Professional Documents
Culture Documents
Reference: 111224
Prepared for: ATLANTIC
STORMWATER, EROSION AND RENEWABLE ENERGY
WASHWATER MANAGEMENT PLAN PARTNERS (Pty) Ltd
Revision: 1
13 July 2015
Document control record
Document prepared by:
Aurecon South Africa (Pty) Ltd
Aurecon Centre
1 Century City Drive
Waterford Precinct
Century City, Cape Town, 7441
Document control
File path P:\Projects\111224 Solar Transport & Stormwater Man Studi\03 PRJ Del\6
REP\Kathu\AEPLegokoSolar_StormwaterManagementPlan_July2015-R1.docx
Current Revision 1
Approval
Name Name
Title Title
STORMWATER, EROSION
AND WASHWATER
MANAGEMENT PLAN
Figures
Figure 1: Key Plan 1
Figure 2: Typical Vegetation 4
Figure 3: Average Rainfall 5
Figure 4: Average Temperature 5
Figure 5: Drainage Characteristics 6
Figure 6: PV Area Main Catchment Areas. 7
Figure 7: Flow Distribution – Facility 9
Figure 8: Access Road 10
Figure 9: Typical Detail - Gravel Drift 11
Figure 10: Typical Detail – Berm 12
Figure 11: Typical Detail – Outlet with Erosion Protection 12
Figure 12 Washing Panels 16
Tables
Table 1: Catchment Areas 7
Table 2: Runoff Coefficient 8
Table 3: Runoff Calculations 9
Atlantic Renewable Energy Partners (Pty) Ltd, on behalf of AEP Legoko Solar (Pty) Ltd, has engaged
Aurecon to prepare a conceptual Stormwater Management Plan (SMP) for the proposed AEP Legoko
Solar PV Facility. on the farm known as Legoko Farm No 460 portion 2, situated in the District of
Kuruman Rd, Northern Cape Province, within the jurisdiction area of the Gamagara Local Municipality
near Kathu.
• Propose drainage elements such as side drains, outlets and other mitigation measures to
• Prepare a conceptual drainage layout plan and strategy for the project site.
• The recurrence period normally applied for this type of development to reduce risk of
increased maintenance during the operational phase, is 1:50 years.
The main economic activities in the area are mining and agriculture with livestock and game farming.
The monthly distribution of average daily maximum temperatures shows that the average midday
temperatures for Kathu range from 17°C in June to 30°C in January. The region is the coldest during
July when the mercury drops close to almost 0°C during the night.
3.2.1.1 PV Area
A2
Access 1
AEP Legoko Solar (Pty) Ltd.
A1
Access 2
It should be noted that in absence of detailed topographical information, 1:50000 topographical map
data was used to establish the drainage patterns. The catchment areas identified are:
Area
Catchment ID
(km²)
A1 11.58
A2 14.44
The runoff coefficient calculated and used in the flood estimation is 0,23 which is typical for the area.
3.3.2.1 PV Area
The runoff distribution for the respective catchment areas will be dictated by the layout of the PV area
as well as internal roads and channels. However the PV area (which is normally a combination of
blocks of similar size) should preferably be orientated in such a way, to minimise impact on natural
drainage patterns.
A typical configuration (subject to the final site development plan) is indicated in the following figure:
LEGEND
Crossing
Drainage Ditch
Existing Watercourse
Roads
Seasonal dams
There are two seasonal water bodies at the centre of the proposed site; water is likely to pond here
during times of rain. These areas should be kept clear to ensure minimum interference with drainage
patterns.
The 1:50 year runoff per catchment area is indicated in the following table:
Time of Peak
Runoff Intensity Area
Catchment ID Concentration Flow
Coefficient
(mm/h) (min) (km²) (m3/s)
A1 0.23 33 74 11.6 0.30
A2 0.23 34 72 14.4 0.38.5
Kuruman
Access 1 N14/6 km 46,26E
R380
AEP Legoko Solar (Pty) Ltd.
3.4.1 General
The existing drainage patterns and characteristics should be preserved as far as possible. To that end
it is suggested that existing contours (and vegetation) be retained as far as possible and that internal
roads are kept to minimum standards.
Drainage structures would generally be small diameter pipes (encased in concrete because of the low
fill anticipated) or preferably gravel or concrete drifts. Gravel drifts should be provided with a cut-off
wall on the down-stream side as a minimum requirement.
Flow
Access road
3.4.3 Berms
Berms are proposed to prevent external water from entering the PV area and directing flow to suitable
areas of release.
3.4.4 Outlets
All culverts located on the access road have concrete outlets with erosion protection.
Side drain outlets should be terminated with suitable erosion protection to reduce the velocity and flow
depth.
Project Life
Width
Stone
Side Drain Lining 3
Pitching Depth
Width
Concrete 1
Depth
Width
D 0.8D
Walls Gabions 3
200min
Application : Slope > 2% in erodible material
Top width = 300mm
1m invert protection downstream
Width
Stone D 0.8D
Masonry
4 200min
with 1:5
slopes Application : Slope > 2% in erodible material
Width = 300mm
1m invert protection downstream
100 mm concrete blinding class 15/19
1000 -
2W to 4W 3000
2W
In/Outlets Structure Concrete 2 W
Plan
Long Section
Application : Lined drain outlet with typical dimensions
Actual dimensions to be verified with detail design
1000 -
2W to 4W 3000
2W
Stilling
Concrete 1 W
Basin
Plan
D
1D to 2D
Long Section
Application : Lined drain drop outlet with typical dimensions
Actual dimensions to be verified with detail design
Although these measures are possibly required, it is highly unlikely due to the flat nature of the terrain
and the very low run-off volumes. It is therefore envisaged that only minimal of these measures will be
required such as:
• Stone masonry walls to reduce the flow velocity in steeper areas
• Side Drain Outlet with stone pitching to prevent erosion
• Temporary berms and straw bales during construction in the vicinity of identified streams to
reduce flow and sediment transport during this phase.
It will also be important to pay attention during the construction phase that no construction activities
will result in ponding water particularly in the vicinity of the roads and structures.
The proposed Stormwater Management Plan presents a proposed strategy for drainage elements
required to accommodate the stormwater through the site, between the PV panels and for the access
road to the facility.
The strategy is to follow the existing contours to minimise impacts on the existing drainage patterns.
The proposed drainage elements should be included in the detailed design to ensure effective
management of the stormwater through the site.