Copyright 2004 and 2005 AIA MASTERSPEC Outline 05/04 (R 05/05)

SECTION 024116 - STRUCTURE DEMOLITION

0.1 SUMMARY

A. Demolition and removal of buildings[ and site improvements].

0.2 QUALITY ASSURANCE

A. Quality Standard: ANSI A10.6 and NFPA 241.

0.3 PROJECT CONDITIONS

A. Hazardous Materials: [Removed prior to start of the Work] [Remediation specified


elsewhere in Contract Documents].

0.4 MATERIALS

A. Satisfactory Soils: Division 31 Section "Earth Moving."

0.5 EXAMINATION

A. [Perform] [Engage a professional engineer to perform] an engineering survey of condition of


building.

0.6 PREPARATION

A. Refrigerant: Remove according to 40 CFR 82.

B. Utility Shut Off: [Owner] [Contractor] [Divisions 15 and 16].

0.7 DEMOLITION

A. Use of explosives is[ not] permitted.

B. Salvage: Items to be salvaged and delivered to Owner are indicated [on Drawings.] [below:]

1. <Insert items to be salvaged.>

C. Below-Grade Construction: [Abandon] [Demolish within 5 feet (1.5 m) of building


footprint] [Demolish completely].

1. Remove [completely] [to at least 6 inches (150 mm) below grade] [to at least 12
inches (300 mm) below grade] [to depths indicated].

STRUCTURE DEMOLITION 024116 - 1


Copyright 2004 and 2005 AIA MASTERSPEC Outline 05/04 (R 05/05)

D. Existing Utilities: [Abandon] [Demolish within 5 feet (1.5 m) of building footprint]


[Demolish completely].

0.8 SITE RESTORATION

A. Below-Grade Areas: [Rough grade] [Fill].

0.9 DISPOSAL OF DEMOLISHED MATERIAL

A. Remove demolished material from site and dispose of [according to Division 01 Section
"Construction Waste Management and Disposal."] [in an EPA-approved landfill.]

END OF SECTION 024116