You are on page 1of 98

DETAILED ESTIMATE

Name of the Construction of P I U Sub Division Office


Work : Building at Nuzvid in Krishna District

Estimate Cost : Rs. 15.00 Lakhs


Name of the Work : Construction of P I U Sub Division Office Building at Nuzvid in
Krishna District Estimate Cost : Rs. 15.00 lakhs

Specification report to accompanying the Detailed Estimate for the work


Construction of P I U Sub Division Office Building at Nuzvid in Krishna District

The Above work sanctioned under MPP Grant,vide G.O.RT.No.888,PR&RD(Procgs-


II),Dept,Dt:26-10-2016, for Rs.15.00Lakhs. Hence the estimate is prepared with following
provisions.

The following items are provided in the Detailed Estimate as per the requirement as
follows
1. Earth work excavtion for foundations
2. PCC 1:4:8 prop. for foundations

3. Brick Masonry for panel walls in super structure with cm 1:8


4. Plastering 12 mm thich two coat
5. M20 mix concrete for foundations columns, beams and slabs
6. Reinforced Brick Masony for panel walls in superstructure with CM (1:4)
7. Doors of size 1.00 x 2.10 m
8. Toilets Doors of size 0.75 x 2.10
9. Ventileaters of size 0.75 x 0.60
10. Applying of Wall putty and Emulsion
11. Zyp board fals ceiling

12. dadooing of walls upto 2.1 m height at toilets

13. Flooring with Non skid Ceramic tiles of size 300 x 300 mm

14. Required Sanitory & Electrical items

Necessary provisions were made in the estimate for VAT @ 5% and Q.C. Charges
at 0.5% , NAC @ 0.1 % etc.

The Deatailed Estimate is prepared with present SSR 2016-2017


RATES AS PER S.S.R 2016-17
2016-17
Sl.No SSR NO Name of the Material
Per Rate
1 2 3 4
93 36.a Sand for concrete Cum 85.13

94 36.c Sand for Mortor (or) plastering Cum 152.13

95 36.b Sand for Filling Cum 85.13

4 M-189(b) Water charges for Rural Kl 77.00

90 34 Gravel Cum 103.00


173 Binding wire Kg 70.00
6 BMT-F-28 Rabit wire mesh (Chicken mesh) 1Sqm 17.00
Coarse Aggregate IRC&SS5, HBG (including
7
Blasting & Crushing Charges)

a R&B33b 10mm Nominal size Cum 935.00

b R&B33c 12mm Nominal size Cum 1097.50

c R&B33d 20mm Nominal size Cum 1365.00


d R&B33e 25mm Nominal size Cum 1312.50
e R&B33f 40mm Nominal size Cum 845.00
f Irr M-045 20-10mm Aggregate size Cum 1582.50
g Irr M-052 13.20/12.50mm Nominal size Cum 1097.00
h Irr-7 10-4.75 mm Nominal size Cum 875.00
i 13.2 mm to 0.09 mm Cum 1067.50
j 11.2 mm to 0.09 mm Cum 950.00
M-016 9.50 to 4.75 mm close graded GSB material Cum 592.00
M-018 4.75 to 2.36 mm close graded GSB material Cum 510.00
49 33.e 19 to 22 mm (IRC & MORTH) Cum 1300.00
51 33.g 40 to 45 mm (IRC & MORTH) Cum 805.00
52 33.i 60 to 63 mm (IRC & MORTH) Cum 489.00
8 M-148 RR stone Cum 252.00
22.a RR stone (For Masonry work -OTG) Cum 250.00
R&B SS-b-
9 Bond stone (600 x 200 x 200mm) Each
28
10 BMT-H-01 Water Proofing compound (Acco-proof) Kg 52.00
1000
11 BMT-A-01 Bricks 2nd Class traditional size (23x11x7 cm) 5200.00
Nos
1000
12 BMT-A-10 Fly ash bricks of size 290X225X140mm (50Kg) 24000.00
Nos
1000
13 BMT-A-11 Fly ash bricks of size 290X200X140mm (50Kg) 19000.00
Nos
1000
14 BMT-A-12 Fly ash bricks of size 290X150X140mm (50Kg) 20000.00
Nos
1000
15 BMT-A-13 Fly ash bricks of size 290X112/100X140mm (50Kg) 11000.00
Nos
Polished shabad stone 15-18 mm thick (0.457
16 BMT-B-05 10 Sqm 1654.00
x0.304))
Polished Kadapa slabs min of 15 mm thick (0.457
17 BMT-B-06 10 Sqm 1379.00
x 457))
18 BMT-B-01 Kadapa slab 40 mm thick (0.457 x 0.457)) 1 Sqm 96.00
Polished Bethmcherla (Marble type) white stone of
19 BMT-B-07 10 Sqm 3859.00
min of 25mm thick (0.254x0.254)
Polished Bethmcherla coloured stone of 25mm
20 BMT-B-08 10 Sqm 2756.00
thick
21 BMT-B-04 Shabad stone 40mm thick 10 Sqm 1239.00
22 BMT-B-03 Shabad stone 25mm thick 10 Sqm 961.00
23 BMT-C-01 Ceramic tiles (7.3mm thick 1st quality) Sqm 465.00
Vitrified tiles polished floor tiles of size not less
24 BMT-C-14 Sqm 1123.00
than795x795x8 mm thick normal colour
Vitrified tiles polished floor tiles of size not less
25 than598x598x8 mm thick normal colour Sqm 631.00

25 BMT-C-07 Coloured glazed tiles Sqm 413.00


26 BMT-E-05 Best Teak wood scantling upto 2.00m Cum 137941.00
27 BMT-E-06 BestTeak wood scantling upto 2.00-3.00m Cum 146840.00
28 BMT-E-01 Medium Teak wood scantling upto 2.00m Cum 80094.00
29 BMT-E-02 Medium Teak wood scantling upto 2.00-3.00m Cum 88994.00
30 BMT-E-08 Best Teak wood planks Cum 173539.00
31 BMT-E-04 Medium Teak wood planks Cum 160189.00
32 BMT-E-15 Sal wood scantlings any length Cum 51994.00
33 BMT-E-16 Sal wood planks any thickness Cum 69327.00
34 BMT-E-17 AC sheet corrugated 6mm thick Sqm 222.00
35 BMT-E-18 AC sheet plain 4mm thick Sqm 159.00
36 BMT-E-19 AC sheet plain 6mm thick Sqm 165.00
Plain or corrugated GI sheet (0.1mm to 0.8mm
37 BMT-E-20 Kg 60.00
thick)
1101 BMS-W-15 Cement Jali 25mm thick Sqm 226.00
1102 BMS-W-16 Cement jolly 40mm thick Sqm 293.00
Cement jolly 50mm thick Sqm 402.00
40 BMT-U-02 Joint filler board 20 mm thick Sqm 902.00
1106 BMS-W-20 Mastic pad 25.4mm thick Sqm 991.00
1107 BMS-W-21 Mastic pad 12.7mm thick Sqm 568.00
174 Jute Rope Mts 8.75
177 Polythene sheet 125 Microns 1 Sqm 18.00
176 Bituminous Selent Lit 69.50
448 BMT-H-147 Bituminous primer Kg 85.00
410 BMT-H-109 Concrete plasticizers and water reducing Agent Lit 150.00
711 BMT-M-24 Supply of Thermocole 12mm thick sheets Sqm 26.00
712 BMT-M-38 Supply of Thermocole 19mm thick sheets Sqm 46.00
PAINTS & POLISHES
485 BMT-J-08 White lead Kg 113.00
44 BMT-J-22 Plastic emulsion Lit 261.00
500 BMT-J-23 Plastic emulsion superior grade Lit 473.00
101 BMT-W-68 White cement Kg 29.00
47 BMT-J-01 Cement Primer Gr.I (Interior) Kg 165.00
48 BMT-J-02 Cement Primer Gr.I (exterior) Kg 210.00
480 BMT-J-03 Rex Oxide Gr.I Lit 142.00
50 BMT-J-05 Wood primer Lit 158.00
497 BMT-J-20 Dry power distember Kg 47.00
52 BMT-J-21 Oil bound washeable distemper Kg 90.00
501 BMT-J-24 Snowcem paintWater proof cement paint Kg 53.00
507 BMT-J-30 Synthetic Enamel paint Gr.I Lit 276.00
55 Mild steel bars MT 48000.00
56 BMT-F-04 Mild steel Tubes & Pipes in all dia Kg 61.00
1049 BMM-V-14 Fabrication of iron girlls, doors & windows 1Kg 24.00

1050 BMM-V-15 Fixing charges of iron grills, doors & windows. 1Kg 4.00

711 BMT-M-37 Supply of Thermocole 12mm thick sheets Sqm 26.00


712 BMT-M-38 Supply of Thermocole 19mm thick sheets Sqm 46.00
Centering charges
A Footings Cum 750.00
C Pedestals Cum 1068.00
D Plinth Beams Cum 2476.00
G Columns Cum 2041.00
H Beams Cum 3428.00
F Sun-Shades Sqm 410.00
E Lintels Cum 2344.00
I Roof slab up to 150mm thick Sqm 389.00
J Roof slab up to 150 to 300mm thick Sqm 399.00
Labour Rates
Mason 1stClass day 445.00
Mason 2ndClass day 400.00
Mazdoor day 350.00
Painter 1st class day 480.00
Painter 2nd class day 375.00
Blacksmith/Barbender day 440.00
Carpenter 1stClass day 420.00
Carpenter 2ndClass day 375.00
Machinery Hire charges
1 Dozer (D 80)-spreading,cutting,clening Hr 2562.60

2 Dozer (D 50)-spreading,cutting,clening Hr 1649.00

3 Motor Grader-spreading,clening,GSB,WMM Hr 3220.00

4 Front end Loader-Soil loading,Aggregate loading Hr 1650.00


Tipper 5.5 cum-Transportaion of
5 Hr 924.10
soil,GSB,WMM,Hot mix
6 Smooth wheeled Roller 8 Tonnes Hr 1122.10

7 Vibratory Roller 8 Tonnes Hr 2637.20

8 Waer Tanker 6 KL Hr 630.00

9 Waer Tanker 8 KL Hr 879.90

10 Tractor wih Rotavator Hr 425.00

11 Air Compressor (7 cm -Diesel) Hr 1166.20

11 Jack Hammer Hr 349.40

12 Wet Mix plant 60 TPH Hr 1650.00

13 Hydraulic Broom Hr 375.00

14 Biumen Pressure Distributor Hr 1500.00

15 Emulsion Pressure Distributor Hr 860.00

16 Hot Mix plant 60 TPH capacity Hr 28200.00

17 Paver finisher Machanical 100 TPH Hr 2250.00


Paver finisher Hydrostatic with sensor conrol 100
17 Hr 3060.00
TPH
18 Generator -100 KVA Hr 1126.00

19 Concrete mixer 0.28 cum Hr 471.10

20 Needle Vibrator 40mm (Perol) Hr 175.40

Seigniorage
Metal Cum 75.00
Sand Cum 50.00
Gravel Cum 30.00

Clearing site
109 1.a Clearing Heavy jungle 1Sqm 3.20
1Sqm
110 b Clearing Light jungle 2.80

1Sqm
112 d Clearing Juliflora 4.40

Cutting and Removing Palmyrah Trees of Girth 30 Each


113 2.a.1 21.00
to 100 cm
Cutting and Removing Palmyrah Trees of Girth 100 Each
114 2.a.2 48.00
to 200 cm
115 2.b.1 Uprooting and Removing Palmyrah Trees of Girth Each 51.00
30 to 100 cm
116 2.b.2 Uprooting and Removing Palmyrah Trees of Girth Each 53.00
100 to 200 cm
60660.50
Name of the Work: Construction of P I U Sub Division Office
Building at Nuzvid in Krishna District

Estimate Cost : Rs. 15.00 Lakhs


GENERAL ABSTRACT
1 COST OF CIVIL WORKS 1288287

2 COST OF WATER SUPPLY & SANITORY ITEMS 63007

3 COST OF BUILDING ELECTRICAL ITEMS 67050

TOTAL 1418344

4 V A T Charges @ 5% 70917

5 Q C Charges @0.5% 7092

6 N A C Charges @0.1% 1418

7 L S for Unforeseen items 839

TOTAL Rs. 1498610


DETAILED ESTIMATE
Name of the Work: Construction of P I U Sub Division Office Building at Nuzvid
in Krishna District
ESTIMATE COST : RS. 15.00 Lakhs
Measurements
S. Description of Amount
No. Work Quantit Rate (Rs.)
No. L B D
y

CIVIL WORK ITEMS


Dismantling, clearing away and carefully stacking useful materials for re-use and disposal of
unserviceable materials with 100m lead as directed by Executive Engineer duly taking actual
1 premeasurements before dismantling including all labour charges , overheads & contractor profit
etc., complete
Stair case Slab 1 x 2 1.20 3.00 0.15 1.08
Stair case Landing 1 x 1 1.20 3.00 0.15 0.54
1.62 2419.00 3919
cum 1 cum
2 Earth work excavation for foundations (Manual Means) of buildings, septic tank, sump, compound
wall in ordinary soils and depositing on bank with an initial lead of 10m and 1m additional lift
charges over the initial depth up to 3m including all operational,incidental, labour charges such as
shoring, sheeting, planking, strutting etc., and overheads & contractors profit complete for finished
item of work excluding dewatering charges etc., as per SS 20 B(APSS 308)

Footing for Stair case 1 x 2 1.65 1.65 1.80 9.80


9.80 183.00 1794
cum 1 cum
3 Plain Cement Concrete (1:4:8) (cement: fine aggregate: Coarse aggregate) for foundations and
under flooring bed using coarse aggregate 40mm size hard , machine crushed granite from
approved quarry including cost and conveyance of all materials like cement, sand, coarse
aggregate, water etc. to site, including sales & other taxes on all materials and including all charges
for machine mixing, laying concrete in foundations and under flooring bed, ramming in 15 cm layers
finishing top surface to the required level curing etc., and overheads & contractors profit complete
for finished item of work. (APSS No. 402)

Footing for Stair case 1 x 2 1.65 1.65 0.15 0.82


0.82 3803.00 3106
cum 1 cum
4 Reinforced Cement Concrete M 20 design mix using 12mm size hard granite machine crushed
graded metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved
quarry, using a minimum quantity of 350 kgs. of cement per 1 cum of concrete including cost and
conveyance of all materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to
site including steel centering, shuttering, machine mixing, laying concrete, lift charges, curing etc.,
and overheads & contractors profit complete for finished item of work (APSS No. 402 & 403) .

a Stair case Foottings


F1 1 x 2 1.50 1.50 0.30 1.35
x 1.35 8420.00 11367
cum 1 cum
b Pedastals 1 x 2 0.60 0.60 0.60 0.43
0.43 8845.00 3821
cum 1 cum
d Columns
C1 1 x 2 0.35 0.23 5.00 0.81
0.81 9988.00 8040
cum 1 cum
e Roof Beams
B3 ( Stair Case Beams ) 1 x 2 0.30 0.30 0.30 0.05
B3 ( Stair Case Beams ) 1 x 2 1.50 0.30 0.30 0.27
B4 ( Cantilever ) 1 x 5 1.50 0.23 0.30 0.52
0.84 8716.00 7335
cum 1 cum
f Roof Slab (125mm thick)
Ground Floor Slab 1 x 1 5.20 3.70 19.24
19.24 1025.00 19721
sqm 1 sqm
g Slab 200mm thick
For stair-case 1 x 2 1.20 4.00 - 9.60

For landing 1 x 1 1.20 3.00 - 3.60

13.20 1488.00 19642


sqm 1 sqm
h 1st Floor columns
C1 1 x 2 0.35 0.23 3.35 0.54

0.54 10459.00 5641


cum 1 cum
i 1st Floor Beams
B1 1 x 2 13.92 0.35 0.30 2.92
B2 1 x 5 5.20 0.35 0.30 2.73
B3 ( Stair Case Beams ) 1 x 2 0.30 0.30 0.30 0.05

B3 ( Stair Case Beams ) 1 x 2 1.50 0.30 0.30 0.27

B4 ( Cantilever ) 1 x 5 1.50 0.23 0.30 0.52

0.84 9027.00 7596


cum 1 cum
j 1st Floor Slab 125mm thick

1 x 1 6.70 13.92 93.26


93.26 1091.00 101751
cum 1 cum
1st Floor Slab 200 mm thick
k
(stairs)
For stair-case 1 x 2 1.20 4.00 9.60
For landing 1 x 1 1.20 3.00 3.60
13.20 1538.00 20302
cum 1 cum
5 Brick masonry for panel walls in superstructure with CM (1:8) prop: (Cement : Screened sand) using
common burnt clay bricks of class as per Table- I of IS:1077-1992, Non- Modular or traditional size
23 x 11 x 7 cms from approved source having minimum crushing strength of 40 Kg/Sqcm. including
cost and conveyance of all materials like cement, screened sand, bricks, water etc., to site,
including sales & other taxes on all materials and such as labour charges, like mixing cement
mortar, scaffolding charges, constructing masonry, lift charges, curing, etc.,and overheads &
contractors profit complete for finished item of work. (APSS No. 501 & 504).

1st Floor
Super stucture 1 x 2 13.92 0.35 3.30 32.16
1 x 3 4.50 0.35 3.30 15.59
47.75
Deductions
Doors 1 x 3 1.00 0.35 2.10 -2.21
Doors 1 x 1 0.75 0.35 2.10 -0.55
Windows 1 x 5 1.80 0.35 1.35 -4.25
-7.01
40.74 5474 223005
cum 1 cum

6 Reinforced Brick masonry for panel walls in superstructure with CM (1:4) prop: (Cement : Screened
sand) using common burnt clay bricks of class as per Table- I of IS:1077-1992, Non- Modular or
traditional size 23 x 11 x 7 cms from approved source having minimum crushing strength of 40
Kg/Sqcm. including cost and conveyance of all materials like cement, screened sand, bricks, water
etc., to site, including sales & other taxes on all materials and such as labour charges, like mixing
cement mortar, scaffolding charges, constructing masonry, lift charges, curing, etc.,and overheads &
contractors profit complete for finished item of work. (APSS No. 501 & 504).

1 St Floor

Toilet 1 x 1 2.40 - 3.60 8.64


Toilet 1 x 1 1.20 - 3.60 4.32
Stair case Hand rail Portion 2 x 2 4.00 - 0.75 12.00
Stair case Landing Portion 1 x 2 3.00 - 0.75 4.50
Stair case Landing Portion 1 x 2 1.20 - 0.75 1.80
Parapit 1 x 2 13.92 - 0.75 20.88
Parapit 1 x 2 5.00 - 0.75 7.50
59.64 751 44790
cum 1 cum
Ground Floor

Stair case Hand rail Portion 2 x 2 4.00 - 0.75 12.00


Stair case Landing Portion 1 x 2 3.00 - 0.75 4.50
Stair case Landing Portion 1 x 2 1.20 - 0.75 1.80
18.30 695 12719
cum 1 cum
7 Providing High Yield Strength Deformed (HYSD) (Fe 415 grade as per IS 1786-1979) of different
diameters for RCC works , including labour charges for straightening, cutting, bending to required
sizes and shapes, placing in position with cover blocks of approved materials and size and tying and
lap-splicing with binding wire of 18 SWG, forming grills for reinforcement work as per approved
designs and drawings, including cost and conveyance of steel bars, including all wastages such as
overlaps, couplings, chairs, spacer bars including cost and conveyance of binding wire, cover blocks
and all incidental, operational, labour charges such as cutting, bending, placing in position, tying
including sales and other taxes on all materials etc. ,and overheads & contractors profit complete for
finished item of work.( APSS No.126)
1st Floor 3.00 53482.00 160446
MT 1 MT
8 Supply and placing of the Design Mix Concrete M 20 grade corresponding to IS 456 with minimum
cement content of 350 kgs per 1 cum of concrete with 20mm size graded machine crushed hard
granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved
quarry including cost and conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and sales & other taxes on all materials, centering using Casurina
Ballies, Bamboos, Wooden Reapers, Runners, Wood Posts, Wall Plates etc., including all
operational, incidental and labour charges such as weigh batching, machine mixing, lifting of
concrete manually, laying concrete, curing , overheads & contractors profit etc., complete but
excluding cost of steel and its fabrication charges for finished item of work (APSS No. 402) For
Lintels

1st Floor
For Door of size-1.00x2.10 m 1 x 4 1.30 0.35 0.15 0.27
For Door of size-0.75x2.10 m 1 x 1 1.05 0.35 0.15 0.06
For windows of size-1.50x1.20
1 x 6 2.10 0.35 0.15 0.66
m
0.99 10467.00 10358
cum 1 cum
9 Ornamental ceiling plastering 12mm thick single coat in CM (1:5) using screened sand including
cost and conveyance of all materials like cement, sand, water etc., to site, including sales & other
taxes on all materials, and all operational, incidental charges on materials and including cost of all
labour charges for mixing mortar, finishing, curing as directed by Engineer-in-charge etc., and
overheads & contractors profit complete for finished item of work.(SS 901,903 & 904)

Ground Floor
Stair case Slab 1 x 2 4.00 1.50 12.00
Landing 1 x 2 1.20 3.00 7.20
19.20 136.00 2611
sqm 1 sqm
1st Floor
Office 1 x 1 4.50 9.27 41.72
DEE Chamber 1 x 1 4.50 3.00 13.50
caridor 1 x 1 1.50 9.25 13.88
Stair case slab 1 x 2 4.00 1.50 12.00
Landing 1 x 2 1.20 3.00 7.20
88.29 154.00 13597
sqm 1 sqm
10 Plastering 12mm thick in two coats using screened sand with base coat of 8mm thick in CM (1:6)
and top coat of 4mm thick in CM (1:4) with dubara sponge finishing including cost and conveyance
of all materials like cement, sand, water etc., to site, including sales & other taxes on all materials,
and all operational, incidental charges on materials and including cost of all labour charges for
mixing mortar, finishing, scaffolding, lift charges, curing, including cutting grooves as directed by
Engineer - in - charge etc., and overheads & contractors profit complete for finished item of work.
(SS 901,903 & 904)

1 St Floor
Super stucture

2 x 2 13.92 - 3.60 200.45


2 x 3 4.50 - 3.60 97.20
1 x 2 2.40 - 3.60 17.28
1 x 2 1.20 - 3.60 8.64
Stair case Hand rail Portion 2 x 4 4.00 - 0.75 24.00
Stair case Landing Portion 2 x 2 3.00 - 0.75 9.00
Stair case Landing Portion 2 x 2 1.20 - 0.75 3.60
Parapit 2 x 2 13.92 - 0.75 41.76
Parapit 2 x 2 5.00 - 0.75 15.00
416.93
Deductions -
Doors 1 x 4 1.00 - 2.10 8.40
Doors 1 x 1 0.75 - 2.10 1.58
Windows 1 x 6 1.80 - 1.35 14.58
24.56
392.37 383.00 150279
sqm 1 sqm
11 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65 mm
and ISI marked flush door shutters of 30 mm thick single shutter with bond wood solid block board
type Core having cross bands and face veneers, hot pressed bonded with water proof phenol
formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both sides
commercial ply with internal lipping on all sides including cost and conveyance to site of teak wood
frame, flush shutter including supply andfixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x
5mm including cost of ISI marked MS powder coated fixtures of 3 Nos. butt hinges (IS:205) 150mm
long, 1 No. aldrop (IS:2681) 300mm long, 1 No. tower bolt (IS:204) of 200 mm x 10 mm dia at top ,
2 Nos. 150 mm long handles (IS:208), 1 No. door stopper and 1 No. rubber bush including fixing
the fixtures to door with required number of screws, bolt and nuts including labour charges for fixing
the frame in position, fixing the shutter to the frame etc., including overheads & contractors profit
complete for finished item of work as per APSS 1001 & 1002 (The vertical frame of door shall be
embedded in flooring for a depth of not less than 10 mm) (1000mm x 2100mm)

1 St Floor
For Door of size-1.00x2.10 m 1 x 5 1.00 - 2.10 10.50 0
10.50 3923.00 41192
sqm 1 sqm
12 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65mm
and ISI marked flush door shutter of 30mm thick single shutter with bond wood solid block board
type Core having cross bands and face veneers, hot pressed bonded with water proof phenol
formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both sides
commercial ply with internal lipping on all sides including cost and conveyance to site of medium
teak wood door frame, flush shutter, including suply and fixing 6 Nos. MS Z hold fasts of size
300mm x 40mm x 5mm including ISI marked MS powder coated fixtures 3 Nos. butt hinges (IS:205)
of 150mm long, 1 No. aldrop (IS:2681) 250 mm long,1 No. tower bolt (IS:204) of 150 mm x 10mm
dia, 2 Nos. 125mm long handles (IS:208),1 No. rubber bush including supplying and fixing 1.20mm
thick PVC sheet to full height of the shutter inside including labour charges for fixing the frame in
position, fixing the shutter to the frame etc., including overheads & contractors profit complete for
finished item of work as per APSS 1001 & 1002. (The vertical frame of door shall be embedded in
flooring for deth of not less than 10mm) ( 750mm x 2100mm )

Toilet Doors
1st Floor
For Door of size-0.75x2.10 m 1 x 1 0.75 - 2.10 1.58
1.58 4321.00 6806
sqm 1 sqm
13 Providing, supplying & fixing of Fixed Louvered Ventilator made out of multi chambered UPVC
sections with TPV gaskets having isolated drainage and reinforced with Galvanized Iron profiles
throughout the window. The outer frame having an overall size of 60 x 55 mm with reinforcement of
1 mm thickness and Mullion with overall size of 74 x 60 mm with reinforcement of 1 mm thickness.
Ventilator shall be provided with 4.5 mm pin head glass, standard hardware, wall thickness of frame
& mullion shall be 2.0 mm including cost and conveyance of all materials, accessories, labour
charges for transportation, erection at site, overheads and contractor profit etc., complete for
finished item of work

Ventilators 1 x 1 0.75 - 0.60 0.45 6823.00 3070


sqm 1 sqm
14 Supplying and fixing Gyp Board Suspended regular single layer false ceiling (GS-MFSC-4.1) using
12.5 mm thick Gyp Board conforming to IS 2095 - 1993 fixing to Gyp steel GI perimeter channels of
size 20 mm x 27 mm x 30 mm(web) of 0.55 mm thick along the perimeter of ceiling screw fixed to
brick work/ partition at 610 mm c/c and suspending the frame work using Intermediate channels (45
mm x 15mm x 15mm x 0.9 mm) from soffit at 1220 mm c/c with ceiling angle (25 mm x 10 mm x
0.55 mm) fixed with GI Cleat and steel expansion fasteners & connecting clip to the ceiling channels
(with knurled web of 51.5 mm x 26 mm x 10.5 mm x 0.55 mm) fixed in direction perpendicular to the
intermediate channel at 457 mm c/c and fixing the 12.5 mm tapered edge Gypboard with 25 mm
drywall screws at 230 mm c/c & jointing and finishing using joint compound and paper tape to have
a flush look including filling the tapered & square edges with jointing compound, two coats of drywall
topcoa including overheads and contractor profit etc., complete for finished item of work

1 x 1 4.50 - 9.27 41.72


1 x 2 4.50 - 3.00 27.00
68.72 910.00 62531
sqm 1 sqm
15 White washing two coats with white cement to ceiling to give an even shade after thouroughly
brushing the surface to remove all dirt and remains of loose powdered materials including cost of all
materials , labour charges and incidental such as scaffolding , lift charges etc., and overheads &
contractors profit complete for finished item of work in all floors.

AS per Plastering and ceiling


499.86 33.00 16495
Qtys.
16 Supplying and fixing of Unplasticised Poly Vinyl Chloride (UPVC) sliding windows three track - two
glass shutters sliding and one mesh shutter duly manufactured using UPVC reinforced profiles of
(94 mm x 45 mm)/(80 mm x 52 mm) x 2.0 mm for outer frames, (58 mm x 39 mm)/(54 mm x 38 mm)
x 2.0 mm for sliding shutter frames capable of mounting single glazing system structurally reinforced
with hot dip galvanized up to 50 microns of minimum thickness of 1.2 mm prefabricated & welded
through fusion welding the window sash shall be fitted with 5 mm thick clear float glass of reputed
make and mesh shutter frame shall be (42 mm x 25 mm)/(52 mm x 21.5 mm) x 2 mm fitted with
nylon/ polymer mesh on rollers/ pulley duly fixed with TPV Gaskets/ EPDM weathering seal resistant
accessories like locking system 1 No., per set of sashes and the system is to be installed at the site
using anchor fasteners, silicon rubber sealant, easy glazing/ deglazing at site etc., including cost
and conveyance of all materials, accessories, labour charges for transportation, erection at site with
templates for casement sizing, overheads and contractors profit etc., complete for finished item of
work

1 St Floor
For Windows of size-1.50x1.20
1 x 6 1.80 - 1.35 14.58
m
14.58 7583.00 110560
sqm 1 sqm
17 Supply & application of one coat water based cement primer of exterior grade II and two coats of
acrylic exterior emulsion paint having VOC (Volatile Organic Compound) content less than 50
grams/litre for exterior walls including cost and conveyance of all materials to site, sales & other
taxes, incidental, operational and all labour charges etc., and overheads & contractors profit
complete for finished item of work in all floors.
1 x 2 13.92 - 3.60 100.22

1 x 2 5.20 - 3.60 37.44

137.66
Deductions

Doors 1 x 4 1.00 - 2.10 -8.40

Windows 1 x 6 1.80 - 1.35 -14.58

-22.98
160.64 0.00 0
sqm 1 sqm
18 Supply & application of one coat water based cement primer of interior grade I and two coats of
acrylic emulsion paint having VOC (Volatile Organic Compound) content less than 50 grams/litre for
internal walls including cost and conveyance of all materials to site, sales & other taxes, incidental,
operational and all labour charges etc., and overheads & contractors profit complete for finished
item of work in all floors.

1 x 2 12.62 - 3.60 90.86


1 x 4 4.50 - 3.60 64.80
1 x 2 1.32 - 3.60 9.50
1 x 2 4.50 - 3.60 32.40
1 x 2 3.00 - 3.60 21.60
Ceiling 1 x 1 4.50 - 9.27 41.72
1 x 2 4.50 - 3.00 27.00
287.88
sqm
Deductions 1 x 5 1.00 - 2.10 -10.50
1 x 1 0.75 - 2.10 -1.58
1 x 6 1.80 - 1.35 -14.58
-26.66
261.23 148.00 42607
1 sqm
19 Providing and applying Wall putty of White Cement or Polymer or Cement based of average 1 to 2
mm thickness over plastered surface to prepare the surface even and smooth after thoroughly
brushing the surface to remove all dirt and remains of loose powdered materials, applying emery
paper, Sand the surface, clean & wipe off loose dust, applying knifing paste filler by putty knife /
muslin pad, air dry for 2 - 3 hrs, sand with 180 and 320 No., emery paper for the surface preparation
including cost and conveyance of all materials to work site and all operational, incidental, labour
charges, over heads and contractors profit etc., complete for finished item of work in all floors for
Internal walls

1 x 2 9.27 - 3.00 55.62


1 x 2 4.50 - 3.00 27.00
1 x 2 4.50 - 3.00 27.00
1 x 2 3.00 - 3.00 18.00
Ceiling 1 x 1 4.50 - 9.27 41.72
1 x 2 4.50 - 3.00 27.00
196.34
sqm
Deductions 1 x 5 1.00 - 2.10 -10.50
1 x 1 0.75 - 2.10 -1.58
1 x 6 1.80 - 1.35 -14.58
-26.66
169.68 193.00 37893
1 sqm
20 Providing Dadooing to internal walls with glazed colour tiles(IVORY OR GREY COLOUR) tiles I st
quality, set over base coat of CM (1:3) 12 mm thick with cement slurry of honey like consistency
spread at the rate of 3.30 kgs per sqm and jointed with white cement paste mixed with pigment
of matching shade to full depth, including cost of all materials like tiles, cement, sand and
water etc., complete including seigniorage charges, etc., complete for finished item of work,

1 St Floor 1 x 2 2.40 - 2.10 10.08


Deduct Door 1 x 2 1.20 - 2.10 -5.04
5.04 577.35 2910
sqm 1 sqm
21 Flooring with non-skid full body ceramic floor tiles of size 300mm x 300mm and thickness between 7
- 8mm 1st quality conforming to IS: 13711, IS: 13712, IS: 13630(Part 1 to 15) of any colour and
finish in all shades and designs as approved by Engineer-in-charge, set over base coat of cement
mortar (1:8), 12mm thick using screened sand over CC bed already laid or RCC roof slab, including
neat cement slurry of honey like consistency spread @ 3.3 Kgs per Sqm & jointed neatly with white
cement paste to full depth mixed with pigment of matching shade, including cost of all materials like
cement, screened sand , water and tiles etc., and overheads & contractors profit complete for
finished item of work. (APSS No.701 & 707)

1st Floor 1 x 1 2.40 1.20 - 2.88


2.88 834.54 2403
sqm 1 sqm
22 Flooring with soluble salt porcelain vitrified tiles screen printed and polished of size 600 x 600 mm
and thickness between 8 to 10mm 1st quality conforming to IS: 13711, IS: 13712, IS: 13630(Parts 1
to 15) of any colour and finish in all shades and designs with borders and design as per the
approved flooring pattern as directed by the Engineer-In -Charge, laying tiles using spacers of 2mm
thick, set over a base coat of CM (1:8) prop. 12mm thick using screened sand over CC bed
already laid or RCC roof slab , including neat cement slurry of honey like consistancy spread @
3.3 kgs per Sqm. and jointed neately with white cement paste to full depth mixed with pigment of
matching shade including cost and conveyance of all materials like cement, sand, water, tiles,
white cement etc., to site (excluding cost of C.C. bed) including cost of base coat and all labour
charges for mixing of cement mortar, laying tiles to required slope as directed by the Engineer-
in-charge etc.,and overheads & contractors profit complete for finished item of work. (APSS No.701
& 707)

1st Floor
1 x 1 4.50 9.27 - 41.72
1 x 2 4.50 3.00 - 27.00
1 x 0 1.50 9.25 - 0.00
68.72 1195.00 82114
sqm 1 sqm

Filling with useful available excavated earth (excluding rock) with a lead of 50 m in trenches, sides
of foundations and basement with initial lead in layers not exceeding 15cm thick, watering and
23 ramming including cost and conveyance of water to work site and all operaitonal, incidental, labour
charges, hire charges of T&P etc., and overheads & contractors profit complete for fnished item of
work (APSS NO.309&310)

Earth Quantity 1 x 2 1.65 1.65 1.80 9.80


Deduct PCC (1:4:8) 1 x 2 1.65 1.65 0.15 0.82
Deduct Footings 1 x 2 1.50 1.50 0.30 1.35
Deduct Pedastal 1 x 2 0.60 0.60 0.60 0.43
Deduct Column Portion 1 x 2 0.23 0.35 0.75 0.12
7.08 245.00 1735
sqm 1 sqm

Supply and placing of the Design Mix Concrete M 20 grade corresponding to IS 456 with minimum
cement content of 350 kgs per 1 cum of concrete using WEIGH BATCHER / MIXER with 20mm
size graded machine crushed hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS
2386 Part 1 to Part 8) from approved quarry including cost and conveyance of all materials like
cement, fine aggregate (sand) coarse aggregate, water etc., to site and including sales & other taxes
24 on all materials , centering using Casurina Ballies , Bamboos , Wooden Reapers , Runners , Wood
Posts , Wall Plates etc., for 60cm wide sun-shades 7.5cm thick at fixed end and 5cm thick at free
end with an average thickness of 6.25cm including all operational, incidental and labour charges
such as weigh batching, machine mixing, lifting of concrete manually, laying concrete, curing,
overheads & contractors profit complete etc., but excluding cost of steel and its fabrication charges
for finished item of work (APSS No. 402, 403 & 903)

For Windows 1 x 6 1.80 _ _ 10.80


For Doors 1 x 3 1.50 _ _ 4.50
15.30 450.00 6885
RM 1 RM

Providing impervious coat to exposed RCC roof slab surfaces to required slopes with CM (1:3)
prop. using screened sand 20mm thick (average) mixed with integral cement water proofing liquid
confirming to IS: 2645-2003 manufactured by reputed manufacturers as approved by Engineer-in-
charge at 1 Kg per one bag of cement, laid over roof slab when it is green, finished smooth with a
floating coat of neat cement and thread lining at regular intervals of 45cmx45cm including cost and
25
conveyance of all materials like cement, sand, water proofing compound, water etc., to site,
including sales & other taxes on all materials and operational, incidental, and labour charges for
mixing mortar, laying, lift charges, rendering smooth and thread lining, curing including rounding
off junctions of wall and slab etc., and overheads & contractors profit complete for finished item of
work. (APSS No. 901 & 903).

For Roof Slab 1 x 1 5.20 13.92 _ 72.38


72.38 3426.83 24805
sqm 10 Sqm

Providing skirting to internal walls to 10 cm height with soluble salt porcelain vitrified tiles screen
printed and polished of thickness between 8 to 10mm 1st quality conforming to IS: 13711, IS:
13712, IS: 13630(Parts 1 to 15) of any colour and finish in all shades and designs, length equal to
flooring tiles, set over base coat of CM(1:5) 12 mm thick using screened sand with cement slurry of
26
honey like consistency spread at the rate of 3.30 kgs per sqm and jointing with white cement paste
mixed with pigment of matching shade to full depth, including cost of all materials like tiles,
cement, sand and water etc.,and overheads & contractors profit complete for finished item of work.
(APSS No.701 &707)

1 x 2 9.27 _ 18.54
1 x 2 4.50 9.00
1 x 1 9.27 9.27
2 x 2 4.50 18.00
2 x 2 3.00 12.00
66.81 87.00 5812
RM 1 RM
Providing 110 mm Dia ISI marked PVC down water take pipes with socket , 2.5mm thick 4.0
kg/sq.cm pressure of ISI marked including cost of necessary PVC Bends, shoes, iron / PVC clamps
and all other accessories and fixing in position including cost and conveyance of all materials, sales
27
& other taxes on materials to site, operational & incidental charges including all labour charges for
fixing at site etc., and overheads & contractors profit complete for finished item of work. (APSS
No. 1328)

For Roof Slab 1 x 3 3.50 _ 10.50


1 x 3 7.00 21.00
31.50 274.00 8631
RM 1 RM
Sub-Total 1288287
WATER SUPPLY & SANITORY ITEMS
1 Constructing 904.0 mm (3’0”) dia brick masonry inspection chamber as per IS - 4111: Part-1:1986
with cement mortar (1:6) prop using 2nd Class Clay Bricks of 225 mm thick from approved source
having a minimum crushing strength of 5 N/sq.mm including plastering with cement mortar 1:3
prop; ½” thick both inside and outside fitted with 20” dia RCC manhole covers and frames including
excavating pits up to a depth of 904 mm (3'-0") in all sorts of soils (exculding rock) and laying
cement conrete (1:4:8) 150 mm thick using 40 mm HBG Metal and P.C.C. 1:2:4 benching and
channel 100 mm thick as per Standard specification and including cost and conveyance of all
materials like cement, sand, bricks, water etc., to site, cost of seigniorage charges on all materials
and all incidental and operational, labour charges like mixing cement mortar, constructing masonry,
lift charges, curing , overheads & contractors profit etc., complete for finished item of work as per
Standard specification.

1 x 1 1.00 7646.00 7646


No. 1 No.
2 Constructing 904.0 mm (3’0”) dia brick masonry inspection chamber as per IS - 4111: Part-1:1986
with cement mortar (1:6) prop using 2nd Class Clay Bricks of 225 mm thick from approved source
having a minimum crushing strength of 5 N/sq.mm including plastering with cement mortar 1:3
prop; ½” thick both inside and outside fitted with 20” dia RCC manhole covers and frames including
excavating pits up to a depth of 1524 mm (5'-0") in all sorts of soils (exculding rock) and laying
cement conrete (1:4:8) 150 mm thick using 40 mm HBG Metal and P.C.C. 1:2:4 benching and
channel 100 mm thick as per Standard specification and including cost and conveyance of all
materials like cement, sand, bricks, water etc., to site, cost of seigniorage charges on all materials
and all incidental and operational, labour charges like mixing cement mortar, constructing masonry,
lift charges, curing , overheads & contractors profit etc., complete for finished item of work as per
Standard specification.

1 x 0 0.00 12032.00 0
No. 1 No.
3 Supplying and fixing of SWR PVC pipes (Prince/Sudhakar/Kisan/Supreme or any ISI brand) 4
Kg/Sq.cm. and fixing all special such as plain bends, off sets, door bends, single junctions, double
junctions as per site requirement, fixing with PVC clamps if necessary with required number of
Bombay nails including cost and conveyance of all materials to site, labour charges, overheads &
contractors profit complete for finished item of work at all floor levels. (APSS No. 1302 1319 &
1326)

160 mm 1 x 6 6.00 536.00 3216


Rm 1 Rm
110 mm 1 x 24 24.00 403.00 9672
Rm 1 Rm
75 mm 1 x 21 21.00 252.00 5292
Rm 1 Rm
4 Supplying and fixing Indian make Flat Back Wash Hand Basin 1st quality conforming to IS:2556-
Part-4:1972 of size 550mm x 400mm with 32 mm nominal size C.P. Fitting with parallel pipe thread
conforming to IS:2963-1979 and fitted with 15 mm nominal bore Chromium Plated Pillar Tap of 1st
quality Indian make heavy duty complete with standard CI brackets including wooden blocks ,1
No.12.70mm PVC connection with brass union nuts CP coated , angle stop cock 12.70mm dia. first
quality Indian make heavy duty, 31.75mm dia. PVC flexible waste pipe 914.4mm length of 1st
quality including cost and conveyance of all materials to site, labour charges , overheads &
contractors profit for finished item of work

1 x 2 2.00 2004.00 4008


No. 1 No.
5 Supplying and fixing European Water Closet of 1st quality conforming to IS:2556-Part-2-1973 of
white glazed with 'S' trap,supplying and fixing best Indian make plastic seat and lid for European
water closets with rubber or plastic Buffers as per IS 2548-1996 and 10 litres capacity single flush
PVC low level cistern with internal components and fixed using required size of nails and screws,
angle stop cock 12.70mm dia. first quality Indian make heavy duty, 12mm PVC connections with
brass union nuts CP coated including cost and conveyance of all materials to site, overheads &
contractors profit etc., complete for finished item of work for all floors.

1 x 1 1.00 5664.00 5664


No. 1 No.
6 Supplying and fixing of 4" (101.6mm) multi floor trap with jali - UPVC/SWR pipe fittings as per site
requirements with standard practice for all floors including cost and conveyance of all materials to
site, labour charges , overheads & contractors profit etc., complete for finished item of work.
1 x 2 2.00 164.00 328
No. 1 No.
7 Supplying and fixing NP Bib Taps of size 12.70mm dia of Indian make heavy duty as approved by
the Engineer-In-Charge including cost and conveyance of all materials, labour charges, overheads
& contractors profit complete for finished item of work in all floors.
1 x 2 2.00 397.00 794
No. 1 No.
8 Supply and fixing of Ashirvad/ Ajay/ Astral Flowguard or equivalent CPVC Pipes and Fittings SDR
13.5 to meet the requirement of ASTM-D 2846 and are produced in CTS (Copper Tube Sizes 1/2" to
2") for hot and cold water (IS 15778:2007) including cost and conveyance of all materials to site,
labour charges for fixing, overheads & contractors profit complete for finished item of work at all floor
levels.

54.00mm OD pipe 1 x 6 6.00 596.00 3576


Rm 1 Rm
41.30mm OD pipe 1 x 12 12.00 409.00 4908
Rm 1 Rm
28.60mm OD pipe 1 x 30 30.00 241.00 7230
Rm 1 Rm
15.90mm OD pipe 1 x 18 18.00 160.00 2880
Rm 1 Rm

Supplying and fixing NP soap dish heavy type of approved make ISI quality with NP screws etc.,
9 complete including cost and conveyance of all materials, labour charges for fixing , overheads &
contractors profit for finished item of work in all floors
1 x 1 1.00 276.00 276
Supplying and fixing TV shape mirror with plastic frame of size 609.6mm x 457.2mm , plywood back
10 with NP screws 1st quality including cost and conveyance of all materials, labour charges ,
overheads & contractors profit for finished item of work in all floors.
1 x 1 1.00 514.00 514
Supplying and fixing of 25.4mm dia , 609.6mm long aluminium anodized towel rods with brackets
11 and aluminium screws including cost and conveyance of all materials, labour charges , overheads &
contractors profit for finished item of work.
1 x 1 1.00 186.00 186
Providing and placing on terrace (at all floor levels)polyetheylene water storage tank with double
layer approved brand and manufacture with cover and suitable locking arrangement and making
12 necessary holes for inlet and outlets and over flow pipes but without fittings and base support for
tanks including cost and conveyance of all materials and labour charges , overheads & contractors
profit complete for finished item of work.
1 x 1000 1000.00 6.82 6816.9

Sub-Total 63007
BUILDING ELECTRICAL ITEMS
1 Wiring with 2 runs of 22/0.3mm ( 1.5 Sq.mm) FRLS/HFFR P.V.C. insulated flexible copper cable (ISI
MARK) in existing pipe with 6A flush type switch control, ceiling rose and 3mm thick hylam sheet
covering to MS switch box including all labour charges etc., complete for light points, bell points, fan
and exhaust fan points in Non residential buildings.

1 x 24 24.00 445.00 10680


No. 1 No
2 Wiring with 2 of 22/0.3mm (1.5 Sq.mm) P.V.C. insulated FRLS/HFFR flexible copper cable (ISI mark)
in existing pipe with 6A switch and 6A, 3 pin/2 pin (2 in one) flush type socket fixing on existing
Common Board covered with 3mm thick hylam sheet including all labour charges etc., complete.

1 x 10 10.00 107.00 1070


No. 1 No
3 Supply & Fixing of 16A/6A, 2 in one, flush type socket with 16A flush type switch control on 6"x8"
size MS switch board covered with 3mm thick hylam sheet including giving connections and all
labour charges etc., complete.

1 x 2 2.00 298.00 596


No. 1 No
4 Supply and run of 1 of 22/0.3mm (1.5 Sq.mm) FRLS/HFFR P.V.C. insulated flexible copper cable in
existing pipe for mains inlcuding all labour charges etc., complete.
1 x 270 270.00 21 5670
Rm 1 Rm
5 Supply and run of 3 of 36/0.3mm (2.5 Sq.mm) FRLS/HFFR P.V.C. insulated flexible copper cable in
existing pipe for mains inlcuding all labour charges etc., complete.
1 x 180 180.00 87 15660
Rm 1 Rm
6 Supply and run of 3 of 56/0.3mm (4 Sq.mm) FRLS/HFFR P.V.C. insulated flexible copper in existing
pipe for mains inlcuding all labour charges etc., complete.
1 x 45 45.00 122 5490
Rm 1 Rm
7 Supply and run of 3 of 84/0.3mm (6 Sq.mm) FRLS/HFFR P.V.C. insulated flexible copper cable in
existing pipe for mains inlcuding all labour charges etc., complete.
1 x 20 20.00 179.00 3580
Rm 1 Rm
8 Supply, Transportaton, and fixing of 1x28W, box type powder coated energy conserving tube light
luminaire with Electronic ballast operating voltage range of 90 volts to 350 volts power factor > 0.98
current less than 130ma crest factor and total hormonic distortion shall be as per IS Specification
with auto cut off at high voltage suitable for 36/40W tube with 5 years guarantee for luminaire,
including all labour charges for fixing on 2 No TW round blocks and giving all connections with
flexible three core wire and cost and conveyance of all materials etc complete. (Trinic make only
with 5 Years guarantee)

1 x 8 8.00 1213.00 9704


No. 1 No
9 Supply of 48" (1200mm) Sweep ISI mark as per IS 374 - 1979 and 5 Star rated Ceiling Fan, with
double ball bearings but without Regulator of makes Crompton High Speed Plus / Bajaj Electra 50 /
Orient Energy Star / Havells ES 50.
1 x 8 8.00 1825.00 14600
No. 1 No
Sub-Total 67050
TOTAL 1418344
10 Provision for VAT charges at 5.00%. 70917
11 Provision for QC charges at 0.50%. 7092
12 Provision for NAC charges at 0.10%. 1418
13 Provision for Unforseen items and price escalation charges 839
Grand TOTAL 1498610
CIVIL DATA : Page-24
D A T A ( SoR 2016-17)
Name of the work: Construction of P I U Sub Division Office Building at Nuzvid in
Krishna District

Add MA charges at 20% 0.20


Overheads&Contractors Profit @13.615% 0.13615
CEMENT MORTAR PER CUM CM (1:2) CM (1:3) CM (1:4) CM (1:5) CM (1:6) CM (1:8)
Cost of Sand for mortar & Plastering
755.48 755.48 755.48 755.48 755.48 755.48
( 1.05 cum )

Cost of cement 3456.00 2304.00 1728.00 1382.40 1152.00 864.00


Mazdoor ( Unskilled ) for mixing mortar
( 0.20 Nos.) 70.00 70.00 70.00 70.00 70.00 70.00

Add MA charges at 20% 14.00 14.00 14.00 14.00 14.00 14.00


Rate per Cum 4295.48 3143.48 2567.48 2221.88 1991.48 1703.48

20 mm HBG graded metal


Arregates 20mm nominal size 0.60 1799.36 1079.62
Arregates 13.20 / 12.50mm nominal size 0.15 1531.36 229.70
Arregates 10mm nominal size 0.15 1369.36 205.40
Arregates 6mm nominal size 0.10 1169.36 116.94
Rate per Cum 1631.66

12 mm HBG graded metal


Arregates 13.20 / 12.50mm nominal size 0.60 1531.36 918.82
Arregates 10mm nominal size 0.20 1799.36 359.87
Arregates 6mm nominal size 0.20 1169.36 233.87
Rate per Cum 1512.56

DATA
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
1 Earth work excavation for foundations (Manual Means) of buildings, septic tank, sump, compound wall
in ordinary soils and depositing on bank with an initial lead of 10m and depth up to 3m including all
operational,incidental, labour charges such as shoring, sheeting, planking, strutting etc., and overheads &
contractors profit complete for finished item of work excluding dewatering charges etc., as per SS 20 B(APSS
308)
(BLD-CSTN-2-1)
Ordinary Soil - Manual Means up to 3m depth
Unit : 1 cum
Taking output : 10.00 cum
a) Labour
Mazdoor ( Unskilled) 3.64 Nos. 350.00 1 No. 1274.00
Add MA charges at 20% 0.20 1274.00 254.80
1528.80
b&c)
Overheads&Contractors Profit @13.615% 0.13615 1528.80 208.15
Cost for 10 cum ( a+b+c) 1736.95
Rate per cum (a+b+c) / 10 173.69
Rate per 1 cum Say 174
CIVIL DATA : Page-25
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
2 Earth work excavation for foundations (Manual Means) of buildings, septic tank, sump, compound wall
in ordinary soils and depositing on bank with an initial lead of 10m and 1m additional lift charges over the
initial depth up to 3m including all operational,incidental, labour charges such as shoring, sheeting, planking,
strutting etc., and overheads & contractors profit complete for finished item of work excluding dewatering charges
etc., as per SS 20 B(APSS 308)
(BLD-CSTN-2-1& COM-LDLFT-6-66)
Rate with initial lead & lift 1.00 cum 173.69 1 cum 173.69
Mazdoor for extra lift ( 1 No. for 60m) 0.02 Nos. 350.00 1 Each 7.00
Add MA charges at 20% 0.20 7.00 1.40
Overheads&Contractors Profit @13.615% 0.13615 8.40 1.14
Rate per 1 cum 183.24
Say 183.00

4 Filling with useful available excavated earth (excluding rock) with a lead of 50 m in trenches, sides of
foundations and basement with initial lead in layers not exceeding 15cm thick, watering and ramming including
cost and conveyance of water to work site and all operaitonal, incidental, labour charges, hire charges of T&P
etc., and overheads & contractors profit complete for fnished item of work (APSS NO.309&310)

(BLD-CSTN-2-9) & Amendment in page 13 of SoR 2014.15


Unit : 1 cum
Taking output : 6.00 cum
a) Labour
Mazdoor ( Unskilled ) 3.12 Nos. 350.00 1 No. 1092.00
Add MA charges at 20% 0.13615 1092.00 148.68
1240.68
Water 0.72 Kl 77.00 1 Kl 55.44
Rate per 6 cum (a+b+c) 1296.12
Overheads&Contractors Profit @13.615% 0.13615 1296.12 176.47
1472.58
Rate per 1 cum 245.43
Say 245

5 Plain Cement Concrete (1:4:8) (cement: fine aggregate: Coarse aggregate) for foundations and under
flooring bed using coarse aggregate 40mm size hard , machine crushed granite from approved quarry
including cost and conveyance of all materials like cement, sand, coarse aggregate, water etc. to site, including
sales & other taxes on all materials and including all charges for machine mixing, laying concrete in foundations
and under flooring bed, ramming in 15 cm layers finishing top surface to the required level curing etc., and
overheads & contractors profit complete for finished item of work. (APSS No. 402)

(BLD-CSTN-3-5)
Unit : 1 cum
A.MATERIALS :
Cement 162.00 Kgs 4800.00 1000 Kgs 777.60
Coarse aggregate 40mm 0.90 Cum 1279.36 1 Cum 1151.42
Fine aggregate ( Sand ) 0.45 Cum 649.50 1 Cum 292.28
Water (including curing) 1.20 kl 77.00 1 kl 92.40
B.MACHINERY :
Concrete Mixer 10 / 7 cft (0.2 / 0.8 1.00 hour 132.80 1 hour 132.80
cum)capacity
Crew charges 1.00 hour 219.70 1 hour 219.70
Add MA on crew charges 0.20 219.70 43.94
C.LABOUR :
1st class mason 0.10 Nos. 445.00 1 Each 44.50
Mazdoor (unskilled) 1.39 Nos. 350.00 1 Each 486.50
Add MA charges at 20% 0.20 531.00 106.20
3347.34
Overheads&Contractors Profit @13.615% 0.13615 3347.34 455.74
Rate per 1 cum 3803.08
Say 3803.00
CIVIL DATA : Page-26
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
10 Supply and placing of the Design Mix Concrete M 20 grade corresponding to IS 456 with minimum cement
content of 350 kgs per 1 cum of concrete using WEIGH BATCHER / MIXER with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved
quarry including cost and conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water
etc., to site and sales & other taxes on all materials , centering using Steel scaffolding pipes , jack props ,
wallers , Foot plates , brackets , steel centering plates etc., including all operational, incidental and labour
charges such as weigh batching, machine mixing, laying concrete, curing etc., and overheads & contractors profit
complete but excluding cost of steel and its fabrication charges for finished item of work (APSS No. 402)

(BLD-CSTN-3-14)
FOUNDATIONS , PLINTH , PEDESTALS ( Below Plinth)
A.MATERIALS :
Cement 350.00 Kgs 4800.00 1000 Kgs 1680.00
20mm HBG graded metal 0.80 Cum 1631.66 1 Cum 1305.33
Sand 0.40 Cum 649.50 1 Cum 259.80
B.LABOUR :
1st class Mason 0.133 Nos 445.00 1 Each 59.19
2nd class Mason 0.267 Nos 400.00 1 Each 106.80
Mazdoor (both men&women) 4.60 Nos 350.00 1 Each 1610.00
Add MA charges at 20% 0.20 1775.99 355.20
C.MACHINERY :
Batching plant 0.50 cum 1.333 hours 198.70 1 hour 264.87
Crew charges 1.333 hours 340.60 1 hour 454.02
Needle vibrator 40mm ( petrol ) 1.333 hours 26.40 1 hour 35.19
Crew charges 1.333 hours 158.20 1 hour 210.88
Add MA on crew charges 0.20 664.90 132.98
Water(including for curing) 1.20 kl 77.00 1 kl 92.40
Rate per 1 cum 6566.65

a Footings
Rate for Design mix M 25 1.00 Cum 6566.65 1 Cum 6566.65
Hire charges of centering and scaffolding 1.00 Cum 277.00 1 Cum 277.00
Labour charges 1.00 Cum 473.00 1 Cum 473.00
Add MA charges at 20% 0.20 473.00 94.60
7411.25
Overheads&Contractors Profit @13.615% 0.13615 7411.25 1009.04
Rate per 1 cum 8420.29
Say 8420.00

b Column pedestals
Rate for Design mix M 25 1.00 Cum 6566.65 1 Cum 6566.65
Hire charges of centering and scaffolding 1.00 Cum 315.00 1 Cum 315.00
Labour charges 1.00 Cum 753.00 1 Cum 753.00
Add MA charges at 20% 0.20 753.00 150.60
7785.25
Overheads&Contractors Profit @13.615% 0.13615 7785.25 1059.96
Rate per 1 cum 8845.21
Say 8845.00

c Plinth Beams
Rate for Design mix M 25 1.00 Cum 6566.65 1 Cum 6566.65
Hire charges of centering and scaffolding 1.00 Cum 1335.00 1 Cum 1335.00
Labour charges 1.00 Cum 1141.00 1 Cum 1141.00
Add MA charges at 20% 0.20 1141.00 228.20
9270.85
Overheads&Contractors Profit @13.615% 0.13615 9270.85 1262.23
Rate per 1 cum 10533.07
Say 10533.00
CIVIL DATA : Page-27
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
d Base slab 230mm thick for Sump / Septic tank :
Rate for Design mix M 20 0.23 Cum 6566.65 1 Cum 1510.33
Hire charges of centering and scaffolding 0.23 Cum 233.00 1 Cum 53.59
Labour charges 0.23 Cum 166.00 1 Cum 38.18
Add MA charges at 20% 0.20 38.18 7.64
1609.74
Overheads&Contractors Profit @13.615% 0.13615 1609.74 219.17
Rate per 1 sqm 1828.90
Say 1829.00

11 Supply and placing of the Design Mix Concrete M 20 grade corresponding to IS 456 with minimum cement
content of 350 kgs per 1 cum of concrete using WEIGH BATCHER / MIXER with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved
quarry including cost and conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water
etc., to site and sales & other taxes on all materials, centering using Casurina Ballies, Bamboos, Wooden
Reapers, Runners, Wood Posts, Wall Plates etc., including all operational, incidental and labour charges such as
weigh batching, machine mixing, lifting of concrete manually, laying concrete, curing , overheads & contractors
profit etc., complete but excluding cost of steel and its fabrication charges for finished item of work (APSS No.
402)

(BLD-CSTN-3-15)
COLUMNS, LINTELS, WATER TANKS, RCC WALL IN BUILDINGS:
A.MATERIALS :
Cement 350.00 Kgs 4800.00 1000 Kgs 1680.00
20mm HBG graded metal 0.80 Cum 1631.66 1 Cum 1305.33
Sand 0.40 Cum 649.50 1 Cum 259.80
B.LABOUR :
1st class Mason 0.167 Nos 445.00 1 Each 74.32
2nd class Mason 0.167 Nos 400.00 1 Each 66.80
Mazdoor (both men&women) 5.60 Nos 350.00 1 Each 1960.00
Add MA charges at 20% 0.20 2101.12 420.22
C.MACHINERY :
Batching plant 0.50 cum 1.333 hours 198.70 1 hour 264.87
Crew charges 1.333 hours 340.60 1 hour 454.02
Needle vibrator 40mm ( petrol ) 1.333 hours 26.40 1 hour 35.19
Crew charges 1.333 hours 158.20 1 hour 210.88
Add MA on crew charges 0.20 664.90 132.98
Water(including for curing) 1.20 kl 77.00 1 kl 92.40
Rate per 1 cum 6956.80

a) COLUMNS :
un supported height up to 3.66 m
Rate for other Floors FF SF TF
Rate as above 6956.80 6956.80 6956.80
Hire charges of centering and scaffolding 229.00 229.00 229.00
Labour charges 1338.00 1473.00 1606.00
Add MA charges at 20% 267.60 294.60 321.20
Lift charges of materials(Manual) 0.00 210.11 420.22
Add MA charges at 20% 0.00 42.02 84.04
Rate per 1 cum 8791.40 9205.54 9617.27
Overheads&Contractors Profit @13.615% 1196.95 1253.33 1309.39
Rate per 1 cum 9988.35 10458.87 10926.66
Say 9988 10459 10927

b) LINTELS :
Rate for other Floors FF SF TF
Rate as above 6956.80 6956.80 6956.80
Hire charges of centering and scaffolding 760.00 760.00 760.00
Labour charges 953.00 1048.00 1144.00
Add MA charges at 20% 190.60 209.60 155.76
Lift charges of materials(Manual) 0.00 210.11 420.22
CIVIL DATA : Page-28
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
Add MA charges at 20% 0.00 28.61 57.21
Rate per 1 cum 8860.40 9213.13 9493.99
Overheads&Contractors Profit @13.615% 1206.34 1254.37 1292.61
Rate per 1 cum 10066.74 10467.50 10786.60
Say 10067 10467 10787

c) WATER TANKS, SUMP, LIFT :


150mm thick side walls
Cost of M 25 design mix 0.15 cum 6956.80 1.00 cum 1043.52

Rate for other Floors FF SF TF


Rate as above 1043.52 1043.52 1043.52
Hire charges of centering and scaffolding 876.00 876.00 876.00
Lift charges of materials(Manual) 0.00 31.52 63.03
Add MA charges at 20% 0.00 6.30 12.61
Rate per 10 sqm 1919.52 1957.34 1995.16
Overheads&Contractors Profit @13.615% 261.34 266.49 271.64
Rate per 1 sqm 2180.86 2223.83 2266.80
Say 2181 2224 2267

d) 200mm thick side walls


Cost of M 20 design mix 0.20 cum 6956.80 1.00 cum 1391.36

Rate for other Floors FF SF TF


Rate as above 1391.36 1391.36 1391.36
Hire charges of centering and scaffolding 876.00 876.00 876.00
Labour charges 0.00 0.00 0.00
Add MA charges at 20% 0.00 0.00 0.00
Lift charges of materials(Manual) 0.00 42.02 84.04
Add MA charges at 20% 0.00 8.40 16.81
Rate per 10 sqm 2267.36 2317.78 2368.22
Overheads&Contractors Profit @13.615% 308.7 315.57 322.43
Rate per 1 sqm 2576.06 2633.35 2690.65
Say 2576 2633 2691

12 Supply and placing of the Design Mix Concrete M 20 grade corresponding to IS 456 with minimum cement
content of 350 kgs per 1 cum of concrete using WEIGH BATCHER / MIXER with 20mm size graded machine
crushed hard granite metal(coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved
quarry including cost and conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water
etc., to site and sales & other taxes on all materials , centering using Casurina Ballies , Bamboos , Wooden
Reapers , Runners , Wood Posts , Wall Plates etc., including all operational, incidental and labour charges such
as weigh batching, machine mixing, lifting of concrete manually, laying concrete, curing , overheads & contractors
profit etc., complete but excluding cost of steel and its fabrication charges for finished item of work (APSS No.
402)

(BLD-CSTN-3-16)
RCC SLABS , BEAMS :
A.MATERIALS :
Cement 350.00 Kgs 4800.00 1000 Kgs 1680.00
20mm HBG graded metal 0.80 Cum 1631.66 1 Cum 1305.33
Sand 0.40 Cum 649.50 1 Cum 259.80
B.LABOUR :
1st class Mason 0.067 Nos 445.00 1 Each 29.82
2nd class Mason 0.133 Nos 400.00 1 Each 53.20
Mazdoor (both men&women) 3.077 Nos 350.00 1 Each 1076.95
Add MA charges at 20% 0.20 1159.97 231.99
C.MACHINERY :
Batching plant 0.50 cum 0.308 hours 198.70 1 hour 61.20
Crew charges 0.308 hours 340.60 1 hour 104.90
Needle vibrator 40mm ( petrol ) 0.308 hours 26.40 1 hour 8.13
Crew charges 0.308 hours 158.20 1 hour 48.73
CIVIL DATA : Page-29
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
Add MA on crew charges 0.20 153.63 30.73
Water(including for curing) 1.20 kl 77.00 1 kl 92.40
Rate per 1 cum 4983.17

A) BEAMS :
un supported height up to 3.66 m
Rate for other Floors FF SF TF
Rate as above 4983.17 4983.17 4983.17
Hire charges of centering and scaffolding 1342.00 1342.00 1342.00
Labour , lift charges for scaffolding 1122.00 1234.00 1346.00
Add MA charges at 20% 224.40 246.80 269.20
Lift charges of materials(Manual) 0.00 116.00 231.99
Add MA charges at 20% 0.00 23.20 46.40
Rate for 1 cum 7671.57 7945.17 8218.76
Overheads&Contractors Profit @13.615% 1044.48 1081.73 1118.98
Rate per 1 cum 8716.05 9026.90 9337.74
Say 8716 9027 9338

B) RCC SLABS :
a) Roof Slabs 115mm thick :
un supported height up to 3.66 m
Rate for Design mix M 25 0.115 Cum 4983.17 1 Cum 573.06

Rate for other Floors FF SF TF


Rate as above 573.06 573.06 573.06
Hire charges of centering and scaffolding 152.00 152.00 152.00
Labour , lift charges for scaffolding 127.00 140.00 152.00
Add MA charges at 20% 0.20 28.00 30.40
Lift charges of materials(Manual) 0.00 13.34 26.68
Add MA charges at 20% 0.00 2.67 5.34
Rate per 1 sqm 852.26 909.07 939.48
Overheads&Contractors Profit @13.615% 116.04 123.77 127.91
Rate per 1 sqm 968.30 1032.84 1067.39
Say 968 1033 1067

b) Roof Slabs 125mm thick :


un supported height up to 3.66 m
Rate for Design mix M 25 0.125 Cum 4983.17 1 Cum 622.90

Rate for other Floors FF SF TF


Rate as above 622.90 622.90 622.90
Hire charges of centering and scaffolding 152.00 152.00 152.00
Labour , lift charges for scaffolding 127.00 140.00 152.00
Add MA charges at 20% 0.20 28.00 30.40
Lift charges of materials(Manual) 0.00 14.50 29.00
Add MA charges at 20% 0.00 2.90 5.80
Rate per 1 sqm 902.10 960.30 992.10
Overheads&Contractors Profit @13.615% 122.82 130.74 135.07
Rate per 1 sqm 1024.92 1091.04 1127.17
Say 1025 1091 1127

c) Roof Slabs 150mm thick :


Rate for Design mix M 25 0.15 Cum 4983.17 1 Cum 747.48

un supported height up to 3.66 m


Rate for other Floors FF SF TF
Rate as above 747.48 747.48 747.48
Hire charges of centering and scaffolding 152.00 152.00 152.00
Lift charges for scaffolding 127.00 140.00 152.00
CIVIL DATA : Page-30
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
Add MA charges at 20% 25.40 28.00 30.40
Lift charges of materials(Manual) 0.00 17.40 34.80
Add MA charges at 20% 0.00 3.48 6.96
Rate per 1 sqm 1051.88 1088.36 1123.63
Overheads&Contractors Profit @13.615% 143.21 148.18 152.98
Rate per 1 sqm 1195.09 1236.54 1276.61
Say 1195 1237 1277

d) Roof Slabs 175mm thick :


Rate for Design mix M 25 0.175 Cum 4983.17 1 Cum 872.06

for un supported height of 3.66 m


Rate for other Floors FF SF TF
Rate as above 872.06 872.06 872.06
Hire charges of centering and scaffolding 156.00 156.00 156.00
Labour , lift charges for scaffolding 131.00 144.00 157.00
Add MA charges at 20% 26.20 28.80 31.40
Lift charges of materials(Manual) 0.00 20.30 40.60
Add MA charges at 20% 0.00 4.06 8.12
Rate per 1 sqm 1185.26 1225.21 1265.17
Overheads&Contractors Profit @13.615% 161.37 166.81 172.25
Rate per 1 sqm 1346.63 1392.02 1437.42
Say 1347 1392 1437

e) Roof Slabs 200mm thick :


Rate for Design mix M 25 0.20 Cum 4983.17 1 Cum 996.63

for un supported height of 3.66 m


Rate for other Floors FF SF TF
Rate as above 996.63 996.63 996.63
Hire charges of centering and scaffolding 156.00 156.00 156.00
Labour , lift charges for scaffolding 131.00 144.00 157.00
Add MA charges at 20% 26.20 28.80 31.40
Lift charges of materials(Manual) 0.00 23.20 46.40
Add MA charges at 20% 0.00 4.64 9.28
Rate per 1 sqm 1309.83 1353.27 1396.71
Overheads&Contractors Profit @13.615% 178.33 184.25 190.16
Rate per 1 sqm 1488.16 1537.52 1586.87
Say 1488 1538 1587

13 Supply and placing of the Design Mix Concrete M 20 grade corresponding to IS 456 with minimum cement
content of 350 kgs per 1 cum of concrete using WEIGH BATCHER / MIXER with 20mm size graded machine
crushed hard granite metal (coarse aggregate - as per IS 383 - 1970 and IS 2386 Part 1 to Part 8) from approved
quarry including cost and conveyance of all materials like cement, fine aggregate (sand) coarse aggregate, water
etc., to site and including sales & other taxes on all materials , centering using Casurina Ballies , Bamboos ,
Wooden Reapers , Runners , Wood Posts , Wall Plates etc., for 60cm wide sun-shades 7.5cm thick at fixed
end and 5cm thick at free end with an average thickness of 6.25cm including all operational, incidental and
labour charges such as weigh batching, machine mixing, lifting of concrete manually, laying concrete, curing,
overheads & contractors profit complete etc., but excluding cost of steel and its fabrication charges for finished
item of work (APSS No. 402, 403 & 903)

(BLD-CSTN-3-16)
A.MATERIALS :
Cement 350.00 Kgs 4800.00 1000 Kgs 1680.00
20mm HBG graded metal 0.80 Cum 1631.66 1 Cum 1305.33
Sand 0.40 Cum 649.50 1 Cum 259.80
B.LABOUR :
1st class Mason 0.067 Nos 445.00 1 Each 29.82
2nd class Mason 0.133 Nos 400.00 1 Each 53.20
Mazdoor (both men&women) 3.077 Nos 350.00 1 Each 1076.95
CIVIL DATA : Page-31
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
Add MA charges at 20% 0.20 1159.97 231.99

C.MACHINERY :
Batching plant 0.50 cum 0.308 hours 236.80 1 hour 72.93
Crew charges 0.308 hours 320.00 1 hour 98.56
Add MA on crew charges 0.20 98.56 19.71
Water(including for curing) 1.20 kl 77.00 1 kl 92.40
Rate per 1 cum 4920.69

Cost of RCC M 25 design mix 0.0375 cum 4920.69 1 cum 184.53

Rate for other Floors FF SF TF


Rate as above 184.53 184.53 184.53
Hire charges of centering and scaffolding 90.00 90.00 90.00
Labour , lift charges for scaffolding 87.60 96.60 105.00
Add MA charges at 20% 17.52 19.32 21.00
Rate per 1 RM 0.00 4.35 8.70
Add MA charges at 20% 0.00 0.87 1.74
Rate per 1 RM 379.65 395.67 410.97
Overheads&Contractors Profit @13.615% 51.69 53.87 55.95
Rate per 1 RM 431.34 449.54 466.92
Say 431 450 467

14 Brick masonry for panel walls in superstructure with CM (1:8) prop: (Cement : Screened sand) using
common burnt clay bricks of class as per Table- I of IS:1077-1992, Non- Modular or traditional size 23 x 11 x 7
cms from approved source having minimum crushing strength of 40 Kg/Sqcm. including cost and conveyance of
all materials like cement, screened sand, bricks, water etc., to site, including sales & other taxes on all materials
and such as labour charges, like mixing cement mortar, scaffolding charges, constructing masonry, lift charges,
curing, etc.,and overheads & contractors profit complete for finished item of work. (APSS No. 501 & 504).

(BLD-CSTN-5-5)
Unit : 1cum
A.MATERIALS :
Cement 36.00 Kgs 4800.00 1000 Kgs 172.80
Common burnt clay bricks 23x11x7cms 512 Nos 5200.00 1000 Nos 2662.40
Fine aggregate ( Sand ) 0.20 cu.m. 649.50 1 cu.m. 129.90
B.LABOUR :
1st class mason 0.24 Nos. 445.00 1 Each 106.80
2nd class mason 0.56 Nos. 400.00 1 Each 224.00
Mazdoor (Unskilled) 1.89 Nos. 350.00 1 Each 661.50
Add MA charges at 20% 0.20 992.30 198.46
water charges @ 1% 0.01 4155.86 41.56
Rate per 1 cum 4197.42

a Up to basement
Rate as worked out above 1.00 Cum 4197.42 1 Cum 4197.42
Add MA charges at 20% 0.20 4197.42 839.48
Rate per 1 cum 5036.90
Say 5037

b) Superstructure :
Rate for other Floors FF SF TF 4F
Rate as worked out above 4197.42 4197.42 4197.42 4197.42
Hire charges for Access Scaffolding 43.17 43.17 43.17 43.17
Labour charges for scaffolding 268.83 381.65 494.35 607.39
Add MA charges at 20% 53.77 76.33 98.87 121.48
Lift charges ( Page 131 of Std. Data ) 0.00 99.23 198.46 297.69
Add MA charges at 20% 0.00 19.85 39.69 59.54
Rate per 1 cum 4563.19 4817.65 5071.96 5326.69
Overheads&Contractors Profit @13.615% 621.28 655.92 690.55 725.23
CIVIL DATA : Page-32
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
Rate per 1 cum 5184.47 5473.57 5762.51 6051.92
Say 5184 5474 5763 6052

15 Reinforced Brick Masonry for partition walls (11.0 cm thick) in CM (1:4) prop. (Cement : Screened sand)
using common burnt clay bricks of class as per Table- I of IS:1077-1992, Non- Modular or traditional size 23
x 11 x 7 cms from approved source having minimum crushing strength of 40 Kg/Sq.cm and placing 2 Nos. of
6mm M.S plain rods in every third layer with free ends of the reinforcement pegged into mortar joints of main
brick walls where applicable including cost and conveyance of all materials like cement, steel, sand, bricks, water
etc., to site, including sales & other taxes on all materials, all operational, incidental charges such as labour
charges for mixing cement mortar, scaffolding charges, constructing masonry, lift charges, curing, etc., and
overheads & contractors profit but excluding cost of steel and its fabrication charges complete for finished item
of work. (APSS No. of 501 & 509)

(BLD-CSTN-5-12)
Unit - 10sqm
A.MATERIALS :
Common burnt clay bricks 23x11x7cms 565 Nos. 5200.00 1000 Nos. 2938.00
Cement 79.20 Kgs 4800.00 1000 Kgs 380.16
Fine aggregate ( Sand ) 0.22 cu.m. 649.50 1 cu.m. 142.89
B.LABOUR :
1st class mason 0.60 Nos. 445.00 1 Each 267.00
2nd class mason 0.60 Nos. 400.00 1 Each 240.00
Mazdoor (Unskilled) 2.75 Nos. 350.00 1 Each 962.50
Add MA charges at 20% 0.20 1469.50 293.90
water charges @ 1% 0.01 5224.45 52.24
Rate per 10 sqm 5276.69
Rate per 1 sqm 527.67

Rate for other Floors FF SF TF 4F


Rate as worked out above 527.67 527.67 527.67 527.67
Hire charges for Access Scaffolding 9.93 9.93 9.93 9.93
Labour charges for scaffolding 61.83 87.78 113.70 139.70
Add MA charges at 20% 12.37 17.56 22.74 27.94
Lift charges ( Page 131 of Std. Data ) 0.00 14.70 29.39 44.09
Add MA charges at 20% 0.00 2.94 5.88 8.82
Rate per 1 sqm 611.80 660.58 709.31 758.15
Overheads&Contractors Profit @13.615% 83.30 89.94 96.57 103.22
Rate per 1 sqm 695.10 750.52 805.88 861.37
Say 695 751 806 861

22 Providing High Yield Strength Deformed (HYSD) (Fe 415 grade as per IS 1786-1979) of different diameters
for RCC works , including labour charges for straightening, cutting, bending to required sizes and shapes,
placing in position with cover blocks of approved materials and size and tying and lap-splicing with binding wire of
18 SWG, forming grills for reinforcement work as per approved designs and drawings, including cost and
conveyance of steel bars, including all wastages such as overlaps, couplings, chairs, spacer bars including cost
and conveyance of binding wire, cover blocks and all incidental, operational, labour charges such as cutting,
bending, placing in position, tying including sales and other taxes on all materials etc. ,and overheads &
contractors profit complete for finished item of work.( APSS No.126)

(BLD-CSTN-4.2)& Amendment in SoR 2011-12 page No. 392


Unit - 1 MT
a) Material
HYSD bars including 5% for overlaps and
wastage 1.05 MT 34500.00 1 MT 36225.00
Binding wire 6.00 Kgs 70.00 1 Kgs 420.00
b) Labour for cutting , bending , shifting to
site , tying and placing in position
1st class Blacksmith / Barbender 3.00 Nos. 440.00 1 Each 1320.00
2nd class Blacksmith / Barbender 7.00 Nos. 440.00 1 Each 3080.00
Mazdoor(Unskilled) 10.00 Nos. 350.00 1 Each 3500.00
Add MA charges at 20% 0.20 7900.00 1580.00
CIVIL DATA : Page-33
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
46125.00

Rate for other Floors FF SF TF 4F


Rate as worked out above 46125.00 46125.00 46125.00 46125.00
Lift charges ( Page 131 of Std. Data ) 0.00 790.00 1580.00 2370.00
Add MA charges at 20% 0.00 158.00 316.00 474.00
Rate per 1 MT 46125.00 47073.00 48021.00 48969.00
Overheads&Contractors Profit @13.615% 6279.92 6408.99 6538.06 6667.13
Rate per 1 MT 52404.92 53481.99 54559.06 55636.13
Say 52405 53482 54559 55636

25 Ornamental ceiling plastering 12mm thick single coat in CM (1:5) using screened sand including cost and
conveyance of all materials like cement, sand, water etc., to site, including sales & other taxes on all materials,
and all operational, incidental charges on materials and including cost of all labour charges for mixing mortar,
finishing, curing as directed by Engineer-in-charge etc., and overheads & contractors profit complete for finished
item of work.(SS 901,903 & 904)

(BLD-CSTN-8-3)
Unit : 10 sqm
A.MATERIALS :
Cement 43.20 Kgs 4800.00 1000 Kgs 207.36
Fine aggregate ( Sand ) 0.15 cu.m. 719.50 1 cu.m. 107.93
B.LABOUR :
1st Class Mason 0.60 Nos. 445.00 1 Each 267.00
Mazdoor (Unskilled) 0.96 Nos. 350.00 1 Each 336.00
Add MA charges at 20% 0.20 603.00 120.60
water charges @ 1% 0.01 1038.89 10.39
Rate per 10 Sqm 1049.27
Rate per 1 Sqm 104.93

Rate for other Floors FF SF TF 4F


Rate as worked out above 104.93 104.93 104.93 104.93
Hire charges for Access Scaffolding 2.37 2.37 2.37 2.37
Labour charges for scaffolding 12.55 17.64 22.73 27.82
Add MA charges at 20% 0.20 3.53 4.55 5.56
Lift charges ( Page 131 of Std. Data ) 0.00 6.03 12.06 18.09
Add MA charges at 20% 0.00 1.21 2.41 3.62
Rate per 1 Sqm 120.05 135.71 149.05 162.39
Overheads&Contractors Profit @13.615% 16.34 18.48 20.29 22.11
Rate per 1 Sqm 136.39 154.19 169.34 184.50
Say 136 154 169 184

26 Plastering 12mm thick in two coats using screened sand with base coat of 8mm thick in CM (1:6) and top coat
of 4mm thick in CM (1:4) with dubara sponge finishing including cost and conveyance of all materials like cement,
sand, water etc., to site, including sales & other taxes on all materials, and all operational, incidental charges on
materials and including cost of all labour charges for mixing mortar, finishing, scaffolding, lift charges, curing,
including cutting grooves as directed by Engineer - in - charge etc., and overheads & contractors profit complete
for finished item of work. (SS 901,903 & 904)
( BLD-CSTN-8-10)
Unit : 10 sqm
A.MATERIALS :
Base coat in CM(1:6) , 8mm thick
Cement 26.40 Kgs 4800.00 1000 Kgs 126.72
Fine aggregate (Sand) 0.11 Cum 719.50 1 Cum 79.15
Top coat in CM(1:4) , 4mm thick
Cement 14.40 Kgs 4800.00 1000 Kgs 69.12
Fine aggregate (Sand) 0.04 Cum 1 Cum 0.00
B.LABOUR :
1st Class Mason 0.63 Nos. 445.00 1 Each 280.35
2nd Class Mason 1.47 Nos. 400.00 1 Each 588.00
CIVIL DATA : Page-34
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
Mazdoor (Unskilled) 3.90 Nos. 350.00 1 Each 1365.00
Add MA charges at 20% 0.20 2233.35 446.67
water charges @ 1% 0.01 2955.01 29.55
Rate per 10 Sqm 2984.56
Rate per 1 Sqm 298.46

Walls in superstructure :
Rate for other Floors FF SF TF 4F
Rate as worked out above 298.46 298.46 298.46 298.46
Hire charges for Access Scaffolding 0.99 0.99 0.99 0.99
Labour charges for scaffolding 6.18 8.78 11.37 13.97
Add MA charges at 20% 0.20 1.76 2.27 2.79
Lift charges ( Page 131 of Std. Data ) 0.00 22.33 44.67 67.00
Add MA charges at 20% 0.00 4.47 8.93 13.40
Rate per 1 Sqm 305.83 336.79 366.69 396.61
Overheads&Contractors Profit @13.615% 41.64 45.85 49.93 54.00
347.47 382.64 416.62 450.61
Say 347 383 417 451

28 Providing impervious coat to exposed RCC roof slab surfaces to required slopes with CM (1:3) prop. using
screened sand 20mm thick (average) mixed with integral cement water proofing liquid confirming to IS: 2645-
2003 manufactured by reputed manufacturers as approved by Engineer-in-charge at 1 Kg per one bag of
cement, laid over roof slab when it is green, finished smooth with a floating coat of neat cement and thread lining
at regular intervals of 45cmx45cm including cost and conveyance of all materials like cement, sand, water
proofing compound, water etc., to site, including sales & other taxes on all materials and operational, incidental,
and labour charges for mixing mortar, laying, lift charges, rendering smooth and thread lining, curing including
rounding off junctions of wall and slab etc., and overheads & contractors profit complete for finished item of work.
(APSS No. 901 & 903).

(BLD-CSTN-10-25)
Unit : 10 sqm
A.MATERIALS :
Cement 100.80 Kgs 4800.00 1000 Kgs 483.84
Fine aggregate (Sand) 0.21 Cum 649.50 1 Cum 136.40
Integral cement waterproofing liquid 0.40 Ltrs 210.00 1.00 Ltrs 84.00
B.LABOUR :
1st Class Mason 0.66 Nos. 420.00 1 Each 277.20
2nd Class Mason 1.54 Nos. 375.00 1 Each 577.50
Mazdoor (Unskilled) 3.70 Nos. 320.00 1 Each 1184.00
Add MA charges at 20% 0.20 2038.70 407.74
water charges @ 1% 0.01 3150.68 31.51
Rate per 10 Sqm 3182.18

Rate for other Floors FF SF TF 4F


Rate as worked out above 3182.18 3182.18 3182.18 3182.18
Lift charges ( Page 131 of Std. Data ) 0.00 203.87 407.74 611.61
Add MA charges at 20% 0.00 40.77 81.55 122.32
3182.18 3426.83 3671.47 3916.11
Overheads&Contractors Profit @13.615% 433.25 466.56 499.87 533.18
3615.43 3893.39 4171.34 4449.29
Rate per 1 Sqm 361.54 389.34 417.13 444.93
Say 362 389 417 445

33 Flooring with non-skid full body ceramic floor tiles of size 300mm x 300mm and thickness between 7 - 8mm
1st quality conforming to IS: 13711, IS: 13712, IS: 13630(Part 1 to 15) of any colour and finish in all shades and
designs as approved by Engineer-in-charge, set over base coat of cement mortar (1:8), 12mm thick using
screened sand over CC bed already laid or RCC roof slab, including neat cement slurry of honey like consistency
spread @ 3.3 Kgs per Sqm & jointed neatly with white cement paste to full depth mixed with pigment of matching
shade, including cost of all materials like cement, screened sand , water and tiles etc., and overheads &
contractors profit complete for finished item of work. (APSS No.701 & 707)

(BLD-CSTN-9-6)
CIVIL DATA : Page-35
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
Unit = 10 sqm.
A. MATERIALS:
Ceramic tiles 7 to 8mm thick (300mm x
300mm) 10.50 Sqm 465.00 1 Sqm 4882.50
Cement for CM(1:8) proportion for base
coat 21.60 Kgs 4800.00 1000 Kgs 103.68
Cement for slurry 33.00 Kgs 4800.00 1000 Kgs 158.40
White Cement 2.00 Kgs 29.00 1 Kg 58.00
Sand for CM(1:8) 0.12 Cum 719.50 1 Cum 86.34
B .LABOUR
Mason 1st class 0.96 Nos 445.00 1 Each 427.20
Mason 2nd class 2.24 Nos 400.00 1 Each 896.00
Mazdoor(un skilled) 3.30 Nos 350.00 1 Each 1155.00
Add MA charges at 20% 0.20 2478.20 495.64
Add water charges 1% 0.01 8262.76 82.63
Rate for 10sqm 8345.39

Rate for other Floors FF SF TF 4F


Rate as worked out above 8345.39 8345.39 8345.39 8345.39
Lift charges ( Page 131 of Std. Data ) 0.00 247.82 495.64 743.46
Add MA charges at 20% 0.00 49.56 99.13 148.69
8345.39 8642.77 8940.16 9237.54
Overheads&Contractors Profit @13.615% 1669.08 1728.55 1788.03 1847.51
Rate per 10 Sqm 10014.47 10371.32 10728.19 11085.05
Rate per 1 Sqm 1001.45 1037.13 1072.82 1108.50
Say 1001 1037 1073 1109

34 Flooring with soluble salt porcelain vitrified tiles screen printed and polished of size 600 x 600 mm and
thickness between 8 to 10mm 1st quality conforming to IS: 13711, IS: 13712, IS: 13630(Parts 1 to 15) of any
colour and finish in all shades and designs with borders and design as per the approved flooring pattern as
directed by the Engineer-In -Charge, laying tiles using spacers of 2mm thick, set over a base coat of CM (1:8)
prop. 12mm thick using screened sand over CC bed already laid or RCC roof slab , including neat cement slurry
of honey like consistancy spread @ 3.3 kgs per Sqm. and jointed neately with white cement paste to full depth
mixed with pigment of matching shade including cost and conveyance of all materials like cement, sand,
water, tiles, white cement etc., to site (excluding cost of C.C. bed) including cost of base coat and all labour
charges for mixing of cement mortar, laying tiles to required slope as directed by the Engineer- in-charge
etc.,and overheads & contractors profit complete for finished item of work. (APSS No.701 & 707)

(BLD-CSTN-9-5)
Unit = 10 sqm.
A. MATERIALS:
Vitrified tiles 8 to 10mm thick of size
600mm x 600mm 10.50 Sqm 631.00 1 Sqm 6625.50
Cement for CM(1:8)proportion for base
coat 21.60 Kgs 4800.00 1000 Kgs 103.68
Cement for slurry 33.00 Kgs 4800.00 1000 Kgs 158.40
White Cement 6.00 Kgs 29.00 1 Kg 174.00
Sand for CM(1:8) 0.12 Cum 719.50 1 Cum 86.34
B .LABOUR
Mason 1st class 0.96 Nos 445.00 1 Each 427.20
Mason 2nd class 2.24 Nos 400.00 1 Each 896.00
Mazdoor(un skilled) 3.30 Nos 350.00 1 Each 1155.00
Add MA charges at 20% 0.20 2478.20 495.64
Add water charges 1% 0.01 10121.76 101.22
Rate for 10sqm 10222.98

Rate for other Floors FF SF TF 4F


Rate as worked out above 10222.98 10222.98 10222.98 10222.98
Lift charges ( Page 131 of Std. Data ) 0.00 247.82 495.64 743.46
Add MA charges at 20% 0.00 49.56 99.13 148.69
10222.98 10520.36 10817.75 11115.13
CIVIL DATA : Page-36
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
Overheads&Contractors Profit @13.615% 1391.86 1432.35 1472.84 1513.32
Rate per 10 Sqm 11614.84 11952.71 12290.59 12628.45
Rate per 1 Sqm 1161.48 1195.27 1229.06 1262.84
Say 1161 1195 1229 1263

35 Providing skirting to internal walls to 10 cm height with soluble salt porcelain vitrified tiles screen printed
and polished of thickness between 8 to 10mm 1st quality conforming to IS: 13711, IS: 13712, IS: 13630(Parts 1
to 15) of any colour and finish in all shades and designs, length equal to flooring tiles, set over base coat of
CM(1:5) 12 mm thick using screened sand with cement slurry of honey like consistency spread at the rate of 3.30
kgs per sqm and jointing with white cement paste mixed with pigment of matching shade to full depth, including
cost of all materials like tiles, cement, sand and water etc.,and overheads & contractors profit complete for
finished item of work.(APSS No.701 &707)

(BLD-CSTN-9-20)
Unit = 10 sqm
Cost of vitrified tiles 8-10mm thick 10.50 sqm 631.00 1 sqm 6625.50
Sand for CM(1:5) base coat 0.12 cum 649.50 1 cum 77.94
Cement for CM(1:5) base coat 34.56 Kgs 649.50 1000 Kgs 22.45
Cement for slurry 33.00 Kgs 649.50 1000 Kgs 21.43
White cement for jointing & pointing 2.00 Kgs 29.00 1 Kg 58.00

B.LABOUR
Mason 1st class 0.77 Nos. 420.00 1 Each 323.40
Mazdoor(unskilled) 0.80 Nos. 320.00 1 Each 256.00
Add MA charges at 20% 0.20 579.40 115.88
Add water charges 1% 0.01 7500.60 75.01
Rate for 10 sqm 7575.61

Rate for other Floors FF SF TF 4F


Rate as worked out above 7575.61 7575.61 7575.61 7575.61
Lift charges ( Page 131 of Std. Data ) 0.00 57.94 115.88 173.82
Add MA charges at 20% 0.00 11.59 23.18 34.76
7575.61 7645.13 7714.66 7784.19
Overheads&Contractors Profit @13.615% 1031.42 1040.89 1050.35 1059.82
Rate per 10 Sqm 8607.03 8686.02 8765.01 8844.01
Rate per 1 RM 86.07 86.86 87.65 88.44
Say 86 87 88 88

36 Providing dadooing to walls with glazed full body ceramic tiles of any size and thickness between 5 to 7mm
1st quality conforming to IS: 13711, IS: 13712, IS: 13630(Parts 1 to 15) of any colour and finish in all shades and
designs with borders as approved by Engineer-in-Charge set over base coat of CM(1:5) 12 mm thick using
screened sand with cement slurry of honey like consistency spread at the rate of 3.30 kgs per sqm and jointing
with white cement paste mixed with pigment of matching shade to full depth, including cost of all materials like
tiles, cement, sand and water etc., and overheads & contractors profit complete for finished item of work.

(BLD-CSTN-9-18)
Unit = 10 sqm
A.MATERIALS :
Cost of glazed coloured tiles 10.50 sqm 413.00 1 sqm 4336.50
Sand for CM(1:5) base coat 0.12 cum 719.50 1 cum 86.34
Cement for CM(1:5) base coat 34.56 Kgs 4800.00 1000 Kgs 165.89
Cement for slurry 33.00 Kgs 4800.00 1000 Kgs 158.40
White cement for jointing & pointing 6.00 Kgs 29.00 1 Kg 174.00
B.LABOUR
Mason 1st class 0.77 Nos. 445.00 1 Each 342.65
Mazdoor(unskilled) 0.80 Nos. 400.00 1 Each 320.00
Add MA charges at 20% 0.20 662.65 132.53
Add water charges 1% 0.01 5716.31 57.16
Rate for 10 sqm 5773.47

Rate for other Floors FF SF TF 4F


Rate as worked out above 5773.47 5773.47 5773.47 5773.47
CIVIL DATA : Page-37
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
Lift charges ( Page 131 of Std. Data ) 0.00 66.27 132.53 198.80
Add MA charges at 20% 0.00 13.25 26.51 39.76
5773.47 5853.00 5932.51 6012.03
Overheads&Contractors Profit @13.615% 786.06 796.89 807.71 818.54
Rate per 10 Sqm 6559.53 6649.89 6740.22 6830.57
Rate per 1 Sqm 655.95 664.99 674.02 683.06
Say 656 665 674 683

39 Providing 110 mm Dia ISI marked PVC down water take pipes with socket , 2.5mm thick 4.0 kg/sq.cm pressure
of ISI marked including cost of necessary PVC Bends, shoes, iron / PVC clamps and all other accessories and
fixing in position including cost and conveyance of all materials, sales & other taxes on materials to site,
operational & incidental charges including all labour charges for fixing at site etc., and overheads & contractors
profit complete for finished item of work. (APSS No. 1328)

PVC pipe 110mm dia 6.00 RM 162.00 1 RM 972.00


MS Clamps 3 Nos. 18.00 1 Each 54.00
Labour charges for fixing pipes 6.00 RM 70.00 1 RM 420.00
Rate per 6 RM 1446.00
241.00
Overheads&Contractors Profit @13.615% 0.13615 241.00 32.81
Rate per 1 RM 273.81
Say 274

40 Supply and fixing jallies ( cement concrete ) of 50mm thick as per the design approved by the Engineer-in-
Charge including cost and conveyance of materials to site and labour charges etc., overheads & contractors
profit complete for finished item of work.

Cost of 50mm thick jali 1.00 sqm 402.00 1 sqm 402.00


1st class mason 0.06 Nos. 420.00 1 Each 25.20
2nd class mason 0.06 Nos. 375.00 1 Each 22.50
Mazdoor(unskilled) 0.275 Nos. 320.00 1 Each 88.00
Add MA charges at 20% 0.20 135.70 27.14
564.84
Rate for other Floors FF SF TF 4F
Rate as worked out above 564.84 564.84 564.84 564.84
Hire charges for Access Scaffolding 9.93 9.93 9.93 9.93
Labour charges for scaffolding 61.83 87.78 113.70 139.70
Add MA charges at 20% 12.37 17.56 22.74 27.94
Lift charges ( Page 131 of Std. Data ) 0.00 1.36 2.71 4.07
Add MA charges at 20% 0.00 0.27 0.54 0.81
Rate for 1 sqm 648.97 681.74 714.46 747.29
Overheads&Contractors Profit @13.615% 88.36 92.82 97.27 101.74
Rate per 1 sqm 737.33 774.56 811.73 849.03
Say 737 775 812 849

41 White washing two coats with white cement to ceiling to give an even shade after thouroughly brushing the
surface to remove all dirt and remains of loose powdered materials including cost of all materials , labour charges
and incidental such as scaffolding , lift charges etc., and overheads & contractors profit complete for finished item
of work in all floors.
(BLD-CSTN-11-5)
Unit : 10 sqm
A.MATERIALS :
White cement 2.00 kgs 29.00 1 kgs 58.00
B.LABOUR :
Painter 1st class 0.063 Nos. 480.00 1 Each 30.24
Painter 2nd class 0.147 Nos. 375.00 1 Each 55.13
Mazdoor(unskilled) 0.32 Nos. 320.00 1 Each 102.40
CIVIL DATA : Page-38
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
Add MA charges at 20% 0.20 187.77 37.55
Sundries including brushes , ladders etc.,
@ 1% 1% 283.32 2.83
Rate per 10 sqm 286.15
Overheads&Contractors Profit @13.615% 0.13615 286.15 38.96
Rate per 10 sqm 325.11
Rate per 1 sqm 32.51
Say 33.00

42 Providing and applying Wall putty of White Cement or Polymer or Cement based of average 1 to 2 mm
thickness over plastered surface to prepare the surface even and smooth after thoroughly brushing the surface to
remove all dirt and remains of loose powdered materials, applying emery paper, Sand the surface, clean & wipe
off loose dust, applying knifing paste filler by putty knife / muslin pad, air dry for 2 - 3 hrs, sand with 180 and 320
No., emery paper for the surface preparation including cost and conveyance of all materials to work site and all
operational, incidental, labour charges, over heads and contractors profit etc., complete for finished item of work
in all floors for Internal walls

(As per Amendment in SoR 2011-12)


Unit = 10 Sqm
wall putty 23.00 Kgs 679.00 20 Kg 780.85
Painter 1st class 0.273 Nos. 535.00 1 Each 146.06
Painter 2nd class 0.637 Nos. 420.00 1 Each 267.54
Mazdoor 0.91 Nos. 370.00 1 Each 336.70
Add MA charges at 20% 0.20 750.30 150.06
Sundries for emery papers, fillers, knife
etc., @ 1% 0.01 1681.20 16.81
1698.02
Overheads&Contractors Profit @13.615% 0.13615 1698.02 231.18
Rate per 10 sqm 1929.20
Rate per 1 sqm 192.92
Say 193.00

43 Supply & application of one coat water based cement primer of exterior grade II and two coats of acrylic
exterior emulsion paint having VOC (Volatile Organic Compound) content less than 50 grams/litre for exterior
walls including cost and conveyance of all materials to site, sales & other taxes, incidental, operational and all
labour charges etc., and overheads & contractors profit complete for finished item of work in all floors.

(BLD-CSTN-12-2& Amendment in SoR 2011-12)


Unit 10 Sqm.
A. Materials:-
Cost of cement primer exterior grade II 1.00 Kg 163.00 1 Kg 163.00
Painter 1st class 0.21 Nos. 535.00 1 Each 112.35
Painter 2nd class 0.49 Nos. 420.00 1 Each 205.80
Acrylic emulsion paint 0.80 Ltrs 152.00 1 Ltrs 121.60
Painter 1st class 0.36 Nos. 535.00 1 Each 192.60
Painter 2nd class 0.84 Nos. 420.00 1 Each 352.80
Add MA charges at 20% 0.20 863.55 172.71
Sundries including brushes , ladders etc.,
@ 1% 0.01 1320.86 13.21
Hire charges for Access Scaffolding 10 sqm 0.99 1 sqm 9.90
Labour charges for scaffolding 10 sqm 6.18 1 sqm 61.80
Add MA charges at 20% 0.20 61.80 12.36
1418.13
Overheads&Contractors Profit @13.615% 0.13615 1418.13 193.08
Rate per 10 sqm 1611.21
Rate per 1 sqm 161.12
Say 161.00
CIVIL DATA : Page-39
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
44 Painting to old wood work and flush shutters with two coats of synthetic enamel paint Grade-II VOC
(Volatile Organic Compound) content less than 50 grams/litre of approved brand and shade including cost and
conveyance of all materials to site and all labour charges etc. complete, sales & other taxes on cost of all
materials etc.and overheads & contractors profit complete in all floors (APSS No.1200, 1207 & 1211) .

(BLD-CSTN-12-12-196)
Cost of Synthetic Enamel Paint 1.10 Ltr 276.00 1 Ltr 303.60
1st Class Painter 0.36 Nos. 480.00 1 Each 172.80
2nd Class Painter 0.84 Nos. 375.00 1 Each 315.00
Add MA charges at 20% 0.20 487.80 97.56
Sundries including brushes , ladders etc.,
@ 1% 0.01 888.96 8.89
897.85
Overheads&Contractors Profit @13.615% 0.13615 897.85 122.24
Rate per 10 sqm 1020.09
Rate per 1 sqm 102.01
Say 102.00

46 Supply & application of one coat water based cement primer of interior grade I and two coats of acrylic
emulsion paint having VOC (Volatile Organic Compound) content less than 50 grams/litre for internal walls
including cost and conveyance of all materials to site, sales & other taxes, incidental, operational and all labour
charges etc., and overheads & contractors profit complete for finished item of work in all floors.

(BLD-CSTN-12-2& Amendment in SoR 2011-12)


Unit 10 Sqm.
A. Materials:-
Cost of cement primer interior grade I 1.00 Kg 128.00 1 Kg 128.00
Painter 1st class 0.21 Nos. 535.00 1 Each 112.35
Painter 2nd class 0.49 Nos. 420.00 1 Each 205.80
Acrylic emulsion paint 0.80 Ltrs 152.00 1 Ltrs 121.60
Painter 1st class 0.36 Nos. 535.00 1 Each 192.60
Painter 2nd class 0.84 Nos. 420.00 1 Each 352.80
Add MA charges at 20% 0.20 863.55 172.71
Sundries including brushes , ladders etc.,
@ 1% 0.01 1285.86 12.86
1298.72
Overheads&Contractors Profit @13.615% 1298.72
0.13615 176.82
Rate per 10 sqm 1475.54
Rate per 1 sqm 147.55
Say 148.00

51 Supplying and fixing Gyp board Fine line Grid false ceiling (GS-FLC-4.6)using 12.5mm thick Gyp Board
sheet tiles of size 595mm x 595mm conforming to IS 2095 - 1992 fixing to Gyp steel precoated GI wall angle of
size 25mm x 25mm x 0.70mm thick along the perimeter of ceiling screw fixed to brick work / partition at 610mm
center to center and suspending the frame work using precoated GI Tee section (24mm x 38mm x 0.7mm) from
soffit at 1220mm center to center fixed with GI Soffit Cleat, rawl plugs and steel expansion fasteners &
connecting clip to the GI Tee section with 4mm dia GI rod with galvanised spring steel level clip of PVC unversal
holding clips system at 1200mm center to center and fixing the 12.5mm Gypboard sheet tiles of size 595mm x
595mm and finishing two coats of drywall top coat, overheads and contractor profit complete for finished item of
work in all floors.

(BLD-CSTN-10-32 & vide Page No. 390 of SoR 2011-12)


Unit - 1 Sqm
A) Material requirement as per India Gypsum
12.5mm Gypboard Tiles
595mm x 595mm 1.00 sqm 281.00 1 sqm 281.00
GI Angle - Precoated - 25mm x 25mm
x0.7mm 0.40 RM 41.00 1 RM 16.40
GI pre coated - T section - 3600mm long -
24mm x 38mm x 0.7mm thick 3.20 RM 54.00 1 RM 172.80
CIVIL DATA : Page-40
Sl. Amount
Description Quantity Rate (Rs.) Per Unit
No. (Rs.)
GI Rod - 4mm dia - Connecting Rod 1.28 RM 12.00 1 RM 15.36
Rawl Plug 1.28 Nos. 2.00 1 No. 2.56
Soffit Cleats 1.28 Nos. 2.00 1 No. 2.56
Universal Holding Clips 5.36 Nos. 3.00 1 No. 16.08
Drywall Top coat 0.15 Ltrs 142.00 1 Ltr 21.30
B) Labour Charges
1st Class Carpenter 0.12 Nos. 480.00 1 No. 57.60
2nd Class Carpenter 0.12 Nos. 375.00 1 No. 45.00
1st Class Painter 0.02 Nos. 480.00 1 No. 11.52
2nd Class Painter 0.024 Nos. 375.00 1 No. 9.00
Power Saw cutter - Hand Operated - 0.012 Nos. 420.00 1 No. 5.04
Operator
Power Drill - Hand Operated - Operator 0.012 Nos. 420.00 1 No. 5.04
Unskilled Mazdoor 0.072 Nos. 320.00 1 No. 23.04
Add MA charges at 20% 0.20 156.24 31.25
C) Machinery
Power Saw cutter - Hand Operated - Hire
Charges 0.32 Hours 125.00 1 Hour 40.00
Power Drill - Hand Operated - Hire 0.32 Hours 116.00 1 Hour 37.12
Charges 792.67
Scaffolding charges @ 1% 0.01 792.67 7.93
Basic Cost per 1 Sqm 800.59
Overheads&Contractors Profit @13.615% 0.13615 800.59 109.00
Rate per 1 sqm 909.60
Say 910
WS & SA DATA 2014-15 Page-41
COMMON SoR 2016-2017
DATA FOR WATER SUPPLY AND SANITARY ITEMS
Sl.No Description Qty Unit Rate Per Unit Amount
Add MA charges at 20% 0.00
Overheads&Contractors Profit @13.615% 0.13615
2 Constructing 904.0 mm (3’0”) dia brick masonry inspection chamber as per IS - 4111: Part-1:1986 with
cement mortar (1:6) prop using 2nd Class Clay Bricks of 225 mm thick from approved source having a
minimum crushing strength of 5 N/sq.mm including plastering with cement mortar 1:3 prop; ½” thick both
inside and outside fitted with 20” dia RCC manhole covers and frames including excavating pits up to a
depth of 904 mm (3'-0") in all sorts of soils (exculding rock) and laying cement conrete (1:4:8) 150 mm thick
using 40 mm HBG Metal and P.C.C. 1:2:4 benching and channel 100 mm thick as per Standard specification
and including cost and conveyance of all materials like cement, sand, bricks, water etc., to site, cost of
seigniorage charges on all materials and all incidental and operational, labour charges like mixing cement
mortar, constructing masonry, lift charges, curing , overheads & contractors profit etc., complete for finished
item of work as per Standard specification.

Rate as per SSR 1 No. 6730.00 Each 6730.00


Overheads&Contractors Profit @13.615% 0.13615 6730.00 916.29
7646.29
Rate per Each say 7646.00

3 Constructing 904.0 mm (3’0”) dia brick masonry inspection chamber as per IS - 4111: Part-1:1986 with
cement mortar (1:6) prop using 2nd Class Clay Bricks of 225 mm thick from approved source having a
minimum crushing strength of 5 N/sq.mm including plastering with cement mortar 1:3 prop; ½” thick both
inside and outside fitted with 20” dia RCC manhole covers and frames including excavating pits up to a
depth of 1524 mm (5'-0") in all sorts of soils (exculding rock) and laying cement conrete (1:4:8) 150 mm
thick using 40 mm HBG Metal and P.C.C. 1:2:4 benching and channel 100 mm thick as per Standard
specification and including cost and conveyance of all materials like cement, sand, bricks, water etc., to site,
cost of seigniorage charges on all materials and all incidental and operational, labour charges like mixing
cement mortar, constructing masonry, lift charges, curing , overheads & contractors profit etc., complete for
finished item of work as per Standard specification.

Rate as per SSR 1 No. 10590.00 Each 10590.00


Overheads&Contractors Profit @13.615% 0.13615 10590.00 1441.83
12031.83
Rate per Each say 12032.00

4 Constructing 457.2 mm x 457.2 mm (1'6"x1'6") brick in CM 1:6 prop. Masonry. Inspection chamber
upto 914.4 mm (3'0") and fitted with light weight 457.2 mm x 457.2 mm (1'6"x1'6") C.I frame and cover of 20
Kg including cost and conveyance of all materials like cement, sand, bricks, water etc., to site, cost of
seigniorage charges on all materials and all incidental and operational, labour charges like mixing cement
mortar, constructing masonry, lift charges, curing , overheads & contractors profit etc., complete for finished
item of work as per Standard specification.

Rate as per SSR 1 No. 3825.00 Each 3825.00


Overheads&Contractors Profit @13.615% 0.13615 3825.00 520.77
4345.77
Rate per Each say 4346.00

5 Supplying and fixing of SWG Gully traps 150mm x 100mm of ISI make confirming to IS 651 & 4127 with
C.I grating & constructing cement brick masonry in CM (1:6) prop., intermediate chamber and fitted with
304.8 mm X 288.6 mm (12"x9") C.I Frame with hinged cover of standard make as approved including cost
and conveyance of all materials to site, labour charges, overheads & contractors profit etc., complete for
finished item of work.

Rate as per SSR 1 No. 568.00 1 Each 568.00


Deduct cost of CI frame and cover 1 No. 124.00 1 No. -124.00
Add for RCC Cover 1 No. 100.00 1 No. 100.00
544.00
Overheads&Contractors Profit @13.615% 0.13615 544.00 74.07
618.07
Rate per Each say 618.00

6 Supplying and fixing of 3" (76.2mm) multi floor trap with jali - UPVC/SWR pipe fittings as per site
requirements with standard practice for all floors including cost and conveyance of all materials to site,
labour charges , overheads & contractors profit etc., complete for finished item of work.
WS & SA DATA 2014-15 Page-42
Sl.No Description Qty Unit Rate Per Unit Amount
Rate as per SSR 1 No. 102.00 1 Each 102.00
Overheads&Contractors Profit @13.615% 0.13615 102.00 13.89
WS & SA DATA 2014-15 Page-43
Sl.No Description Qty Unit Rate Per Unit Amount
115.89
Rate per Each say 116.00

7 Supplying and fixing of 4" (101.6mm) multi floor trap with jali - UPVC/SWR pipe fittings as per site
requirements with standard practice for all floors including cost and conveyance of all materials to site,
labour charges , overheads & contractors profit etc., complete for finished item of work.
Rate as per SSR 1 No. 144.00 1 Each 144.00
Overheads&Contractors Profit @13.615% 0.13615 144.00 19.61
163.61
Rate per Each say 164.00

8 Supplying and fixing 580mm x 440mm long Orissa pan white glazed Water Closet 1st quality ISI
marked confirming to IS:2556-Part-3-1981 with "P" or "S" trap, ISI marked and providing masonry seat, CC
squatting plate and 10 litres capacity single flush PVC low level cistern with internal components fixed on 2
Nos. of teak wood blocks of size 76.20mm x 101.60mm using required size of nails, screws as approved by
Engineer-in-charge, angle stop cock 12.70mm dia. first quality Indian make heavy duty, 12.70mm PVC
connection with brass union nuts CP coated , 31.75mm brass plumber union, P trap or S trap of Indian W.C.
shall be encased on CC (1:2:4) 150mm alround well above the joint to stop leakage at the joint etc.,
complete including cost and conveyance of all materials to site, cost of CC bed, labour charges and
seigniorage charges, overheads & contractors profit etc., complete for finished item of work.

Cost of Orissa pan 1 No. 1584.00 1 Each 1584.00


Add MA on labour charges for fixing Orissa
pan 0.00 377.00 0.00
Cost of Brick masonry seat 1 No. 328.00 1 Each 328.00
Cost of C C squatting plate 1 No. 98.00 1 Each 98.00
Cost of slim line PVC flush tank 10 Ltrs.
capacity single flush 1 No. 1455.00 1 Each 1455.00
Angle stop cock 12.70mm 1 No. 474.00 1 Each 474.00
Add MA on labour charges for fixing angle
stop cock 0.00 43.00 0.00
12.70mm PVC connection with brass union
nuts 1 No. 102.00 1 Each 102.00
Add MA on labour charges for fixing PVC
connection with brass union nuts 0.00 20.00 0.00
31.75mm brass plumber union 1 No. 69.00 1 Each 69.00
Add MA on labour charges for fixing 31.75mm
brass plumber union 0.00 14.00 0.00
Cutting holes in brick masonry 1 No. 47.00 1 Each 47.00
Add MA on labour charges for cutting holes in
brick masonry 0.00 47.00 0.00
Teak wood blocks 76.2mm x 101.6mm 0 Nos. 26.00 1 Each 0.00
Add MA on labour charges for fixing Teak
wood blocks 0.00 9.00 0.00
4157.00
Overheads&Contractors Profit @13.615% 0.13615 4157.00 565.98
4722.98
Rate per Each 4723

9 Supplying and fixing European Water Closet of 1st quality conforming to IS:2556-Part-2-1973 of white
glazed with 'S' trap,supplying and fixing best Indian make plastic seat and lid for European water closets
with rubber or plastic Buffers as per IS 2548-1996 and 10 litres capacity single flush PVC low level cistern
with internal components and fixed using required size of nails and screws, angle stop cock 12.70mm dia.
first quality Indian make heavy duty, 12mm PVC connections with brass union nuts CP coated including cost
and conveyance of all materials to site, overheads & contractors profit etc., complete for finished item of
work for all floors.

Cost of EWC with 'S' trap 1 No 1964.00 1 Each 1964.00


Add MA on labour charges for fixing EWC 0.00 264.00 0.00
Supply and fixing of 10 lts. Capacity lowdown
PVC flushing tank 1 No 1455.00 1 Each 1455.00
Plastic seat and lid for European Water Closet
and rubber buffers 1 No 891.00 1 Each 891.00
WS & SA DATA 2014-15 Page-44
Sl.No Description Qty Unit Rate Per Unit Amount
Add MA on labour charges for fixing Plastic
seat and lid for EWC and rubber buffers 0.00 76.00 0.00
Angle stop cock 12.70mm 1 No. 474.00 1 Each 474.00
Add MA on labour charges for fixing angle
stop cock 0.00 43.00 0.00
12.70mm dia PVC connection with brass union
nuts 1 No 102.00 1 Each 102.00
Add MA on labour charges for fixing PVC
connection with brass union nuts 0.00 20.00 0.00
Cutting holes in brick masonry 1 No. 47.00 1 Each 47.00
Add MA on labour charges for cutting holes in
brick masonry 0.00 47.00 0.00
Cost of 76.2 x 101.60 mm teakwood blocks
2 Nos 26.00 1 Each 52.00
Add MA on labour charges for fixing Teak
wood blocks 0.00 9.00 0.00
4985.00
Overheads&Contractors Profit @13.615% 0.13615 4985.00 678.71
5663.71
Rate per Each 5664.00

10 Supplying and fixing Indian make Flat Back Wash Hand Basin 1st quality conforming to IS:2556-Part-
4:1972 of size 550mm x 400mm with 32 mm nominal size C.P. Fitting with parallel pipe thread conforming to
IS:2963-1979 and fitted with 15 mm nominal bore Chromium Plated Pillar Tap of 1st quality Indian make
heavy duty complete with standard CI brackets including wooden blocks ,1 No.12.70mm PVC connection
with brass union nuts CP coated , angle stop cock 12.70mm dia. first quality Indian make heavy duty,
31.75mm dia. PVC flexible waste pipe 914.4mm length of 1st quality including cost and conveyance of all
materials to site, labour charges , overheads & contractors profit for finished item of work

Cost of Wash hand basin 1 No. 1764.00 1 Each 1764.00


Add MA on labour charges for fixing Wash
hand basin 0.00 377.00 0.00
Angle stop cock 12.70mm 1 No. 474.00 1 Each 0.00
Add MA on labour charges for fixing angle
stop cock 0.00 43.00 0.00
12.70mm PVC connection with brass union
nuts 1 No. 102.00 1 Each 0.00
Add MA on labour charges for fixing PVC
connection with brass union nuts 0.00 20.00 0.00
Deduct cost of NP chain and rubber plug 1 No. 42.00 1 Each 0.00
31.75mm dia. PVC flexible waste pipe 1 No. 26.00 1 Each 0.00
1764.00
Overheads&Contractors Profit @13.615% 0.13615 1764.00 240.17
2004.17
Rate per Each say 2004.00
WS & SA DATA 2014-15 Page-45
Sl.No Description Qty Unit Rate Per Unit Amount

11 Supplying and fixing NP soap dish heavy type of approved make ISI quality with NP screws etc., complete
including cost and conveyance of all materials, labour charges for fixing , overheads & contractors profit for
finished item of work in all floors

Cost of NP soap dish 1 No. 243.00 1 Each 243.00


Add MA charges at 20% 0.00 12.00 0.00
243.00
Overheads&Contractors Profit @13.615% 0.13615 243.00 33.08
276.08
Rate per Each say 276.00

12 Supplying and fixing TV shape mirror with plastic frame of size 609.6mm x 457.2mm , plywood back
with NP screws 1st quality including cost and conveyance of all materials, labour charges , overheads &
contractors profit for finished item of work in all floors.

Rate as per SSR 1 No. 452.00 Each 452.00


Add MA charges at 20% 0.13615 0.00 0.00
452.00
Overheads&Contractors Profit @13.615% 0.13615 452.00 61.54
513.54
Rate per Each say 514.00

13 Supplying and fixing of 25.4mm dia , 609.6mm long aluminium anodized towel rods with brackets and
aluminium screws including cost and conveyance of all materials, labour charges , overheads & contractors
profit for finished item of work.
Rate as per SSR 1 No. 164.00 Each 164.00
Add MA charges at 20% 0.00 44.00 0.00
164.00
Overheads&Contractors Profit @13.615% 0.13615 164.00 22.33
186.33
Rate per Each
say 186.00

14 Supplying and fixing steel surgical long elbow action handle 12.7mm dia bib cock as approved by the
Engineer-In-Charge including cost and conveyance of all materials, labour charges , overheads & contractors
profit complete for finished item of work in all floors.
Rate as per SSR 1 No. 990.00 Each 990.00
Overheads&Contractors Profit @13.615% 0.13615 990.00 134.79
1124.79
Rate per Each say 1125

15 Supplying and fixing NP bib taps of size 12.70mm dia of Indian make heavy duty as approved by the
Engineer-In-Charge including cost and conveyance of all materials, labour charges , overheads & contractors
profit complete for finished item of work in all floors.
Rate as per SSR 1 No. 349.00 Each 349.00
Add MA charges at 20% 0.00 29.00 0.00
349.00
Overheads&Contractors Profit @13.615% 0.13615 349.00 47.52
396.52
Rate per Each say 397

16 Supplying and fixing of SWR PVC pipes (Prince/Sudhakar/Kisan/Supreme or any ISI brand) 4 Kg/Sq.cm.
and fixing all special such as plain bends, off sets, door bends, single junctions, double junctions as per site
requirement, fixing with PVC clamps if necessary with required number of Bombay nails including cost and
conveyance of all materials to site, labour charges, overheads & contractors profit complete for finished item
of work at all floor levels. (APSS No. 1302 1319 & 1326)

a) 75mm dia
Data for 6 RM
Cost of 75mm dia pipe 6.00 RM 432.00 3 RM 864.00
Cost of PVC clamps 3 Nos. 15.00 Each 45.00
Labour charges 6.00 RM 70.00 1 RM 420.00
1329.00
Rate per 1 RM 221.50
WS & SA DATA 2014-15 Page-46
Sl.No Description Qty Unit Rate Per Unit Amount
Overheads&Contractors Profit @13.615% 0.13615 221.50 30.16
251.66
say 252.00

b) 90mm dia
Data for 6 RM
Cost of 90mm dia pipe 6.00 RM 696.00 3 RM 1392.00
Cost of PVC clamps 3 Nos. 17.00 Each 51.00
Labour charges 6 RM 70.00 1 RM 420.00
1863.00
Rate per 1 RM 310.50
Overheads&Contractors Profit @13.615% 0.13615 310.50 42.27
352.77
say 353.00
WS & SA DATA 2014-15 Page-47
Sl.No Description Qty Unit Rate Per Unit Amount
c) 110mm dia
Data for 6 RM
Cost of 110mm dia pipe 6.00 RM 828.00 3 RM 1656.00
Cost of PVC clamps 3 Nos. 18.00 Each 54.00
Labour charges 6 RM 70.00 1 RM 420.00
2130.00
Rate per 1 RM 355.00
Overheads&Contractors Profit @13.615% 0.13615 355.00 48.33
403.33
say 403.00

d) 160mm dia
Data for 6 RM
Cost of 160mm dia pipe 6.00 RM 1153.00 3 RM 2306.00
Cost of PVC clamps 3 Nos. 35.00 Each 105.00
Labour charges 6 RM 70.00 1 RM 420.00
2831.00
Rate per 1 RM 471.83
Overheads&Contractors Profit @13.615% 0.13615 471.83 64.24
536.07
say 536.00

17 Supply and fixing of Ashirvad/ Ajay/ Astral Flowguard or equivalent CPVC Pipes and Fittings SDR
13.5 to meet the requirement of ASTM-D 2846 and are produced in CTS (Copper Tube Sizes 1/2" to 2") for
hot and cold water (IS 15778:2007) including cost and conveyance of all materials to site, labour charges for
fixing, overheads & contractors profit complete for finished item of work at all floor levels.

a) 15.90mm OD pipe
Rate as per SoR 1 No. 141.00 Each 141.00
Overheads&Contractors Profit @13.615% 0.13615 141.00 19.20
Rate per 1 RM 160.20
say 160

b) 22.20mm OD pipe
Rate as per SoR 1 No. 149.00 Each 149.00
Overheads&Contractors Profit @13.615% 0.14000 149.00 20.86
Rate per 1 RM 169.86
say 170

c) 28.60mm OD pipe
Rate as per SoR BMW I.222 1 No. 198.00 Each 198.00
Overheads&Contractors Profit @13.615% 0.14000 198.00 27.72
Rate per 1 RM 225.72
say 226

d) 34.90mm OD pipe
Rate as per SoR 1 No. 289.00 Each 289.00
Overheads&Contractors Profit @13.615% 0.13615 289.00 39.35
Rate per 1 RM 328.35
say 328

e) 41.30mm OD pipe
Rate as per SoR 1 No. 360.00 Each 360.00
Overheads&Contractors Profit @13.615% 0.13615 360.00 49.01
Rate per 1 RM 409.01
say 409

f) 54.00mm OD pipe
Rate as per SoR 1 No. 525.00 Each 525.00
Overheads&Contractors Profit @13.615% 0.13615 525.00 71.48
Rate per 1 RM 596.48
say 596
WS & SA DATA 2014-15 Page-48
Sl.No Description Qty Unit Rate Per Unit Amount
18 Supply and fixing of Ashirvad/ Ajay/ Astral Flowguard or equivalent CPVC Pipes and Fittings SDR 11
to meet the requirement of ASTM-D 2846 and are produced in CTS (Copper Tube Sizes 1/2" to 2") for hot
and cold water (IS 15778:2007) including cost and conveyance of all materials to site, labour charges for
fixing, overheads & contractors profit complete for finished item of work at all floor levels.

a) 15.90mm OD pipe
Rate as per SoR 1 No. 156.00 Each 156.00
Overheads&Contractors Profit @13.615% 0.13615 156.00 21.24
Rate per 1 RM 177.24
say 177

b) 22.20mm OD pipe
Rate as per SoR 1 No. 189.00 Each 189.00
Overheads&Contractors Profit @13.615% 0.13615 189.00 25.73
Rate per 1 RM 214.73
say 215

c) 28.60mm OD pipe
Rate as per SoR 1 No. 227.00 Each 227.00
Overheads&Contractors Profit @13.615% 0.13615 227.00 30.91
Rate per 1 RM 257.91
say 258

d) 34.90mm OD pipe
Rate as per SoR 1 No. 310.00 Each 310.00
Overheads&Contractors Profit @13.615% 0.13615 310.00 42.21
Rate per 1 RM 352.21
say 352

e) 41.30mm OD pipe
Rate as per SoR 1 No. 383.00 Each 383.00
Overheads&Contractors Profit @13.615% 0.13615 383.00 52.15
Rate per 1 RM 435.15
say 435

f) 54.00mm OD pipe
Rate as per SoR 1 No. 560.00 Each 560.00
Overheads&Contractors Profit @13.615% 0.13615 560.00 76.24
Rate per 1 RM 636.24
say 636

19 Supplying & fixing GI pipe Medium Grade properties & weight as per IS 1239 ISI mark in ground or on
wall including cost of tees, elbows, bends, reducers, couplings, running joints, union flanges, unions etc.
with necessary excavation in all types of soils except rock requiring blasting, refilling, chiselling masonry
walls and making good the walls & floors to the original surface and fixing MS clamps on TW blocks on walls
including cost and conveyance of all materials and labour charges , overheads & contractors profit complete
for finished item of work.

a) 15mm Nominal bore


Rate as per SSR 1.00 RM 204.00 1 RM 204.00
Add MA charges at 20% 0.00 41.00 0.00
204.00
Overheads&Contractors Profit @13.615% 0.13615 204.00 27.77
231.77
Rate per 1 RM say 232

b) 20mm Nominal bore


Rate as per SSR 1.00 RM 227.00 1 RM 227.00
Add MA charges at 20% 0.00 41.00 0.00
227.00
Overheads&Contractors Profit @13.615% 0.13615 227.00 30.91
257.91
Rate per 1 RM say 258

c) 25mm Nominal bore


WS & SA DATA 2014-15 Page-49
Sl.No Description Qty Unit Rate Per Unit Amount
Rate as per SSR 1.00 RM 297.00 1 RM 297.00
Add MA charges at 20% 0.00 41.00 0.00
297.00
Overheads&Contractors Profit @13.615% 0.13615 297.00 40.44
337.44
Rate per 1 RM say 337
WS & SA DATA 2014-15 Page-50
Sl.No Description Qty Unit Rate Per Unit Amount
d) 32mm Nominal bore
Rate as per SSR 1.00 RM 417.00 1 RM 417.00
Add MA charges at 20% 0.00 41.00 0.00
417.00
Overheads&Contractors Profit @13.615% 0.13615 417.00 56.77
473.77
Rate per 1 RM say 474

e) 40mm Nominal bore


Rate as per SSR 1.00 RM 466.00 1 RM 466.00
Add MA charges at 20% 0.00 44.00 0.00
466.00
Overheads&Contractors Profit @13.615% 0.13615 466.00 63.45
529.45
Rate per 1 RM say 529

f) 50mm Nominal bore


Rate as per SSR 1.00 RM 412.00 1 RM 412.00
Add MA charges at 20% 0.00 67.00 0.00
412.00
Overheads&Contractors Profit @13.615% 0.13615 412.00 56.09
468.09
Rate per 1 RM say 468

20 Supplying and fixing 65 mm Nominal Bore GI pipe Medium Grade properties & weight as per IS 1239
in ground or on wall with GI fittings such as elbows tees couplings, nipples, plugs including excavation for
trenches and refilling the trenches ,chiselling masonry walls and making good the walls & floors to the
original surface and fixing MS clamps on TW blocks on walls including cost and conveyance of all materials
and labour charges , overheads & contractors profit complete for finished item of work except for GI bends
union and GI connectors with checkout and socket Tata or Zenith make or equivalent

Rate as per SSR 1.00 RM 892.00 1 RM 892.00


Overheads&Contractors Profit @13.615% 0.13615 892.00 121.45
1013.45
Rate per 1 RM say 1013

21 Supplying and fixing Gunmetal Gate ( GM peet ) valve as per IS-778 Class - I , Indian make heavy type
including cost and conveyance of all materials , labour charges , overheads & contractors profit complete for
finished item of work.

a) 15mm Nominal bore


Rate as per SSR 1 No. 636.00 Each 636.00
Add MA charges at 20% 0.00 44.00 0.00
636.00
Overheads&Contractors Profit @13.615% 0.13615 636.00 86.59
722.59
Rate per Each say 723

b) 20mm Nominal bore


Rate as per SSR 1 No. 858.00 Each 858.00
Add MA charges at 20% 0.00 44.00 0.00
858.00
Overheads&Contractors Profit @13.615% 0.13615 858.00 116.82
974.82
Rate per Each say 975
WS & SA DATA 2014-15 Page-51
Sl.No Description Qty Unit Rate Per Unit Amount
c) 25mm Nominal bore
Rate as per SSR 1 No. 1233.00 Each 1233.00
Add MA charges at 20% 0.00 44.00 0.00
1233.00
Overheads&Contractors Profit @13.615% 0.13615 1233.00 167.87
1400.87
Rate per Each say 1401

d) 32mm Nominal bore


Rate as per SSR 1 No. 1875.00 Each 1875.00
Add MA charges at 20% 0.00 44.00 0.00
1875.00
Overheads&Contractors Profit @13.615% 0.13615 1875.00 255.28
2130.28
Rate per Each say 2130

e) 40mm Nominal bore


Rate as per SSR 1 No. 2533.00 Each 2533.00
Add MA charges at 20% 0.00 67.00 0.00
2533.00
Overheads&Contractors Profit @13.615% 0.13615 2533.00 344.87
2877.87
Rate per Each say 2878

f) 50mm Nominal bore


Rate as per SSR 1 No. 3711.00 Each 3711.00
Add MA charges at 20% 0.00 90.00 0.00
3711.00
Overheads&Contractors Profit @13.615% 0.13615 3711.00 505.25
4216.25
Rate per Each say 4216

g) 65mm Nominal bore


Rate as per SSR 1 No. 5730.00 Each 5730.00
Add MA charges at 20% 0.00 112.00 0.00
5730.00
Overheads&Contractors Profit @13.615% 0.13615 5730.00 780.14
6510.14
Rate per Each say 6510

h) 80mm Nominal bore


Rate as per SSR 1 No. 8494.00 Each 8494.00
Add MA charges at 20% 0.00 133.00 0.00
8494.00
Overheads&Contractors Profit @13.615% 0.13615 8494.00 1156.46
9650.46
Rate per Each say 9650

22 Providing and placing on terrace (at all floor levels)polyetheylene water storage tank with double
layer approved brand and manufacture with cover and suitable locking arrangement and making necessary
holes for inlet and outlets and over flow pipes but without fittings and base support for tanks including cost
and conveyance of all materials and labour charges , overheads & contractors profit complete for finished
item of work.

Rate as per SSR 1 Ltr 6.00 1 Ltr 6.00


Add MA charges at 20% 0.00 1.00 0.00
6.00
Overheads&Contractors Profit @13.615% 0.13615 6.00 0.82
Rate per 1 Ltr 6.82
WS & SA DATA 2014-15 Page-52
Sl.No Description Qty Unit Rate Per Unit Amount
23 Supplying and fixing of stainless steel sink of size 508.00mm x 457.2mm x 203.20mm, 1mm thick of
Indian make fixed on cantilever brackets including supply and fixing 31.75mm C.P. waste coupling, 31.75
mm dia PVC flexible waste pipe of 914.4 mm length of Ist quality ncluding chiselling brick masonry wall and
making good & restoring to original surfaces , overheads & contractors profit complete for finished item of
work in all floors

Rate as per SSR 1 No 5396.00 Each 5396.00


Add MA charges at 20% 0.00 449.00 0.00
5396.00
Overheads&Contractors Profit @13.615% 0.13615 5396.00 734.67
6130.67
Rate per Each say 6131

23 Supplying and fixing of stainless steel sink of size 914.4 mm x457.2mm, 1mm thick of Indian make
fixed on cantilever brackets including supply and fixing 31.75mm C.P. waste coupling, 31.75 mm dia PVC
flexible waste pipe of 914.4 mm length of Ist quality ncluding chiselling brick masonry wall and making good
& restoring to original surfaces overheads & contractors profit complete.for finished item of work in all floors.

Rate as per SSR 1 No 7552.00 Each 7552.00


Add MA charges at 20% 0.00 506.00 0.00
7552.00
Overheads&Contractors Profit @13.615% 0.13615 7552.00 1028.20
8580.20
Rate per Each say 8580

24 Supplying and fixing white glazed flat back Bowl urinals of size 440 mm x 265 mm x 315 mm with
integral flushing rim fixed with screws complete Indian make (HSW/Parry/Neycer) conforming to IS:2556-
1995 as approved by Engineer-in-charge, including supply and fixing 12.7mm PVC connection with brass
plumber union nuts CP coated, 12.70mm push cock 1st quality of approved make , 31.75 mm dia PVC
flexible waste pipe of 914.4 mm length of Ist quality including cost and conveyance of all materials to site,
labour charges , overheads & contractors profit complete for finished item of work for all floors.

Rate as per SSR 1 No 810.00 Each 810.00


Add MA charges at 20% 0.00 150.00 0.00
12.7mm PVC connections with brass plumber
union nuts 1 No 102.00 Each 0.00
Add MA charges at 20% 0.00 20.00 0.00
12.70mm NP push cock 1 No 271.00 Each 0.00
31.75mm dia. PVC flexible waste pipe 1 No 26.00 Each 0.00
810.00
Overheads&Contractors Profit @13.615% 0.13615 810.00 110.28
920.28
Rate per Each Say 920

25 Supplying and fixing white glazed flat back half stall urinals of size 590 mm x 375 mm x 390 mm with
integral flushing rim fixed with screws complete Indian make (HSW/Parry/Neycer) conforming to IS:2556-
1995 as approved by Engineer-in-charge, including supply and fixing 12.7mm PVC connection with brass
plumber union nuts CP coated, 12.70mm push cock 1st quality of approved make , 31.75 mm dia PVC
flexible waste pipe of 914.4 mm length of Ist quality including cost and conveyance of all materials to site,
labour charges etc., overheads & contractors profit complete for finished item of work for all floors.

Rate as per SSR 1 No 3100.00 Each 3100.00


Add MA charges at 20% 0.00 150.00 0.00
12.7mm PVC connections with brass plumber
union nuts 1 No 102.00 Each 102.00
Add MA charges at 20% 0.00 20.00 0.00
12.70mm NP push cock 1 No 271.00 Each 271.00
31.75mm dia. PVC flexible waste pipe 1 No 26.00 Each 26.00
3499.00
Overheads&Contractors Profit @13.615% 0.13615 3499.00 476.39
3975.39
Rate per Each Say 3975
WS & SA DATA 2014-15 Page-53
Sl.No Description Qty Unit Rate Per Unit Amount
26 Supplying and fixing of 16mm to 20 mm thick polished marble slab partitioins of size 4' 0" x 2' 0" for
urinals including full rounding the edges , fixing in position, polishing, including cost and conveyance of all
materials and labour charges , overheads & contractors profit complete for finished item of work for all floors.

Rate as per SSR 0.72 Sqm 1001.97 1 Sqm 721.42


Chiselling the brick masonry wall 1.20 RM 30.00 1 RM 36.00
Add MA charges at 20% 0.00 36.00 0.00
Rounding the edges of marble 2.40 RM 374.00 1 RM 897.60
Labour charges for fixing ( dadooing labour
charges ) 0.72 Sqm 662.65 10 Sqm 47.71
Add MA charges at 20% 0.00 47.71 0.00
1702.73
Overheads&Contractors Profit @13.615% 0.13615 1702.73 231.83
1934.56
Rate per Each Say 1935

27 Supplying and fixing of 101.60mm x 609.60mm white glazed porcelain channels 1st quality fixed in brick
masonry to the required slopes , white cement pointing including cost and conveyance of all materials and
labour charges , overheads & contractors profit complete for finished item of work for all floors.

Rate as per SSR 1 No 545.00 1 Each 545.00


Rate for 1 RM (1/0.6096) 545.00 894.03
Overheads&Contractors Profit @13.615% 0.13615 894.03 121.72
1015.75
Say 1016

28 Construction of brick masonry support for GI pipe of size 304.80mm x 228.60mm x 228.60 mm in CM
(1:8) prop including plastering and finishing with 12mm thick in CM (1:5) including cost and conveyance of
all materials and all labour charges, overheads & contractors profit complete for finished item of work for all
floors.

Rate as per SSR 1 No 76.00 1 Each 76.00


Add MA charges at 20% 0.00 22.00 0.00
76.00
Overheads&Contractors Profit @13.615% 0.13615 76.00 10.35
86.35
JOINARY DATA
1 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65 mm
and ISI marked flush door shutters of 30 mm thick double shutters with bond wood solid block board
type Core having cross bands and face veneers, hot pressed bonded with water proof phenol
formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both sides commercial
ply with internal lipping on all sides including cost and conveyance to site of teak wood frame, flush
shutter including

supply and fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked
MS powder coated fixtures of 6 Nos. butt hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm
long, 2 Nos. tower bolts (IS:204) of 200 mm x 10 mm dia at top, 2 Nos. 150 mm long handles (IS:208), 2
Nos. door stoppers and 2 Nos. rubber bushes including fixing the fixtures to door with required number
of screws, bolt and nuts including labour charges for fixing the frame in position, fixing the shutter to the
frame etc., including overheads & contractors profit complete for finished item of work as per APSS 1001
& 1002 (The vertical frame of door shall be embedded in flooring for a depth of not less than 10 mm)
(1200mm x 2100mm)

(BLD-CSTN-13-16)
Size : 1.20m x 2.10m 2.52 Sqm
Quantity analysis
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743 cum

Outer frame - Horizontal 1 x 1.20

= 1.20 x 0.10 x 0.065 0.00780 cum


0.03523 cum

30 mm thick flush shutter 2 x 0.55 x 2.05 2.255 sqm

Cost of medium TW frame 2 m


0.0274 cum 88994 1 cum 2441.11
to 3m length
Cost of medium TW frame
0.0078 cum 80094 1 cum 624.73
below 2 m length
Cost of 30 mm thick flush
2.255 sqm 1314 1 sqm 2963.07
shutter
Cost of MS Z hold fasts 6 Nos. 25 Each 150
Cost of MS powder coated
2 Nos. 56 Each 112
tower bolt 200mm long
Cost of MS powder coated butt
6 Nos. 44 Each 264
hinges 150mm long
Cost of MS powder coated
1 No. 181 Each 181
aldrop 300mm long
Cost of MS powder coated
2 Nos. 50 Each 100
handle 150mm long
Cost of MS powder coated door
2 Nos. 50 Each 100
stopper
Cost of rubber bush 2 Nos. 25 Each 50
Labour charges for frame work 0.035 cum 9692.45 1 cum 341.47
Add for MA @ 20% 0.2 341.47 68.29

Labour charges for fixing flush


door shutter to the frame , 2.255 sqm 348 1 sqm 784.74
fixing the fixtures to the shutter

Add for MA @ 20% 0.2 784.74 156.95


Add for nails & screws etc. 6.34
Rate for 2.52 sqm 8343.69
Rate for 1 sqm 3310.99
Overheads&Contractors Profit
0.13615 3310.99 450.79
@13.615%
Rate for 1 sqm 3761.78
Say 3762.00

2 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65 mm
and ISI marked flush door shutters of 30 mm thick single shutter with bond wood solid block board
type Core having cross bands and face veneers, hot pressed bonded with water proof phenol
formaldehyde synthetic resin factory made conforming to IS 2202-1991 (Part-I) both sides commercial
ply with internal lipping on all sides including cost and conveyance to site of teak wood frame, flush
shutter including supply and

fixing 6 Nos. MS Z hold fasts of size 300 mm x 40 mm x 5mm including cost of ISI marked MS powder
coated fixtures of 3 Nos. butt hinges (IS:205) 150mm long, 1 No. aldrop (IS:2681) 300mm long, 1 No.
tower bolt (IS:204) of 200 mm x 10 mm dia at top , 2 Nos. 150 mm long handles (IS:208), 1 No. door
stopper and 1 No. rubber bush including fixing the fixtures to door with required number of screws, bolt
and nuts including labour charges for fixing the frame in position, fixing the shutter to the frame etc.,
including overheads & contractors profit complete for finished item of work as per APSS 1001 & 1002
(The vertical frame of door shall be embedded in flooring for a depth of not less than 10 mm) (1000mm
x 2100mm)

(BLD-CSTN-13-16)
Size : 1.00m x 2.10m 2.1 sqm
Quantity analysis
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743 cum
Outer frame - Horizontal 1 x 1.00
= 1.00 x 0.10 x 0.065 0.00650 cum
0.03393 cum

30 mm thick flush shutter 0.90 x 2.05 1.845 sqm

Cost analysis
Cost of medium TW frame 2 m
0.02743 cum 88994 1 cum 2441.11
to 3m length
Cost of medium TW frame up to
0.0065 cum 80094 1 cum 520.61
2 m length
Cost of 30 mm thick flush
1.845 sqm 1314 1 sqm 2424.33
shutter
Cost of MS Z hold fasts 6 Nos. 25 Each 150
Cost of MS powder coated
1 No. 56 Each 56
tower bolt 200mm long
Cost of MS powder coated butt
3 Nos. 44 Each 132
hinges 150mm long
Cost of MS powder coated
1 No. 181 Each 181
aldrop 300mm long
Cost of MS powder coated
2 Nos. 50 Each 100
handle 150mm long
Cost of MS powder coated door
1 No. 50 Each 50
stopper
Cost of rubber bush 1 No. 25 Each 25
Labour charges for frame work 0.0339 cum 9692.45 1 cum 328.86
Add for MA @ 20% 0.2 328.86 65.77

Labour charges for fixing flush


door shutter to the frame , 1.845 sqm 348 1 sqm 642.06
fixing the fixtures to the shutter

Add for MA @ 20% 0.2 642.06 128.41


Add for nails & screws etc. 6.3
Rate for 2.10 sqm 7251.46
Overheads&Contractors Profit
0.13615 7251.46 987.29
@13.615%
8238.74
Rate for 1 sqm 3923.21
Say 3923.00

3 Providing, supplying & fixing of Fixed Louvered Ventilator made out of multi chambered UPVC
sections with TPV gaskets having isolated drainage and reinforced with Galvanized Iron profiles
throughout the window. The outer frame having an overall size of 60 x 55 mm with reinforcement of 1
mm thickness and Mullion with overall size of 74 x 60 mm with reinforcement of 1 mm thickness.
Ventilator shall be provided with 4.5 mm pin head glass, standard hardware, wall thickness of frame &
mullion shall be 2.0 mm including cost and conveyance of all materials, accessories, labour charges for
transportation, erection at site, overheads and contractor profit etc., complete for finished item of work

Rate as per SSR 1.00 Sqm 6005.00 1.00 Sqm 6005.00


Overheads&Contractors Profit
@13.615% 0.13615 6005.00 817.58
Rate for 1 Sqm 6822.58
Say 6823.00

4 Supplying and fixing of Unplasticised Poly Vinyl Chloride (UPVC) sliding windows three track -
two glass shutters sliding and one mesh shutter duly manufactured using UPVC reinforced profiles of
(94 mm x 45 mm)/(80 mm x 52 mm) x 2.0 mm for outer frames, (58 mm x 39 mm)/(54 mm x 38 mm) x
2.0 mm for sliding shutter frames capable of mounting single glazing system structurally reinforced with
hot dip galvanized up to 50 microns of minimum thickness of 1.2 mm prefabricated & welded through
fusion welding the window sash shall be fitted with 5 mm thick clear float glass of reputed make and
mesh shutter frame shall be (42 mm x 25 mm)/(52 mm x 21.5 mm) x 2 mm fitted with nylon/ polymer
mesh on rollers/ pulley duly fixed with TPV Gaskets/ EPDM weathering seal resistant accessories like
locking system 1 No., per set of sashes and the system is to be installed at the site using anchor
fasteners, silicon rubber sealant, easy glazing/ deglazing at site etc., including cost and conveyance of
all materials, accessories, labour charges for transportation, erection at site with templates for casement
sizing, overheads and contractors profit etc., complete for finished item of work

Rate as per SSR 1.00 Sqm 6674.00 1.00 Sqm 6674.00


Overheads&Contractors Profit
@13.615% 0.13615 6674.00 908.67
Rate for 1 Sqm 7582.67
Say 7583.00

5 Supply and fixing doors as per drawings with medium teak wood frame of section 100mm x 65mm
and ISI marked flush door shutter of 30mm thick single shutter with bond wood solid block board type
Core having cross bands and face veneers, hot pressed bonded with water proof phenol formaldehyde
synthetic resin factory made conforming to IS 2202-1991 (Part-I) both sides commercial ply with internal
lipping on all sides including cost and conveyance to site of medium teak wood door frame, flush
shutter, including suply and fixing 6 Nos. MS Z hold fasts of size 300mm x 40mm x 5mm including ISI
marked MS powder coated fixtures 3 Nos. butt hinges (IS:205) of 150mm long, 1 No. aldrop (IS:2681)
250 mm long,

1 No. tower bolt (IS:204) of 150 mm x 10mm dia, 2 Nos. 125mm long handles (IS:208),1 No. rubber
bush including supplying and fixing 1.20mm thick PVC sheet to full height of the shutter inside including
labour charges for fixing the frame in position, fixing the shutter to the frame etc., including overheads &
contractors profit complete for finished item of work as per APSS 1001 & 1002. (The vertical frame of
door shall be embedded in flooring for deth of not less than 10mm) ( 750mm x 2100mm )

(BLD-CSTN-13-16)
Quantity analysis Size : 0.75m x 2.10m 1.575 sqm
Outer frame - Vertical 2 x 2.11
= 4.22 x 0.10 x 0.065 0.02743 cum
Outer frame - Horizontal 1 x 0.75
= 0.75 x 0.10 x 0.065 0.00488 cum
0.03231 cum
30 mm thick flush shutter 0.65 x 2.05 1.333 sqm

Cost analysis
Cost of medium TW frame 2 m
to 3m length 0.02743 cum 88994.00 1 cum 2441.11
Cost of medium TW frame up to
2 m length 0.00488 cum 80094.00 1 cum 390.86
Cost of 30 mm thick flush
shutter 1.333 sqm 1314.00 1 sqm 1751.56
Cost of MS Z hold fasts 6 Nos. 25.00 Each 150.00
Cost of MS powder coated
tower bolt 150mm long 1 No. 38.00 Each 38.00
Cost of MS powder coated Butt
hinges 150mm long 3 Nos. 44.00 Each 132.00
Cost of MS powder coated
aldrop 250mm long 1 No. 151.00 Each 151.00
Cost of MS powder coated
handle 125mm long 1 No. 34.00 Each 34.00
Cost of rubber bush 1 No. 25.00 Each 25.00
Cost of 1.20mm thick PVC
sheet 1.333 sqm 160.00 1 sqm 213.28
cost of Fevicol & labour
charges for fixing PVC sheet 1.333 sqm 75.00 1 sqm 99.98
Labour charges for frame work 0.03231 cum 0.00 1 cum 0.00
Add for MA @ 20% 0.20 0.00 0.00

Labour charges for fixing flush


door shutter to the frame ,
fixing the fixtures to the shutter 1.333 sqm 348.00 1 sqm 463.88
Add for MA @ 20% 0.20 463.88 92.78
Add for nails & screws etc. 6.91
Rate for 1.68 sqm 5990.35
Overheads&Contractors Profit
@13.615% 0.13615 5990.35 815.59
6805.94
Rate for 1 sqm 4321.23
Say 4321.00

6 Supply and fixing of best Sal wood window of size 0.91x1.22 meters of Hyderabad type fully panelled,
including furniture and fixtures like hinges, tower bolts aldrops and wind appliances andfixing of 16mm
dia. MS rods at 100mm C/C horizontally and including cost and conveyance of all materials and all
labour charges etc., complete.
FINISHED DATAS 2016-17
Quan- Rate Amount
SD/ SSR No. Description of work Unit
tity Rs. Rs.
LIGHT POINT WITH FLUSH TYPE SWITCH (Non-Residential
Buildings)
(Makes of wires:- KEI/Polycab/Havells/GM/Million/HPL/Gold Medal/Power Flex/RPG/Anchor)

(Makes of switches:- GM G Home/Gold Medal Olive/Million Zoom/Anchor Penta Cherry)

DATA SD-2.1.1 Wiring with 2 runs of 22/0.3mm ( 1.5 Sq.mm) FRLS/HFFR P.V.C. insulated
b flexible copper cable (ISI MARK) in existing pipe with 6A flush type switch
control, ceiling rose and 3mm thick hylam sheet covering to MS switch box
including all labour charges etc., complete for light points, bell points, fan and
exhaust fan points in Non residential buildings.

Taking Output = 6 Points


a) Material
1.5.9 22/0.3mm FRLS/HFFR PVC
100 M 1 1358.00 1358.00
copper wire
1.7.1 6A 1 way flush type switch each 6 18.00 108.00
1.7.13 6A 2 way Ceiling Rose 3 plate
each 6 21.00 126.00

8.1.51 10"x8" size, 3mm thick hylam


Sq.Inch 80 0.60 48.00
sheet
b) Labour charges :

8.1.74 Skilled Electrician day 0.6 440.00 264.00


8.1.75 Semi skilled Electrician day 1.2 375.00 450.00
8.1.82 Helpers day 0.6 345.00 207.00
Sundries 7.00
C) Cost for 6 Points 2568
Rate per Point 428.00
6A SOCKET ON COMMON BOARD
DATA SD-2.1.5 Wiring with three runs of 1.5 sq.mm FRLS PVC insulated flexible copper
Taking Output = 1 Point

a) Material

1.7.1 6A 1 way flush type switch each 1 18.00 18.00


1.7.4 6A, 3 pin/2 pin, 2 in one flush
each 1 27.00 27.00
type socket
b) Labour charges :

8.1.74 Skilled Electrician day 0.067 440.00 29.48


8.1.82 Helpers day 0.067 345.00 23.12
Sundries 0.41
Rate per each Point 98.00

6A SOCKET ON SEPARATE BOARD


DATA SD-2.1.3 Wiring with 2 of 22/0.3mm (1.5 Sq.mm) P.V.C. insulated FRLS/HFFR flexible
copper cable (ISI mark) in existing pipe with 6A switch and 6A, 3 pin/2 pin (2
in one) flush type socket fixing on existing separate MS switch board covered
with 3mm thick hylam sheet including all labour charges etc., complete.
Taking Output = 15 Points
a) Material
1.5.9 22/0.3mm FRLS/HFFR PVC
100 M 1 1293.00 1293.00
copper wire
1.7.1 6A 1 way flush type switch
each 15 18.00 270.00

1.7.4 6A, 3 pin/2 pin, 2 in one flush


each 15 27.00 405.00
type socket
8.1.51 4"x7" size, 3mm thick hylam
Sq.Inch 420 0.60 252.00
sheet
b) Labour charges :
8.1.74 Skilled Electrician day 1.5 440.00 660.00
8.1.75 Semi skilled Electrician day 1.5 375.00 562.50
8.1.82 Helpers day 1.5 345.00 517.50
Sundries 15.00
C) Cost for 15 Points 3975
Rate per Each Point 265.00

16A/6A, SWITCH CUM SOCKET (2 in 1)


DATA SD-2.1.5 Supply & Fixing of 16A/6A, 2 in one, flush type socket with 16A flush type
switch control on 6"x8" size MS switch board covered with 3mm thick hylam
sheet including giving connections and all labour charges etc., complete.
a) Material

1.7.10 16A flush type Switch-Socket


combined (2in1) each 1 102.00 102

8.1.51 6"x8" size, 3mm thick hylam Sq.Inch 48 0.60 28.8


sheet
1.3.10 6"x8" MS Switch Box
each 1 105.00 105
concealed
b) Labour charges :

8.1.74 Skilled Electrician day 0.067 440.00 29.48


8.1.82 Helpers day 0.067 345.00 23.115
Sundries 1.605
Rate per each 290.00

RUN OF MAINS
DATA
DATA SD-3.1.3 Supply and run of 1 of 22/0.3mm (1.5 Sq.mm) FRLS/HFFR P.V.C. insulated
flexible copper cable in existing pipe for mains inlcuding all labour charges etc.,
complete.
Taking Output = 100 M
a) Material
1.5.9 22/0.3mm FRLS/HFFR PVC 100 M 1 1358.00 1358.00
copper wire
b) Labour charges :
8.1.74 Skilled Electrician day 0.34 440.00 149.60
8.1.75 Semi Skilled Electrician day 1 375.00 375.00
8.1.82 Helpers day 0.34 345.00 117.30
Sundries 0.10
C) Cost for 100 RM 2000.00
Rate per Metre = C/100 20.00
150 M / day

DATA SD- Supply and run of 3 of 36/0.3mm (2.5 Sq.mm) FRLS/HFFR P.V.C. insulated
3.1.4a flexible copper cable in existing pipe for mains inlcuding all labour charges etc.,
complete.
Taking Output = 100 M

a) Material

1.5.10 36/0.3mm FRLS/HFFR PVC


copper wire 100 M 3 2195.00 6585.00

b) Labour charges :
8.1.74 Skilled Electrician day 1.02 440.00 448.80
8.1.75 Semi Skilled Electrician day 3 375.00 1125.00
8.1.82 Helpers day 1.02 345.00 351.90
Sundries 4.30
C) Cost for 100 RM 8515.00
Rate per Metre 85.15
DATA SD-3.1.5 Supply and run of 1 of 14/0.3mm (4 Sq.mm) FRLS/HFFR P.V.C. insulated
flexible copper in existing pipe for mains inlcuding all labour charges etc.,
complete.

Taking Output = 100 M


a) Material
1.5.11 56/0.3mm FRLS/HFFR PVC 100 M 1 1001.00 1001.00
copper wire
b) Labour charges :

8.1.74 Skilled Electrician day 0.34 400.00 136.00


8.1.75 Semi Skilled Electrician day 1 320.00 320.00
8.1.82 Helpers day 0.34 320.00 108.80
Sundries & rounding off -5.70

112.96
C) Cost for 100 RM 1673.06

Rate per Metre 16.73

2.34
DATA SD-3.1.5 Supply and run of 2 of 56/0.3mm (4 Sq.mm) FRLS/HFFR P.V.C. insulated
flexible copper in existing pipe for mains inlcuding all labour charges etc.,
complete.

Taking Output = 100 M


a) Material
1.5.11 56/0.3mm FRLS/HFFR PVC 100 M 2 3200.00 6400.00
copper wire
b) Labour charges :

8.1.74 Skilled Electrician day 1 400.00 400.00


8.1.75 Semi Skilled Electrician day 3 320.00 960.00
8.1.82 Helpers day 1 320.00 320.00
Sundries & rounding off -5.70

336.00
C) Cost for 100 RM 8410.30

Rate per Metre 84.10


11.77442
DATA SD-3.1.6 Supply and run of 3 of 84/0.3mm (6 Sq.mm) FRLS/HFFR P.V.C. insulated
flexible copper cable in existing pipe for mains inlcuding all labour charges etc.,
complete.
2.342284
DATA SD-3.1.5 Supply and run of 3 of 56/0.3mm (4 Sq.mm) FRLS/HFFR P.V.C. insulated
flexible copper in existing pipe for mains inlcuding all labour charges etc.,
complete.

Taking Output = 100 M


a) Material
1.5.11 56/0.3mm FRLS/HFFR PVC 100 M 3 3360.00 10080.00
copper wire
b) Labour charges :

8.1.74 Skilled Electrician day 1.02 440.00 448.80


8.1.75 Semi Skilled Electrician day 3 375.00 1125.00
8.1.82 Helpers day 1.02 345.00 351.90
Sundries & rounding off -5.70
C) Cost for 100 RM 12000.00
Rate per Metre 120.00

DATA SD-3.1.6 Supply and run of 3 of 84/0.3mm (6 Sq.mm) FRLS/HFFR P.V.C. insulated
flexible copper cable in existing pipe for mains inlcuding all labour charges etc.,
complete.
Taking Output = 100 M
a) Material
1.5.12 84/0.3mm FRLS/HFFR PVC
copper wire 100 M 3 5250.00 15750.00

b) Labour charges :
8.1.74 Skilled Electrician day 1.02 440.00 448.80
8.1.75 Semi Skilled Electrician day 3 375.00 1125.00
8.1.82 Helpers day 1.02 345.00 351.90
Sundries 4.30
C) Cost for 100 RM 17680.00
Rate per Metre 176.80

DATA Supply, Transportaton, and fixing of 1x28W, box type powder coated energy
conserving tube light luminaire with Electronic ballast operating voltage range of
90 volts to 350 volts power factor > 0.98 current less than 130ma crest factor
and total hormonic distortion shall be as per IS Specification with auto cut off at
high voltage suitable for 36/40W tube with 5 years guarantee for luminaire,
including all labour charges for fixing on 2 No TW round blocks and giving all
connections with flexible three core wire and cost and conveyance of all
materials etc complete. (Trinic make only with 5 Years guarantee)

3.8.2 Cost of fitting without tube Each 1 1060.00 1060.00


3.7.7 Cost of 36/40W tube Each 1 45.00 45.00
1.6.8 23/0060 twin core wire M 1 10.40 10.40
8.1.35 Cost of TW Round Blocks Each 2 7.00 14.00
8.1.6 Rawl Plugs Each 2 0.28 0.56
1.4.23 35/38mm screws Each 2 0.96 1.92
b) Labour charges.
8.1.75 Semi skilled Electrician day 0.1 375.00 37.50
8.1.82 Helper day 0.1 345.00 34.50
sundries LS 1 1.12 1.12
Rate per Each 1205.00

DATA Supply of 48" (1200mm) Sweep ISI mark as per IS 374 - 1979 and 5 Star rated
Ceiling Fan, with double ball bearings but without Regulator of makes Crompton
High Speed Plus / Bajaj Electra 50 / Orient Energy Star / Havells ES 50.

5.1.1 Supply of 48" (1200mm)


Sweep ISI mark as per IS 374
- 1979 and 5 Star rated
Ceiling Fan, with double ball
bearings but without Regulator Each 1 1825 1825.00
of makes Crompton High
Speed Plus / Bajaj Electra 50 /
Orient Energy Star / Havells
ES 50.

DATA 9.7.35 Labour charges for fixing of ceiling fan with regulator including transportation, 3
core wire leads etc complete
a) Material
1.6.8 23/0060 twin core wire M 1 9.90 9.90
b) Labour charges.

Fixing of ceiling fan


8.1.75 Semi skilled Electrician day 0.125 375.00 46.88
8.1.84 Helper day 0.125 375.00 46.88
sundries LS 0.10
Rate per Each 103.75
Note : Labour is Considered
for8 jobs / day

DATA Supply of Goldmedal Olive/Million Zoom/Anchor Penta cherry make flush type
Electronic fan regulator hum free step type socket size, 2 Module with cover
frame in the existing switch board.
1.7.12
Supply of Goldmedal
Olive/Million Zoom/Anchor
Penta cherry make flush type
Electronic fan regulator hum Each 1 220.00 220
free step type socket size, 2
Module in the existing switch
board.

Rate per each 220.00

SD- Supply and erecting 19/20mm steel tube down rod of 0.45 meter length with
9.7.25 bolts & nuts duly painted with matching colour of fan complete

a) Material
8.1.24 19/20mm steel tube down rod
with bolts & nuts for fan with M 0.45 66.00 29.70
maching colour.
b) Labour charges for
Fixing
Helper day 0.1 345.00 34.50
sundries like paint etc LS 4.60
68.80
DEDUCT cost of 9" size fan
down rod originally supplied
-13.80
with the fan by the
manufacturer
Rate per Each 55.00
Note : Labour is Considered for 10 jobs / day

SD- Supply and erecting 19/20mm steel tube down rod of 0.6 meter length with
9.7.25 bolts & nuts duly painted with matching colour of fan complete

a) Material
8.1.24 19/20mm steel tube down rod
with bolts & nuts for fan with M 0.6 66.00 39.60
maching colour.
b) Labour charges for
Fixing
Helper day 0.1 345.00 34.50
sundries like paint etc LS 4.70
78.80
DEDUCT cost of 9" size fan
down rod originally supplied
-13.80
with the fan by the
manufacturer
Rate per Each 65.00
Note : Labour is Considered for 10 jobs / day

SD- Supply and fixing of Ceiling Fan hook with Anchor Hook fasteners with 12/15mm
9.7.24 dia MS Rod / bar duly drilled in RCC slab with making the slab as original.

a) Material
8.1.23 12 / 15 MS plain rod fan hook
each 1 22.00 22.00

b) Labour charges for


Fixing
Skilled Electrician day 0.166 440.00 73.04
Semi Skilled Electrician/Helper
day 0.166 345.00 57.27

Sundries like hire charges of


T&P required like drilling
machine, power suply etc., 12.69
and rounding off
Rate per Each 165.00
Note : Labour is Considered for 10 jobs / day

DATA Supply,Transportation of light duty exhaust fan of makes Crompton / Bajaj


Bahar WG / Havells Ventil Air-DB / Orient hill air of 12" (300 mm) size 900 rpm
with metal blades wiremesh with all accessories etc complete

5.1.11 Supply,Transportation of light


duty exhaust fan 12"(300
mm) size 900 rpm with metal
Each 1 1350.00 1350.00
blades wiremesh with all
accessories etc complete

DATA Supply,Transportation of Heavy duty exhaust fan 12"(300 mm) size 900 rpm
with ISI mark of makes Crompton / Almonard / Havells Turbo Force with metal
blades wiremesh with all accessories etc complete

5.1.13 Supply,Transportation of
Heavy duty exhaust fan
12"(300 mm) size 900 rpm
with metal blades wiremesh Each 1 2645.00 2645.00
with all accessories etc
complete

DATA 9.7.36 Labour charges for fixing of Exhaust fan in wall with necessary connections and
masonary work of making hole, finishing etc., complete

a) Material

1.6.8 23/0060 twin core wire M 1 10.40 10.40


8.1.50 Cement kg 25 6.60 165.00
b) Labour charges.

8.1.74 Skilled Electrician day 0.25 440.00 110.00


8.1.82 Helper day 0.25 345.00 86.25
8.1.79 Skilled Mason day 0.25 350.00 87.50
Sundries such as Sand, Bolt,
LS 1 5.85 5.85
Nuts etc.,
Rate per Each 465.00

DATA SD- Labour charges for fixing of Exhaust fan over the existing ventilator frame at
9.7.36 places where fixing in wall is not feasible on 2 No of required sizes of 25x6mm
MS flats duly painted and fixed across the ventilators and extended on the walls
on either side with matching holes drilled for fixing the exhaust fan and screws/
anchor fasteners etc., grouted in the wall with necessary connections etc.,
complete

a) Material
1.6.8 23/0060 Twin flat wire M 1 10.40 10.40
25x6mm MS flats duly painted
Each 2 75.00 150.00
b) Labour charges.
8.1.77 Skilled Electrician day 0.25 440.00 110.00
8.1.85 Helper day 0.25 345.00 86.25
Sundries like Bolt, Nuts,
screws/anchor fasteners etc., LS 1 13.35 13.35

Rate per Each 370.00

DATA Supply and Fixing of batten holder/angle holder of makes Million


Zoom/Goldmedal Olive/ Anchor on existing block with 5W retrofit tiny CFL Night
Lamp of makes Wipro / G.E. / Phillips / Crompton / Bajaj and all labour charges
etc., complete, in lieu of ceiling rose.

a) Material
1.7.14 BH/SBH each 1 20.00 20
3.7.23 5W retrofit tiny CFL Night
Lamp of makes Wipro /
G.E./Phillips / Crompton / each 1 115.00 115
Bajaj.
1.7.13 less cost of ceiling rose each 1 21.00 -21
b) Labour charges :
8.1.74 Skilled Electrician day 0.05 440.00 22
8.1.82 Helpers day 0.05 345.00 17.25
Rate per each 153.25
Less cost of labour for
fixing of ceiling rose 39.25

Rate per each 114.00


Note BH should be allowed in place of ceiling rose without extra
cost.

DATA Supply and Fixing of batten holder/angle holder of makes Million


Zoom/Goldmedal Olive/ Anchor on existing block with 18/20W Retrofit CFL of
makes Wipro / G.E. / Phillips / Crompton / Bajaj and all labour charges etc.,
complete, in lieu of ceiling rose.

a) Material
1.7.14 BH/SBH each 1 20.00 20
3.7.33 18/20W Retrofit CFL of makes
Wipro / G.E./Phillips / each 1 170.00 170
Crompton / Bajaj.
1.7.13 less cost of ceiling rose each 1 21.00 -21
b) Labour charges :
8.1.74 Skilled Electrician day 0.05 440.00 22
8.1.82 Helpers day 0.05 345.00 17.25
Rate per each 208.25
Less cost of labour for
39.25
fixing of ceiling rose
Rate per each 169.00
Note BH should be allowed in place of ceiling rose
without extra cost.
DATA SHEET AS PER SSR 2016-17

DATA Description SSR Quantity Unit Rate Amount


NO SL NO
TAKING OUT PUT 1 No
Supply and fixing of 6-32A SP MCBs,10 KA Breaking Capacity Legrand make 'c' curve including giving
connections in the existing Distribution Boards and labour charges etc., complete.
1 b) Labour charges
2 Skilled Electrician 8.1.74 0.040 day 1 day 440.00 17.60

3 Helper 8.1.82 0.040 day 1 day 345.00 13.80

4 Labour for 1 No 31.40

5 a) Material
Legrand make 6-32A
6 2.9.1 1.00 No 1 No 201.00 201.00
SP MCB.
7 Cost of Material 201.00

Sundries etc 0.60

Rate per each 233.00

TAKING OUT PUT 1 No


Supply and fixing of 32A DP MCB Legrand make including giving connections in the existing Distribution
Boards and labour charges etc., complete.
1 b) Labour charges
2 Skilled Electrician 8.1.74 0.050 day 1 day 440.00 22.00
3 Helper 8.1.82 0.050 day 1 day 345.00 17.25
4 Labour for 1 No 39.25
5 a) Material
Legrand make 40A DP
6 2.9.3 1.00 No 1 No 595.00 595.00
Isolator.
7 Cost of Material 595.00
Sundries etc 0.75
Rate per each 635.00

TAKING OUT PUT 1 No


Supply and fixing of 63A FP MCB Legrand make including giving connections in the existing Distribution
Boards and labour charges etc., complete.
1 b) Labour charges
2 Skilled Electrician 8.1.74 0.100 day 1 day 440.00 44.00
3 Helper 8.1.82 0.100 day 1 day 345.00 34.50
4 Labour for 1 No 78.50
5 a) Material
Legrand make 63A FP
6 2.9.8 1.00 No 1 No 1899.00 1899.00
Isolator.
7 Cost of Material 1899.00
Sundries etc 2.50
Rate per each 1980.00

TAKING OUT PUT 1 No


Supply and fixing of Wipro / G.E. / Phillips / Crompton / Bajaj make 36/40W Electronic Ballast for
fluorescent Lamps with connections & labour charges etc., complete.
1 b) Labour charges
2 Skilled Electrician 8.1.74 0.050 day 1 day 440.00 22.00
3 Helper 8.1.82 0.050 day 1 day 345.00 17.25
4 Labour for 1 No 39.25
5 a) Material
Supply of 36W
Electronic ballast with
power factor greater
than 0.9 to 0.95
suitable for FTL.
6 Make : Crompton 3.6.63 1.000 No 1 No 275.00 275.00
Model No.EBN 136D /
Bajaj Model No.BJHF
136 / Havells LHBF
27904025 or its
equivalent.
7 Cost of Material 275.00
Sundries etc 0.75
Rate per each 315.00

TAKING OUT PUT 1 No


Supply and fixing of Wipro / G.E. / Phillips / Crompton / Bajaj make 20W/18W V.P.I.T. Ballast for

fluorescent Lamps with connections & labour charges etc., complete.


1 b) Labour charges
2 Skilled Electrician 8.1.74 0.050 day 1 day 440.00 22.00
3 Helper 8.1.82 0.050 day 1 day 345.00 17.25
4 Labour for 1 No 39.25
5 a) Material
Wipro / G.E. /
Phillips / Crompton /
6 3.6.40 1.000 No 1 No 180.00 180.00
Bajaj make 20W/18W
VPIT ballast
7 Cost of Material 180.00
Sundries etc 0.75
Rate per each 220.00
TAKING OUT PUT 1 No
Supply and fixing of Wipro / G.E. / Phillips / Crompton / Bajaj make 36W/40W/20W/18W Starter for
fluorescent Lamps with connections & labour charges etc., complete.
1 b) Labour charges
2 Skilled Electrician 8.1.74 0.010 day 1 day 440.00 4.40

3 Helper 8.1.82 0.010 day 1 day 345.00 3.45

4 Labour for 1 No 7.85

5 a) Material

Wipro / G.E. /
Phillips / Crompton /
6 Bajaj make 3.6.46 1.000 No 1 No 11.00 11.00
36W/40W/20W/18W
Starter

7 Cost of Material 11.00

Sundries etc 0.15

Rate per each 19.00


TAKING OUT PUT 1 No
Supply and fixing of Wipro / G.E. / Phillips / Crompton / Bajaj make 36/40W Fluorescent Tube with
connections & labour charges etc., complete.
1 b) Labour charges
2 Skilled Electrician 8.1.74 0.010 day 1 day 440.00 4.40
3 Helper 8.1.82 0.010 day 1 day 345.00 3.45
4 Labour for 1 No 7.85
5 a) Material

Wipro / G.E. /
Phillips / Crompton /
6 3.7.7 1.000 No 1 No 45.00 45.00
Bajaj make 36/40W
Fluorescenet Tube.

7 Cost of Material 45.00


Sundries etc 0.15
Rate per each 53.00
TAKING OUT PUT 1 No
Supply and fixing of Wipro / G.E. / Phillips / Crompton / Bajaj make 18/20W Fluorescent Tube with
1 b) Labour charges
2 Skilled Electrician 8.1.74 0.010 day 1 day 440.00 4.40

3 Helper 8.1.82 0.010 day 1 day 345.00 3.45

4 Labour for 1 No 7.85

5 a) Material

Wipro/G.E./Phillips/Cr
ompton/Bajaj make
6 3.7.4 1.000 No 1 No 41.00 41.00
18/20W Fluorescenet
Tube.
7 Cost of Material 41.00
Sundries etc 0.15
Rate per each 49.00
TAKING OUT PUT 1 No
Supply and fixing of BH / SBH of makes Anchor / Gold Medal Olive / Million Zoom including giving
1 b) Labour charges
2 Skilled Electrician 8.1.74 0.010 day 1 day 440.00 4.40
3 Helper 8.1.82 0.010 day 1 day 345.00 3.45
4 Labour for 1 No 7.85

5 a) Material

BH/SBH of makes
6 Anchor/Gold Medal 1.7.14 1.000 No 1 No 20.00 20.00
Olive/Million Zoom
7 Cost of Material 20.00
Sundries etc 0.15
Rate per each 28.00
TAKING OUT PUT 1 No
Supply and fixing of Goldmedal Olive/Million Zoom/Anchor Penta cherry make ISI mark 6A, 1-way flush type

Switch in the existing switch board including connections and all labour charges etc., complete.
1 b) Labour charges
2 Skilled Electrician 8.1.74 0.010 day 1 day 440.00 4.40
3 Helper 8.1.82 0.010 day 1 day 345.00 3.45
4 Labour for 1 No 7.85

5 a) Material

GGoldmedal
Olive/Million
Zoom/Anchor Penta
6 1.7.1 1.00 No 1 No 18.00 18.00
cherry make ISI mark
6A, 1-way flush type
Switch

7 Cost of Material 18.00


Sundries etc 0.15
Rate per each 26.00

TAKING OUT PUT 1 No


Supply and fixing of 12 module galvanised heavy guage modular metal switch box in place of the
existing damaged switch board including connections, cost of all accessories and all labour charges
etc., complete.
1 a) Labour charges :

2 Skilled Electrician 1316 0.10 day 1 day 440.00 44.00

3 Helper 1322 0.10 day 1 day 345.00 34.50

4 Labour for 1 No 78.50

5 b) Material

12 module galvanised
6 heavy guage modular 1.3.6 1.00 No 1 No 209.00 209.00
metal switch box

7 Cost of Material 209.00


Sundries etc 2.50
Rate per each 290.00

TAKING OUT PUT 1 No


Supply and fixing of 8/9 module galvanised heavy guage modular metal switch box in place of the
existing damaged switch board including connections, cost of all accessories and all labour charges
etc., complete.

1 a) Labour charges :

2 Skilled Electrician 1316 0.10 day 1 day 440.00 44.00

3 Helper 1322 0.10 day 1 day 345.00 34.50

4 Labour for 1 No 78.50

5 b) Material
8/9 module galvanised
6 heavy guage modular 1.3.5 1.00 No 1 No 170.00 170.00
metal switch box

7 Cost of Material 170.00


Sundries etc 1.50
Rate per each 250.00

TAKING OUT PUT 1 No


Supply and fixing of 400W of Goldmedal Olive/Million Zoom/Anchor Penta cherry make flush type Electronic
fan regulator hum free step type socket size in the existing switch board including connections and all labour
charges etc., complete.
1 Labour charges
2 Skilled Electrician 8.1.74 0.010 day 1 day 440.00 4.40

3 Helper 8.1.82 0.010 day 1 day 345.00 3.45

4 Labour for 1 No 7.85

5 a) Material

Goldmedal
Olive/Million
Zoom/Anchor Penta
cherry make ISI mark
6 1.7.12 1.00 No 1 No 220.00 220.00
flush type 400W
Electronic fan
regulator hum free
step type socket size

7 Cost of Material 220.00


Sundries etc 2.15
Rate per each 230.00

TAKING OUT PUT 1 No


Supply and fixing of Crompton/Bajaj/HPL/Havells make 150W Copper Ballast in the existing SV/MH
street light fixture with connections and labour charges etc., complete.
1 b) Labour charges
2 Skilled Electrician 8.1.74 0.100 day 1 day 440.00 44.00
3 Helper 8.1.82 0.100 day 1 day 345.00 34.50
4 Labour for 1 No 78.50
5 a) Material

150W Copper Ballast


for S.V. Lamp Street
6 Light fixture 3.3.9 1.000 No 1 No 1005.00 1005.00
Crompton/Bajaj/ HPL/
Havells make

7 Cost of Material 1005.00

Sundries etc 1.50

Rate per each 1085.00

TAKING OUT PUT 1 No


Supply and fixing of Wipro/G.E./Phillips/Crompton/BajajHPL/Havells make Ignitor in the existing
SV/MH street light fixture with connections and labour charges etc., complete.
1 b) Labour charges
2 Skilled Electrician 8.1.74 0.100 day 1 day 440.00 44.00

3 Helper 8.1.82 0.100 day 1 day 345.00 34.50

4 Labour for 1 No 78.50

5 a) Material

Wipro/G.E./Phillips/Cr
ompton/Bajaj,
6 3.3.17 1.000 No 1 No 180.00 180.00
HPL/Havells make
Ignitor for S.V. Lamp

7 Cost of Material 180.00


Sundries etc 1.50
Rate per each 260.00

TAKING OUT PUT 1 No


Supply and fixing of Crompton/Bajaj/HPL/Havells make 150W S.V. Lamp in the existing SV street
light fixture with connections and labour charges etc., complete.
1 b) Labour charges
2 Skilled Electrician 8.1.74 0.050 day 1 day 440.00 22.00
3 Helper 8.1.82 0.050 day 1 day 345.00 17.25
4 Labour for 1 No 39.25
5 a) Material

Crompton/Bajaj/HPL/H
6 avells make 150W 3.4.11 1.000 No 1 No 650.00 650.00
S.V. Lamp

7 Cost of Material 650.00


Sundries etc 0.75
Rate per each 690.00

TAKING OUT PUT 1 No


Supply and fixing of Crompton/Bajaj/HPL/Havells make 33 mfd Capacitor in the existing SV/MH
street light fixture with connections and labour charges etc., complete.
1 b) Labour charges
2 Skilled Electrician 8.1.74 0.050 day 1 day 440.00 22.00
3 Helper 8.1.82 0.050 day 1 day 345.00 17.25
4 Labour for 1 No 39.25
5 a) Material
Crompton/Bajaj/HPL/H
avells make 33 mfd
6 3.3.22 1.000 No 1 No 519.00 519.00
Capacitor (ELEC-
3.3.31)
7 Cost of Material 519.00
Sundries etc 1.75
Rate per each 560.00

18.1.2 TAKING OUT PUT 1 No


Rewinding the motor of the ceiling fan of 1200mm / 1400mm of all types and makes and over
hauling including minor repairs and testing for original speed and consumption
a) Material
35 / 36 Copper
enamelled winding 8.1.40 0.2 Kg 1 Kg 701.00 140.20
wire of fine quality.

Labour charges
towards removing
unserviceable winding 50% 140.20 70.10
wire and cleaning. (on
cost of winding wire)

Labour charges
towards rewinding the
coils complete with
100% 140.20 140.20
connections etc.,
complete.(on cost of
winding wire)

Sundries such as
sleeves cotton tape,
minolex paper, 40% 140.20 56.08
solution etc., with
transportion charges.

Total 406.58
Less cost towards old
8.1.49 0.2 Kg 1 Kg 165.00 -33.00
winding wire
Sundries etc 1.42
Rate per each 375.00

18.2.8 TAKING OUT PUT 1 No


Supply and fixing of Ceiling Fan Capacitor suitable for Ceiling Fan including giving connections &
labour charges etc., complete.
1 b) Labour charges
2 Skilled Electrician 8.1.74 0.025 day 1 day 440.00 11.00
3 Helper 8.1.82 0.025 day 1 day 345.00 8.63
4 Labour for 1 No 19.63
5 a) Material
Capacitor of ceiling fan
6 5.6.8 1.00 No 1 No 38.00 38.00

7 Cost of Material 38.00


Sundries etc 0.38
Rate per each 58.00

18.2.6 TAKING OUT PUT 1 No


Replacing the ball bearing of ceiling fan complete with alignment of shaft and tested.
1 b) Labour charges
2 Helper 8.1.82 0.600 day 1 day 345.00 207.00
3 Labour for 1 No 207.00
4 a) Material
Ball Bearings suitable
for table / cabin/
5 ceiling / Exhaust Fan 5.6.6 1.000 No 1 No 84.00 84.00
inclusive of taxes.

6 Cost of Material 84.00


Sundries etc 4.00
Rate per each 295.00

TAKING OUT PUT 1 No


Replacement by supply and fixing of starting capacitor of 80 to 120 mfd. by new approved make capacitor
suitable for compressor motor of 1.0/1.5 Ton A.C. Unit.
1 b) Labour charges
2 Skilled Electrician 8.1.74 0.050 day 1 day 440.00 22.00
3 Helper 8.1.82 0.050 day 1 day 345.00 17.25
4 Labour for 1 No 39.25
5 a) Material

starting capacitor of
80 to 120 mfd. by new
approved make
6 5.5.8 1.00 No 1 No 180.00 180.00
capacitor suitable for
compressor motor of
1.0/1.5 Ton A.C. Unit.

7 Cost of Material 180.00


Sundries etc 0.75
Rate per each 220.00

TAKING OUT PUT 1 No


Replacement by supply and fixing of running capacitor of 80 to 120 mfd. by new approved make capacitor
suitable for compressor motor of 1.0/1.5 Ton A.C. Unit.
1 b) Labour charges
2 Skilled Electrician 8.1.74 0.050 day 1 day 440.00 22.00
3 Helper 8.1.82 0.050 day 1 day 345.00 17.25

4 Labour for 1 No 39.25

5 a) Material

Running capacitor of
80 to 120 mfd. by new
approved make
6 5.5.9 1.00 No 1 No 220.00 220.00
capacitor suitable for
compressor motor of
1.0/1.5 Ton A.C. Unit.

7 Cost of Material 220.00


Sundries etc 0.75
Rate per each 260.00

TAKING OUT PUT 1 No


Replacement by supply and fixing of relay by approved make having pickup voltage 220 Volts and dropout
voltage 120 Volts suitable for 1.0 / 1.50 Ton A.C. Unit.
1 b) Labour charges
2 Skilled Electrician 8.1.74 0.050 day 1 day 440.00 22.00
3 Helper 8.1.82 0.050 day 1 day 345.00 17.25
4 Labour for 1 No 39.25
5 a) Material

Relay by approved
make having pickup
voltage 220 Volts and
6 5.5.10 1.00 No 1 No 225.00 225.00
dropout voltage 120
Volts suitable for 1.0 /
1.50 Ton A.C. Unit.

7 Cost of Material 225.00


Sundries etc 0.75
Rate per each 265.00

TAKING OUT PUT 1 No


Replacement by supply and fixing of Filter and capillary tube including welding etc., complete for 1.0 / 1.5 /
2.0 Ton A.C.Unit.
1 b) Labour charges
2 Skilled Electrician 8.1.74 0.100 day 1 day 440.00 44.00
3 Helper 8.1.82 0.100 day 1 day 345.00 34.50
4 Labour for 1 No 78.50
5 a) Material

Filter and capillary


tube including welding
6 etc., complete for 5.5.11 1.00 No 1 No 485.00 485.00
1.0 / 1.5 / 2.0 Ton
A.C.Unit.

7 Cost of Material 485.00


Sundries etc 1.50
Rate per each 565.00

TAKING OUT PUT 1 No


Replacement by supply and fixing of Fan motor capacitor 6 mfd by new capacitor for A.C machine of
1.0/1.5 /2.0 Ton Capacity.
1 b) Labour charges
2 Skilled Electrician 8.1.74 0.050 day 1 day 440.00 22.00
3 Helper 8.1.82 0.050 day 1 day 345.00 17.25
4 Labour for 1 No 39.25
5 a) Material

Fan motor capacitor 6


mfd by new capacitor
6 for A.C machine of 5.5.6 1.00 No 1 No 156.00 156.00
1.0/1.5 / 2.0 Ton
Capacity.

7 Cost of Material 156.00


Sundries etc 0.75
Rate per each 196.00

TAKING OUT PUT 1 No


Replacement by supply and fixing of Multi speed Fan Motor suitable for 1.0 / 1.5 / 2.0 Ton Window A.C.Unit
of makes Crompton / AU.
1 b) Labour charges
2 Skilled Electrician 8.1.74 0.100 day 1 day 440.00 44.00
3 Helper 8.1.82 0.100 day 1 day 345.00 34.50
4 Labour for 1 No 78.50
5 a) Material

Multi speed Fan Motor


suitable for 1.0 / 1.5 /
6 2.0 Ton Window 5.5.5 1.00 No 1 No 1590.00 1590.00
A.C.Unit of makes
Crompton / AU.

7 Cost of Material 1590.00


Sundries etc 1.50
Rate per each 1670.00
TAKING OUT PUT 1 No
Replacement by supply and fixing of Thermostat switch suitable for 1.0 / 1.5 / 2.0 Ton A.C.Unit.

1 b) Labour charges
2 Skilled Electrician 8.1.74 0.100 day 1 day 440.00 44.00
3 Helper 8.1.82 0.100 day 1 day 345.00 34.50
4 Labour for 1 No 78.50
5 a) Material
Thermostat switch
6 suitable for 1.0 / 1.5 / 5.5.7 1.00 No 1 No 410.00 410.00
2.0 Ton A.C.Unit.

7 Cost of Material 410.00

Sundries etc 1.50

Rate per each 675.00

TAKING OUT PUT 1 No


Replacement by supply and fixing of 1.0 / 1.5 Ton brand new Rotary type sealed compressor including

transportation, installation, giving all connections, testing etc., complete except gas charging and taking
away the old damaged compressor on buy back basis.
1 b) Labour charges
2 Skilled Electrician 8.1.74 0.500 day 1 day 440.00 220.00
3 Helper 8.1.82 0.500 day 1 day 345.00 172.50
4 Labour for 1 No 392.50
5 a) Material

Supply of 1.0 / 1.5


Ton brand new Rotary
6 5.5.3 1.00 No 1 No 8150.00 8150.00
type sealed
compressor.

Transportation
7 0.02 1 No 8150.00 163.00
Charges on Unit Cost

Deduct cost of old


8 unserviceable -300.00
damaged compressor

9 Cost of Material 8013.00


Sundries etc 4.50
Rate per each 8410.00

TAKING OUT PUT 1 No


Replacement by supply and fixing of 2.0 Ton brand new Rotary type sealed compressor including

transportation, installation, giving all connections, testing etc., complete except gas charging and taking

away the old damaged compressor on buy back basis.


1 b) Labour charges
2 Skilled Electrician 8.1.74 0.500 day 1 day 440.00 220.00
3 Helper 8.1.82 0.500 day 1 day 345.00 172.50
4 Labour for 1 No 392.50
5 a) Material

Supply of 2.0 Ton


6 brand new Rotary type 5.5.4 1.00 No 1 No 9250.00 9250.00
sealed compressor.

Transportation
7 0.02 1 No 9250.00 185.00
Charges on Unit Cost

Deduct cost of old


8 unserviceable -300.00
damaged compressor
9 Cost of Material 9135.00
Sundries etc 2.50
Rate per each 9530.00
LEAD STATEMENT
Name of Construction of P I U Sub Division Office Building at Nuzvid in Krishna District
the Work:
Conveyance Initial Cost
Name of the
Sl.No Name of the Material Unit Without Total Amount
Quarry
KM Amount seignorage

1 2 3 4 5 6 7 8
Ordinary Portland Cement 43 / 53 grade (including
1 1 MT 4800.00 4800.00
loading charges)

2 Reinforcement steel Fe- 500 1 MT 35000.00 35000.00

3 Reinforcement steel Fe- 415 1 MT 34500.00 34500.00

4 Mild steel bars 1 MT 34000.00 34000.00

5 Structural steel 1 MT 34000.00 34000.00

6 MS flats 1 MT 34000.00 34000.00

7 Sand (un-screened for concrete items) Ibrahimpatnam 52.00 554.50 1 Cum 95.00 649.50

8 Sand (screened for mortar, plastering items) Ibrahimpatnam 52.00 554.50 1 Cum 165.00 719.50

9 Sand for filling Ibrahimpatnam 52.00 554.50 1 Cum 95.00 649.50

10 Common burnt clay bricks (23x11x7cm) Local 5.00 1 Cum 5200.00 5200.00

Flyash cement / lime solid blocks (50 Kgs/ sq.cm)


11 Local 5.00 1 Cum 24000.00 24000.00
290mmx225mmx140mm
Flyash cement / lime solid blocks (50 Kgs/ sq.cm)
12 Local 5.00 1 Cum 11000.00 11000.00
290mmx100mmx140mm

13 Aggregates 40mm nominal size (HBG) G.konduru 39.00 434.36 1 Cum 845.00 1279.36

14 Aggregates 20mm nominal size (HBG) G.konduru 39.00 434.36 1 Cum 1365.00 1799.36

15 Aggregates 13.20 / 12.50mm nominal size (HBG) G.konduru 39.00 434.36 1 Cum 1097.00 1531.36

16 Aggregates 10mm nominal size (HBG) G.konduru 39.00 434.36 1 Cum 935.00 1369.36

17 Aggregates 6mm nominal size (HBG) G.konduru 39.00 434.36 1 Cum 735.00 1169.36
18 Rough Stone (OTG) Tukkuluru 7.00 96.11 1 Cum 180.00 276.11

19 Rough Stone (HBG) Local 15.00 184.83 1 Cum 0.00 184.83

20 Gravel / Quarry spall Local 5.00 73.93 1 Cum 103.00 176.93

Polished Shahabad / Tandur stone slabs 15mm to


21 425.00 4001.67 1 Cum 1654.00 5655.67
18mm thick
Polished black Kadapa slabs minimum of 15mm
22 274.00 1 Cum 1379.00 1379.00
thick (0.457m x 0.457m)
High Polished Granite 16 to 18 mm thick up to 8'-00
23 1 Cum 0.00 0.00
(2.43 M) other than black and regular colours
High Polished Granite 16 to 18 mm thick up to 8'-00
24 1 Cum 0.00
(2.43 M) black.

Certificate :
(1) Certified that the above rates are correct. (2) Certified that the above leads are correct.
(3) Certified that the Quarries are nearest. (4) Certified that the meterials are avilable in the above Quarrys
Lead Chart 2016-17

Lead SS rate for 2016-17

Earth, Sand,
Metal, Stone
Gravel 1000mm dia 900 mm RCC pipes 700mm dia
1 31.50 30.40 0.25 197.40 0.25 163.80 0.25
2 44.10 42.50 0.5 197.40 0.5 163.80 0.5
3 58.80 58.80 1 197.40 1 163.80 1
4 71.40 71.40 2 197.40 2 163.80 2
5 84.00 84.00 3 197.40 3 163.80 3
6 96.60 96.60 4 197.40 4 163.80 4
7 109.20 109.20 5 197.40 5 163.80 5
8 121.80 121.80 6 206.90 6 173.30 6
9 134.40 134.40 7 216.40 7 182.80 7
10 147.00 147.00 8 225.90 8 192.30 8
11 159.60 159.60 9 235.40 9 201.80 9
12 172.20 172.20 10 244.90 10 211.30 10
13 184.80 184.80 11 254.40 11 220.80 11
14 197.40 197.40 12 263.90 12 230.30 12
15 210.00 210.00 13 273.40 13 239.80 13
16 222.60 222.60 14 282.90 14 249.30 14
17 235.20 235.20 15 292.40 15 258.80 15
18 247.80 247.80 16 301.90 16 268.30 16
19 260.40 260.40 17 311.40 17 277.80 17
20 273.00 273.00 18 320.90 18 287.30 18
21 285.60 285.60 19 330.40 19 296.80 19
22 298.20 298.20 20 339.90 20 306.30 20
23 310.80 310.80 21 349.40 21 315.80 21
24 323.40 323.40 22 358.90 22 325.30 22
25 336.00 336.00 23 368.40 23 334.80 23
26 348.60 348.60 24 377.90 24 344.30 24
27 361.20 361.20 25 387.40 25 353.80 25
28 373.80 373.80 26 396.90 26 363.30 26
29 386.40 386.40 27 406.40 27 372.80 27
30 399.00 399.00 28 415.90 28 382.30 28
31 409.50 409.50 29 425.40 29 391.80 29
32 420.00 420.00 30 434.90 30 401.30 30
33 430.50 430.50 31 444.40 31 410.80 31
34 441.00 441.00 32 453.90 32 420.30 32
35 451.50 451.50 33 463.40 33 429.80 33
36 462.00 462.00 34 472.90 34 439.30 34
37 472.50 472.50 35 482.40 35 448.80 35
38 483.00 483.00 36 491.90 36 458.30 36
39 493.50 493.50 37 501.40 37 467.80 37
40 504.00 504.00 38 510.90 38 477.30 38
41 514.50 514.50 39 520.40 39 486.80 39
42 525.00 525.00 40 529.90 40 496.30 40
43 535.50 535.50 41 539.40 41 505.80 41
44 546.00 546.00 42 548.90 42 515.30 42
45 556.50 556.50 43 558.40 43 524.80 43
46 567.00 567.00 44 567.90 44 534.30 44
47 577.50 577.50 45 577.40 45 543.80 45
48 588.00 588.00 46 586.90 46 553.30 46
49 598.50 598.50 47 596.40 47 562.80 47
50 609.00 609.00 48 605.90 48 572.30 48
51 619.50 619.50 49 615.40 49 581.80 49
52 630.00 630.00 50 624.90 50 591.30 50
53 640.50 640.50 51 634.40 51 600.80 51
54 651.00 651.00 52 643.90 52 610.30 52
55 661.50 661.50 53 653.40 53 619.80 53
56 672.00 672.00 54 662.90 54 629.30 54
57 682.50 682.50 55 672.40 55 638.80 55
58 693.00 693.00 56 681.90 56 648.30 56
59 703.50 703.50 57 691.40 57 657.80 57
60 714.00 714.00 58 700.90 58 667.30 58
61 724.50 724.50 59 710.40 59 676.80 59
62 735.00 735.00 60 719.90 60 686.30 60
63 745.50 745.50 61 729.40 61 695.80 61
64 756.00 756.00 62 738.90 62 705.30 62
65 766.50 766.50 63 748.40 63 714.80 63
66 777.00 777.00 64 757.90 64 724.30 64
67 787.50 787.50 65 767.40 65 733.80 65
68 798.00 798.00 66 776.90 66 743.30 66
69 808.50 808.50 67 786.40 67 752.80 67
70 819.00 819.00 68 795.90 68 762.30 68
71 829.50 829.50 69 805.40 69 771.80 69
72 840.00 840.00 70 814.90 70 781.30 70
73 850.50 850.50 71 824.40 71 790.80 71
74 861.00 861.00 72 833.90 72 800.30 72
75 871.50 871.50 73 843.40 73 809.80 73
76 882.00 882.00 74 852.90 74 819.30 74
77 892.50 892.50 75 862.40 75 828.80 75
78 903.00 903.00 76 871.90 76 838.30 76
79 913.50 913.50 77 881.40 77 847.80 77
80 924.00 924.00 78 890.90 78 857.30 78
81 934.50 934.50 79 900.40 79 866.80 79
82 945.00 945.00 80 909.90 80 876.30 80
83 955.50 955.50 81 919.40 81 885.80 81
84 966.00 966.00 82 928.90 82 895.30 82
85 976.50 976.50 83 938.40 83 904.80 83
86 987.00 987.00 84 947.90 84 914.30 84
87 997.50 997.50 85 957.40 85 923.80 85
88 1008.00 1008.00 86 966.90 86 933.30 86
89 1018.50 1018.50 87 976.40 87 942.80 87
90 1029.00 1029.00 88 985.90 88 952.30 88
91 1039.50 1039.50 89 995.40 89 961.80 89
92 1050.00 1050.00 90 1004.90 90 971.30 90
93 1060.50 1060.50 91 1014.40 91 980.80 91
94 1071.00 1071.00 92 1023.90 92 990.30 92
95 1081.50 1081.50 93 1033.40 93 999.80 93
96 1092.00 1092.00 94 1042.90 94 1009.30 94
97 1102.50 1102.50 95 1052.40 95 1018.80 95
98 1113.00 1113.00 96 1061.90 96 1028.30 96
99 1123.50 1123.50 97 1071.40 97 1037.80 97
100 1134.00 1134.00 98 1080.90 98 1047.30 98
101 1144.50 1144.50 99 1090.40 99 1056.80 99
102 1155.00 1155.00 100 1099.90 100 1066.30 100
103 1165.50 1165.50 101 1109.40 101 1075.80 101
104 1176.00 1176.00 102 1118.90 102 1085.30 102
105 1186.50 1186.50 103 1128.40 103 1094.80 103
106 1197.00 1197.00 104 1137.90 104 1104.30 104
107 1207.50 1207.50 105 1147.40 105 1113.80 105
108 1218.00 1218.00 106 1156.90 106 1123.30 106
109 1228.50 1228.50 107 1166.40 107 1132.80 107
110 1239.00 1239.00 108 1175.90 108 1142.30 108
111 1249.50 1249.50 109 1185.40 109 1151.80 109
112 1260.00 1260.00 110 1194.90 110 1161.30 110
113 1270.50 1270.50 111 1204.40 111 1170.80 111
114 1281.00 1281.00 112 1213.90 112 1180.30 112
115 1291.50 1291.50 113 1223.40 113 1189.80 113
116 1302.00 1302.00 114 1232.90 114 1199.30 114
117 1312.50 1312.50 115 1242.40 115 1208.80 115
118 1323.00 1323.00 116 1251.90 116 1218.30 116
119 1333.50 1333.50 117 1261.40 117 1227.80 117
120 1344.00 1344.00 118 1270.90 118 1237.30 118
121 1354.50 1354.50 119 1280.40 119 1246.80 119
122 1365.00 1365.00 120 1289.90 120 1256.30 120
123 1375.50 1375.50 121 1299.40 121 1265.80 121
124 1386.00 1386.00 122 1308.90 122 1275.30 122
125 1396.50 1396.50 123 1318.40 123 1284.80 123
126 1407.00 1407.00 124 1327.90 124 1294.30 124
127 1417.50 1417.50 125 1337.40 125 1303.80 125
128 1428.00 1428.00 126 1346.90 126 1313.30 126
129 1438.50 1438.50 127 1356.40 127 1322.80 127
130 1449.00 1449.00 128 1365.90 128 1332.30 128
131 1459.50 1459.50 129 1375.40 129 1341.80 129
132 1470.00 1470.00 130 1384.90 130 1351.30 130
133 1480.50 1480.50 131 1394.40 131 1360.80 131
134 1491.00 1491.00 132 1403.90 132 1370.30 132
135 1501.50 1501.50 133 1413.40 133 1379.80 133
136 1512.00 1512.00 134 1422.90 134 1389.30 134
137 1522.50 1522.50 135 1432.40 135 1398.80 135
138 1533.00 1533.00 136 1441.90 136 1408.30 136
139 1543.50 1543.50 137 1451.40 137 1417.80 137
140 1554.00 1554.00 138 1460.90 138 1427.30 138
141 1564.50 1564.50 139 1470.40 139 1436.80 139
142 1575.00 1575.00 140 1479.90 140 1446.30 140
143 1585.50 1585.50 141 1489.40 141 1455.80 141
144 1596.00 1596.00 142 1498.90 142 1465.30 142
145 1606.50 1606.50 143 1508.40 143 1474.80 143
146 1617.00 1617.00 144 1517.90 144 1484.30 144
147 1627.50 1627.50 145 1527.40 145 1493.80 145
148 1638.00 1638.00 146 1536.90 146 1503.30 146
149 1648.50 1648.50 147 1546.40 147 1512.80 147
150 1659.00 1659.00 148 1555.90 148 1522.30 148
151 1669.50 1669.50 149 1565.40 149 1531.80 149
152 1680.00 1680.00 150 1574.90 150 1541.30 150
153 1690.50 1690.50
154 1701.00 1701.00
155 1711.50 1711.50
156 1722.00 1722.00
157 1732.50 1732.50
158 1743.00 1743.00
159 1753.50 1753.50
160 1764.00 1764.00
161 1774.50 1774.50
162 1785.00 1785.00
163 1795.50 1795.50
164 1806.00 1806.00
165 1816.50 1816.50
166 1827.00 1827.00
167 1837.50 1837.50
168 1848.00 1848.00
169 1858.50 1858.50
170 1869.00 1869.00
171 1879.50 1879.50
172 1890.00 1890.00
173 1900.50 1900.50
174 1911.00 1911.00
175 1921.50 1921.50
176 1932.00 1932.00
177 1942.50 1942.50
178 1953.00 1953.00
179 1963.50 1963.50
180 1974.00 1974.00
181 1984.50 1984.50
182 1995.00 1995.00
183 2005.50 2005.50
184 2016.00 2016.00
185 2026.50 2026.50
186 2037.00 2037.00
187 2047.50 2047.50
188 2058.00 2058.00
189 2068.50 2068.50
190 2079.00 2079.00
191 2089.50 2089.50
192 2100.00 2100.00
193 2110.50 2110.50
194 2121.00 2121.00
195 2131.50 2131.50
196 2142.00 2142.00
197 2152.50 2152.50
198 2163.00 2163.00
199 2173.50 2173.50
200 2184.00 2184.00
201 2194.50 2194.50
202 2205.00 2205.00
203 2215.50 2215.50
204 2226.00 2226.00
205 2236.50 2236.50
206 2247.00 2247.00
207 2257.50 2257.50
208 2268.00 2268.00
209 2278.50 2278.50
210 2289.00 2289.00
211 2299.50 2299.50
212 2310.00 2310.00
213 2320.50 2320.50
214 2331.00 2331.00
215 2341.50 2341.50
216 2352.00 2352.00
217 2362.50 2362.50
218 2373.00 2373.00
219 2383.50 2383.50
220 2394.00 2394.00
221 2404.50 2404.50
222 2415.00 2415.00
223 2425.50 2425.50
224 2436.00 2436.00
225 2446.50 2446.50
226 2457.00 2457.00
227 2467.50 2467.50
228 2478.00 2478.00
229 2488.50 2488.50
230 2499.00 2499.00
231 2509.50 2509.50
232 2520.00 2520.00
233 2530.50 2530.50
234 2541.00 2541.00
235 2551.50 2551.50
236 2562.00 2562.00
237 2572.50 2572.50
238 2583.00 2583.00
239 2593.50 2593.50
240 2604.00 2604.00
241 2614.50 2614.50
242 2625.00 2625.00
243 2635.50 2635.50
244 2646.00 2646.00
245 2656.50 2656.50
246 2667.00 2667.00
247 2677.50 2677.50
248 2688.00 2688.00
249 2698.50 2698.50
250 2709.00 2709.00
251 2719.50 2719.50
252 2730.00 2730.00
253 2740.50 2740.50
254 2751.00 2751.00
255 2761.50 2761.50
256 2772.00 2772.00
257 2782.50 2782.50
258 2793.00 2793.00
259 2803.50 2803.50
260 2814.00 2814.00
261 2824.50 2824.50
262 2835.00 2835.00
263 2845.50 2845.50
264 2856.00 2856.00
265 2866.50 2866.50
266 2877.00 2877.00
267 2887.50 2887.50
268 2898.00 2898.00
269 2908.50 2908.50
270 2919.00 2919.00
271 2929.50 2929.50
272 2940.00 2940.00
273 2950.50 2950.50
274 2961.00 2961.00
275 2971.50 2971.50
276 2982.00 2982.00
277 2992.50 2992.50
278 3003.00 3003.00
279 3013.50 3013.50
280 3024.00 3024.00
281 3034.50 3034.50
282 3045.00 3045.00
283 3055.50 3055.50
284 3066.00 3066.00
285 3076.50 3076.50
286 3087.00 3087.00
287 3097.50 3097.50
288 3108.00 3108.00
289 3118.50 3118.50
290 3129.00 3129.00
291 3139.50 3139.50
292 3150.00 3150.00
293 3160.50 3160.50
294 3171.00 3171.00
295 3181.50 3181.50
296 3192.00 3192.00
297 3202.50 3202.50
298 3213.00 3213.00
299 3223.50 3223.50
300 3234.00 3234.00
301 3244.50 3244.50
302 3255.00 3255.00
303 3265.50 3265.50
304 3276.00 3276.00
305 3286.50 3286.50
306 3297.00 3297.00
307 3307.50 3307.50
308 3318.00 3318.00
309 3328.50 3328.50
310 3339.00 3339.00
311 3349.50 3349.50
312 3360.00 3360.00
313 3370.50 3370.50
314 3381.00 3381.00
315 3391.50 3391.50
316 3402.00 3402.00
317 3412.50 3412.50
318 3423.00 3423.00
319 3433.50 3433.50
320 3444.00 3444.00
321 3454.50 3454.50
322 3465.00 3465.00
323 3475.50 3475.50
324 3486.00 3486.00
325 3496.50 3496.50
326 3507.00 3507.00
327 3517.50 3517.50
328 3528.00 3528.00
329 3538.50 3538.50
330 3549.00 3549.00
331 3559.50 3559.50
332 3570.00 3570.00
333 3580.50 3580.50
334 3591.00 3591.00
335 3601.50 3601.50
336 3612.00 3612.00
337 3622.50 3622.50
338 3633.00 3633.00
339 3643.50 3643.50
340 3654.00 3654.00
341 3664.50 3664.50
342 3675.00 3675.00
343 3685.50 3685.50
344 3696.00 3696.00
345 3706.50 3706.50
346 3717.00 3717.00
347 3727.50 3727.50
348 3738.00 3738.00
349 3748.50 3748.50
350 3759.00 3759.00
351 3769.50 3769.50
352 3780.00 3780.00
353 3790.50 3790.50
354 3801.00 3801.00
355 3811.50 3811.50
356 3822.00 3822.00
357 3832.50 3832.50
358 3843.00 3843.00
359 3853.50 3853.50
360 3864.00 3864.00
361 3874.50 3874.50
362 3885.00 3885.00
363 3895.50 3895.50
364 3906.00 3906.00
365 3916.50 3916.50
366 3927.00 3927.00
367 3937.50 3937.50
368 3948.00 3948.00
369 3958.50 3958.50
370 3969.00 3969.00
371 3979.50 3979.50
372 3990.00 3990.00
373 4000.50 4000.50
374 4011.00 4011.00
375 4021.50 4021.50
376 4032.00 4032.00
377 4042.50 4042.50
378 4053.00 4053.00
379 4063.50 4063.50
380 4074.00 4074.00
381 4084.50 4084.50
382 4095.00 4095.00
383 4105.50 4105.50
384 4116.00 4116.00
385 4126.50 4126.50
386 4137.00 4137.00
387 4147.50 4147.50
388 4158.00 4158.00
389 4168.50 4168.50
390 4179.00 4179.00
391 4189.50 4189.50
392 4200.00 4200.00
393 4210.50 4210.50
394 4221.00 4221.00
395 4231.50 4231.50
396 4242.00 4242.00
397 4252.50 4252.50
398 4263.00 4263.00
399 4273.50 4273.50
400 4284.00 4284.00
401 4294.50 4294.50
402 4305.00 4305.00
403 4315.50 4315.50
404 4326.00 4326.00
405 4336.50 4336.50
406 4347.00 4347.00
407 4357.50 4357.50
408 4368.00 4368.00
409 4378.50 4378.50
410 4389.00 4389.00
411 4399.50 4399.50
412 4410.00 4410.00
413 4420.50 4420.50
414 4431.00 4431.00
415 4441.50 4441.50
416 4452.00 4452.00
417 4462.50 4462.50
418 4473.00 4473.00
419 4483.50 4483.50
420 4494.00 4494.00
421 4504.50 4504.50
422 4515.00 4515.00
423 4525.50 4525.50
424 4536.00 4536.00
425 4546.50 4546.50
426 4557.00 4557.00
427 4567.50 4567.50
428 4578.00 4578.00
429 4588.50 4588.50
430 4599.00 4599.00
431 4609.50 4609.50
432 4620.00 4620.00
433 4630.50 4630.50
434 4641.00 4641.00
435 4651.50 4651.50
436 4662.00 4662.00
437 4672.50 4672.50
438 4683.00 4683.00
439 4693.50 4693.50
440 4704.00 4704.00
441 4714.50 4714.50
442 4725.00 4725.00
443 4735.50 4735.50
444 4746.00 4746.00
445 4756.50 4756.50
446 4767.00 4767.00
447 4777.50 4777.50
448 4788.00 4788.00
449 4798.50 4798.50
450 4809.00 4809.00
451 4819.50 4819.50
452 4830.00 4830.00
453 4840.50 4840.50
454 4851.00 4851.00
455 4861.50 4861.50
456 4872.00 4872.00
457 4882.50 4882.50
458 4893.00 4893.00
459 4903.50 4903.50
460 4914.00 4914.00
461 4924.50 4924.50
462 4935.00 4935.00
463 4945.50 4945.50
464 4956.00 4956.00
465 4966.50 4966.50
466 4977.00 4977.00
467 4987.50 4987.50
468 4998.00 4998.00
469 5008.50 5008.50
470 5019.00 5019.00
471 5029.50 5029.50
472 5040.00 5040.00
473 5050.50 5050.50
474 5061.00 5061.00
475 5071.50 5071.50
476 5082.00 5082.00
477 5092.50 5092.50
478 5103.00 5103.00
479 5113.50 5113.50
480 5124.00 5124.00
481 5134.50 5134.50
482 5145.00 5145.00
483 5155.50 5155.50
484 5166.00 5166.00
485 5176.50 5176.50
486 5187.00 5187.00
487 5197.50 5197.50
488 5208.00 5208.00
489 5218.50 5218.50
490 5229.00 5229.00
491 5239.50 5239.50
492 5250.00 5250.00
493 5260.50 5260.50
494 5271.00 5271.00
495 5281.50 5281.50
496 5292.00 5292.00
497 5302.50 5302.50
498 5313.00 5313.00
499 5323.50 5323.50
500 5334.00 5334.00
501 5344.50 5344.50
502 5355.00 5355.00
503 5365.50 5365.50
504 5376.00 5376.00
505 5386.50 5386.50
506 5397.00 5397.00
507 5407.50 5407.50
508 5418.00 5418.00
509 5428.50 5428.50
510 5439.00 5439.00
511 5449.50 5449.50
512 5460.00 5460.00
513 5470.50 5470.50
514 5481.00 5481.00
515 5491.50 5491.50
516 5502.00 5502.00
517 5512.50 5512.50
518 5523.00 5523.00
519 5533.50 5533.50
520 5544.00 5544.00
521 5554.50 5554.50
522 5565.00 5565.00
523 5575.50 5575.50
524 5586.00 5586.00
525 5596.50 5596.50
526 5607.00 5607.00
527 5617.50 5617.50
528 5628.00 5628.00
529 5638.50 5638.50
530 5649.00 5649.00
531 5659.50 5659.50
532 5670.00 5670.00
533 5680.50 5680.50
534 5691.00 5691.00
535 5701.50 5701.50
536 5712.00 5712.00
537 5722.50 5722.50
538 5733.00 5733.00
539 5743.50 5743.50
540 5754.00 5754.00
541 5764.50 5764.50
542 5775.00 5775.00
543 5785.50 5785.50
544 5796.00 5796.00
545 5806.50 5806.50
546 5817.00 5817.00
547 5827.50 5827.50
548 5838.00 5838.00
549 5848.50 5848.50
550 5859.00 5859.00
551 5869.50 5869.50
552 5880.00 5880.00
553 5890.50 5890.50
554 5901.00 5901.00
555 5911.50 5911.50
556 5922.00 5922.00
557 5932.50 5932.50
558 5943.00 5943.00
559 5953.50 5953.50
560 5964.00 5964.00
561 5974.50 5974.50
562 5985.00 5985.00
563 5995.50 5995.50
564 6006.00 6006.00
565 6016.50 6016.50
566 6027.00 6027.00
567 6037.50 6037.50
568 6048.00 6048.00
569 6058.50 6058.50
570 6069.00 6069.00
571 6079.50 6079.50
572 6090.00 6090.00
573 6100.50 6100.50
574 6111.00 6111.00
575 6121.50 6121.50
576 6132.00 6132.00
577 6142.50 6142.50
578 6153.00 6153.00
579 6163.50 6163.50
580 6174.00 6174.00
581 6184.50 6184.50
582 6195.00 6195.00
583 6205.50 6205.50
584 6216.00 6216.00
585 6226.50 6226.50
586 6237.00 6237.00
587 6247.50 6247.50
588 6258.00 6258.00
589 6268.50 6268.50
590 6279.00 6279.00
591 6289.50 6289.50
592 6300.00 6300.00
593 6310.50 6310.50
594 6321.00 6321.00
595 6331.50 6331.50
596 6342.00 6342.00
597 6352.50 6352.50
598 6363.00 6363.00
599 6373.50 6373.50
600 6384.00 6384.00
601 6394.50 6394.50
602 6405.00 6405.00
603 6415.50 6415.50
604 6426.00 6426.00
605 6436.50 6436.50
606 6447.00 6447.00
607 6457.50 6457.50
608 6468.00 6468.00
609 6478.50 6478.50
610 6489.00 6489.00
611 6499.50 6499.50
612 6510.00 6510.00
613 6520.50 6520.50
614 6531.00 6531.00
615 6541.50 6541.50
616 6552.00 6552.00
617 6562.50 6562.50
618 6573.00 6573.00
619 6583.50 6583.50
620 6594.00 6594.00
621 6604.50 6604.50
622 6615.00 6615.00
623 6625.50 6625.50
624 6636.00 6636.00
625 6646.50 6646.50
626 6657.00 6657.00
627 6667.50 6667.50
628 6678.00 6678.00
629 6688.50 6688.50
630 6699.00 6699.00
631 6709.50 6709.50
632 6720.00 6720.00
633 6730.50 6730.50
634 6741.00 6741.00
635 6751.50 6751.50
636 6762.00 6762.00
637 6772.50 6772.50
638 6783.00 6783.00
639 6793.50 6793.50
640 6804.00 6804.00
641 6814.50 6814.50
642 6825.00 6825.00
643 6835.50 6835.50
644 6846.00 6846.00
645 6856.50 6856.50
646 6867.00 6867.00
647 6877.50 6877.50
648 6888.00 6888.00
649 6898.50 6898.50
650 6909.00 6909.00
651 6919.50 6919.50
652 6930.00 6930.00
653 6940.50 6940.50
654 6951.00 6951.00
655 6961.50 6961.50
656 6972.00 6972.00
657 6982.50 6982.50
658 6993.00 6993.00
659 7003.50 7003.50
660 7014.00 7014.00
661 7024.50 7024.50
662 7035.00 7035.00
663 7045.50 7045.50
664 7056.00 7056.00
665 7066.50 7066.50
666 7077.00 7077.00
667 7087.50 7087.50
668 7098.00 7098.00
669 7108.50 7108.50
670 7119.00 7119.00
671 7129.50 7129.50
672 7140.00 7140.00
673 7150.50 7150.50
674 7161.00 7161.00
675 7171.50 7171.50
676 7182.00 7182.00
677 7192.50 7192.50
678 7203.00 7203.00
679 7213.50 7213.50
680 7224.00 7224.00
681 7234.50 7234.50
682 7245.00 7245.00
683 7255.50 7255.50
684 7266.00 7266.00
685 7276.50 7276.50
686 7287.00 7287.00
687 7297.50 7297.50
688 7308.00 7308.00
689 7318.50 7318.50
690 7329.00 7329.00
691 7339.50 7339.50
692 7350.00 7350.00
693 7360.50 7360.50
694 7371.00 7371.00
695 7381.50 7381.50
696 7392.00 7392.00
697 7402.50 7402.50
698 7413.00 7413.00
699 7423.50 7423.50
700 7434.00 7434.00
701 7444.50 7444.50
702 7455.00 7455.00
703 7465.50 7465.50
704 7476.00 7476.00
705 7486.50 7486.50
706 7497.00 7497.00
707 7507.50 7507.50
708 7518.00 7518.00
709 7528.50 7528.50
710 7539.00 7539.00
711 7549.50 7549.50
712 7560.00 7560.00
713 7570.50 7570.50
714 7581.00 7581.00
715 7591.50 7591.50
716 7602.00 7602.00
717 7612.50 7612.50
718 7623.00 7623.00
719 7633.50 7633.50
720 7644.00 7644.00
721 7654.50 7654.50
722 7665.00 7665.00
723 7675.50 7675.50
724 7686.00 7686.00
725 7696.50 7696.50
726 7707.00 7707.00
727 7717.50 7717.50
728 7728.00 7728.00
729 7738.50 7738.50
730 7749.00 7749.00
731 7759.50 7759.50
732 7770.00 7770.00
733 7780.50 7780.50
734 7791.00 7791.00
735 7801.50 7801.50
736 7812.00 7812.00
737 7822.50 7822.50
738 7833.00 7833.00
739 7843.50 7843.50
740 7854.00 7854.00
741 7864.50 7864.50
742 7875.00 7875.00
743 7885.50 7885.50
744 7896.00 7896.00
745 7906.50 7906.50
746 7917.00 7917.00
747 7927.50 7927.50
748 7938.00 7938.00
749 7948.50 7948.50
750 7959.00 7959.00
751 7969.50 7969.50
752 7980.00 7980.00
753 7990.50 7990.50
754 8001.00 8001.00
755 8011.50 8011.50
756 8022.00 8022.00
757 8032.50 8032.50
758 8043.00 8043.00
759 8053.50 8053.50
760 8064.00 8064.00
761 8074.50 8074.50
762 8085.00 8085.00
763 8095.50 8095.50
764 8106.00 8106.00
765 8116.50 8116.50
766 8127.00 8127.00
767 8137.50 8137.50
768 8148.00 8148.00
769 8158.50 8158.50
770 8169.00 8169.00
771 8179.50 8179.50
772 8190.00 8190.00
773 8200.50 8200.50
774 8211.00 8211.00
775 8221.50 8221.50
776 8232.00 8232.00
777 8242.50 8242.50
778 8253.00 8253.00
779 8263.50 8263.50
780 8274.00 8274.00
781 8284.50 8284.50
782 8295.00 8295.00
783 8305.50 8305.50
784 8316.00 8316.00
785 8326.50 8326.50
786 8337.00 8337.00
787 8347.50 8347.50
788 8358.00 8358.00
789 8368.50 8368.50
790 8379.00 8379.00
791 8389.50 8389.50
792 8400.00 8400.00
793 8410.50 8410.50
794 8421.00 8421.00
795 8431.50 8431.50
796 8442.00 8442.00
797 8452.50 8452.50
798 8463.00 8463.00
799 8473.50 8473.50
800 8484.00 8484.00
801 8494.50 8494.50
802 8505.00 8505.00
803 8515.50 8515.50
804 8526.00 8526.00
805 8536.50 8536.50
806 8547.00 8547.00
807 8557.50 8557.50
808 8568.00 8568.00
809 8578.50 8578.50
810 8589.00 8589.00
811 8599.50 8599.50
812 8610.00 8610.00
813 8620.50 8620.50
814 8631.00 8631.00
815 8641.50 8641.50
816 8652.00 8652.00
817 8662.50 8662.50
818 8673.00 8673.00
819 8683.50 8683.50
820 8694.00 8694.00
821 8704.50 8704.50
822 8715.00 8715.00
823 8725.50 8725.50
824 8736.00 8736.00
825 8746.50 8746.50
826 8757.00 8757.00
827 8767.50 8767.50
828 8778.00 8778.00
829 8788.50 8788.50
830 8799.00 8799.00
831 8809.50 8809.50
832 8820.00 8820.00
833 8830.50 8830.50
834 8841.00 8841.00
835 8851.50 8851.50
836 8862.00 8862.00
837 8872.50 8872.50
838 8883.00 8883.00
839 8893.50 8893.50
840 8904.00 8904.00
841 8914.50 8914.50
842 8925.00 8925.00
843 8935.50 8935.50
844 8946.00 8946.00
845 8956.50 8956.50
846 8967.00 8967.00
847 8977.50 8977.50
848 8988.00 8988.00
849 8998.50 8998.50
850 9009.00 9009.00
851 9019.50 9019.50
852 9030.00 9030.00
853 9040.50 9040.50
854 9051.00 9051.00
855 9061.50 9061.50
856 9072.00 9072.00
857 9082.50 9082.50
858 9093.00 9093.00
859 9103.50 9103.50
860 9114.00 9114.00
861 9124.50 9124.50
862 9135.00 9135.00
863 9145.50 9145.50
864 9156.00 9156.00
865 9166.50 9166.50
866 9177.00 9177.00
867 9187.50 9187.50
868 9198.00 9198.00
869 9208.50 9208.50
870 9219.00 9219.00
871 9229.50 9229.50
872 9240.00 9240.00
873 9250.50 9250.50
874 9261.00 9261.00
875 9271.50 9271.50
876 9282.00 9282.00
877 9292.50 9292.50
878 9303.00 9303.00
879 9313.50 9313.50
880 9324.00 9324.00
881 9334.50 9334.50
882 9345.00 9345.00
883 9355.50 9355.50
884 9366.00 9366.00
885 9376.50 9376.50
886 9387.00 9387.00
887 9397.50 9397.50
888 9408.00 9408.00
889 9418.50 9418.50
890 9429.00 9429.00
891 9439.50 9439.50
892 9450.00 9450.00
893 9460.50 9460.50
894 9471.00 9471.00
895 9481.50 9481.50
896 9492.00 9492.00
897 9502.50 9502.50
898 9513.00 9513.00
899 9523.50 9523.50
900 9534.00 9534.00
901 9544.50 9544.50
902 9555.00 9555.00
903 9565.50 9565.50
904 9576.00 9576.00
905 9586.50 9586.50
906 9597.00 9597.00
907 9607.50 9607.50
908 9618.00 9618.00
909 9628.50 9628.50
910 9639.00 9639.00
911 9649.50 9649.50
912 9660.00 9660.00
913 9670.50 9670.50
914 9681.00 9681.00
915 9691.50 9691.50
916 9702.00 9702.00
917 9712.50 9712.50
918 9723.00 9723.00
919 9733.50 9733.50
920 9744.00 9744.00
921 9754.50 9754.50
922 9765.00 9765.00
923 9775.50 9775.50
924 9786.00 9786.00
925 9796.50 9796.50
926 9807.00 9807.00
927 9817.50 9817.50
928 9828.00 9828.00
929 9838.50 9838.50
930 9849.00 9849.00
931 9859.50 9859.50
932 9870.00 9870.00
933 9880.50 9880.50
934 9891.00 9891.00
935 9901.50 9901.50
936 9912.00 9912.00
937 9922.50 9922.50
938 9933.00 9933.00
939 9943.50 9943.50
940 9954.00 9954.00
941 9964.50 9964.50
942 9975.00 9975.00
943 9985.50 9985.50
944 9996.00 9996.00
945 10006.50 10006.50
946 10017.00 10017.00
947 10027.50 10027.50
948 10038.00 10038.00
949 10048.50 10048.50
950 10059.00 10059.00
951 10069.50 10069.50
952 10080.00 10080.00
953 10090.50 10090.50
954 10101.00 10101.00
955 10111.50 10111.50
956 10122.00 10122.00
957 10132.50 10132.50
958 10143.00 10143.00
959 10153.50 10153.50
960 10164.00 10164.00
961 10174.50 10174.50
962 10185.00 10185.00
963 10195.50 10195.50
964 10206.00 10206.00
965 10216.50 10216.50
966 10227.00 10227.00
967 10237.50 10237.50
968 10248.00 10248.00
969 10258.50 10258.50
970 10269.00 10269.00
971 10279.50 10279.50
972 10290.00 10290.00
973 10300.50 10300.50
974 10311.00 10311.00
975 10321.50 10321.50
976 10332.00 10332.00
977 10342.50 10342.50
978 10353.00 10353.00
979 10363.50 10363.50
980 10374.00 10374.00
981 10384.50 10384.50
982 10395.00 10395.00
983 10405.50 10405.50
984 10416.00 10416.00
985 10426.50 10426.50
986 10437.00 10437.00
987 10447.50 10447.50
988 10458.00 10458.00
989 10468.50 10468.50
990 10479.00 10479.00
991 10489.50 10489.50
992 10500.00 10500.00
993 10510.50 10510.50
994 10521.00 10521.00
995 10531.50 10531.50
996 10542.00 10542.00
997 10552.50 10552.50
998 10563.00 10563.00
999 10573.50 10573.50
1000 10584.00 10584.00
Loading 52.00 103.90
Unloadin
15.90 15.90
g
The conveyance of bitumen for
700mm dia 600mm dia bulk and packed

103.95 0.25 93.45 Packed --- Rs. 1.75per Km/ MT P-8 of preamble-Roads&bridges
103.95 0.5 93.45 Bulk --- Rs. 1.65 per Km/ MT (round the trip)
103.95 1 93.45
103.95 2 93.45
103.95 3 93.45
103.95 4 93.45
103.95 5 93.45
108.99 6 97.79
114.03 7 102.13
119.07 8 106.47
124.11 9 110.81
129.15 10 115.15
134.19 11 119.49
139.23 12 123.83
144.27 13 128.17
149.31 14 132.51
154.35 15 136.85
159.39 16 141.19
164.43 17 145.53
169.47 18 149.87
174.51 19 154.21
179.55 20 158.55
184.59 21 162.89
189.63 22 167.23
194.67 23 171.57
199.71 24 175.91
204.75 25 180.25
209.79 26 184.59
214.83 27 188.93
219.87 28 193.27
224.91 29 197.61
229.95 30 201.95
234.99 31 206.29
240.03 32 210.63
245.07 33 214.97
250.11 34 219.31
255.15 35 223.65
260.19 36 227.99
265.23 37 232.33
270.27 38 236.67
275.31 39 241.01
280.35 40 245.35
285.39 41 249.69
290.43 42 254.03
295.47 43 258.37
300.51 44 262.71
305.55 45 267.05
310.59 46 271.39
315.63 47 275.73
320.67 48 280.07
325.71 49 284.41
330.75 50 288.75
335.79 51 293.09
340.83 52 297.43
345.87 53 301.77
350.91 54 306.11
355.95 55 310.45
360.99 56 314.79
366.03 57 319.13
371.07 58 323.47
376.11 59 327.81
381.15 60 332.15
386.19 61 336.49
391.23 62 340.83
396.27 63 345.17
401.31 64 349.51
406.35 65 353.85
411.39 66 358.19
416.43 67 362.53
421.47 68 366.87
426.51 69 371.21
431.55 70 375.55
436.59 71 379.89
441.63 72 384.23
446.67 73 388.57
451.71 74 392.91
456.75 75 397.25
461.79 76 401.59
466.83 77 405.93
471.87 78 410.27
476.91 79 414.61
481.95 80 418.95
486.99 81 423.29
492.03 82 427.63
497.07 83 431.97
502.11 84 436.31
507.15 85 440.65
512.19 86 444.99
517.23 87 449.33
522.27 88 453.67
527.31 89 458.01
532.35 90 462.35
537.39 91 466.69
542.43 92 471.03
547.47 93 475.37
552.51 94 479.71
557.55 95 484.05
562.59 96 488.39
567.63 97 492.73
572.67 98 497.07
577.71 99 501.41
582.75 100 505.75
587.79 101 510.09
592.83 102 514.43
597.87 103 518.77
602.91 104 523.11
607.95 105 527.45
612.99 106 531.79
618.03 107 536.13
623.07 108 540.47
628.11 109 544.81
633.15 110 549.15
638.19 111 553.49
643.23 112 557.83
648.27 113 562.17
653.31 114 566.51
658.35 115 570.85
663.39 116 575.19
668.43 117 579.53
673.47 118 583.87
678.51 119 588.21
683.55 120 592.55
688.59 121 596.89
693.63 122 601.23
698.67 123 605.57
703.71 124 609.91
708.75 125 614.25
713.79 126 618.59
718.83 127 622.93
723.87 128 627.27
728.91 129 631.61
733.95 130 635.95
738.99 131 640.29
744.03 132 644.63
749.07 133 648.97
754.11 134 653.31
759.15 135 657.65
764.19 136 661.99
769.23 137 666.33
774.27 138 670.67
779.31 139 675.01
784.35 140 679.35
789.39 141 683.69
794.43 142 688.03
799.47 143 692.37
804.51 144 696.71
809.55 145 701.05
814.59 146 705.39
819.63 147 709.73
824.67 148 714.07
829.71 149 718.41
834.75 150 722.75

You might also like