Professional Documents
Culture Documents
DRAWING No: _ DESCRIPTION: Erection of Boiler MANUFACTURER'S SERIAL NO.: QIP NO.: REV. No.: 0
1.2 Weld Matrix/Weld Map ASME Sec. IX, Drawings Weld Matrix/Weld Map H/R
List of Qualified Welders and NDE ASME SEC-V ASME NDE Procedures
1.6 H/R
Personnel SEC-IX WPQ/WOPQ
DRAWING No: _ DESCRIPTION: Erection of Boiler MANUFACTURER'S SERIAL NO.: QIP NO.: REV. No.: 0
ITP / Pre-Installation
4.2 Allignment of front wall tubes Drawings
Report
H
ITP / Pre-Installation
4.3 Allignment of side wall tubes Drawings
Report
H
ITP / Pre-Installation
4.4 Allignment of back wall tubes Drawings
Report
H
ITP / Pre-Installation
4.5 Allignment of front wall header Drawings
Report
H
ITP / Pre-Installation
4.6 Allignment of side wall header Drawings
Report
H
ITP / Pre-Installation
4.7 Allignment of Back wall header Drawings
Report
H
DRAWING No: _ DESCRIPTION: Erection of Boiler MANUFACTURER'S SERIAL NO.: QIP NO.: REV. No.: 0
5 Fit-UP INSPECTION
DRAWING No: _ DESCRIPTION: Erection of Boiler MANUFACTURER'S SERIAL NO.: QIP NO.: REV. No.: 0
6 WELDING INSPECTION
ITP / Welding
6.3 welding of tubes with front wall header ASME Sec 1/IX
Inspection Report
W
ITP / Welding
6.4 welding of tubes with side wall header ASME Sec 1/IX
Inspection Report
W
ITP / Welding
6.5 welding of tubes with back wall header ASME Sec 1/IX
Inspection Report
W
DRAWING No: _ DESCRIPTION: Erection of Boiler MANUFACTURER'S SERIAL NO.: QIP NO.: REV. No.: 0
ITP / Welding
6.7 Welding of down-comers/risers ASME Sec 1/IX
Inspection Report
W
ITP / Welding
6.8 Welding of Cyclone ASME Sec 1/IX
Inspection Report
W
ITP / Welding
6.9 Welding of tubes with tubes ASME Sec 1/IX
Inspection Report
W
QIP / Inspection
ASME SEC-V , ASME Request /
7 NDE SEC-I Dimensional
Inspection Report,
ASME SEC-V , ASME
7.1 100% RT of all Butt joints SEC-1
ITP / RT REPORT H/R
9 Final Inspection H
DRAWING No: _ DESCRIPTION: Erection of Boiler MANUFACTURER'S SERIAL NO.: QIP NO.: REV. No.: 0
Note: After the final hydrostatic test Boiler shall Air Cleaning Inspection
9.3 be dried and cleaned completely. Report
H/R
10 SURFACE PREPARATION H