Project Name:
Document Description:
Location: Substation
Equipment Description: Over Current & Earth Fault Relay of Bus Coupler
Relay Checks:
Items Status
Visual Inspection
Relay Damaged
Rating Information
Case Earth Installed
Test Block connection checked
Relay Energized
Measurement Checks
Input CT Ratio Injected Current (A) Calculated Current (A) Measured Current (A)
AB
BC
CA
ABC
Note: During the testing of ABC fault, C.B tripping was confirmed.
Model/ Type:
Manufacturer:
Serial No: