ID Task Task Name Duration Start Finish Predecessors Resource Names Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019

Mode Dec Jan Feb Mar Apr May Jun Jul Aug
1 SDB BALANCE WORK 116 days Jan 30 '19 Jul 10 '19
2 STAFF OFFICE 85 days Mar 2 '19 Jun 28 '19
3 Tie beam formwork 5 days Mar 2 '19 Mar 7 '19
4 Tie beam Reinforcment 3 days Mar 8 '19 Mar 12 '19 3
5 Tie beam concrete 1 day Mar 13 '19 Mar 13 '19 4 Column to be added
6 Column Shaft up to Roof beam 4 days Mar 14 '19 Mar 19 '19 5
7 Backfilling 5 days Mar 25 '19 Mar 29 '19 6SS+7 days
8 Roof beam 5 days Apr 1 '19 Apr 5 '19 7
9 Building works Including Architectural 60 days Apr 8 '19 Jun 28 '19
& Finishing work
10 Roof Work 20 days Apr 8 '19 May 3 '19 8
11 Brick Work 20 days May 6 '19 May 31 '19 10
12 Fixing Door & Window Frams 5 days May 15 '19 May 21 '19 11SS+7 days
13 Plastering 10 days Jun 3 '19 Jun 14 '19 11
14 Paniting 10 days Jun 17 '19 Jun 28 '19 13
15 Ceiling Works 10 days Jun 17 '19 Jun 28 '19 13
16 Floor finishing 10 days May 27 '19 Jun 7 '19 11FF+5 days
17 SDB 4 (Balance) 13 days Feb 25 '19 Mar 13 '19
18 Column Rainforcment 2 days Feb 25 '19 Feb 26 '19
19 Column Formwork 2 days Feb 27 '19 Feb 28 '19 18 This was lapsed as
20 Column Concrete Placing 1 day Mar 1 '19 Mar 1 '19 19 today no beam was
constructed.
21 Roof Beam Formwork 7 days Mar 4 '19 Mar 12 '19 20
22 Roof beam rainforcment 2 days Mar 7 '19 Mar 8 '19 21SS+3 days
23 Beam Concrete 1 day Mar 13 '19 Mar 13 '19 21,22
24 SDB 5 17 days Feb 26 '19 Mar 20 '19
25 Side Wall Rainforcment 2 days Feb 26 '19 Feb 27 '19
26 Side Wall Formwork 2 days Feb 28 '19 Mar 1 '19 25
27 Wall Concrete Placing 1 day Mar 4 '19 Mar 4 '19 26
28 Column Rainforcment 1 day Mar 5 '19 Mar 5 '19 27
This was lapsed
29 Column Formwork 2 days Mar 6 '19 Mar 7 '19 28
30 Column Concrete Placing 1 day Mar 8 '19 Mar 8 '19 29
31 Roof Beam Formwork 7 days Mar 11 '19 Mar 19 '19 30
32 Roof beam rainforcment 2 days Mar 14 '19 Mar 15 '19 31SS+3 days
33 Beam Concrete 1 day Mar 20 '19 Mar 20 '19 31,32
34 Water Tank 19 days Mar 5 '19 Mar 29 '19
35 Tie Beam Formwork 3 days Mar 5 '19 Mar 7 '19
36 Tie Beam Rainforcment 2 days Mar 8 '19 Mar 11 '19 35
37 Tie Beam Concrete 1 day Mar 12 '19 Mar 12 '19 36
38 Column rainforcment Up to 467.6MSL 1 day Mar 13 '19 Mar 13 '19 37
39 Column Formwork 1 day Mar 14 '19 Mar 14 '19 38
40 Column Concrete 1 day Mar 15 '19 Mar 15 '19 39

Task Project Summary Manual Task Start-only Deadline

Project: Remaing Works Split Inactive Task Duration-only Finish-only Progress


Date: Mar 27 '19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
ID Task Task Name Duration Start Finish Predecessors Resource Names Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019
Mode Dec Jan Feb Mar Apr May Jun Jul Aug
41 Beam & Slab Formwork 3 days Mar 18 '19 Mar 20 '19 40
42 Rainforcment 1 day Mar 21 '19 Mar 21 '19 41 This was lapsed
43 Slab & Beam Concrete 1 day Mar 22 '19 Mar 22 '19 42
44 Fixing Steel Lader & Guradrail 5 days Mar 25 '19 Mar 29 '19 43
45 Roof Work 60 days Mar 30 '19 Jun 21 '19
46 SDB-1 20 days Mar 30 '19 Apr 25 '19
47 SDB-2 20 days Apr 15 '19 May 10 '19 46SS+10 days
48 SDB-3 20 days Apr 29 '19 May 24 '19 47SS+10 days
49 SDB-4 20 days May 13 '19 Jun 7 '19 48SS+10 days
50 SDB-5 20 days May 27 '19 Jun 21 '19 49SS+10 days
51 Retaining wall 19 days Feb 23 '19 Mar 21 '19
52 Excavation 4 days Feb 23 '19 Feb 27 '19
53 Screed concrete 1 day Feb 28 '19 Feb 28 '19 52
54 Reinforcment for base 3 days Mar 1 '19 Mar 5 '19 53
55 Formwork 1 day Mar 6 '19 Mar 6 '19 54
56 Concrete Placing 1 day Mar 7 '19 Mar 7 '19 55
Retaining wall was not
57 1st Lift 5 days Mar 8 '19 Mar 14 '19 completed and please
58 consider two stage of
Reinforcment 1 day Mar 8 '19 Mar 8 '19 56 construction for
59 Formwork 3 days Mar 11 '19 Mar 13 '19 58 retaining wall.
60 concrete Placing 1 day Mar 14 '19 Mar 14 '19 59 This was lapsed
61 2nd lift 5 days Mar 15 '19 Mar 21 '19
62 Reinforcment 1 day Mar 15 '19 Mar 15 '19 60
63 Formwork 3 days Mar 18 '19 Mar 20 '19 62
64 Concrete Placing 1 day Mar 21 '19 Mar 21 '19 63
65 Road Construction 75 days Mar 4 '19 Jun 14 '19
This was lapsed
66 Excavation up to Sub-Grade including 15 days Mar 4 '19 Mar 22 '19
Compaction Pls expedite the process
67 Sub-Base 15 days Mar 25 '19 Apr 12 '19 66 of soil delivery.

68 Construction of Drain 20 days Apr 15 '19 May 10 '19 67


69 Laying of ABC 15 days May 13 '19 May 31 '19 68
70 Laying of Asphalt 3 days Jun 3 '19 Jun 5 '19 69
71 Construction of Concrete Blocks 10 days Mar 25 '19 Apr 5 '19 66 This was lapsed

72 Construction of Steel Gates 10 days Jun 3 '19 Jun 14 '19 69 Pls re calculate the
duration of the fencing
73 Architectural & Landscaping 73 days Apr 1 '19 Jul 10 '19 work, with your current
work force this cannot
74 Perimeter Fence 30 days Apr 1 '19 May 10 '19 be completed.
75 Turfing 5 days Jun 6 '19 Jun 12 '19 70,64 Pls prepare detailed
programme for the
76 Fixing Guard Rail 20 days Jun 13 '19 Jul 10 '19 75 fencingworks.
77 Slope Protection 60 days Jan 30 '19 Apr 23 '19 This work is not in your Scope and this
78 Rubble Packing Excavation 10 days Feb 20 '19 Mar 5 '19 work will be done by Finnex.
79 Rubble packing & concrete work 20 days Mar 6 '19 Apr 2 '19 78 Pls delete this.
80 Bottom Drain 60 days Jan 30 '19 Apr 23 '19
Task Project Summary Manual Task Start-only Deadline

Project: Remaing Works Split Inactive Task Duration-only Finish-only Progress


Date: Mar 27 '19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 2
ID Task Task Name Duration Start Finish Predecessors Resource Names Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019
Mode Dec Jan Feb Mar Apr May Jun Jul Aug
81 Capping Concrete 15 days Apr 3 '19 Apr 23 '19 79
This work is not in your Scope and this work
82 Storm Water System 57 days Mar 20 '19 Jun 6 '19 will be done by Finnex.
83 Construction of Manhols & catchpits 7 days Mar 20 '19 Mar 28 '19
Pls delete this.
84 Construction of Endcasment 15 days Mar 29 '19 Apr 18 '19 83
85 Laying Pipes 15 days Apr 19 '19 May 9 '19 84
86 Construction of Outfall structures 25 days May 3 '19 Jun 6 '19 85SS+10 days
87 M&E 70 days Mar 21 '19 Jun 26 '19
AC installation is not possible with the
88 Yard light system 10 days Jun 13 '19 Jun 26 '19 75 Building works.
89 A/C Installation 10 days Jun 10 '19 Jun 21 '19 16
90 Water Tank & Staff office plumbing 7 days Jun 3 '19 Jun 11 '19 11
work
91 Leachate System 15 days Mar 21 '19 Apr 10 '19 33
92 Staff Office Electrical works 10 days Jun 10 '19 Jun 21 '19 16

Task Project Summary Manual Task Start-only Deadline

Project: Remaing Works Split Inactive Task Duration-only Finish-only Progress


Date: Mar 27 '19 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone