Testing Certification and
quency of the vibrations is a harmonic of the natural frequency
of the hoist rope and severe and dangerous whipping has oc- Acceptance
curred. Such a situation is most likely with a long, flat span of It is common practice for the purchaser to require the manu-
rope between the hoist and head sheave. The following rules of facturer to certify that the rope will meet the nominal breaking
thumb have been developed to assist designers to set up a good strength. Certification usually includes a test report providing
hoist and head sheave arrangement. full particulars on the wires used to manufacture the rope as well
1. Keep the vertical rope angle as close to 45° as possible. as breaking strength in a failure load test to ultimate load. A test
2. The slope distance along the rope, between the tangent to destruction by an independent laboratory can be specified.
points at the drum and the sheave, should not be an even multiple However, such a test involves additional costs and is not nor-
of the drum circumference. mally specified in the United States.
The hoist designer should analyze the harmonic behaviors
of the ropes and select the type of drum grooving which will
17.5.5.5 Rope Operating Practices
avoid harmonic vibrations. This has been reviewed by Dimitriov
and Whillier (1973). When unacceptable rope movements do The correct wire rope properly installed on well-designed
occur, it is necessary to reduce hoisting speed or payload, or to equipment maintained in good working condition provides the
install an intermediate tower with idler sheaves between the hoist foundation for satisfactory rope performance. In order to attain
and headframe. and sustain the required rope performance, it will be necessary
Rope Sag—A rope between a ground-mounted hoist and a that the rope be properly operated and adequately maintained.
head sheave sags and takes the form of a catenary. With a Well-developed rope operating practices should consider the fol-
heavy rope and a light load, the sag can be significant and cause lowing: (1) rope storage, (2) rope installation, (3) rope changing
problems at the sheave deck and the hoisthouse wall if not procedures, (4) rope operating practices, (5) equipment mainte-
considered. Such a situation could occur during sinking a deep nance, (6) lubrication, and (7) inspection procedures.
shaft when there is an empty bucket at the dump. ROPE STORAGE. Whether the rope must be stored temporar-
INCLINED (SLOPE) HAULAGE. The selection of ropes for an ily or indefinitely, it should be indoors where it can be shielded
inclined shaft differs little from selection for a vertical shaft. The from weather, corrosive fumes, and excessive heat that might
three major differences are (1) calculation of rope tensions, (2) dry the lubricant or fiber core.
sizing of sheaves, and (3) abrasive wear. R OPE INSTALLATION AND H ANDLING . Ropes should be
Calculation of Rope Tension —The tension in the rope is the wound onto the drum under load. The direction of coiling should
sum of the gravitational, frictional, and accelerational forces. be determined by the accepted rule of thumb method, as shown
The gravitational force is the sum of the weights of the car(s), in any rope handbook, and the individual turns should be tamped
payload, and the rope multiplied by the sine of the angle of the together using a copper hammer to avoid gaps between coils.
incline. The friction force is commonly taken as 2.5% of the Before cutting, the rope supplier or a technical handbook detail-
weight of the car and payload plus 10% of the rope load. To ing correct cutting procedures should be consulted (Anon.,
allow for acceleration, 10% is added to the gravitational and 1980).
friction forces. D RUM H OIST R OPE-CHANGING P ROCEDURE. Rope chang-
Sizing of Sheaves—Because of the space restrictions under- ing procedures for drum hoists are relatively easy and are de-
ground and the need for portability, deflection sheaves are com- scribed in rope handbooks. Precautions must be taken, however,
monly smaller than used elsewhere for hoisting ropes. Minimum to ensure that adequate tensions are applied to provide correct
D/d ratios are presented in Table 17.5.4. spooling during installation.
Abrasive Wear—Abrasive wear is more likely to be a problem FRICTION H OIST R OPE -C HANGING P ROCEDURE . Rope-
in a slope than in a vertical shaft and this potential problem changing on friction hoists can be carried out using one of four
should be addressed in rope selection. One approach is to select methods.
ropes with thicker wires such as 6 × 7. Some designers increase 1. Method 1. A rope-changing station is located midway in
the factor of safety to allow more wear on the rope before it the shaft. Headropes are changed by chairing the conveyances
needs to be replaced. at mid-shaft, where reels of new cable have also been positioned,
1670 MINING ENGINEERING HANDBOOK
disconnecting both ends of the headropes and connecting one L UBRICATION . Atmospheric moisture, shaft water, and
end of the old rope to one end of the new rope. The opposite end chemical fumes are a few of the agents that will cause corrosion.
of the old ropes is connected to empty reels. All headropes are This frequently leads to wire breakage and premature removal
changed at one time by rotating the friction wheel and thus of mine hoist ropes. In mines with very wet and corrosive shafts,
lifting the new ropes. The old ropes are wound on the empty it is distinctly advantageous to apply a lubricant that will pene-
reels. After the new rope has been hoisted into position and the trate the interior of the rope and that contains a corrosion inhibi-
old ropes wound on the spare reels, both ends of the new ropes tor. Lubricants with water-displacing properties are also avail-
are connected to the conveyance. Tail ropes are changed from able and are useful at end attachments.
the bottom of the shaft (see method 4). INSPECTION P ROCEDURES. In order to achieve optimum
2. Method 2. A portable rope winch located on the surface rope performance, an inspection procedure that requires findings
removes all head ropes one at a time, winding them on empty to be recorded, fully diagnosed, and translated into appropriate
reels. New head ropes are lowered by this winch and installed action should be instituted.
on the conveyances. During this procedure, one conveyance is The presence of the foregoing not only allows the operator
located at the top of the shaft, and one conveyance is located at to estimate the remaining safe working life of the rope but can
the bottom of the shaft. Tail ropes are changed from the bottom also pinpoint the source causing such damage to the rope. For
of the shaft (see method 4). example:
3. Method 3. Both head ropes and tailropes are changed 1. Marked reduction in diameter may be due to a loss of
from the bottom of the shaft, using the hoist to raise the new rope’s elasticity, excessive abrasion, or corrosion.
ropes into position. 2. Broken wires may be due to worn out sheave, or drum
4. Method 4. In this method, the tail ropes are installed from grooves, tight oversized sheaves or gappy coiling.
the bottom of the shaft, following a five-step procedure: (1) 3. “Kinking” and “birdcaging” of working ropes generally
locate no. 1 conveyance at the bottom of the shaft, (2) locate no.2 result from a sudden release of load.
conveyance at the top of the shaft, (3) release the rope clamp on The term “kinking” in rope use describes the snarling back
the bottom of no. 1 conveyance and start reeling the rope to be of a rope on itself in the form of a loop resulting in a bend in the
removed on a spare reel, (4) lower no.2 conveyance and remove rope when straightened out, while “birdcaging” is applied to the
rope clamp on the bottom of no.2 conveyance and complete springing of strands away from the core or inner strands.
winding up the end of the rope removed, and (5) install the new A thorough evaluation of all facts obtained through routine
tail rope with the reverse procedure. The new tail rope will be inspections, examinations and tests, and compliance with statu-
hoisted into position. tory mining acts is needed to decide how early a rope should be
The head ropes could also be installed by the use of an discarded for the sake of safety, and how late can it be removed
auxiliary rope-changing winch located at the collar elevation in for the sake of economy.
line with the bending rotation of the hoisting ropes. The final
method selected depends upon the amount of room available on 17.5.5.6 Rope Attachments
the surface, orientation of hoist ropes, available space in the
headframe, and personal preference. Wire rope end attachments are as important as the rope to
ROPE OPERATING PRACTICES. Mine ropes are operated and which they are fastened. Therefore, the selection of the correct
maintained correctly when the following conditions are met: type of attachments should be based on an understanding of how
1. Drum and sheave groove contours are correct. they affect ultimate rope serviceability and efficiency.
There are only two ways to attach something to a wire rope:
2. Filler, starter, and riser strips are used on the drums
(1) forming a loop in the rope, and (2) attaching a fitting to the
where necessary.
rope. Loops are made either by splicing the rope to itself, or by
3. Rope crossovers on the drum are prevented.
use of clamps or wedges. Fittings secured directly to wire rope
4. Shock loadings and overloads are avoided.
can be applied by cold forming (snagging) of the metal in the
5. Vibration stresses are kept to a minimum.
fittings, by pouring a liquid material such as molten zinc, or
6. Peening and abrasive actions are minimized. by a wedging arrangement. In this section, some of the most
7. Rope cutbacks are appropriately completed. commonly used attachments are described.
8. Cage-end attachments are refastened at regular intervals. FACTOR OF SAFETY. The factor of safety for rope attach-
9. The rope is lubricated at regular intervals with the correct ments is not specifically covered in CFR Title 30 (Anon., 1989).
lubricant. However, it is considered good engineering practice to design
E QUIPMENT M AINTENANCE . Maintenance of equipment the rope attachments to be stronger than the rope, that is, the
that comes in contact with the rope is important and should not rope will fail before the attachments. British codes require a
be overlooked during the design or operating phase. Some items factor of safety of 10 based on static loads.
to be considered are the following: When an attachment is made to a rope, the attachment
1. Tight sheave and drum grooves will pinch the rope, re- commonly weakens the rope locally. The efficiency of an attach-
stricting wire and strand movement. ment is expressed as the percentage of strength left in the rope
2. Incorrectly designed rope crossovers on drum hoists will after installation of the attachment. The efficiencies to be ex-
crush or flatten the rope, induce the core to pop, and severely pected from the various types of attachments when correctly
scrub wires. This can be prevented through the correct design installed are presented in Table 17.55
of filler, starter, and riser strips on the drum flange. CAPPELS. Cappels are rope fittings attached directly to the
3. Faulty bearings can cause vibration stresses, which in rope. These types of fittings consist of a pair of wedges grooved
turn cause fatigue fractures that are most likely to concentrate to suit the particular rope diameter and interlocked to ensure
at the end attachment. complementary movement. A number of bands driven over the
4. Corrugated deflection sheaves, drums and rollers can diverging exterior surfaces of the cappel limbs provides the initial
cause high unit pressures, aggravated wear, excessive rope vibra- compressive force to ensure that the wedges grip the rope. The
tion, and early wire fatigue. Correct measuring and trimming of limbs’ internal surfaces have been machined to fit the external
tread diameters will prevent this problem. surfaces of the wedges. A safety block is fastened on the end of
HOISTING SYSTEMS 1671
Table 17.5.5. Rope Attachment Efficiencies the exterior shape, (7) design interior members (guides, buntons,
etc.), (8) design shaft lining, (9) check ventilation characteristics,
(10) determine ground stabilization and temporary ground sup-
port, (11) determine shaft collaring method, (12) determine shaft
sinking method, and (13) evaluate and modify starting at item 1.

17.5.6.2 Purpose of Shaft


One of the first items to be examined when designing a shaft
is to identify its intended purpose. Shafts usually fall into one of
the following categories: (1) production (ore and waste han-
dling), (2) service (personnel and materials handling), (3) ventila-
tion (upcast or downcast), (4) exploration (for defining mineral
deposits), and (5) combination of the above.

17.5.6.3 Location and Inclination


LOCATION. Generally, the location of a new shaft at the
the rope, protruding beyond the bottom of the wedges. Several mine site is determined after establishing the following: (1) mine
types of cappels are used for hoist ropes including the wedge and surface layout, (2) location, dip, and extent of the ore body, (3)
loop. number of working levels to be considered, (4) location of ore
T HIMBLES. In North America, most mine hoist ropes on and waste handling facilities, (5) water collection sump require-
drum hoists are terminated with a wire rope thimble and U-bolt ments, (6) safety and stability of the shaft pillar, and (7) the
cable clamps. With this type of attachment, a loop is formed in future planned expansion of the shaft. The bottom of the shaft,
the rope and the thimble placed within this loop. The free end where possible, must also be in a stable formation and should be
of rope is then clamped to the long end to secure the thimble. able to facilitate any planned, future redeepening. The location
Thimbles are made of cast steel, whereas the clamps, shack- of the shaft must also avoid adverse surface features and should
les, and pins are made of 1.5% manganese steel. satisfy surface layout plus logistics of surface and underground
SWIVELS. When winding with balance ropes, the lay length ore and waste handling facilities.
tends to shorten as each conveyance in turn approaches the INCLINATION. The dip of the ore body is the main factor
bottom landing. It is for this reason that swivels are provided in involved in deciding to sink either a vertical or inclined shaft. A
order to allow the ropes to spin and regain their normal length. secondary factor is the relative ground strength and geologic
Shaft conditions and loadings influence the type of swivel used. formations to be encountered by the proposed shaft.
ATTACHMENT MAINTENANCE AND INSPECTION. It is desir- The main advantages associated with vertical shafts are (1)
able that all types of attachments be installed as recommended hoisting speeds are greater, (2) shaft maintenance costs are lower,
by the manufacturer. If thimbles and clips are to be used, then (3) sinking can be carried out faster, and (4) sinking can be
the manufacturers’ recommendation for the correct number of achieved in almost any type of ground.
clips, amount of turn back, clip positions, and correct torques Inclined shafts (slopes) are generally associated with inclined
should be followed closely. If a wedge-type connection is being (dipping) ore bodies where the length of crosscutting to reach
applied, then care should be taken to properly clean the rope the ore body from a vertical shaft becomes longer with the
surface. Frequent applications of cement dust and subsequent increase in depth of the shaft. They have the advantage of min-
steel brushing will remove all the surface lubricant. imizing development to reach the ore from the shaft and are
In some jurisdictions, statutory mining regulations requires used frequently in coal mines.
that all types of attachments be inspected both visually and non-
destructively on a regular basis. In other parts of the world,
removal criteria for attachments have been established. 17.5.6.4 Number of Hoists
The number of hoists (and conveyances) required to meet
hoisting demands has a major impact in the design of a shaft
17.5.6 SHAFTS
(see procedure, 17.5.3.5).
A shaft is a vertical or inclined primary opening in rock that
provides access to and serves various levels of a mine. Primary 17.5.6.5 Compartment Size
openings are those which are considered to be permanent and
require a high degree of safety. Chapter 17.4 discusses design The cross-sectional area of a particular compartment (hori-
and construction details. zontal area) is dependent upon its use. In order to determine the
most appropriate size, it is necessary to list the items to be
transported in the compartment, determine their approximate
17.5.6.1 Shaft Design Procedure dimensions and weight, indicate their direction of flow and their
A suggested procedure for the design of shafts follows. It is approximate quantities. Another important factor to be consid-
important that the steps be followed in the given sequence. It ered is the size of the shaft sinking bucket. After having deter-
should be noted that the process is iterative and involves working mined the size of compartments for cage, counterweight, and
through the process several times before an optimum design is skips, the remaining area is then divided to accommodate ventila-
achieved. The shaft design procedure involves the following tion, manway, and pipe facilities.
steps: (1) define purpose of the shaft, (2) identify location and SIZE OF SKIP COMPARTMENT. The skip capacity is deter-
determine inclination, (3) determine the number of hoists re- mined by such variables as the hoisting capacity, material den-
quired, (4) determine the size of conveyances and compartments, sity, lump size, and vertical height available in the headframe.
(5) determine the arrangement of compartments, (6) determine Generally speaking, the skip dimensions and cross-sectional area
1672 MINING ENGINEERING HANDBOOK
are determined by the skip supplier. Good design practice allows the drum, the necessity for deflection sheaves, and the type of
the following clearances: rope construction for the tail ropes.
Skip compartment size:
face to face on guides = outside dimension of skip guide 17.5.6.7 Exterior Shape
shoes + 1 in. (25 mm)
front to back = outside dimension of skip + 3 in. The exterior shape of a shaft is established by considering
(75 mm) ground stability factors. A circular shape provides better resist-
ance to deformation by lateral pressure. In fair to competent
SIZE OF CAGE COMPARTMENT. Cages are generally used to formations, an opening excavated in this form is generally self-
transport personnel and materials. The following clause of CFR supporting. In weak formations, the circular shape is adaptable
Title 30 (57.19-66 Mandatory) applies in the United States: to a variety of lining materials, concrete, steel segments, or cast-
in-place concrete. Competent formations can be excavated to a
“In shafts inclined over 45°. . . . Each person shall be rectangular shape and be generally self-supporting. An elliptical
provided a minimum of 1.5 ft2 (0.14 m2) of floor space.” shape offers better support than a rectangle but not as good as
a circular one. The geotechnical considerations leading to the
The cage capacity is determined by the cage supplier based selection of an exterior shape are beyond the scope of this discus-
on a knowledge of the following factors (1) the amounts of sion, but their importance in the overall design process cannot
material to be transported, (2) the dimensions and weights of the be overstated (see Chapter 10.5). Also shafts may have different
major pieces of equipment to be lowered and raised, (3) the exterior shapes at different depths, reflecting the different strata
number of personnel to be lowered and raised per shift, and encountered.
(4) type of conveyance preferred (i.e, single deck, double deck,
combination skip/cage, etc.)
After establishing the cross-sectional area for the cage, the 17.5.6.8 Interior Members
cage compartment is sized the same way as the skip compartment Guides and buntons are the main vertical and horizontal
to provide similar clearances. structural elements in a mine shaft conveyance system. The
S IZE OF M ANWAY C OMPARTMENT . From CFR Title 30 primary function of these members is to facilitate running of
(57.11-37 Mandatory): Ladderways constructed after November the shaft’s conveyances. Their characteristics influence not only
15, 1979 shall have a minimum unobstructed cross-sectional speed of operation and amount of maintenance required, but also
opening of 24 by 24-in. (610 by 610 m) measured from the face production and ventilation costs. Therefore, the choice of sets
of the ladder. and guides is of great importance to achieving operational cost
(57/11-41 Mandatory): Fixed ladders with an inclination of savings.
more than 70° from the horizontal shall be offset with substantial SHAFT GUIDES DESCRIPTION. Shaft guides are used in verti-
landings at least every 30 ft (9.1 m) or have landing gates at least cal shafts to keep the skips, cages, and counterweights in proper
every 30 ft (9.1 m). shaft position. The two types of guides in use are (1) fixed guides
In addition to the above, it is necessary to provide adequate (wood, rail, and steel), and (2) rope guides.
clearance at the landing platform to allow a person to move from Wooden Guides—Wooden guides are supported by the hori-
one ladder to the next offset ladder. Generally, an additional zontal sets installed in the shaft. They are favored where convey-
floor area of 36 by 24 in. (914 by 610 mm) is provided. ances require safety devices. This is due to the fact that the
SIZE OF C OUNTERWEIGHT C OMPARTMENT. The counter- decelerating characteristics of safety dogs on wood are more
weight compartment can be of any size or shape as long as it reliable than on steel or rail. When hoisting on wooden guides,
provides sufficient space and clearance for the safe passage of a speed of 2200 fpm (11.2 m/s) with a medium-sized skip is the
the counterweight with the same clearances as for skips and practical upper limit. Wooden guides are subject to changes in
cages. dimensions due to changes in moisture content. They are also
SIZE OF SERVICE COMPARTMENT. There are no hard and subject to wear to a greater extent than steel guides. Wooden
fast design rules for sizing the services compartment except that guides generally are not used in shafts where fire hazards exist,
the cross-sectional area of the compartment should be adequate such as in coal mines.
to provide the following: (1) separate locations for communica- Rail Guides—Rail guides are common in inclined shafts.
tions (signaling) and power lines, (2) space for locating air, water, These guides vary in size, with the larger rails giving a wider
pump, backfill lines, (3) clearance for pipe fittings, and (4) space bearing surface for the wheel. The steel rail provides a harder
for pipe column brackets. surface but presents a smaller wear area; this creates more wear
and maintenance on conveyance guide shoes and wheels.
Steel Guides—Structural steel tubes (SST) sections are be-
17.5.6.6 Compartment Arrangement
coming more popular as guides for production shafts where
The arrangement of the compartments in relationship to one higher speeds and heavy loads require a fairly rigid and stable
another depends upon the surface layout, underground layout, section. With steel guides, the conveyances are usually equipped
and the type and size of hoist to be used. Because these design with adequately sized guide roller assemblies to minimize wear
details are not known precisely during the initial design stages, between the guides and shoes on the conveyance. When hoisting
one must first make a “best estimate” and be prepared to change on steel guides, a speed of 3000 fpm (15.2 m/s) is a practical
the arrangement as the final design evolves. upper limit.
On surface, the orientation of the compartments in relation Rope Guides—Rope guides are also used for guiding convey-
to the hoist and headframe is of major importance. Good rope ances in vertical shafts. These are generally used with multirope
practice for drum hoists requires that the location of the hoist hoisting systems where the effect of hoist-rope torque is minimal
in relation to the shaft and headframe be in line to provide or nonexistent. Half locked coil ropes are used for this service.
acceptable rope fleet angles. Rope guides do not require any intermediate support, thereby
For friction hoists, the center-to-center distance on the com- eliminating the steel sets required for fixed guides. Since rope
partments is a major consideration for determining the size of guides are not able to withstand the horizontal forces of loading
HOISTING SYSTEMS 1673
and unloading, the conveyance must be supported by other pressures are less than 250 psi (1724 kPa) and when the stress
means in these areas. Fixed guides are used at the extremes of field is uniform and compressive in nature. Steel is more suitable
travel, and a retractable guiding system should be considered at for a completely water-tight lining and is capable of withstanding
intermediate levels. There are several schemes by which rope tensile stresses. These stresses could arise if the shaft is subjected
guides are suspended and tensioned, and the selection of any one to bending loads caused by subsidence or buckling loads caused
of these will depend on the particular installation. by a non-uniform horizontal stress field.
Because rope guides eliminate the need for horizontal bun- Steel lining can be butt-welded to give permanent water-
tons, the ability of the shaft to handle airflow is enhanced. In a tightness and has a higher buckling safety factor than tubbing.
large shaft, with multiple conveyances traveling at the same time, Steel is particularly useful as a lining for shafts sunk by drilling
the aerodynamic effects can cause unexpected rope deflections. methods. Cast iron tubbing consists of several segments bolted
These effects should be studied during the design stage. Since to form a ring and requires a lead gasket to be placed between
rope guides are the smoothest of all guides, hoisting speeds up segments.
to 4000 ft/min (20 m/s) are feasible. D ESIGN C ONSIDERATIONS FOR SHAFT LINING. The design
SHAFT BUNTON DESCRIPTION. Shaft buntons are horizontal requirements for lining a structure is governed by the required
members used to divide the shaft into compartments. They also duty of the shaft and environmental conditions in which it is
support and carry the shaft guides, pipes and cables. Buntons constructed. Careful consideration of the following points should
can be of any cross-sectional shape and can be installed in a be made in the design of structural lining: (1) precise behaviour
shaft at any spacing. However, the correct design and layout of of the rock mass in situ, (2) self-supporting action of the rock
buntons and their installation at a suitable spacing minimizes itself, (3) effect of separation of the lining due to certain vertical
the air resistance of shafts and hence reduces ventilation op- and horizontal movements of the surrounding rock formation,
erating costs. (4) construction of watertight linings, and (5) economics of the
G UIDE AND B UNTON S TRUCTURAL D ESIGN . Although lining structure.
there are no universally accepted loading parameters for the The design of steel or cast iron linings is a much more
design of the shaft members, buntons and guides may be designed complex process, since the buckling characteristics of an elas-
using empirical static loadings, generally accepted in the indus- tically embedded hollow cylinder with external pressure must be
try, and discussed in the next segments. evaluated. Although the details of such a design are not discussed
Bunton Loading—The static loads considered acting on set here, several reports on the subject are available in the technical
members are literatures (Ostrowski, 1972; de la Vergne and Cooper, 1983;
1. The known weight of steel to be supported. DeHart, 1983).
2. The vertical friction load on the guides transferred to the
set members. The friction load is assumed equal to 3% of rope 17.5.6.10 Ventilation Characteristics
end load, where rope end load is calculated by adding the weight The shaft is generally the largest single contributor to total
of conveyance, the attachments, and the payload in the con- mine air resistance when it is equipped with rigid guides for
veyance. hoisting purposes. The resistance consists of two components:
3. A horizontal load transferred from guide members to set (1) frictional resistance, caused by viscous drag in the thin air
members assumed equal to 10% of rope end load. layer at the shaft walls and the periphery of the vertical elements
Guide Loading—The static loads considered acting on the (guides, pipes, cables, ropes, etc.) of the shaft; and (2) shock
guide members are as for buntons. As mentioned earlier, there resistance, due to the transverse sets (buntons and dividers),
is no general consensus on these loading parameters and they completely immersed in the airstream, thereby obstructing the
have been challenged by several authors with diverging opinions flow, and recurring at intervals throughout the shaft.
(Bently, 1973; Backerberg, 1970; Van Wyk, 1961). These transverse elements create turbulence in the airstream
with corresponding loss of flow energy. The turbulent waves
17.5.6.9 Shaft Lining below buntons and conveyances often contribute very much
more to the total shaft resistance than the skin friction of the
Shaft lining may be comprised of shotcrete, cast-in-place shaft walls. The forces caused by the buntons are parallel to the
concrete, or steel and cast iron tubbing. When a lining is re- airstream, and proportional to velocity pressure, frontal area,
quired, the selection depends on a number of design considera- surface texture, and shape. Because the frontal area of all the
tions that relate to the strata being excavated. For further discus- buntons in a shaft is likely to be more than the frontal area of
sion, see Chapter 17.4. the cages and skips, the aerodynamic design of the bunton is of
SHOTCRETE. Sprayed concrete, 5 in. (125 mm) or more in importance in the design of a mine shaft.
thickness, may be used to control immediate raveling and weath- A reduction in the shaft resistance can be achieved through
ering of the shaft walls. To date, shotcrete has not been used (1) improving the aerodynamic effect of horizontal obstructions
extensively to provide long term support, nor as the only means such as buntons, (2) minimizing the frontal area of the set mem-
of lining in shafts. bers, and (3) increasing the spacing between the horizontal ob-
CONCRETE. The use of concrete for permanent support is structions. Practical experience has indicated that there is little
becoming more common. Shafts may be fully lined or partially ventilation advantage to be gained from spacing greater than 15
lined with “concrete rings” with areas of open ground between ft (4.6 m).
the rings. Common spacing used for ringed shafts is 4-ft (1.2-m) General treatment of mine ventilation theory and practice is
high concrete rings with a 4-ft (1.2-m) open area between, re- offered in Chapters 11.6 and 11.7.
sulting in an 8-ft (2.4-m) set interval. Concrete is generally placed
12 in. (305 mm) in thickness, with a minimum of 10 in. (254 17.5.6.11 Ground Stabilization and Temporary
mm).
STEEL OR CAST IRON TUBBING. Although the use of con- Support
crete as a lining material is becoming more common, there are Table 17.5.6 identifies three types of ground support problem
certain geologic conditions where steel or cast iron tubbing is encountered in shaft sinking and their corresponding solutions.
a more appropriate material. Concrete is suitable when water For a detailed discussion of ground control, see Chapter 10.5.
1674 MINING ENGINEERING HANDBOOK
Table 17.5.6. Ground Support Problems Encountered in
Shaft Sinking
Problem Solution
Ground is too weak or wet Pre-grout, freeze, drill and
to allow any type of ex- pump water wells.
cavation
Ground requires support Rock bolts, screen, shot-
during excavation crete, limit amount of un-
supported ground.
Shaft requires permanent Install timber sets, steel
protection to allow sets, pour concrete lining
hoisting either partial or rings, in-
stall steel or cast iron
liner.

17.5.6.12 Shaft Collar


Shaft construction begins with the excavation and forming
of the shaft collar. The collar assists in forming the desired shape
for the initial length of the shaft and provides the necessary
stability and alignment for the remaining length of shaft to be
excavated. Completion of the collar also allows erection of the
headframe, sheave deck, and hoisting facilities for the sinking
operation. The collar acts as a barrier to prevent water and soil
from entering the shaft.
Collar construction methods are beyond the scope of this
chapter but include steel sheet piling cofferdam, drilled inter-
locking concrete piles, steel walings with sheeting, drop caisson,
drilling, pregrouting and sinking, open cut and dewater with
well points, and deep well pumping.
Fig. 17.5.15. Types of headframe structures.
17.5.6.13 Shaft Sinking
Following completion of shaft collaring, the actual shaft can produce economically viable, structurally compatible, and
sinking is carried out usually by one of the following methods: visually appealing headframes for any new development.
(1) conventional methods of drill-and-blast or pilot raising and Advantages of concrete structures include (1) effective use
slashing, or (2) mechanized methods of raise boring or blind can be made of space within the structure for tower-mounted
shaft boring. These are discussed in Chapter 17.4. friction hoists, (2) when used in conjunction with ground-
mounted drum hoists, the hoist may be located at any position
17.5.7 HEADFRAMES around the headframe, (3) maintenance costs are low, (4) high
damping effect of the massive concrete structure on shock and
The basic purpose of a headframe installed over a shaft is to vibration, (5) simplicity of collar layout and interconnection with
support the sheave wheel over which a hoisting rope passes for service buildings, (6) provision for future expansion, and (7)
raising or lowering conveyances. The construction of a head- durability and resistance to corrosion. Disadvantages of concrete
frame is also necessary to allow dumping of hoisted materials include (1) lengthy construction period, (2) higher capital cost
aboveground. Structurally, there are two types of headframes: in comparison with a steel headframe, and (3) no salvage value.
(1) headframe structures with backlegs such as an A-frame, and For steel structures, advantages include (1) lighter founda-
(2) four-post and six-post and headframe structures of tower tion loads, (2) adaptability to minor changes, (3) salvage value,
form (Fig. 17.5.15). (4) capital cost saving in remote areas, (5) can be pre-fabricated
into transportable lengths for on site assembly, and (6) speedy
construction. The main disadvantage of steel is that it is prone
17.5.7.1 Construction Materials
to corrosion, and thus not suitable as a production headframe
Headframes may be constructed of timber, steel, or concrete. for corrosive ore (e.g., salt and sulfides) unless the steel is treated.
Modern trends to high-capacity hoisting have necessitated the
construction of very large headframes, which effectively preclude 17.5.7.2 Headframe Design Considerations
the use of timber as a construction material.
COMPARISON—STEEL VS. CONCRETE. Butler and Schneyd- A successful design must be based on an overall integrated
erberg (1981) outlined the principal criteria that should be used hoisting system design, which involves a critical examination of
as a basis for a realistic evaluation of the merits of concrete and the impact of at least the following list of items: (1) loads, (2)
steel for a headframe. A summary of their arguments is given in foundations, (3) mine services, (4) sinking provisions, (5) equip-
Table 17.5.7. ment monitoring facilities, (6) conveyance handling and rope
Although the arguments given appear to favor concrete handling, (7) heating and ventilation, and (8) others, such as
headframes, it should be noted that both concrete and steel local mining regulations.
HOISTING SYSTEMS 1675
Table 17.5.7. Design Considerations for Concrete and Steel Headframes
Consideration Criterion For Concrete Structures For Steel Structures

Foundation Requires sound bedrock Lighter steel headframe can be erected on


non-corrosive weak ground formations.
Construction Slipformed concrete tower can (in favor- Can be erected in all weather.
able weather) cut construction time.
Accommodation of shaft sinker Can accommodate temporary sheave deck Cannot facilitate installation of temporary
to facilitate shaft sinking. head gear without extensive modification
to the permanent structure.
Additional facilities Provides sufficient enclosed space to Steel structure usually not capable of car-
house hoist’s electrics, control room, rying extra loads.
and ventilation equipment.
Stiffness and damping effect Concrete structure is stiffer to resist vibra- Steel structure is more prone to vibration
tion during high speed. unless design is based on sophisticated
dynamic studies.
Plant layout damping effect Flexible to logistics, stiffer to resist vibra- Steel structure is more prone to vibration
tion during high speed hoisting and in unless design is based on sophisticated
strong wind environment. dynamic studies.
Adaptability to changes and future addi- Due to high load-bearing capability, con- Steel headframe, although amenable to mi-
tions crete towers tend to be more flexible for nor changes, requires costly modification
future planned expansion. for major expansion.
Reclamation Concrete headframe has no salvage value. Steel headframe can be relocated and re-
used and has good salvage value.
Corrosion, durability and maintenance Virtually immune to corrosion; can be Susceptible to corrosion, thus incurs higher
made air-tight to isolate sensitive equip- maintenance cost; requires periodic re-
ment from outside corrosive atmo- painting and cladding replacement.
sphere.
Aesthetics Visually more appealing to most people. On unbroken flat horizons, large structure
is often an aesthetic problem.
Cost Depending on location and availability of In remote locations a steel headframe con-
the material, concrete headframe can be struction is usually cheaper.
less costly.
Source: Butler and Schneyderberg, 1981.

LOADINGS. All headframes should be designed to withstand In the case of headframes for drum hoists, provision must
a combination of loads, comprised of the following: (1) dead load be made for (1) lifting equipment and access for maintenance of
consisting of the weight of the headframe, sheave wheels, ore sheaves, (2) access and anchorage facility to support the ends of
bins, and contents; (2) live load from hoisting at maximum ca- hoist ropes, when doubling down for pretensioning drum end
pacity; (3) breaking loads of the ropes when the conveyance is coils, and (3) sub-collar loading access for double deck cages.
stopped by the crash beams or if it is jammed in the shaft (break- According to Cook and Werner (1966), the design of head-
ing stresses introduced by an overwind are usually transferred frames for friction hoists should address the following: (1) sup-
to the structural system, often through an arrestor gear, and porting facility at predetermined elevations for hoist or balance
thus the supporting structure must be critically analyzed with a ropes and conveyances or counterweights during installation and
thorough understanding of the arrestor mechanism); (4) wind changes; (2) clearance for installation of conveyance arrestor
load, the intensity of which depends on the location, height, and gear; (3) provisions for handling shaft ventilation air and for
shape of the structure; (5) snow load; and (6) temperature and sealing machinery rooms; (4) arrangement of MG sets close to
seismic stresses, taken from published data relating to the geo- hoist motors to minimize runs of heavy bus bars; (5) lifting
graphic area of the shaft location. equipment access during head and tail rope changing; (6) sup-
FOUNDATION. Simply stated, the foundation should be capa- port, accommodation, inspection, removal, and replacement
ble of withstanding and absorbing stresses imposed by the struc- facilities for rope guides where used; (7) ventilation to specific
ture and associated loads. machines and areas, controlling moisture, dust, and temperature
MINE SERVICES. The design of the headframe must suit where required; (8) accommodation of sinking arrangements; (9)
surface layouts for providing the essential mine services. When accommodation of all services for air, water, communications,
possible, it should be located close to the shaft collar house, and power lines to the shaft and to the headframe-mounted
waiting area, lamproom, first-aid room, hoist house, mainte- equipment; (10) the accommodation of stairwells and elevators;
nance shop, changing house, and administrative offices. The type and (11) lighting and lightning protection.
and design of headframe must also take into account the shaft SINKING PROVISIONS. After the decision has been made to
internal arrangement, position of the hoist with respect to the sink a shaft, considerations should be given to the type of surface
shaft, and the position of the sheave steel. Facilities for several sinking plant (such as headframe and hoist) that is to be used
key concerns listed must be considered and adequately developed for shaft sinking. In particular, it should be determined whether
during the conceptual design stage: (1) arrangement of skip the sinking plant is to be temporary or is to make use of the
dumping area in relation to ore and waste storage and handling permanent headframe and/or hoist.
facilities, (2) clearance required for installation, maintenance, Temporary Headframe—Generally, a temporary headframe
and removal of conveyances, (3) lifting equipment required for is used during shaft sinking by the contractor. These headframes
maintenance of conveyances, and (4) access required for mainte- may be a wood or steel structure in modular form. Some steel
nance of conveyances, dump areas, etc. headframes may be fabricated from hollow structural steel,
1676 MINING ENGINEERING HANDBOOK
which combines strength with light weight, and facilitates easy
erection and dismantling. Headframes of this type are portable
and have a high resale potential.
Design criteria for a temporary sinking headframe are the
same as for a permanent headframe. Its height depends upon the
method of rock disposal and size of bucket. The sinking head-
frame should embody features for dumping buckets or skips, for
protecting personnel on the surface and in the shaft from falling
pieces of rock while dumping, and minimizing work of top men
in dumping buckets and removing broken rock. The design of
temporary headframe structures should accommodate an ade-
quate-sized storage bin and sufficient clearance for a rock dis-
posal vehicle.
Permanent Headframe—Current trends favor installation of
a permanent headframe for the sinking operation, as it tends to
be more economical and time saving. The permanent main skele-
ton can be designed to facilitate erection and installation of the
sinking sheaves at a suitable elevation. The structure can then
be finished and equipped during the shaft sinking operation. The
use of the permanent structure as a sinking headframe can make
the permanent hoisting facilities available at an earlier date fol-
lowing completion of the shaft sinking program.
E QUIPMENT MONITORING FACILITIES. Two main hoisting
incidents, which can be detrimental to personnel and equipment
and require monitoring, are (1) overtravel at the shaft extremities
(i.e., sump, headframe), and (2) overspeed during the duty cycle.
In order to protect against these incidents, it is mandatory that
monitoring and safety devices be installed in the headframe.
Operation of all hoists are monitored mechanically by con-
trollers, such as the Lilly hoist controller. These are powered off
the hoist drums and check hoisting speed, overtravel at each end
of the wind, and deceleration in the end zones. Additionally,
track limit switches and conveyance arrestors must be incorpo-
rated. The function of track limit switches is to provide indepen-
dent overtravel protection in the headframe. Fig. 17.5.16. Vertical general arrangement of headframe.
Ultimate protection against overwind is provided for all fric-
tion hoists by conveyance arrestors. These are installed at the
ends of travel in each hoisting compartment. The headframe
arrestors are designed to retard an ascending conveyance from quate provisions for a heating system. In tower-mounted friction
70% of full speed at an acceleration of 0.9g. Shaft arrestors are hoisting systems, with all of the hoists, motors, and controls,
designed to retard an empty descending conveyance from full etc., enclosed in the headframe, it is necessary to provide a space
speed at 2g. ventilation system, supplying filtered air for both cooling and
Where applicable, the headframe should accommodate in- heating.
stallations of a crash beam and catch gear. With drum winders, MINING R EGULATIONS. Mining operations, including the
the crash beam is located below the sheaves in the headframe. design and construction of the headframe and shaft facilities, are
In the event of an excessive overwind, it stops the conveyance subject to local, state, and federal regulations that relate to,
from traveling beyond this point. Should a conveyance be in- among other things, safety of permanent structures and environ-
volved in an overwind situation in which the hoist ropes breaks, mental protection. These regulations affect the design and con-
the conveyance and tail ropes will fall down the shaft, causing struction of mine facilities.
damage. To prevent this, catch gear should be provided in the HEIGHT. Due to today’s increasing public awareness of the
headframe to “catch” the conveyance. aesthetic impact of industrial development, the height of the
C ONVEYANCE AND R OPE H ANDLING. In the design and headframe should be considered. This is especially true for loca-
layout of a headframe, provisions must be made for the handling tions in flat terrain where any large structure can be seen for
and changing of conveyances, hoisting ropes, and rope guides (if long distances. The height of a headframe is generally based on
applicable). Friction hoisting often requires the use of very large (1) storage bin capacity requirements for ore and waste, (2)
skips and cages. Because of their size, the service and handling clearance for loading facility under the storage bin, (3) arranging
of these conveyances, and the tying off the head and tail ropes that the resultant force from headframe loadings falls within the
associated with them, considerable problems can arise. In the backleg post, and (4) providing minimum clearance for convey-
friction hoist headframe, these can be facilitated through the ance overtravel beyond its normal travel to the headsheaves.
installation of an adequately sized overhead traveling crane. In Of the above, the determination of the minimum clearance for
the drum hoist headframe, handling and changing of convey- overrun distance is the principal design consideration. This mini-
ances and ropes are relatively easy and are usually achieved mum clearance is obtained after establishing the value of three
through the use of mobile cranes, rope blocks, and tugger hoists. separate allowances (1) operating allowance, (2) rope stretch
HEATING AND VENTILATION. In warm climates, the head- allowance, and (3) stopping allowance (Fig 17.5.16).
frame may be left open. However, in colder climates, it is neces- Operating Allowance—An operating allowance is required
sary to design the headframe as an enclosed structure with ade- to allow for variations in repeatability of the final stop position
HOISTING SYSTEMS 1677
of the conveyance in the headframe. In multilevel hoisting with Anon., 1948, “The Mechanical Parts of Electrical Mine Hoists,” Domin-
drum hoists, this tolerance compensates for differences in coiling ion Engineer, Vol. 15, No. 8, Part 3, Aug., Fig. 36, p.5.
and rope stretch. In the case of friction hoists, the allowance Anon., 1980a, Ropeman’s Handbook, National Coal Board, 3rd ed.
Anon., 1980b, “Wire Ropes for Mines,” American National Standards
compensates for creep during resynchronization and also allows
Institute, ANSI M11.1.
a reasonable gap for rope adjustment due to permanent rope Anon., 1981a, “Report On The Efficiency of Hoist Rope End Attach-
stretch. ments,” INCO Metals Co., Sudbury, Ontario, Jan.
Rope Stretch Allowance— This is included to avoid contact Anon., 1981b, “Procedures for Hoist and Shaft Inspection and Mainte-
with the track limit switch when empty conveyances are hoisted. nance,” Vol. I and II, USBM, PB83-148049 and PB83-148056,
The rope stretch allowance generally includes an additional l-ft Washington, DC.
(0.3-m) margin as well as the extra travel length during brake Anon., 1981c, Wire Rope User’s Manual, Committee of Wire Rope
deadtime and because of the effect of deceleration. Producers, American Iron and Steel Institute, 2nd ed.
Stopping Allowance—A stopping allowance is to ensure that Anon., 1987, “Occupational Health and Safety Act and Regulations for
clearance remains between the top of the conveyance and the Mines and Mining Plants,” Ontario Government, Apr.
Anon., 1989, Code of Federal Regulations, Mineral Resources, Title 30,
first obstruction in the headframe.
Parts 0 to 199, Washington, DC.
Calculations for Minimum Clearance—In an article describ- Albert, L., Cameron, A.M., and Gullick, J.W., 1975, “Hoisting Plants
ing hoisting plants at International Nickel Co., calculations for of International Nickel,” Proceedings, Hoisting Conference, AIME,
minimum headframe clearances were presented for both drum New York, Feb. 21.
hoists and friction hoists (Albert, Cameron, and Gullick, 1975). Atkinson, L.T.J., and Preator, R.W.T., 1973, “Theoretical and Experi-
These calculations are summarized in the following. mental Techniques Used in the Design of Winding Engine Drum
In computations for minimum clearances, two assumptions Structure,” Proceedings International Conference on Hoisting—
on hoist speed are made: (1) for rope stretch allowance, the hoist Men, Materials, Minerals, South African Institute of Mechanical
speed is 30 fpm (0.15 m/s); and (2) for the stopping allowance, Engineers, Oct. 16–24, pp. 253–271.
it is assumed that the speed has been reduced to 300 fpm (1.5 Backerberg, A.C., 1970, HSS Application Report, ADUSS 27-4119-01,
US Steel Corp., Jan. 22.
m/s).
Beerkircher, G., 1975, “Proper Selection to Fit the Application,” Pro-
For drum hoists, the minimum clearance from the top of the
ceedings, Hoisting Conference, AIME, New York, Feb. 21.
hoist rope capping, in its lowest fully dumped position, to the Bently, D.M., 1973, “The Equipment of Vertical Shafts—Present South
rim of the headsheave is given by (in English units): African Mining Practices and Development Trends,” Proceedings
7th Commonwealth Mining and Metallurgy Congress.
clearance = operating allowance + overtravel to Lilly limit Brucker, D., 1975, “Faster and Deeper—The Sagas of the Times in
+ rope stretch allowance + stopping allowance Hoisting,” ASEA Info. No AS100-104E, Montreal, Quebec, May 3.
Butler, D.W., and Schneyderberg, A.C., 1981, “Headframe Design Selec-
tion, Steel vs Concrete,” V.B. Cook Co., Ltd., Thunder Bay, On-
tario.
Cook, V.B., and Werner, M.P., 1966, “Layout Design and Construction
(17.5.43) of Concrete Towers for Tower Mounted Friction Hoists,” CIM
Bulletin, Vol. 59, No. 649, May, pp. 593–602.
where P is maximum rated payload in lb, L is maximum hoisting Cummins, A.B., and Given, I.A., eds., 1973, SME Mining Engineering
distance in ft, A is equivalent area of rope in in2., E is rope elastic Handbook, SME-AIME, New York, pp. 15–1 to 15–69.
modulus in psi, V 1 = 0.5 fps, V2 = 0.5 fps, a is hoist deceleration Dean, D.L., 1962, “Static and Dynamic Analysis of Guy Cables,” Trans-
rate in fps2, and t is brake deadtime in sec. actions of ASCE, Vol. 127, Pt. II, pp. 382–419.
For friction hoists, the minimum clearance from the top of DeHart, R.C., 1983, “Design of Large Diameter Shaft Liners,” Current
the skip in its lowest position to the underside of the arrestor Technology in Drilled Shaft Design and Construction, Vol. 2,
gear is given by (in English units): N.M.I.T. and I.S.D.T. Joint Seminar, Golden, CO.
De la Vergne, J., 1978, personal correspondence.
De la Vergne, J., and Cooper, L.O., 1983, “Simplified Procedure for the
Design of the Full Hydrostatic Steel Mine Shaft Line,” Transactions,
AIME, Vol. 274.
Delorme, G., 1977, “Selection and Maintenance of Ropes and Attach-
(17.5.44) ments for Use in Mine Shafts,” CIM Mechanical—Electrical Opera-
tors’ Conference, Sudbury, Ontario.
Dimitriov, C., and Whillier, A., 1973, “Vibrations In Winding Ropes,”
The required arrestor travel distance must be added to the Proceedings, International Conference on Hoisting—Men, Materials,
above clearance in order to calculate the total clearance to the Minerals, South African Institute of Mechanical Engineers, Oct.
headframe crash beam. The arrestor travel length is given by 16–24, pp. 350–362.
(English units): Dolan, H., 1961, “Rope Attachments and Associated Apparatus for
Hoisting and Guide Ropes in Vertical Mine Shafts,” Reliance Rope
Attachment Co., Cardiff, Wales.
(17.5.45) Duncan, J.M., et al., 1979, “Materials Handling for Urban Tunneling
in Rock,” Urban Mass Transportation Administration, UMTA-
MA-06-0100-79-7, May NTIS, Springfield, VA.
where L is arrestor travel length in ft, V is conveyance speed at Eastcott, P., de H., 1977, “Innovations in Hoisting Systems,” CIM Bulle-
time of entry in fps, a is maximum declaration rate of 0.9g tin, Vol. 70, No. 787, Nov., pp. 76–87.
(= 28.98 fps2), H is height of arrestor gear (assume 4 ft), and the Edwards, F.A., 1988, “A Systematic Approach to the Design of Mine
safety margin is 5 ft. Shaft Hoisting Systems,” Proceedings International Conference on
Hoisting of Men, Materials and Minerals, Canadian Institute of
Mining and Metallurgy, Vol. 1, June 12–17, pp. 39–73.
REFERENCES AND BIBLIOGRAPHY Harmon, J.H., 1973, “Hoists and Hoisting Systems,” SME Mining Engi-
Anon., 1942, “Electric Mine Hoists,” Westinghouse Electric Corpora- neering Handbook, Chap. 15, SME-AIME, New York, pp. 15–54 to
tion, East Pittsburgh, PA. 15–59.
1678 MINING ENGINEERING HANDBOOK
Harvey, T., 1973a, “Automatic Skip Loading—Techniques for Design Penning, F.A., et al., 1977, “Development of Vertical Shaft Skip and
and Implementation of Logic Requirements,” Proceedings, Interna- Guide Design,” USBM 17-4148, Jun., Washington, DC.
tional Conference on Hoisting—Men, Materials, Minerals, South Schulz, S.H., 1973, “Shaft Installations of High Winding Capabilities,”
African Institute of Mechanical Engineers, Oct. 16–24, pp. 140– Proceedings International Conference on Hoisting—Men, Materials,
143. Minerals, South African Institute of Mechanical Engineers, Oct.
Harvey, T., 1973b, “The Calculation of Rope Sizes and Power Require- 16–24, pp. 169–176.
ments of Winders,” Proceedings International Conference on Souter, B.N., 1973, “Ore Handling Arrangements in Shafts of the Repub-
Hoisting—Men, Materials, Minerals, South African Institute of Me- lic of South Africa,” Proceedings International Conference on
chanical Engineers, Oct. 16–24, pp. 177–186. Hoisting—Men, Materials, Minerals, South African Institute of Me-
Landau, F., and Hedstrom, K., 1973, “Some Aspects of Modern Hoisting chanical Engineers, Oct. 16–24, pp. 54–84.
Equipment,” Proceedings International Conference on Hoisting— Staley, W.W., 1936, “Mine Hoists,” Mine Plant Design, 1st ed.,
Men, Materials, Minerals, South African Institute of Mechanical McGraw-Hill, New York, p. 137.
Engineers, Oct. 16–24, pp. 200–210. Tiley, G.L., 1957, “Friction Hoist Design Considerations,” CIM Bulle-
McCrossan, J.A.J., 1973, “Mine Winder Brake Design,” Proceedings tin, Vol. 50, No. 542, Jun., pp. 326–333.
International Conference on Hoisting—Men, Materials, Minerals, Tudhope, I.S.D., 1973, “Multi-Rope Winders for High Capacity
South African Institute of Mechanical Engineers, Oct. 16–24, pp. Hoisting,” Proceedings, International Conference on Hoisting—Men,
276–284. Materials, Minerals, South African Institute of Mechanical Engi-
Muller, G.F., 1978, “Thyristor Drives Captures Mine Hoist Markets,” neers, Oct. 16–24, pp. 152–168.
Engineering and Mining Journal, Vol. 179, No. 8, Aug., pp. 65–71. Van Wyk, C.F.B., 1961, “A Review of Progress in the Design of Shaft
Oakden, H., 1973, “Methods of Controlling Coiling of Multiple Layers Requirement Aimed at a Reduction in Shaft Resistance,” South
of Wire Rope on Cylindrical Drums with Particular Reference to the African Mechanical Engineer.
LeBus System,” Proceedings International Conference on Hoisting— Whillier, A., 1976, Computer Aids in the Design of Mine Hoists So As
Men, Materials, Minerals, South African Institute of Mechanical to Avoid Problems of Rope Whip,” Proceedings, Conference on
Engineers, Oct. 16–24, pp. 384–388. Automation in Mining, Mineral and Metal Processing, South African
Ostrowski, W.J.S., 1972, “Design Considerations for Modern Shaft Lin- Council for Automation and Computation, pp. 631–638, Sep.
ings,” CIM Bulletin, Vol. 65, No. 726, Oct., pp. 58–71. 13–17.

You might also like