You are on page 1of 12

Geotech Geol Eng (2013) 31:557–568

DOI 10.1007/s10706-012-9608-0

ORIGINAL PAPER

Investigation of Induced Trench Method Using a Full Scale


Test Embankment
Alper Turan • M. Hesham El Naggar •

Dave Dundas

Received: 7 May 2012 / Accepted: 13 December 2012 / Published online: 14 March 2013
 Springer Science+Business Media Dordrecht 2013

Abstract The construction of highway embank- utilities. The test embankment comprised four sec-
ments in urban areas often interferes with existing tions, which facilitated the evaluation of four config-
underground facilities such as sewer lines and other urations including the conventional backfill, induced
buried conduits. In many instances, the extra loads trenching and two at-grade geogrid-reinforcing bridg-
imposed by embankment construction on buried ing with different spans. Each configuration consisted
conduits would be unacceptably high. Severe conse- of a 3 m deep trench overlain by a 10 m wide, 10 m
quences of overstressing an underground utility con- long and 6 m high embankment section. Earth load
duit include damage and interruption of services for cells were installed to monitor stresses at the fill/
both the utility and highway. Typical alternatives ground interface and at depths of 1.5 and 3 m. The
considered to address this problem include: relocation numerical models of the test embankment are gener-
of utility lines; embankment load reduction using ated using the finite difference program FLAC. This
lightweight fill; at-grade pile cap bridging; at-grade paper presents the results of stress measurements in
geogrids-reinforced bridging; and induced (imperfect) the 3 m wide trench under embankment loads and the
trenches. The relocation, lightweight fill and pile cap results of numerical varification analyses. The results
alternatives are usually cost prohibitive. A full-scale showed that the use of induced trench method (ITM)
instrumented test embankment is constructed by resulted in substantial reduction in vertical stresses
Ontario Ministry of Transportation to study the effects relative to positive projection method case. It was also
of embankment construction on the underground observed that horizontal stresses increased when ITM
is employed.

A. Turan (&)  D. Dundas Keywords Induced trench  Test embankment 


Material Engineering Research Office (MERO), Ministry Underground utilities  Stress reduction
of Transportation, 1201 Wilson Ave., Downsview,
ON M3M1J8, Canada
e-mail: alperturan@hotmail.com; alper.turan@ontario.ca
1 Introduction
D. Dundas
e-mail: dave.dundas@ontario.ca
The induced trench method (ITM) is a construction
M. H. El Naggar technique employed to reduce the vertical pressures on
Department of Civil and Environmental Engineering,
buried structures, typically resulting from the con-
The University of Western Ontario, London,
ON N6A 5B9, Canada struction of a high embankment fill on the structure. In
e-mail: helnaggar@eng.uwo.ca this technique, a layer of compressible material is

123
558 Geotech Geol Eng (2013) 31:557–568

placed directly above the buried structure to induce backfilling of trench using the conventional method
positive arching, thus reducing the vertical pressures. (PPM), ITM and two at-grade geogrid reinforcing
This technique has been in use for almost a century and bridges with 1.5 and 3 m width are investigated as part
numerous existing utility lines and conduits are of the field test. The present study focuses only on the
installed employing ITM. However, the reliability of PPM and ITM installations. The field performance of
this method as a long-term, reliable and constructible geogrids reinforcing bridges is investigated elsewhere.
solution is being questioned. This skepticism led some Numerical models that can simulate the complex SSI
jurisdictions in North America to discontinue its use, mechanisms occurring during PPM and ITM installa-
which is also manifested in the removal of this method tions are developed and verified using the experimen-
from the American Concrete Pipe Association Hand- tal results. These models are then employed to
book (2004). However, some jurisdictions, including understand the stress schemes within and around the
the New Brunswick Department of Transportation buried structure.
(NBDOT), continue to benefit from the successful use The paper outlines the methodology adopted for the
of ITM. The NBDOT has supervised the construction full scale field tests and numerical analyses, presents
of approximately 80 induced trench installations in the the results of field tests and numerical analyses and
province since 1991, and recent inspections have provides some conclusions. It is envisioned that the
confirmed good performance for a period of data presented in this study will serve as a validation
10–15 years (Hansen et al. 2007). Gaining a better case for development of analytical approaches for the
understanding of how the method works and devel- evaluation of stress reduction on buried culverts
oping clear design guidelines are required to address installed using ITM. Data presented in this paper also
the uncertainties associated with the empirical nature have the potential to lead to an improved understand-
of the design. ing of SSI effects on the behavior of buried structures
The current version of the Canadian Highway in general.
Bridge Design Code (CSA 2006) and the AASHTO
load resistance factored design (LRFD) bridge design
specifications (AASHTO 2007) do not include any 2 Background
clauses related to ITM. The only recommendations
regarding the culvert installations are related to The stress reducing effects of lightweight compress-
installations using the positive projection method ible materials used above buried structures has long
(PPM). The design recommendations given in these been recognized. Materials such as baled hay or straw,
codes for PPM include the assumptions of uniform leaves, compressible soil, or expanded polystyrene are
earth pressure on top of the culvert crown and the previously used to reduce stresses exerted on the
uniform pressure on the bottom slab of culvert that is buried utilities. As part of ITM installation, the
equal to the sum of the crown pressure and the pressure compressible material placed above the buried struc-
due to dead load of culvert. Ontario Ministry of ture experiences more settlement relative to the
Transportation (MTO) has successfully implemented surrounding soil, which results in a reverse arching
the induced trench method in the past. However, the deformation. Schematic of above-mentioned mecha-
implementation of ITM installations in MTO projects nism is depicted in Fig. 1. The relative deformation
has been terminated in recent years due to the between the soil immediately above the buried
abovementioned uncertainties. In order to gain a structure and the surrounding soil may result in an
better understanding to re-introduce ITM installations increase or decrease in the soil pressures exerted on the
into embankment construction practice, a full scale structure depending on the direction of relative
instrumented test embankment is constructed over a settlement. If the soil above the structure settles less
trench in order to study various stress reduction than that of the adjacent soil, the shear forces exerted
measures. on the soil column above the structure by the
The objectives of this paper are to understand the surrounding soil mass results in a mechanism called
soil-structure-interaction (SSI) mechanism involved negative arching (Selig 1972; Vaslestad et al. 1993).
and evaluate the stress reductions achieved by the use Negative arching increases the pressures exerted on
of ITM installation. The stresses generated due to the buried structures and it is addressed in CHBDC (2006)

123
Geotech Geol Eng (2013) 31:557–568 559

Fig. 1 Schematics of The surface of embankment


positive projecting and
induced trench installation
methods (SEMB settlement of Neutral plane
foundation soil; SPPM
settlement of soil above the
conduit in PPM; SITM
settlement of soil above the
conduit in ITM)

SEMB SPPM SEMB SITM SEMB

Compressible
Zone

Shear Forces

Ground surface
PPM ITM
SITM > SEMB > SPPM

via the introduction of a series of vertical and Pipe Association (ACPA) eliminated the imperfect
horizontal arching factors. If the settlement of the soil trench method from the 2001 edition of the Concrete
above the structure is more than that of the adjacent Pipe Handbook (ACPA 2001) primarily for these
soil (e.g. ITM) positive arching mechanism takes reasons. However, full-scale tests, conducted on two
place, which reduces the soil pressures on the circular culverts and one box culvert by the Norwegian
structure. Road Research Laboratory (Vaslestad et al. 1993)
Initial studies on ITM include those by Marston and showed that there was no increase in earth pressure
Anderson (1913), Marston (1922, 1930). Spangler after a 3 year period. McAffee and Valsangkar (2008)
(1950a, b) and Spangler and Handy (1973) reintro- instrumented a circular induced trench culvert and
duced this method, which is referred to as Marston and observed no load increase 2 years after the completion
Spangler (M-S) theory in Concrete Pipe Design of the embankment. McAffee (2005) investigated a
Manuals (ACPA 1980, 1998). A number of research- twin culvert installation using ITM in Baddeck, Nova
ers identified various shortcomings of M-S approach Scotia, which has performed well for over 35 years.
such as the effect of geometry and stiffness of the Hansen et al. (2007) reported that field inspection of
compressible zone, the mechanical properties of the 80 ITM installations in New Brunswick performed
backfill material, the shape of buried structure and the favorably and satisfy the serviceability conditions. In
magnitude of lateral loads (e.g. Sladen and Oswell addition, there are a limited number of full-scale and
1988; Scario 2003; Handy 2004). Brown (1967) reduced scale physical model tests reported in the
presented the first study that quantified the pressure literature on the ITMs. Kang et al. (2007a) quantita-
reduction effect of the soft zone by using the finite tively studied the parameters that influence the earth
element method. The studies by Sladen and Oswell loads in ITM. They also investigated the effect of side
(1988), Sven and Liedberg (1997) and Vaslestad fill treatment and bedding for buried concrete pipes. In
(1990) pointed out that the M-S method suffers a separate parametric study, Kang et al. (2007b)
deficiencies and results in earth pressure estimates studied the influence on ITM installation on a flexible
that are overly conservative. PVC pipe.
Despite the significant potential of ITM for stress McGuigan and Valsangkar (2010) studied the
reduction, the long term performance is uncertain. The performance of the box culverts installed using ITM
concern regarding the long-term behavior is largely using scale physical modelling. They concluded that
due to the lack of reliable information on the the stress reductions were achieved on top, side and
mechanical properties of the lightweight materials bottom of the box culvert. In a recent study, McGuigan
and the optimum geometry. The American Concrete and Valsangkar (2011) investigated the behaviour of

123
560 Geotech Geol Eng (2013) 31:557–568

Table 1 List of physical model studies on ITMs


Title Type Structure tested Remarks

Vaslestad et al. Field test Box culvert 37 % reduction of the vertical stresses relative to the overburden stresses
(1993) on top of the box. No pressures on the sides and bottom are reported
Floyd and Clark Field test Box culvert No results are reported due to problems related to instrumentation
(1979)
Okabayashi et al. Centrifuge test Box culvert Recommended optimized size and location of compressible EPS layer
(1994)
MacLeod (2003) Centrifuge test Box culvert Reported 80 % reduction in vertical stress relative to the overburden
stresses on top of the culvert and a small increase in the lateral stresses
Bourque (2002) Centrifuge test Twin box Studied the effect of culvert spacing and compressible material geometry
culvert
McAffee and Field test and Single box and Reported 64–76 % reduction in vertical stress relative to the overburden
Valsangkar centrifuge test pipe culvert stresses on top of the culvert and larger lateral stresses relative to vertical
(2005) stresses
Parker et al. Field test Single pipe Reported 76 % reduction in vertical stress relative to the overburden
(2008) culvert stresses on top of the culvert and a small increase in the lateral stresses
The maximum horizontal pressure measured on the side of the culvert was
reported to be 0.45 times the overburden pressure

twin culverts installed using PPM and ITM under high A design procedure for ITM was initially developed
embankments using centrifuge testing and numerical by Marston (1922) and improved by Spangler (1950a,
analyses. They reported significant stress reductions in b). This design method quantifies the load on conduits
ITM case relative to PPM. The literature review shows installed by ITM as follows:
that a significant number of studies were performed
using field and laboratory physical tests as well as W ¼ Cn c B2c ð1Þ
numerical methods. These studies provided consistent
where, Cn is load coefficient, c is the unit weight of fill
conclusions regarding the benefits of ITM. Table 1
material and Bc is the out-to-out horizontal span of the
gives a summary of some model studies on the ITM.
conduit. Although graphic illustrations are provided
for the computation of coefficient, Cn, there are many
practical difficulties as the parameters used to deter-
3 ITM Design Approaches
mine the coefficient cannot be evaluated readily.
These parameters include the settlement ratio and the
Two analytical design approaches used for the design
height of the plane of equal settlement to be
of ITM type culvert installations are summarized here.
determined by a graphical method as summarized in
The first method is M-S method, which is based on the
Kang (2007). In order to use the M-S equation, it is
works by Marston (1922) and Spangler (1950a, b).The
essential to determine the value of the settlement ratio,
second method, the Vaslestad Method, is based on the
rsd, which is defined as follows:
work by Vaslestad et al. (1993).
sg  ðsd þ sf þ dc Þ
3.1 Marston-Spangler Method (M-S Method) rsd ¼ ð2Þ
sd
ITM installations are traditionally performed by where, rsd is settlement ratio; sg is settlement of surface
backfilling and compacting thoroughly on both sides of compacted soil; sd is compression of fill in ditch
and for some distance above buried pipe. Then a within height; sf is the settlement of flow line of pile; dc
trench is typically constructed in this compacted fill by is deflection of conduit, i.e. shortening of its vertical
removing a prism of soil having the same width as the dimension; and (sd ? sf ? dc) is settlement of critical
conduit and refilling with very loose lightweight plane. Although the settlement ratio, rsd, is a rational
materials. quantity used in the development of the load formula,

123
Geotech Geol Eng (2013) 31:557–568 561

it is very difficult to determine the actual value that earth pressure cells are placed in granular protective
will be developed in a specific case. However, surrounds located at two different depths in the trench.
Spangler and Handy (1982) presented some recom- The test embankment comprises four distinct sec-
mended values of the settlement ratio for various tions. The first section is constructed as a conventional
culvert types and foundation deformation characteris- control section (Sect. 1), which includes an instru-
tics based on field observations on actual culverts mented trench that is conventionally backfilled with
under embankments. Cn values may be determined granular material up to the grade level (PPM). The
graphically using settlement ratio, rsd and projection second section represents an ITM installation (Sect. 2),
ratio, p0 , which is depth/width ratio of the ditch. which includes an instrumented trench backfilled with
granular material that is overlain by a layer of
3.2 Vaslestad Method compressible Styrofoam chips up to the grade level.
The third and fourth sections include geogrid void
The details of this method are outlined in Vaslestad bridges installed on the instrumented trenches with
et al. (1993). In this method, the earth loads acting on different trench widths. The evaluation of the third and
the buried culverts are calculated by applying an fourth sections is performed as part of a separate study
arching factor to the overburden pressure. This arching and is beyond the scope of the present work.
factor is based on the friction number, Sv. Vaslestad’s The layout of test embankment is depicted in Fig. 2.
equation for estimating vertical earth pressures on an Test configuration comprises a 3 m deep trench back-
induced trench culvert is given as follows; filled up to the grade level, which underlies an
embankment with the footprint dimension of
rv ¼ NA cH ð3Þ
64 m 9 34 m in length and width and a height of
2Sv HB
1e 6 m. The slopes of the embankment are constructed with
NA ¼ ð4Þ
2Sv HB a 2H:1 V inclination. Figure 3a, b show the details of
instrumented trenches for Sects. 1 and 2, respectively.
where, NA is arching factor; Sv is Janbu’s friction
number; B is width of culvert, and H is the height of fill 4.1.2 Construction and Instrumentation
above the culvert.
The site is leveled and topsoil is removed prior to the
construction of test embankment. A 1.5 m wide trench
4 Methodology is excavated to a depth of 3 m. At a level 1 m above the
bottom of trench, trench slopes are cut to 1H:1V to
This study comprises full scale model tests and maintain the integrity of trench side slopes during the
numerical analyses for culvert installation using the construction (see Fig. 3). Two drainage sumps are
PPM and ITM. This section outlines the methodology installed at each end to maintain a dry condition in the
adopted for field testing and numerical modeling. trench. The base of the trench is filled with a 300 mm
thick compacted granular pad comprising Granular-A
4.1 Description of Field Tests (OPSS 314). The earth pressure cells are then installed.
The earth pressure cells with vibrating wire pressure
4.1.1 Test Embankment Geometry transducers are used. The earth pressure transducers
are placed at the bottom (3 m from the grade) and the
An instrumented test embankment is constructed over a mid-height (1.5 m from grade) of the trench with
3 m deep trench to study the stress reductions that can be horizontal and vertical orientations in order to allow
achieved by means of ITM installations under embank- measurement of vertical and horizontal pressures,
ment loadings. The test embankment is constructed as respectively. The pressure transducers are placed
part of Highway 407 contract and is located near the within a 0.5 m 9 1 m 9 1 m granular protective
Highway 407 and Weston Road in Vaughan, Ontario. surrounds. The granular surrounds are constructed as
Since the objective of the testing program is to evaluate lightly compacted at mid-height pressure cell and well
the stresses reductions achieved by means of ITM compacted at the bottom pressure cell to see the effect
installation, no actual culverts are installed. Instead, the of the surround compaction on the measured stresses.

123
562 Geotech Geol Eng (2013) 31:557–568

Fig. 2 Plan and profile of test embankment

(a) (b)
Fig. 3 Trench cross-sections for Sects. 1 (PPM) and 2 (ITM)

The protective surrounds, which are constructed to Granular-A, which constitutes the rest of the fill
eliminate any possible damage to the pressure cells, are material in the trench. The steel separators are removed
constructed using steel separators in four sides. The as the level of granular surrounds reached 0.5 m height.
steel separators separate the lightly compacted and A total of 2 transducer couples (vertical and horizontal)
well compacted granular surrounds from compacted are installed at the bottom and mid-height of each

123
Geotech Geol Eng (2013) 31:557–568 563

trench for each section and an additional transducer is pressure triaxial tests. The other category includes
installed at the interface between trench backfill and models that are based on uniaxial strain confined
embankment. The trench backfill encapsulating gran- compression tests such as the model by Katona et al.
ular surrounds, comprise Granular A compacted to (1976). Duncan-Chang model used in this study is
95 % of Standard Proctor Dry Density. The pneumatic based on the work by Duncan and Chang (1970), who
lines are extended through a PVC pipe, which followed expanded the Kondner (1963)’s basic hyperbolic
the edges of trench and connected to a monitoring stress–strain relationship to derive the tangent modu-
station. lus of elasticity as follows:
The embankment is constructed using native cohe-    
sive soils in the area. The soil is placed in lifts of r3 n Rf ð1  sin /Þðr1  r3 Þ 2
Et ¼ Ke Patm 1
300 mm and compacted to 95 % of Standard Proctor Patm 2c cos / þ 2r3 sin /
Dry Density. The portion of the embankment fill ð5Þ
immediately above the trench is placed manually and
where Et tangent elastic modulus, r1 and r2 maximum
compacted by self propelled compaction equipment
and minimum stresses, / angle of internal friction; c
(Bomag BW65S). The embankment fill, including the
cohesion, Rf failure ratio, Ke modulus number, Patm
zone above the trench, is compacted using regular
atmospheric pressure, and n modulus exponent.
compaction equipment after its height reached 1.3 m.
Tangential bulk modulus and tangential Poisson’s
ratio are expressed as follows:
4.2 Description of Numerical Model  
r3 m
Bt ¼ Kb Patm ð6Þ
4.2.1 Numerical Modeling and Boundary Conditions Patm
 
1 Et
Numerical analyses of the test embankment are mt ¼ 1 ð7Þ
2 3Bt
performed using the finite difference software, FLAC
(Itasca 2005). Two sets of numerical models are where, Bt tangential bulk modulus, vt tangential
developed to analyze stresses generated in cases of Poisson’s ratio, Kb bulk modulus number, m bulk
PPM installation and ITM installation. An elastic– modulus exponent.
plastic soil model with Mohr–Coulomb failure crite- A plane-strain model is considered to be applicable
rion is used to simulate the soil behavior during the full to the analysis of test embankment and is used in this
scale field test due to the simplicity of the model and study. A fully fixed boundary condition was applied at
availability of model parameters. the base of the models. The lateral extend of the models
The strength parameters are determined from a is positioned such that a distance equal to five times of
geotechnical investigation conducted prior to the embankment width is maintained between the toe of
construction of test embankment. However, no direct the embankment and the external boundaries of the soil
determination for the stiffness properties of soil is domain. The boundaries are assumed to be free in the
performed. Thus, elastic moduli for various soils are vertical direction and fixed in the horizontal direction.
determined based on experience and calibrated con-
sidering the deformation of embankment. The stresses 4.2.2 Subsurface Conditions and Material Properties
within the trench are affected by the stiffness of the
granular fill. Thus, the hyperbolic Duncan-Chang The subsurface conditions are determined using three
model (Duncan and Chang 1970) is used to model the boreholes drilled within the footprint of embankment.
stress dependant variation of stiffness of the fill The soil stratigraphy comprises two layers: Layer 1 is
materials within the trench. The mechanical behavior clayey-silt-till/silty-clay-till and extends from the
of the compressible lightweight fill (styrofoam chips) ground surface to a depth of 10 m; Layer 2 is silt/
is modeled using a linear elastic material model. silty-clay which extends to a depth of 20 m. The
There are two general categories of stiffness and/or embankment is constructed using native clayey silt-
compressibility models for soils (Kim and Yoo 2005). till/silty-clay-till material. Table 2 summarizes the
The models presented by Hardin (1971) and Duncan mechanical properties of foundation soils, embank-
and Chang (1970) are based on constant confining ment fill and the materials that comprise the trench fill.

123
564 Geotech Geol Eng (2013) 31:557–568

Table 2 Material properties assumed for field test and parametric analysis
Elastic Ke n Rf Internal friction Unit weight Poisson’s ratio
modulus (kPa) angle () (kN/m3)

Layer 1 130,000 – – – 40 22 0.35


Layer 2 160,000 – – – 42 22 0.35
Embankment fill 95,000 – – – 33 20 0.35
Styrofoam chipsa 700 – – – N/A 6.4 0.05
Lightly compacted surround – 400 0.5 0.9 33 18 0.3
Well compacted surround – 850 0.5 0.6 35 18 0.3
Granular trench fill – 950 0.5 0.6 36 20 0.3
a
Linear elastic material behavior is assumed

5 Results and Discussion influence of the installation method on the stresses


occurring in a trench, rather than presenting a realistic
The results of the field test are presented here along stress values that may occur in a conduit installation.
with the results of the numerical analyses. The The results of instrumented field test are summa-
objective of the numerical analyses performed in this rized in this section along with the accompanying
study is to investigate the trends of stress variations numerical results. Figure 4 shows the variation of
measured during the field tests using the estimated soil vertical stresses measured at the foundation-embank-
properties. The accuracy of the numerical analyses is ment interface (cell 5) with the embankment height.
subjected to realistic material property assumptions. Vertical stresses depicted in Fig. 4 show a typical
Thus, the results of the numerical models were increase that is linearly proportional to depth of
calibrated against the actual settlement plate readings embankment.
collected before and after the construction of test
embankment. Table 3 summarizes the settlement 5.1 Stresses Measured at Mid-height of the Trench
monitoring results along with the vertical deforma- (1.5 m)
tions estimated using finite element model at these
locations. The comparisons of the measured and The measured stresses at a depth of 1.5 m in the trench
calculated stresses for PPM and ITM installations (cells 1, 2, 6 and 7) and the stresses calculated using
show that despite local differences in the magnitudes FLAC are shown in Figs. 5 and 6 for the vertical and
of stresses, the similar trends of stresses are captured horizontal directions, respectively. The results indi-
using the material properties outlined in Table 2. The cate that there is a reasonable agreement between the
complex geometry of embankment-trench system and measured and calculated vertical and horizontal
the use of material with different stiffness values stresses. The results shown in Fig. 5 indicate that the
around the load cells make the stress regime within the vertical stresses increased as the embankment height is
trench very complex both in field test and numerical increased. This increase ranges from 32 to 76 kPa for
analyses. Thus, the main objective is to show the PPM installation and from 20 to 40 kPa for ITM

Table 3 Measured and


North mid-slope North crest Center South crest South mid-
calculated deformations
(Point 1) (Point 2) (Point 3) (Point 4) slope (Point 5)

Field measurement
Baseline reading (m) 81.560 85.590 85.771 85.830 81.800
Final reading (m) 81.555 85.580 85.755 85.820 81.795
Deformation (mm) 5 10 16 10 5
Finite element 6 10 15 10 6
model results

123
Geotech Geol Eng (2013) 31:557–568 565

Fig. 5 Measured and calculated vertical stress at 1.5 m depth


Fig. 4 Vertical stress measured at the foundation-embankment
in trench (Cells 2 and 7)
interface

installation for embankment heights of 0 and 6 m,


respectively. The results indicate that 47 % reduction
in vertical stresses is achieved by the use of ITM
installation when the full embankment height is
accomplished.
The horizontal stress showed an inverse trend. The
results shown in Fig. 6 indicate that the increased
embankment height increased the horizontal stresses
from 10 to 27 kPa for PPM installation and from 25 to
31 kPa for ITM installation. The results indicate that
the use of ITM installation increased the horizontal
stresses relative to those generated by the PPM
installation. This increase is as high as 2.5 times at
the start of embankment construction. However, the
difference diminished as the embankment height
increased. The increase of horizontal stresses in ITM
case is attributed to the arching of stresses around the
compressible zone. Similar observations were made
by several researchers (Kang et al. 2007a, b; McGu-
igan and Valsangkar 2010, 2011).
The results also show that both vertical and Fig. 6 Measured and calculated horizontal stresses at 1.5 m
horizontal stresses measured/calculated at this depth depth in trench (Cells 1 and 6)

123
566 Geotech Geol Eng (2013) 31:557–568

monitoring point are substantially lower than the as the embankment height is increased. This increase
values one would practically approximate using the ranges from 70 to 140 kPa for PPM installation and
depth of overburden and the unit weigh of material. from 50 to 105 kPa for ITM installation for embank-
Such reduction is caused by lightly compacted ment heights of 0 and 6 m, respectively. The results
uniform granular surround, which has a substantially indicate that 25 % reduction in vertical stresses is
lower stiffness that reduced the magnitude of both achieved by the use of ITM installation when the full
vertical and horizontal stresses. embankment height is achieved.
The results shown in Fig. 8 indicate that the
5.2 Stresses Measured at the Bottom of the Trench increased embankment height resulted in higher
(3 m) horizontal stresses, which increased from 14 to
32 kPa for PPM installation and from 22 to 38 kPa
The measured stresses at 3 m depth in the trench (cells for ITM installation. The results show that the use of
3, 4, 8 and 9) and the corresponding value calculated ITM installation resulted in an increase in the
from the numerical analysis are shown in Figs. 7 and 8 horizontal stresses relative to those generated by the
for vertical and horizontal directions, respectively. use of PPM installation. This increase is as high as
The magnitudes of stresses at this depth are influenced 60 % at the start of embankment construction. How-
not only by the installation method (i.e. the existence ever, similar to the stresses at 1.5 m depth, the
of compressible zone in ITM) but also the stress difference diminished as the embankment height
arching caused by the lightly compacted fill above this increased. There is a sudden reduction of the stresses
location. The measured and calculated stresses (both in the field measurements of ITM case when the
vertical and horizontal) show a reasonable agreement embankment height reached around 3 m (mid-height).
at this depth as well. The results shown in Fig. 7 This reduction, which is recovered as the embankment
indicate that the measured vertical stresses increased height increased, may be attributed to a reading error.

Fig. 7 Measured and calculated vertical stresses at 3 m depth Fig. 8 Measured and calculated horizontal stresses at 3 m
in trench (Cells 4 and 9) depth in trench (Cells 3 and 8)

123
Geotech Geol Eng (2013) 31:557–568 567

It should also be noted that the difference between installation. The difference between horizontal
the horizontal stresses occurred at PPM and ITM cases stresses resulting from PPM and ITM were highest
is not as pronounced at this depth, possibly due to the at lower embankment height and diminishes as the
higher stiffness of well compacted granular surround. embankment height increases. This difference was
more pronounced at 1.5 m then it was at 3 m,
largely due to the lower stiffness of the surround
6 Summary and Conclusions material.
• It is noted that the stiffness of the granular
A full scale instrumented test embankment is con- surround has a significant impact on both vertical
structed by Ontario Ministry of Transportation in order and horizontal stresses. The lightly compacted
to study the effects of embankment construction on the granular surround encapsulating the load cell at
existing underground utilities. The test embankment 1.5 m had a smaller value of stiffness, which
comprised four sections, which facilitated the evalu- resulted in significant reductions in both vertical
ation of four different configurations including the and horizontal stresses. Thus, it is anticipated that a
conventional backfill, induced trenching and two at- lightly compacted backfill encapsulating the cul-
grade geogrid reinforcing bridging with different verts may result in such reduction.
spans. Each configuration consisted of a 3 m deep
trench underneath a 10 m wide, 10 m long and 6 m Acknowledgments The authors acknowledge the valuable
high embankment section. Earth pressure cells were contributions by the reviewers and the support provided by the
installed to monitor stresses at the fill/ground interface Ontario Ministry of Transportation, Material Engineering and
and at the depths of 1.5 and 3 m. A numerical model of Research Office.
the full scale instrumented test embankment is devel-
oped using the finite difference program FLAC. The
References
numerical model incorporated the measured and
estimated material properties of the induced trench, AASHTO (2007) LRFD bridge design specifications, 4th edn.
and was utilized to analyze the stress conditions within American Association of State Highway and Transporta-
and around the trench, and to further understand the tion Officials, Washington, DC
trends of changes in stresses as a result of installation ACPA (1980) ACPA concrete pipe handbook. American Con-
crete Pipe Association, Vienna, VA
methods. This paper presents the results of stress ACPA (1998) ACPA concrete pipe handbook. American Con-
measurements in a utility trench overlain by an crete Pipe Association, Irving, TX
embankment. The measurements that were obtained ACPA (2001) ACPA concrete pipe handbook. American Con-
both during and after construction of the full-scale test crete Pipe Association, Vienna, VA
ACPA (2004) ACPA concrete pipe handbook. American Con-
embankment were compared with the results of the crete Pipe Association, Vienna, VA
numerical model, which helped clarify mechanisms of Bourque S (2002) Centrifuge and numerical modeling of
stress reduction. induced trench twin conduits. M.Sc.E. thesis, University of
The following is a summary of the results and New Brunswick, Fredericton, NB
Brown CB (1967) Forces on rigid culverts under high fills.
conclusions arising from this study: J Struct Div ASCE 93(5):195–215
• The vertical and horizontal stresses at trench Canadian Standards Association (2006) Canadian highway
bridge design code. CSA-S6-06
depths of 1.5 and 3 m increased with increasing Duncan JM, Chang CY (1970) Nonlinear analysis of stress and
embankment height. strain on soils. J Soil Mech Found Div 96(5):1629–1653
• When full embankment depth was reached, use of Floyd KJ, Clark RE (1979) Construction and instrumentation of
ITM resulted in a 47 % reduction in vertical induced experiment under high fill. State of Illinois
Department of Transportation, Springfield, Il. Interim
stresses at 1.5 m depth relative to the vertical report IHD-19
stresses resulting from PPM installation. This Handy RL (2004) Anatomy of an error. J Geotech Geoenviron
reduction remained at 25 % at 3 m depth. Eng (ASCE) 130(7):768–771
• The use of ITM installation method resulted in an Hansen P, Miller L, Valsangkar AJ, Bourque S, MacLeod T
(2007) Performance of induced trench culverts in New
increase in horizontal stresses relative to the Brunswick. In: Proceedings of the annual conference of the
horizontal stresses resulting from the use of PPM Transportation Association of Canada, Saskatoon, Sask.,

123
568 Geotech Geol Eng (2013) 31:557–568

14–17 Oct 2007. Transportation Association of Canada, McAffee RP, Valsangkar AJ (2008) Field performance, centri-
Ottawa, Ont fuge testing, and numerical modelling of an induced trench
Hardin BO (1971) Characterization and use of shear stress-strain installation. Can Geotech J 45:85–101
relations for airfield subgrade and base course material. McGuigan BL, Valsangkar AJ (2010) Centrifuge testing and
AFN-TR-71-60, Air Force Weapons Laboratory, Kirkland numerical analysis of box culverts installed in induced
AFB, NM trenches. Can Geotech J 47(2):147–163
Itasca Consulting Group (2005) FLAC, Fast Lagrangian anal- McGuigan BL, Valsangkar AJ (2011) Earth pressures on twin
ysis of continua, Version 5.0, Itasca Consulting Group, positive projecting and induced trench box culverts under
Minneapolis, Minnesota high embankments. Can Geotech J 48(2):173–185
Kang J (2007) Soil-structure-interaction and imperfect trench Okabayashi K, Ohtani W, Akiyama K, Kawamura M (1994)
installation applied to deeply buried conduits. PhD thesis, Centrifugal model test for reducing the earth pressure on
Auburn University, Auburn AL, USA the culvert by using the flexible material. In: Proceedings
Kang J, Parker F, Yoo C (2007a) Soil-structure interaction and of the 4th international offshore and polar engineering
imperfect trench installations for deeply buried concrete conference, Osaka, Japan, 10–15 April 1994. International
pipes.’’. J Geotech Geo-environ Eng ASCE Society of Offshore and Polar Engineers, Cupertino, Calif.
133(3):277–285 pp 620–624
Kang J, Parker F, Yoo C (2007b) Soil-structure interaction and Parker BA, McAffee RP, Valsangkar AJ (2008) Field perfor-
imperfect trench installations for deeply buried corrugated mance and analysis of 3-m-diameter induced trench culvert
PVC pipes. Transp Res Rec TRB 2028:192–202 under a 19.4-m soil cover. Transp Res Rec 2045(08):68–76
Katona MG, Smith JM, Odello RS, Allgood JR (1976) Scario JH (2003) Reappraisal of Marton’s formula. J Transp Eng
CANDE—a modern approach for the structural design and (ASCE) 129(6):703–712
analysis of buried culverts. FHWA-RD-77-5, Federal Sladen JA, Oswell JM (1988) The induced trench method—a
Highway Administration, Turner-Fairbank Highway critical review and case history. Can Geotech J 25:541–549
Research Center, McLean, Va Spangler MG (1950a) A theory of loads on negative projecting
Kim K, Yoo CH (2005) Design loading on deeply buried box conduits. Proceedings of the Highway Research Board, 30,
culverts. J Geotech Geoenviron Eng 131:20 Transportation Research Board, Washington, DC,
Kondner RL (1963) Hyperbolic stress–strain response: cohesive pp 153–161
soils. J Soil Mech Found Div ASCE 98(1):115–143 Spangler MG (1950b) Field measurements of the settlement
MacLeod T (2003) Earth pressures on induced trench conduits. ratios of various highway culverts, Bulletin 171. Iowa
M.Sc.E. thesis, University of New Brunswick, Fredericton, Engineering Experiment Station, Ames, IA
NB Spangler MG, Handy RL (1973) Loads on underground con-
Marston A (1922) Second progress report to the joint concrete duits, soil engineering, 3rd edn. Harper Collins, New York,
culvert pipe committee. Iowa Engineering Experimental pp 658–686
Station, Ames, IA Spangler MG, Handy RL (1982) Soil engineering, 4th edn.
Marston A (1930) The theory of external loads on closed con- Harper and Row, New York
duits in the light of the latest experiments. Bulletin 96. Sven N, Liedberg D (1997) Load reduction on a rigid pipe pilot
Iowa Engineering Experiment Station, Ames, IA study of a soft cushion. Transp Res Rec 1594:217–223
Marston A, Anderson AO (1913) The theory of loads on pipes in Vaslestad J (1990) Soil structure interaction of buried culverts.
ditches and tests of cement and clay drain tile and sewer PhD thesis, The Norwegian Institute of Technology,
pipe. Bulletin 31. Iowa Engineering Experiment Station, Norway
Iowa State College, Ames, IA Vaslestad J, Johansen TH, Holm W (1993) Load reduction on
McAffee RP (2005) Soil-structure interaction in rigid culverts rigid culverts beneath high fills: long-term behavior.
installed in induced trenches. Ph.D. thesis, University of Transportation Research Record, 1415, Transportation
New Brunswick, Fredericton, NB Research Board, Washington, DC, pp 58–68
McAffee RP, Valsangkar AJ (2005) Performance of an induced
trench installation. Transp Res Rec 1936(1):230–237

123

You might also like