Data magnetics Technologies

Inventory Management and Point of Sale

Estimation Document

Date: 02-04-2019

Please see the below estimates for different stages for development for this project. Our first goal is to get a solid
scope and design document and have developers a clear point of view of what they are going to develop.

Activity Time (Working Days) Date


Information Gathering (all members) 3 02 to 05-04-2019
Scope Document (parallel Working: Usman, 5 02 to 09-04-2019
Nauman)
Design Document (Raees Collaboration for screen 10 10 to 23-04-2019
designs) (Usman, Dev team, Nauman)
Database Design and Class Diagrams (parallel 10 10 to 23-04-2019
Working: Usman and Dev Team)
Iteration 1: Development of Inventory Screens To be calculated after To be calculated after
layout seeing capability of seeing capability of
developers developers
Iteration 2: Development of Inventory Back end To be calculated after To be calculated after
Development seeing capability of seeing capability of
developers developers
Iteration 3: Development of Sale module front end To be calculated after To be calculated after
Development seeing capability of seeing capability of
developers developers
Iteration 4: Development of sale Back end To be calculated after To be calculated after
Development seeing capability of seeing capability of
developers developers