GROUND WORKS
Excavation
Oversite
A Remove top soil average not exceeding
150mm deep big pool 162 m2 650
Working Space
C Excavate working space to receive pool
and all its elements 92 m3 1495
Filling
F Back fill excavation with laterite and compact 92 m3 4550
Concrete Work
Blinding
G 75mm thick blinding in cement and sand
mix (1:4) 146 m2 3900
Total To Collection
Water bar
A 9" sika water bar to joint between pool
base and its retaining wall 62 m 6500
Reinforcement
Wire Mesh
D Wire mesh to pool deck 299 m2 1040
Form Work
Sawn Timber formwork to:
Engine Room
G 1 units 1950000
Construction of engine room not exceeding 10 x 4 meter
floor size and 4meter high, of concrete elements with
proper ventilative services, adequate illumination, and all
necessary functional accessories
Total to Collection
COLLECTION
PAGE 1
PAGE 2
FINISHES
Wall
Rendering
12mm render to vertical wall of pool in
sand and cement mix (1:3) inclusive of
water proof cement in cement mix (1:1)
Tile
Tile finish(spanish) to rendered surface of wall or
any approved equal fixed with suitable adhesive
Floor
Tile
C 8mm thick non-slip tiles surface tiles laid on
screeded surface(measured seperately) to
surrounding pool perimeter [Labour Only] 299 m2 910
Screeding
F 38mm cement and sand Screeding (1:4)
finished fair in water proof cement and
portland cement mix (1:1) 417 m2 1495
Finishes to Summary
SERVICES
Mechanical and Electrical
PURIFICATION EQUIPMENTS
A Skimmer 2 m 45500
B Drains 2 Nr 32,500
POOL ILLUMINATION
Services to Summary
Maintenance
Maintenance to summary
SUMMARY
1 GROUND WORKS
2 FINISHES
3 SERVICES
4 MAINTENANCE
Total
Add
Preliminaries
VAT 5% 5%
GRAND TOTAL
105,300.00
330,395.00
137,540.00
30,368.00
321,750.00
418,600.00
569,400.00
1,744,600.00
1,030,900.00
1,784,250.00
6,473,103.00
403,000.00
1,821,820.00
1,076,530.00
310,960.00
1,028,300.00
43,940.00
1,950,000.00
6,634,550.00
6,473,103.00
6,634,550.00
13,107,653.00
136,890.00
579,150.00
272,090.00
473,200.00
843,700.00
623,415.00
2,928,445.00
91,000.00
65,000.00
114,400.00
93,600.00
793,000.00
2,730,000.00
390,000.00
306,800.00
384,800.00
1,755,000.00
2,340,000.00
390,000.00
9,453,600.00
390,000.00
390,000.00
13,107,653.00
2,928,445.00
9,453,600.00
390,000.00
25,879,698.00
1,423,383.39
27,303,081.39
1,365,154.07
28,668,235.46
GROUND WORKS
A
Excavations(pool) and Concreteworks (in-situ concrete to:pool
base, walls and deck; Reinforcement works; Formworks)
FINISHES
B Rendering(pool wall), screeding(pool base and deck), and Tiling
works(pool wall, pool base and pool deck)
EQUIPMENTS
C Supply of pool equipment and fittings complete, to include
all service works
TREATMENT
E Chemical treatment to pool water for use
COMMISSION
F
Clearing / Cleaning and test running; and hand over of site
Total
Add
Preliminaries
VAT 5% 5%
GRAND TOTAL
13,107,653.00
2,928,445.00
7,090,200.00
2,363,400.00
390,000.00
200,000.00
26,079,698.00
1,223,383.39
1,365,154.07
28,668,235.46