You are on page 1of 7

1 Excavation Plan for KP181+900

SHIN YANG SDN BHD

PROVISION OF REPAIR AND MAINTENANCE OF ACCESS ROADS AND


SLOPE STABILIZATION WORKS WITHIN RIGHT OF WAY (ROW) OF
SABAH-SARAWAK GAS PIPELINE (SSGP) PROJECT (SARAWAK
LOCATIONS) FOR PETRONAS CARIGALI SDN BHD.
PACKAGE B (LAWAS: KP 92 - KP 210)

DOCUMENT TITLE : EXCAVATION PLAN FOR KP181+900

Prepared By Review By

Signature

Name Nurhafizah Ahmad


Designation Site Engineer
Department/
SYSB
Company
Date 30/01/2019
2 Excavation Plan for KP181+900

TABLE OF CONTENT

Contents Page

1.0 Introduction...............................................................................................................................3

2.0 Scope of Works for Excavation.................................................................................................3

3.0 Excavation Works (Trenching, Trimming & Cutting)...............................................................3

3.1.1 Excavation works for Concrete Blocks Installation.................................................4

3.1.2 Excavation works for Drainage Construction and Installation................................5

4.0 Excavation Activities and Layout Plan......................................................................................7

5.0 Appendices................................................................................................................................7

Appendix A: PETRONAS Technical Standard - Excavation (PTS 18.52.18).........................7


3 Excavation Plan for KP181+900

1.0 Introduction
This excavation plan outline the methodology use to ensure potential hazard for
excavation works at KP181+900 can be control.

2.0 Scope of Works for Excavation


 Excavation for installation and construction of drains and wing wall with the
maximum depth of 1.25m

 Excavation for installation of 2-layer precast concrete blocks with maximum depth of
1.5m

 Trimming/Lay for installation of gabion mattress and 1-layer precast concrete block

3.0 Excavation Works (Trenching, Trimming & Cutting)


The excavation plan addresses the requirements and safe practices to ensure the safety
of site personnel who work in or around the excavation area.

 Before performing the excavation works, peg out 2.5m right hand side (RHS) and
left hand side (LHS) from centerline of gas pipeline and marked with warning tape.
(Note: Excavation works within 5m of pipeline area shall only be carried out after
verification and approval by PMT and PGB representatives).

 Apart from the boundary of both 2.5m left and right side from centerline of gas
pipeline, the excavation works could proceed as per construction drawing

 Prior to excavation works, GTS shall carry out site assessment to classify soil,
inspecting proactive systems and designing excavation method (sloping, benching,
shoring etc.) and recorded in Geotechnical-Geohazard Data Capture Proforma form

 RA and Work Leader shall assess surrounding/inspect and evaluate site condition
using Excavation and Trenching/Pit Checklist form to make sure it is safe prior to
4 Excavation Plan for KP181+900

start works. The approval shall be sign by PMT’s Construction Engineer,


Construction Manager, HSE Manager and QAQC Manager.
2-LAYER PRECAST CONCRETE BLOCKS
 Apply safe work practice in accordance with the excavation procedure by assigned
banksman and Site Engineer/Work Leader need to closely monitor during excavation
works. All the excavation area shall be barricaded and proper signage to be placed at
suitable location<1.5m
to ensure other site personnel or visitor aware about the excavation
<1.0m
depth depth
works

3.1.1 Excavation works for Concrete Blocks Installation


 The approved excavation plan sketch and checklist shall be attached with PTW for
all permit application.

Note: For hot work permit, PGB shall be notify 7 days earlier for any excavation within
2.5m LHS & RHS from centerline of pipeline for approval.

 For the area which required two (2) layers of concrete blocks to be install, excavate
the existing ground about 3 meter width and less than 1.5 meter depth for the
concrete blocks platform which including the cobblestone thickness and concrete
blocks height as shown in figure 1.

Figure 1: Cross Section of 2-layers’ Concrete Blocks

 Excavation slope wall angle shall be 1 V: 1.5 H (34°) based on PTS 18.52.18 or more
depends on soil condition for original soil and for fill embankment shall be more
than 34°.
5 Excavation Plan for KP181+900

 For other areas which only have one (1) layer of blocks, the depth and width of the
excavation shall be 1.25 meter and 2 meter consecutively. Use these references as an
indicator for block’s excavation.

 Excavation depth = cobblestones + concrete blocks height

 Excavation width = Concrete blocks width + 500mm both side for workspace

Figure 2: Cross Section of 1-layers’ Concrete Blocks

 All excavated spoil shall be placed more than 1m away from the trench. Minimize
the movement of excavator near the trench while workers working inside the trench

 All other personnel that not involved in excavation activities shall stay away from
excavation area

3.1.2 Excavation works for Drainage Construction and Installation


 Observation on to soil condition is compulsory prior to start work. The approved
excavation plan sketch and checklist shall be attached.

 Perform trench excavation and preparation for the formation level of the drain.
6 Excavation Plan for KP181+900

 The dimension of the trench shall be larger than the size of the R.C. drain as per
construction drawing so that workers will have enough work space for formwork
erection.

 For R.C. U-Drain installation works, open up the trench size about 2 meter width for
the workspace and maximum of 1.25 meter depth which including lean concrete
thickness, slab base thickness and walls height.

 Excavation slope wall shall be as per PTS 18.52.18. Any running water from upper
slope shall be diverted by constructing temporary earth drain, if necessary.

 Use these references as an indicator for drain’s trenching excavation.

Excavation depth = lean concrete thickness + base slab thickness + walls height
Excavation width = Drain width + 500mm both side for workspace

Figure 3: Cross Section of 2-layers’ Concrete Blocks

 All excavated spoil shall be placed more than 1m away from the trench. Minimize
the movement of excavator near the trench while workers working inside the trench

 All other personnel shall stay away from excavation area


7 Excavation Plan for KP181+900

4.0 Excavation Activities and Layout Plan

Direction of excavation

Figure 4: Excavation Activities and Layout Plan

Excavation Activities

Drainage (<1.25m depth) Gabion Mattress (<0.5m depth)

2-layer Precast C. Blocks (<1.5m depth) 1-layer Precast C. Blocks (<1.5m depth)

5.0 Appendices
Appendix A: PETRONAS Technical Standard - Excavation (PTS
18.52.18)

You might also like