Professional Documents
Culture Documents
Revision History
3 20Oct2014 Updated Section 6.7.1, Definitions of High Risk Work licence T Knight K. Rolls M. Collins
responsibilities for licensed Basic, Intermediate and Advanced
Rigger classes.
4 11 Aug 2015 Revision of 6.4.1 to include requirements of pick and carry M Collins M Collins M Collins
operations with side slopes >2.50
5 6 Oct 2015 Updated section 6.1.8b Inclination Factors. N. Kidd M Collins M Collins
This document remains the property of McConnell Dowell Corporation. Its contents are confidential and shall not be reproduced,
destroyed or given away without the express, written permission of McConnell Dowell Corporation. The electronic version of this
document in MMS Database on designated server(s) is the Master Copy and is a controlled document. Unless specifically noted
thereon, other copies of this document are uncontrolled. Based on MMS Template# 010-J011-000 Rev3 2Oct2014
COMMERCIAL-IN-CONFIDENCE
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
TABLE OF CONTENTS
1 PROCESS SUMMARY .................................................................................................................... 6
2 OBJECTIVES .................................................................................................................................. 6
3 DEFINITIONS .................................................................................................................................. 6
4 RESPONSIBILITIES ........................................................................................................................ 6
4.1 Project Manager (PM) ............................................................................................................... 6
4.2 Senior Project OHS representative (SPOHSR) .......................................................................... 6
4.3 Superintendents and Supervisors (S) ........................................................................................ 7
4.4 McConnell Dowell and subcontractor personnel ........................................................................ 7
4.5 Contracts and Procurement Personnel ...................................................................................... 7
4.6 Crane Lift Supervisor ................................................................................................................ 7
5 PROCESS DESCRIPTION .............................................................................................................. 7
5.1 Plan the Job .............................................................................................................................. 7
5.1.1 Review legislation, standards, other related MCD SOPs and Project Risk Register ............. 7
5.1.2 Select lifting equipment that is fit for purpose ...................................................................... 8
5.1.3 Identify licence or competency requirements for crane and lifting personnel ....................... 8
5.1.4 Select Plant operators ........................................................................................................ 9
5.1.5 Initial inspection and approval to bring plant on site ...........................................................10
5.1.6 Report defects...................................................................................................................10
5.1.7 Statutory plant inspections ................................................................................................10
5.1.8 Develop a plant maintenance schedule .............................................................................11
5.1.9 Arrange maintenance and refuelling ..................................................................................11
5.2 Do the Job ...............................................................................................................................12
5.2.1 Plan the lift ........................................................................................................................12
5.2.2 Daily plant inspections.......................................................................................................12
5.2.3 Report defects...................................................................................................................12
5.2.4 Prepare work area and evaluate weather ..........................................................................13
5.2.5 Conduct the lift ..................................................................................................................13
5.3 Supervise and Monitor Lifting Operations .................................................................................13
5.3.1 Supervise the lifting operation ...........................................................................................13
5.4 Take action when safety risks are identified..............................................................................13
5.4.1 Report and Take Action.....................................................................................................13
6 TECHNICAL STANDARDS .............................................................................................................14
COMMERCIAL-IN-CONFIDENCE PAGE 2 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
COMMERCIAL-IN-CONFIDENCE PAGE 3 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
COMMERCIAL-IN-CONFIDENCE PAGE 4 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
COMMERCIAL-IN-CONFIDENCE PAGE 5 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
1 PROCESS SUMMARY
To manage crane and lifting operations in order to minimise or eliminate the risk of injuries, fatalities and
incidents
This Safe Operating Procedure addresses the following MCD Golden Rules:
2 OBJECTIVES
This procedure applies to all crane and lifting activities conducted on land within McConnell Dowell
controlled sites and activities, and to all McConnell Dowell employees, contractors and visitors when
involved in crane and lifting operations.
3 DEFINITIONS
Competent Person – A person, who has through training, qualification, experience, or a combination of
these, has the knowledge and skill enabling them to correctly perform the required tasks.
Lifting equipment – Any equipment or device used or designed to be used directly or indirectly to
connect a load to a crane and which does not form part of the load e.g. Wire rope slings, chain slings,
synthetic fibre slings, hooks, fittings, swivels, shackles, eye bolts, rigging screws, wedge sockets, plate
clamps and lifting beams.
SWL – Safe Working Load
WLL – Working Load Limit
4 RESPONSIBILITIES
4.1 PROJECT MANAGER (PM)
COMMERCIAL-IN-CONFIDENCE PAGE 6 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
• Monitor compliance with the procedure and report noncompliance to the Project Manager
• Prepare and supervise crane and lifting operations in accordance with this procedure
• Ensure that sufficient resources are available to conduct a safe lift
• Make sure that all purchased or hired-in lifting equipment to be used on MCD projects, complies
with the relevant standards of the country, and is fit for purpose.
• All contracts awarded comply fully with the requirements and intent of this procedure.
5 PROCESS DESCRIPTION
5.1 PLAN THE JOB
5.1.1 Review legislation, standards, other related MCD SOPs and Project Risk Register
Review the Project OH&S Legal & Other Start of project SPOHSR Project OH&S Legal &
Requirements to identify any legislation that is Other Requirements
relevant to this procedure
Refer to Compliance with
Legal & Other
Requirements
(MMS # 000-D004-000),
and Project Compliance
with Legal & Other
Requirements
(MMS # 300-E012-100).
COMMERCIAL-IN-CONFIDENCE PAGE 7 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
5.1.3 Identify licence or competency requirements for crane and lifting personnel
Once the types of cranes to be used on the project Commencement SPOHSR Crane operators must hold
are known, the specific licence requirements to of project and appropriate certification or
operate these vehicles are identified. ongoing license for the country state
Record the licence and competency requirements throughout project or region relevant to the
project
See Appendix A –
Certificates of Competency
(below) for Australian
competency tickets
Record any licence
requirements in Project
Training Plan – Legislation
Compliance
Identify the specific licence requirements for the Commencement SPOHSR See Appendix A –
range of persons assisting crane operations of project and Certificates of Competency
Record the licence and competency requirements ongoing (below) for Australian
throughout project competency tickets.
Identify whether any additional training is required to Commencement SPOHSR Difficult site conditions may
operate the plant of project and mean that operators need
ongoing additional training even
throughout project though they have the
requisite licenses.
COMMERCIAL-IN-CONFIDENCE PAGE 8 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
Rescind the authority to operate plant As soon as Supervisor Where there is a medical
management SPOHSR condition the issue is to be
becomes aware discussed with the
employee before any
decision is made.
COMMERCIAL-IN-CONFIDENCE PAGE 9 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
Write-down all defects and damage in the inspection As required Plant operator Mobile Equipment Daily
report. Inspection Report
If the defect requires immediate attention or (MMS # 045-F030-100).
endangers the safety of employees, phone the
supervisor immediately.
If plant is unsafe to operate tag with an ‘Out of Immediately Supervisor Refer to procedure Tagging
Service’ tag. and Locking (MMS # 020-
E015-100)
Arrange for repairs. As required Supervisor
Identify any statutory requirements for Plant At project SPOHSR See 6.5 Maintenance,
inspection or any requirements listed in relevant commencement Lifting Inspection and repairs –
Standards Supervisor Crane (below) for MCD
requirements
See 6.9 Maintenance,
Inspection and repairs --
Rigging and lifting
Equipment (below) for MCD
requirements.
Record any statutory
inspection requirements in
Project Legal & Other
Requirements (MMS #
020-J004-YYYY and MMS
# 025-J001-YYYY)
Schedule inspections on the project plant At project SPOHSR Project plant maintenance
maintenance and inspection schedule commencement and inspection schedule
Arrange inspections See schedule SPOHSR Record completed
inspections in the project
plant register
COMMERCIAL-IN-CONFIDENCE PAGE 10 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
COMMERCIAL-IN-CONFIDENCE PAGE 11 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
Develop the lift plan. When planning the Supervisor See section 5.11(below) for
lift MCD lift plan requirements
Obtain the Ground Load Bearing Capacity When planning the Supervisor See section 6.13 (below) for
Calculations for Outrigger placement lift MCD requirements
Identify additional equipment required When planning the Lift Supervisor
lift
Develop Safe Work Method statement (SWMS) Prior to the lift Supervisor
Communicate SWMS to workgroup Prior to the lift Supervisor
Set up crane and inspect crane and all lifting Prior to the lift Lift Supervisor See section 6.1 (below) for
equipment inspection requirements
after crane has been
mobilised.
Lift and place the load Supervisor See sections 6.8 (below) for
Rigger MCD requirements on
executing the lift.
COMMERCIAL-IN-CONFIDENCE PAGE 12 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
Observe the lifting operations of both MCD Ongoing Supervisor Monitor compliance with this
employees and contractors Rigger standard.
Conduct regular inspections of lifting operation Weekly Lift Supervisor Check that a JSEA/SWMS
Supervisor has been completed for the
Rigger job. Stop the job if no
JSEA/SWMS is available.
SPOHSR
Refer to HSE Inspections
and monitoring (MMS #
020-D010-100).
COMMERCIAL-IN-CONFIDENCE PAGE 13 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
Report inappropriate or unsafe operations involving As required All site Complete hazard report
crane use and lifting operations management form
and
employees
6 TECHNICAL STANDARDS
6.1 CRANE SELECTION AND PLANNING
Before selecting a crane for service, the following criteria are to be taken into account:
• The result of an appraisal of an existing crane, if applicable.
• The maximum permitted forces on the supporting structure.
• Power supply.
• Rated capacity of the crane.
• Classification of the crane taking into account the application, including;
- type of loads to be lifted;
- mass of loads to be lifted;
- speed of lifts; and
- frequency of lifts.
• The maximum load that will be imposed on the crane.
• The maximum load moment that will be imposed on the crane.
• The nature of the rigging or slinging to be used.
• The position from which the load is to be lifted.
• The position in which the load is to be placed.
• The movement limitations of the crane and the load.
• Other limitations of the crane.
• Multiple crane lifting.
• Working environment including hazardous gases, corrosive atmospheres and high ambient
temperatures including full speed operation against in-service wind load.
• Projected upgrades of plant.
• The provision of additional crane capacity to cater, where necessary, for changes in the site
environment, for example, increases in lifted load mass due to manufacturing tolerances, rapid
changes in weather conditions.
COMMERCIAL-IN-CONFIDENCE PAGE 14 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
6.1.1 Pre-Mobilisation
• Selection of cranes
• Lightning protection
• Earthing for the conditions – e.g. static build up due to EMR, wind etc
• Site access and crane siting
• Safety of personnel and public entering into the site and the lift area
• Procedures for setting up of the crane
• Procedures for lifting operations
• Procedures for dismantling of the crane
• Selection of the personnel
• Communication systems(s)
• Weather conditions
• Ground conditions
• Proximity of excavations
• Selection of lifting gear to the appropriate standards
• PPE requirements
• Emergency procedures
• Procedures for non-routine lifts – Multiple Lifting Operations
• For multiple crane lift MCD Insurance underwriters require notification
• Night Operations
• Parking & Storage facilities for crane components
• Marking of crane and ancillary equipment e.g. rated capacity, safety signs
• Access for servicing
• Interface with existing plant and traffic
• Obtaining of approvals from statutory authorities or other relevant parties
• Appraising an existing crane for suitability for use, and ensuring that the appraisal is carried out by
a competent person.
• Suitable equipment is available for the installation, maintenance, operation and dismantling of the
crane.
• Condition monitoring of the crane and associated equipment.
• The maintenance, inspection and safe operation of the crane and associated equipment.
• The preparation, availability and maintenance of instructions for the assembly, operation,
maintenance and inspection of the crane.
• For Heavy Lifts, e.g. Bridge Beams; Tilt-up Panels and other lifts where the load is 50 tonnes or
more, certification of the ground bearing capacity must be obtained from a geo-technical engineer
before performing a lift.
• A competent person must make sure that loads imposed by the crane can be sustained by the
ground or any other means of support and that the crane can operate within the levels and other
parameters specified by the manufacturer.
• Where the crane is required to work in the vicinity of an excavation or an embankment, the
possibility of slip or collapse of the supporting surface is to be evaluated by a competent person –
and where applicable the embankment or excavation is to be reinforced.
• Loads are not to be imposed on any new concrete supporting structure until the structure has
reached sufficient strength.
• An assessment should be carried out by a structural engineer when planning to position a crane
on a suspended surface. A suspended surface could include but not limited to the following;
suspended concrete slabs, wharfs, jetties, barges or any other instance where the surface integrity
or rating is unknown.
• The assessment should ensure that the supporting surface is capable of supporting loads imposed
by the crane, and the loadings it would apply to the supporting surface during its proposed
operation.
• The structure needs to be assessed during various stages of the job, including driving to the set up
location on the structure, set up, use and, if different or the structure is changed during the job,
dismantling and removal of the crane.
• Where there is a requirement to use a propping system for the supporting structure, a structural
engineer must advise of the correct location and ensure the design considers all loading factors
that will be imposed upon it. A competent site representative is to ensure the propping system is
functioning and maintained in line with the engineer’s advice.
• If the crane cannot be set up in the planned location than full assessment is to reoccur.
• Assessment items to address, but are not limited to the following include;
- Crane model
COMMERCIAL-IN-CONFIDENCE PAGE 16 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
- Crane configuration
- Any crane de-ratings
- Maximum outrigger loadings
- Type of dunnage to be placed under outriggers
- Principal Contractor details and representative
- Structural Engineer completing assessment
• The crane operator has the right to refuse to operate, where the above assessment cannot be
validated and provided on site.
Prior to commencing crane and lifting operations the Crane Operator is to review the prevailing weather
conditions (wind speed and direction, visibility, etc.). Crane and lifting operations shall not commence if the
weather or environmental conditions are likely to jeopardise the safety of the activity – refer to Appendix F
Adverse Weather Guidelines, for a comprehensive guide to the effects of varying wind speeds on land and
water.
Crane and lifting operations occurring in a marine environment may be subject varying conditions (such as
swell or unexpected wave action) which have potential to shock or dynamic load lifting plant and equipment,
particularly when loading or unloading equipment to and from barges or vessels.
If a load suddenly comes onto the lifting equipment, or if a load being lowered is suddenly stopped, the
weight of the load borne by the equipment is effectively increased. The movement of the vessel and the
hoist motion of the crane can combine to produce severe dynamic loading of up to three times the static
weight of the load.
Shock loading is not only experienced by the crane: the lifting accessories between the load and crane will
also be subject to increased loading and, in the case of chains, shackles, etc. this may result in deformation
known as permanent set.
Twist may be induced in lifting equipment leading to the whole lifting assembly becoming tangled and
shackles becoming jammed in their attachment points. Such deformation prevents the shackles being
pulled into line with the sling and they become loaded in the wrong direction.
In addition, the length of the slings can become uneven, causing unequal load distribution.
The inherent risks associated with lifting operations in a marine environment, including the dynamic loading
described above, mean that agreed requirements in the risk assessment are adhered to.
Crane lifting operations on floating barges and vessels are inherently dangerous activities and McConnell
Dowell requires the highest standards of planning and operation when these activities are being
performed.
The requirements of all relevant local legislation and regulations are to be complied with in all
circumstances
The crane manufacturers’ requirements for operating their specific cranes on floating barges and vessels
must always be followed.
COMMERCIAL-IN-CONFIDENCE PAGE 17 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
Cranes will be tied down in all conditions except within smooth water limits, and only where site specific
conditions permit. In such situations a documented risk assessment must be undertaken. The risk
assessment is to fully describe the particular activity or lift to be performed and when and how the crane
can be used without the tie downs.
Cranes on barges shall be appropriately de-rated for all conditions.
Where a project specific assessment shows that an amendment to the guidelines below is warranted,
such an amendment is to be considered for that project only.
The tie down system for a crane shall be designed for the following loads:-
1. Smooth Waters – 0.1g lateral force in any direction;
2. Partially Smooth Waters - 5° heel, 2.5° trim, 0.1g heave, 0.1g lateral force in down
heel/trim direction;
3. Other areas – special analysis is required by independent certified naval architect.
Friction between the crane and the barge is not to be taken into account to mitigate these forces.
COMMERCIAL-IN-CONFIDENCE PAGE 18 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
These provisions do not apply to any coastal or ocean tow, any tow longer than 4 hours in duration, any
extreme environmental event (e.g. cyclones) or any operations outside of Inshore Operational Areas. Tie
downs/sea fastenings are to be specifically designed for such tows.
Refer to USL Code of Australia for definitions.
• The crane will only be operated within the rated capacity and design classification
• Power supply is compatible with the crane requirements (Gantry Cranes)
• Clear safe and defined pathways for cranes operated by pendant or wireless control is to be
provided and maintained (Gantry Cranes)
• All cranes are to be kept clean
• Tools and loose objects are to be stowed and secured
• The crane is to be inspected in accordance with the Operations and Maintenance Manual and/or
local regulatory requirements
• The crane is to be inspected daily by the crane operator to identify maintenance or repair items that
may affect the efficient or safe operation of the crane.
• The SWL is to be stencilled on the crane.
• All cranes be fitted with “Christmas Tree Lights”
• No repair work or maintenance or refuelling is to be carried whilst the crane is operating.
• Only one competent person (certified dogman/ rigger or local equivalent) is to give signals to the
crane operator.
• Persons entering a crane operating area must make contact and be acknowledged by the person
in charge of the area prior to entering the area. Crane operators should never be approached
directly.
• Barricades or guarding may be required where necessary.
• The crane is not to be left unattended in the operating mode.
• The crane driver is to be familiar with any electrical power cables or conductors in the lift area and
any other potential hazard.
• Clearances are to be maintained and procedures developed to prevent unplanned contact between
any parts of cranes working in the same site (refer to AS 1418 or AS 2550)
• The crane driver is not to use a mobile telephone whilst operating the crane.
• When travelling a crane without a load, all chains and slings must be removed from the hook unless
it is either tied to the crane to ensure it cannot bounce or twist: or independently tied back to the
hook in such a way that any possible dislodgement caused by the movement of the jib is prevented.
6.2.2 Competency
• The crane operator is to hold a valid license and/or certification, specific to the type and size of the
crane and/or lifting equipment that is been used.
• All operators who operate any crane are to be familiar with the following:
- Safe operation of the particular crane
- Locations and operation of all safety backup systems
COMMERCIAL-IN-CONFIDENCE PAGE 19 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
6.3 COMMUNICATION
At all times, there is to be adequate communication between all personnel involved in the lifting operation.
Either hand signals or radio equipment appropriate for the relevant lifting operation is to be used.
Crane Operators and dogman/ riggers or local equivalent must be familiar with the system of signalling
being used for the operation. The signals presented in Appendix C are recommended for adoption in
Australia. The local equivalent should be consulted when operating outside of Australia.
The Crane Operator must:
• Ensure that the signalling system to be used is clearly agreed between the crane crew prior to
commencing any crane and lifting activities.
• Only respond to signals given by the dogman/ rigger or local equivalent or ‘STOP’ when given a
signal by other persons in an emergency situation.
• Maintain visual contact with the dogman/ rigger or local equivalent at all times.
• Cease lifting operations if contact is lost and only recommence when a clear line of communication
is re established.
• Cease crane operations if inclement weather or darkness impairs the ability to see the dogman/
rigger or and operations cannot continue safely.
The Crane Operator is to reach a clear understanding with the dogman/ rigger or local equivalent before
lifting operations begin on the protocols to be used.
If there is any interruption to the communication (e.g. third-party transmission) the Crane Operator must
STOP the lifting operation immediately, only resuming when communication with the dogman/ rigger or
local equivalent is re-established.
Radio checks shall be carried out prior to the start of the lifting operation. When directing the load,
instructions shall be clear and precise.
Where appropriate, a communication method can be used whereby the signaller gives a continuous signal
to continue the movement. The equipment operator shall stop immediately if he does not receive the signal.
During periods of no radio communication, all lifting operations should be reviewed with suitable controls
identified and agreed by personnel involved to enable safe execution of the operation.
The following protocol is recommended for radio communication during lifting operations:
• Call signs should be set up and adhered to.
COMMERCIAL-IN-CONFIDENCE PAGE 20 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
• Call signs must be used at all times to establish the authenticity of commands or directions.
• At the end of an instruction or enquiry the transmitting operator should indicate the end of the
message by the command ‘over’.
• The receiving operator should indicate understanding of any dialogue through the response ‘roger’.
• Under no circumstances should the transmitting operator assume understanding without
acknowledgement (‘roger’) from the receiving operator.
• If the receiving operator is unsure regarding a message, the operator must not acknowledge but
should repeat the message as he understands it and ask for confirmation or simply request the
transmitting operator to repeat.
• At the close of communication the transmitting operator should indicate the end of the transmission
with the command ‘over and out’.
• For single function operations the dogman/ rigger or local equivalent should relay to the Crane
Operator using terminology such as: ‘up on the hoist’, ‘Boom up’, ‘Slew right’, etc. Where it is
necessary to carry out an operation slowly the dogman/ rigger or local equivalent should instruct
the Crane Operator accordingly. To stop a function the dogman/ rigger or local equivalent should
instruct the Crane Operator to ‘Stop’. To stop all operations the dogman/ rigger or local equivalent
should instruct the Crane Operator with ‘All stop’.
• For simultaneous function operations the dogman/ rigger or local equivalent should relay to the
Crane Operator using terminology such as: ‘Come up on the load and boom down’, etc. To stop a
function the dogman/ rigger or local equivalent should instruct the Crane Operator to ‘Stop on the
boom, slew right only’, etc. To stop all operations the dogman/ rigger or local equivalent should
instruct the Crane Operator with ‘All stop’.
• Under no circumstances should profane language be used while transmitting.
• Should the radio antenna become damaged exposing the central core, the antenna must
immediately be replaced in order to maintain not only optimum performance but to ensure user
safety.
• Radio messages should reflect work requirements only; general conversation should not be carried
out over the air waves.
• Always ensure that you fully depress the transmission button before speaking into the microphone.
Speak clearly at all times and do not release the button until a few seconds after completing your
message.
• When directing the crane, ensure that any accompanying colleagues’ radios are switched off – if
more than one radio is switched on in close proximity interference and distortion of the signal will
take place when an instruction is transmitted.
• During blind lifts when the load is being hoisted or lowered for a long time do not maintain the
transmission button in the depressed position for the duration of the lift – the dogman/ rigger or
local equivalent should give the initial instruction and then talk to the Crane Operator as required
to reassure the Operator that the line of communication is still active and that the lift remains under
control.
• During high winds, ensure that the area of the microphone you speak into is not exposed to the
wind as background noise created may distort the transmission.
• Ensure that the radio microphone is not exposed to rain. If a plastic carrying case offering full
protection of the radio is not available, a simple precautionary measure such as a small plastic bag
or a piece of cling film around the microphone will ensure that it remains dry.
COMMERCIAL-IN-CONFIDENCE PAGE 21 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
• Do not carry the radio in a pocket always ensure that they are carried on the body by either a belt
clip or protective holster. Consider using the protective holster when working at height or climbing
ladders to ensure that the radio does not become a dropped object if dislodged.
• No person is to walk between the load and the crane whilst the load is being carried on site roads
or within any work area.
• Dogman/ Riggers are to escort the cranes when travelling with loads on site, and must not travel in
the crane cab under any circumstances.
• Use of tag lines to tie load to crane at >2.5o side slope gradients is prohibited.
• When travelling without a load, the hook block is to be secured to prevent swinging and damage to
boom sections. Where this is impractical the hook block should be held fast against the boom head.
• Loads are to be kept as close to the ground as possible when travelling.
• If unstable ground conditions or obstructions in travel path are present, the control methods for
these hazards are to be included in a specific JSEA.
Pick and Carry cranes shall be de-rated as follows:
• 0.0 – 0.6 o manufacturer approved load charts and specifications apply.
• >0.6 – 2.5 o de rate in line with manufacturer approved load charts and specifications.
• >2.5 - <5.0 o de rate by a full 60% of normal SWL capacity, regardless of boom position and
length*.
• >5.0 o the activity is to cease and be reassessed to identify another means of load lifting or
transportation.
* Additional MCD safety factor exceeding manufacturer’s instructions
• All multiple crane lifts are to comply with the relevant Australian Standard as a minimum
• Other than for designed lifts, lifting operations using two or more cranes will use cranes of the same
type.
• The following minimum capacity requirements for each crane is to apply (where hoisting operation
is not designed):
• For 2 cranes - 20% greater than the calculated share of the load.
• For 3 cranes - 33% greater than the calculated share of the load.
• For 4 or more cranes- 50% greater than the calculated share of the load.
• Where load is suspended from more than one hoist line the load must be handled in such a way
that:
- The rated load for each line is not exceeded
- The load being handled does not exceed the rated capacity of the crane.
- Supervision is to be provided by a competent person, who is not one of the crane operators.
COMMERCIAL-IN-CONFIDENCE PAGE 22 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
• Crane and crab motions are to be synchronised or one crane placed in free slew mode
• To allow for the probability of the motions of the cranes or crabs not being accurately synchronized,
particularly if the cranes or crabs have dissimilar operating characteristics, the operation must be
performed at slow speeds with extreme care being exercised to maintain the hoist ropes as close
to vertical as possible.
• NOTES:
- 1. The rated capacity of a crane is calculated on the assumption that the load will be raised and
lowered in a vertical plane. The crane structure will have been designed to withstand any lateral
loads imposed by accelerations in the various crane and crab motions, but it is unsafe to rely
on this lateral strength to withstand horizontal components of non-vertical lifts.
- 2. In practice, there will always be some variation due to differences in response to the
activation of the motion controller and the setting and efficiency of the braking system
• In pick and carry operations, the axis of both or all cranes or crabs is to be kept aligned in the same
direction where possible. The possibility is that once out of alignment especially during cornering;
the movement of one crane or crab may push or pull either the other crane(s) or crab(s) and cause
loss of stability. Load chart limitation during articulation is to adhered to
• NOTE: Instruments are available to monitor constantly the angle of the load, and the verticality and force in
each hoist rope throughout the lifting operation. Their use is recommended.
• Tag lines must be used on loads when in pick and carry operations with the exception of dual crane
operations
• Cranes will not pick and carry loads on a fly or with a fly in the un-stowed position
• Dual crane pick and carry is a critical lift requiring a lift study
6.4.3 Controls
• All lifts require JSEA/SWMS to be completed and reviewed by the Crane Crew and responsible
Supervisor prior to commencing the activity.
COMMERCIAL-IN-CONFIDENCE PAGE 23 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
• Lifting of persons in workboxes (Refer MMS Safe Operating Procedure # 020-T003-100 Workbox
Use).
• Working near overhead power lines (Refer MMS Safe Operating Procedure # 020-T009-100 –
Overhead Power Lines)
• Documentation specific to the operation being carried out should accompany the Crane Lift Plan.
This includes items such as erection sequences, relevant drawings, fixings etc.
Crane Lift Plans are to show weight, radius, crane capacity and % of SWL and a drawing showing the plan
view of the crane and load.
Crane Lift Plans (MMS # 600-F003-100) are required to be completed when any of the following conditions
apply:
6.5.1 Maintenance
• Where past experience has shown particular problems with a crane, a specific rectification program
will be instigated and documented.
• All malfunctions and problems will be corrected before the crane is returned to service.
• Maintenance is to be carried out in accordance with the Manufacturer’s recommendations.
• A documented record is to be maintained for any maintenance completed.
• Routine inspections should take place at intervals not exceeding those shown in the operator’s
handbook.
6.5.2 Inspections
The following items should be checked for compliance with manufacturers’ specifications and safe
operation as part of a pre-operational inspection of a crane:
• Check the oil levels, fuel level and lubrication of all moving parts.
• Check the ropes, rope terminal fittings and anchorages, rope drums and sheaves for any damage
and wear.
• Check that all water is drained from air reservoirs.
• Check the crane for any loose or damaged structural component including supports and outriggers
where fitted. Loose joints may be readily noticed by flaking or marking on the paint surface or by
rust marks. Similarly, cracks may often be detected by rust runs.
• Visually inspect structural members and other critical components such as brakes, gears,
fasteners, pins, shafts, wire ropes, sheaves, locking devices and electrical contacts.
• Check the security of the counterweight. Where this is in the form of removable weights, check that
the weights correspond to those shown on the counterweight chart for the operating condition in
use.
• Check that the load moment system where fitted is correctly set or fitted (or both) with the program
appropriate to the boom or jib length, and fly-jib lengths and falls or parts of rope.
• Check that the indicator appropriate to the boom, jib or fly-jib length is fitted.
• Check that the crane cabin is in a tidy condition and free from grease and oil, rags, tools and
materials other than those for which storage provision is made.
• Check the pneumatic systems and hydraulic systems including their safety devices.
• Check the operation of the crane through all motions with particular attention to brakes.
• Check the operation of all limit switches or cut-outs, emergency and safety devices.
• Exercise caution in making the checks in the event of non-operation.
• Check that, where radio communications are being used, the calling signal is functioning and any
messages may be clearly heard.
• Check signage, including warning signs and control markings.
• Check that fire extinguishers are in place and satisfactory for use.
• Additional items nominated in the manufacturer’s instructions or operator’s handbook.
• Inspection is to include all items specified by the manufacturer for annual inspection along with all
routine inspection and maintenance items.
• As the result of a periodic inspection, a competent person may recommend a major inspection.
COMMERCIAL-IN-CONFIDENCE PAGE 25 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
• For details of inspections for particular types of cranes, refer to relevant Part of the AS 2550 series.
• Where the crane has a non-positive lifting attachment, (vacuum, magnetic etc) suitably qualified
personnel are to carry out maintenance according to the manufacturer’s recommendations. If such
recommendations are not available, then twice-yearly maintenance is to be carried out. Permanent
and electro-permanent lifting magnets are to undergo a yearly residual magnetism check of the
magnet core. Where vacuum lifting attachments are used, the frequency of inspection is to be twice
daily to ensure no seal damage the machines continue to function as designed.
• Vacuum and magnetic devices are to be fitted with failsafe devices where available
6.6 REPAIRS
Any part of a crane that becomes worn beyond manufacturer’s tolerances, damaged as to constitute a
hazard, impairs the operation of the crane, or constitutes a hazard before the next routine inspection, must
be repaired or replaced. The repairs and parts must comply with the manufacturer’s recommendations and
specifications, or the recommendations of a competent person, taking due cognizance of the Standard to
which it was designed and must be carried out by competent persons under competent direction and
supervision. The repairs are to be appropriately tested. All repairs are to be adequately documented and
recorded.
• A competent person is to make an assessment of the defects and damage requiring repair based
on the manufacturer’s tolerances and in accordance with AS 2550.1. The assessment is to be
recorded and form a report. The report should contain the following:
• Details of how the incident happened or circumstances leading to the discovery of the defective
parts.
• Nature and extent of the damage and defects.
• Proposed action based on the manufacturer’s recommendations.
Following the review of the competent person’s report, the equipment may only be repaired or scrapped.
Where any component is scrapped, arrangements should be made to dispose of the damaged component
in a manner that ensures it remains unusable as a load-carrying component.
COMMERCIAL-IN-CONFIDENCE PAGE 26 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
• The repairer selected to carry out the work must be acceptable to the competent person. Repair
work is to be carried out according to the following:
• Personnel with the necessary qualifications and experience will be engaged on the work.
• Work instructions will be provided.
• All work is to be in accordance with manufactures recommendations
• Sign off line manufacturers prior to work commencing
• All work to be managed by ITP, SMP, QMP, QC checklists.
• All work will be conducted in accordance with relevant Australian Standards or other applicable
national or international Standards.
• All final non-destructive testing will be conducted by a competent person.
• A records management system is to be established for the documentation produced by repairers
and received from other bodies for transfer to the owner.
• The examination of welding repairs must be carried out in accordance with the manufacturer’s
repair procedure, or the appropriate weld inspection Standard.
• Preapproval for the welding procedures and qualifications of welders is required.
6.7.1 Competency
The slinging method is to be determined by a person who is competent in load slinging in accordance
with local Safety Regulations.
Project management is to identify the specific local licensing requirements for persons undertaking lifting
operations.
Within Australia the Riggers licence capabilities are defined as;:
Dogging – consists of the application of slinging techniques to move a load (including the selection and
inspection of lifting gear) and/or the directing of a crane/hoist operator in the movement of a load when the load
is out of the view of the crane/hoist operator.
COMMERCIAL-IN-CONFIDENCE PAGE 27 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
Before selecting any rigging and lifting equipment, the following should be taken into account;
• Load
• Headroom
• Frequency of use- life of sling
• Type of load – Steel, Machinery, timber, crates, shipping container etc
• Current inspection certificate
• Cost versus efficiency
• Length of sling
• Method of slinging
• Environment – corrosion, heat etc
• Storage requirements
• A visual inspection will be conducted prior to use of rigging and slinging equipment.
• Never combine different types of slings.
• Shackles are to be used where slings are attached to eyebolts or lugs.
• Shackle diameter must not be less than sling diameter.
• Multiple individual slings are to be shackled together on the hook.
• All hooks are to be supplied with devices to prevent load movement.
• Lifting clutches are to be proof load tested at least at twelve (12) monthly intervals, with a record
kept on site to verify such testing.
• Inspections must be conducted by a competent person and be recorded by that person.
• All rigging and lifting equipment either purchased or hired on a project, must have all certifications
relevant to the item in accordance with the relevant local standard.
COMMERCIAL-IN-CONFIDENCE PAGE 28 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
• Items to be kept include but not limited to records from the manufacturer or supplier, identifying that
the equipment has passed all relevant testing and has been supplied in accordance with the
relevant local standard. Items include equipment such as; slings, shackles, eyebolts, lifting
clutches, chain blocks etc.
• All rigging and lifting equipment certification and inspection/test records are to be maintained and
readily available.
• Suitable storage arrangement available for the particular types of equipment – typically hung up off
the ground in a covered, dry, clean, well ventilated place, away from direct sunlight.
• If one or more of the defects, listed in Error! Reference source not found. is identified, the item
is to be removed from service immediately, tagged out and condition fully assessed prior to being
discarded.
6.7.4 Chains
Care
Use
COMMERCIAL-IN-CONFIDENCE PAGE 29 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
• Coupling links should be inspected for any signs of wear at their load bearing points, for excessive
play of the load pin within the body halves and for impaired rotation of the body halves around the
load pin.
• Chain links or fittings having any defects should be clearly marked to indicate rejection and the
chain sling should be withdrawn from service until properly repaired and retested prior to returning
to service.
Remember - Every link must be examined
Note: A nylon sling loses 15-18% of its strength on wetting with water, but regains that loss of strength after
drying out.
Inspection
Synthetic slings should be inspected for the following prior to use:
• One major disadvantage of woven webbing slings is that when used to lift loads such as concrete
slabs, grit can penetrate the sling causing internal fibre damage, which is not always obvious.
• Internal wear, caused by repeated flexing, particularly where particles of grit have penetrated into
the fibres.
• Damage to a fixed protective coating or sleeve can allow abrasive grit easy access to the sling
fibres.
• Melting or shrinkage of fibres due to exposure to high temperatures. Remember that high
temperatures can result from friction as well as from a hot environment.
• Prolonged exposure to ultra violet light, generally from sunlight, will weaken synthetic fibres - this
may be indicated by powdering of the outer layer.
• Chemical attack may also cause fibres to break down and soften. Surface fibres may be plucked
or rubbed off and there may be local stiffening of the sling.
Shackles
Shackles are used for interconnecting components in lifting, tensioning and staying systems. A shackle
consists of a body, a removable pin and any applicable locking device.
• All shackles are to be Alloy steel shackles of grade S or better
• Commercial grade shackles are not to be used for lifting purposes.
• Stainless steel shackles are not to be used for lifting purposes.
• All shackles are to have the SWL cast or stamped into the shackle body
• Compliance certificate for the batch supplied is to be available in the Project plant files
• Ensure that all markings are clearly legible.
• Ensure pin is the correct type. Never replace the pin of a shackle with a bolt.
• The threads of the pin and body are undamaged and the pin screws freely into position.
• The body and pin is not unduly worn and free from distortion, nicks, gouges, cracks and excessive
wear and corrosion.
• The pin is screwed tightly with the collar and the pin is bedded evenly on the surface of the shackle
eye.
• The correct type of pin is used for the application.
COMMERCIAL-IN-CONFIDENCE PAGE 31 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
• A bolt type shackle has a split cotter (safety pin) attached correctly.
• Shackles should not be heat treated as this may affect their working load limit.
• Never modify, repair or reshape a shackle by welding, heating or bending as this will affect the
working load limit.
Eye Bolts
• Eyebolts of 12mm or smaller should not be used in general lifting, staying or tensioning purposes.
• Commercial grade eyebolts are not to be used for lifting purposes or to support loads.
• Stainless steel eyebolts are not to be used for lifting purposes.
• Eyebolts should be screwed down fully to the face of the load to be lifted.
• WLL markings are clear and suit the application.
• Conduct a visual inspection for deformation and cracking.
• Conduct a visual inspection of the inside eye for wear.
• Conduct a visual inspection and check for damaged threads.
• Ensure the thread centre is aligned with centre of eye.
• Ensure the eyebolt’s thread form and the thread form in the corresponding hole or nut is
the same.
• Avoid excessive tightening of eyebolts.
• Metric and imperial eyebolts that conform to the Australian Standard have a safety factor of 6:1.
• When using eyebolts in pairs, it is essential that care be taken to properly align them. Eyebolts
must not be forced into alignment as overstress will cause a reduction in the WLL.
• A continuous sling should not be used with pairs of eyebolts. When lifting with pairs of eyebolts
supported by slings, always use slings with individual lengths.
Eyebolts should be inspected periodically by a competent person as per AS2317 or local equivalent.
Lifting Beams
COMMERCIAL-IN-CONFIDENCE PAGE 32 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
Sundry Equipment
• All sundry rigging equipment is to fully comply with the relevant Australian standard or local
equivalent as a minimum.
• The slinging method is to be determined by the shape, size and weight of each load.
• Slings are to be positioned over flat surfaces not over sharp edges or corners.
• Use protective padding when using any sling around sharp corners.
• Secure the lifting area from unauthorised entry.
• Tag lines of 16mm natural fibre rope or equivalent are to be used as necessary to control load
sway.
• For large or long loads (12m+) attach 2 taglines and controllers or more if required
• Dual crane lifts do not require tag lines
• Loads are to be balanced.
• Ensure no part of the load can slide or fall out during lifting.
• Don’t stand between the load and other obstructions.
• Keep hands and feet well clear of pinch points.
• Loads are not to be lifted over personnel.
While undertaking the lift, the operator and the dogman/ rigger must:
COMMERCIAL-IN-CONFIDENCE PAGE 33 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
• Before giving direction to hoist up, ensure the boom is positioned directly over the load
• Loads are to be lifted slowly to prevent swing
• Loads are to be lifted just high enough to clear obstacles
• Operators must not leave the load suspended in the air when leaving the cab
• No person is allowed to climb on or off a moving crane or load
• Do not allow anyone to stand under a suspended load or near lines under stress
• No person is to enter the fall zone until the load is as close as practicable to the landing point
• If the operation cannot continue in accordance with the agreed procedure, the operation shall stop
and the procedure reassessed to take into consideration the reason for the stoppage.
• If the reassessment is considered a relatively minor deviation from the agreed procedure the
documentation (SWMS) shall be clearly marked with the actions considered appropriate and
agreed prior to operations recommencing.
• If the reassessment is considered a major deviation from the agreed procedure then the appropriate
actions shall be taken, as a minimum will require the documentation to be marked and amended in
accordance with the revised proposals agreed. If the deviation is significant it may require
production of a drawing revision, calculations or other information as applicable.
6.9.1 Inspection
All chains and slings purchased new are to be accompanied by manufacturers testing certificates and
tagged appropriately as per the equipment’s required standard.
Used equipment coming to site, must have records that it has satisfactorily passed inspections by a
competent person in the previous twelve (12) months.
The person performing annual inspections is to be a person employed by an accredited third party specialist
testing and inspection organization (such as Bullivants, Nobles or a local equivalent) that has completed
appropriate training and has the skills and knowledge to carry out such inspections.
Quarterly inspections (3 monthly) are to be carried out on lifting equipment by a competent person. Records
of outcomes from these inspections are to be kept and maintained with the equipment’s records.
A person deemed competent to carry out these inspections is someone who has the practical and
theoretical knowledge and relevant experience, sufficient to enable the person to detect and evaluate any
defects or weakness that may affect the intended performance of the equipment. The visual inspection
checklist is located in Error! Reference source not found.. If any of the items fail to meet any of the
required checks, the equipment should be tagged out of service and not to be used and upon assessment
either discarded or repaired.
COMMERCIAL-IN-CONFIDENCE PAGE 34 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
Certificates of
Manufacturer/Supplier
equipment certification
and test results to be Before initial introduction
Certified lifting
provided with new or to service
testing/inspecting
used within last twelve
authority
(12) months
All Rigging and Lifting
Re-inspect equipment
Equipment
annually or as per Manufacturer/Supplier
manufacturer’s If not specified – twelve
recommendations or (12) monthly as minimum Certified lifting
relevant Australian interval. testing/inspecting
Standard or local authority
equivalent.
Inspect condition of
Prior to each use Competent Person
equipment
Chain Slings –Grade T
Inspect equipment and
Quarterly Intervals Competent Person
record results
Inspect condition of
Prior to each use Competent Person
equipment
Steel Wire Rope
Inspect equipment and
Quarterly Intervals Competent Person
record results
Inspect condition of
Prior to each use Competent Person
Round Slings – equipment
Synthetic Fibre Inspect equipment and
Quarterly Intervals Competent Person
record results
Inspect condition of
Prior to each use Competent Person
Flat Synthetic – equipment
Webbing Slings Inspect equipment and
Quarterly Intervals Competent Person
record results
Inspect condition of
Prior to each use Competent Person
equipment
Lifting Devices
Inspect equipment and
Quarterly Intervals Competent Person
record results
• All repair and modification to lifting equipment is to be designed and fabricated in accordance with
applicable standards and the modified design registered by the design authority.
• After repair or modification, lifting equipment must be tested by application of a proof load, specified
by a competent person, and then thoroughly examined. A test certificate stating the Working Load
Limit and the proof load is to be obtained and retained on site.
• The design and specifications of purpose made lifting equipment must be approved by the design
authority.
• A report of the examination is to be produced.
• Modification and repair of lifting equipment is to be in accordance to the applicable standards.
COMMERCIAL-IN-CONFIDENCE PAGE 35 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
The requirements from AS 1418.8 or its local equivalent are to apply when earthmoving equipment including
backhoes, front-end loaders, excavators, tool carriers and similar units are used for lifting freely suspended
loads as a secondary function associated with the normal application of the equipment.
Where it is intended to use the earthmoving equipment for cranage operations other than those indicated
above, or where variable rated capacities are specified, all requirements of AS 1418.5 or its local equivalent
are to apply.
Lift point - A lifting lug located on the boom, arm, linkage, front end loader bucket or quick-hitch as specified
by the manufacturer, to which a load may be attached for lifting freely suspended loads.
Lift point radius/reach - The lift point radius/reach is the horizontal distance from either the centre-line of
the front wheel or equivalent position on track, or the axis of rotation or the centre-line of the load supporting
axle as appropriate, to the vertical load line. Where a non-slewing machine is fitted with stabilizers, the
reach shall be measured from the centre-line of the stabilizers nearest to the load.
Rated lift bucket position - The bucket attitude with the bucket fully rolled forward and the load suspended
from the bucket as recommended by the manufacturer.
• The earthmoving equipment shall be travelled only with arm and boom retracted to minimum
practicable radius.
• No person is permitted under the boom or suspended load.
• All persons operating the earth moving equipment are to have the appropriate certificate of
competency and/or training
• The person slinging the load or directing the operator is to have a certificate of competency for
dogging or rigging.
• No persons are to be lifted by earth moving equipment.
• Lift points are to be arranged such that accidental unhooking of the load cannot occur.
• Operational speed is to be reduced from high-speed mode.
• Where the sling or tackle is wrapped over the back of the bucket, it is not to come into contact with
any sharp projection or sharp edge.
• Loads are not to be suspended from bucket teeth or adaptors.
• Reference is to be made to the manufacturer’s manual for correct operation.
• A service record (logbook) is to be used to record servicing, maintenance and repair work, and
details of any malfunction that may occur with the machine.
COMMERCIAL-IN-CONFIDENCE PAGE 36 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
The rated capacity is the maximum mass (expressed in kilograms) that may be handled at the maximum
lift point radius, or reach, expressed in metres in the most adverse configuration for each lift point without
the strength, hydraulic, and stability requirements being exceeded.
The rated capacity comprises of the mass of the lifted load and the lifting attachments. Where a bucket is
fitted, the rated capacity is to be established at the rated lift bucket position that results in the maximum
radius.
A rated capacity chart, identifying the lift point location(s) and the corresponding rated capacity at that
position, is to be mounted inside the operator’s cab and is to show the following:
• Manufacturer’s name and model.
• Boom identification (length in metres), where applicable.
• Arm identification (length in metres), where applicable.
• Shoe width (in millimetres) and track gauge and length (in metres), where applicable.
• Deductions for attachments such as a bucket, lifting devices or quick hitch device to allow
determination of the net load that can be lifted.
• Tyre track and size (in millimetres) and inflation pressure (in kilopascal), where applicable.
• Bucket mass (in kilograms) and width (in millimetres), or quick hitch mass (in kilograms), as
applicable.
• NOTE: Buckets and quick hitches should have their mass marked on them.
• Ground speed limit for pick-and-carry rated load for rubber-tyred equipment (in kilometres per
hour).
• The maximum permitted slope for lifting and pick and carry operations.
• Where controlled lowering devices are fitted, a notice of the effect to be displayed.
• Any other equipment conditions that may impact on rated capacity.
Earthmoving equipment that is used to lift freely suspended loads that have a rated lift capacity at maximum
radius/reach greater than 1 t is to be fitted with a controlled lowering device on the raising boom cylinder(s).
The control-lowering device is to meet the requirement of ISO 8643, to protect against hydraulic hose
failure. Where control lowering devices are not provided, the following is to apply:
• A load greater than 1 t shall not be lifted.
• Controls shall be in place to ensure that uncontrolled lowering shall not result in injury or death to
persons in the area.
• Suspended loads shall not be lifted over personnel, in any circumstances.
7.1.4 Stability
Stability of earthmoving equipment is to be such that the rated capacity is not greater than
the appropriate percentage of the tipping load that has to be applied to tip the earthmoving
equipment within AS 1418.8 Section 5 or it is local equivalent.
Where the earthmoving equipment requires the use of stabilizers in order to achieve stability, the equipment
is to be supported by such stabilizers.
COMMERCIAL-IN-CONFIDENCE PAGE 37 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
The rated hydraulic lift capacity of earthmoving equipment is to be such that the rated
capacity is not greater than 87% of the hydraulic capacity at maximum reach/radius.
The rated capacity at each lifting point is to be prominently marked at the lifting point. This is not to be
exceeded under any circumstance, that is, the lifted load plus any attachments (bucket, etc.) shall not
exceed the rated capacity.
Deductions from the rated capacity for larger than standard buckets or quick hitch devices are to be
considered to determine the maximum allowable mass of the item that may be lifted. Reference is to be
made to the manufacturer’s manual for correct operation.
7.1.6 Quick-hitches
Quick-hitches that are fitted to earthmoving equipment used to lift freely suspended loads are to comply
with the requirements in AS 4772 or its local equivalent. (Safe use of earth moving machinery fitted with a
quick-hitch)
Where equipment is used and is fitted with a quick hitch, the following requirements apply:
• Loads only to be suspended from the manufacturer’s designated lift point on the quick-hitch unless
a designated lifting attachment is fitted.
• All non-lifting attachments to be removed before any lifting operation is undertaken.
• Quick-hitches to be used only to support attachments specifically designed to fit and specifically
designed for the duty to be undertaken.
• Host machine load rating charts to allow for the additional mass of the quick-hitch.
• Quick-hitches to be maintained in proper working order at all times.
The earthmoving equipment configured to lift freely suspended loads is to display at a readily accessible
and prominent location and on permanent and legible notices the following information, where appropriate:
• Name or mark of the supplier.
• Model designation.
• Serial number.
• Where earthmoving plant is to be used for lifting a freely suspended load, all controls shall be
labelled in accordance with ISO 7000.
8 RECORDS
Daily inspection records
Lift Plans
Maintenance records
Plant incoming inspections – internal and external inspections
COMMERCIAL-IN-CONFIDENCE PAGE 38 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
9 REFERENCES
Competency Register 030-F044-100
Competency Register – By person 030-F045-100
Compliance with Legal & Other Requirements 000-D004-000
Crane Lift Plan 600-F003-100
Height 020-T005-100
HSE Risk Management 020-D012-100
Mobile Equipment Daily Inspection Report 045-F030-100
Overhead Power Lines 020-T009-100
Project Training Plan 030-J008-100
Plant & Equipment Register 045-F136-100
Plant Operator Assessment 030-F047-100
Project Compliance with Legal & Other Requirements 300-E012-100
Storage Maintenance & Refuelling of Machinery 025-L007-100
Workbox Use 020-T003-100
COMMERCIAL-IN-CONFIDENCE PAGE 39 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
10 APPENDICES
APPENDIX A – LICENCES TO PERFORM HIGH RISK WORK
The following is a list of the licenses for high risk work, as given in the National Standard
for Licensing Persons Performing High Risk Work (April 2006), that are relevant to the crane industry in
Australia:
(DG) Dogging
(RB) Basic rigging
(RI) Intermediate rigging
(RA) Advanced rigging
(CT) Tower crane operation
(CS) Self-erecting tower crane operation
(CP) Portal boom crane operation
(CB) Bridge and gantry crane operation
(CV) Vehicle loading crane operation
(CN) Non-slewing mobile crane operation
(C2) Slewing mobile crane operation (up to 20 t)
(C6) Slewing mobile crane operation (up to 60 t)
(C1) Slewing mobile crane operation (up to 100 t)
(CO) Slewing mobile crane operation (open/over 100 t)
(WP) Boom-type elevating work platform operation
(HM) Materials hoist (cantilever platform) operation
(HP) Hoist (personnel and materials) operation
(BP) Concrete placing boom operation
NOTES:
1. The above list was correct at time of publishing.
2. The National (Australian) Standard for Licensing Persons Performing High Risk Work can be downloaded
from the Safe Work Australia website at: www.safeworkaustralia.gov.au
3. For crane operations conducted outside of Australia, local regulations should be consulted to determine
any specific local requirements.
COMMERCIAL-IN-CONFIDENCE PAGE 40 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
and turnbuckles
Pre-Use Inspection/Check for rigging
Wire Rope
Synthetic Slings
Chains
Hooks
Sheave blocks
Shackles
Sockets
Rigging screws
Eye Bolts
Hoists
Clamps
Winches
and Lifting equipment
COMMERCIAL-IN-CONFIDENCE PAGE 41 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
COMMERCIAL-IN-CONFIDENCE PAGE 42 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
COMMERCIAL-IN-CONFIDENCE PAGE 43 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
Definition
A feature fitted on some mobile cranes that allow the hook and load to fall under gravity in an uncontrolled
manner.
Background
There have been a number of serious accidents caused by loads dropping in a free fall manner.
The free fall feature has been traditionally fitted on cranes for activities such as clam shell dredging and
dynamic pile compaction. However, the risk associated with an inadvertent activation of the free fall
feature can be high and the provision is rarely needed. Most mobile crane manufacturers dot not provide
this feature on new cranes. The risk to workers from falling loads and potential damage to the crane and
crane operator is considerable.
McConnell Dowell Policy
McConnell Dowell policy is that no crane is to operate with an active free fall feature. This policy can only
be relaxed with written approval of the relevant Executive/General Manager. The policy applies to both
McConnell Dowell and hired in cranes.
Requirements for McConnell Dowell Cranes
The free fall capabilities on McConnell Dowell cranes are to be permanently deactivated. This
deactivation of the free fall should include removal of free fall switches on the crane and a certificate from
the crane manufacturer or a competent person (preferably a professional engineer) to state that the free
fall function has been permanently removed.
Requirements for Hired-in Cranes
Owners of cranes with free fall features that do not have a physical lockout arrangement to prevent
inadvertent activation are to engage a competent person to install a lockout and test the arrangement.
Owners are also to engage a competent person to inspect and test to ensure that the lockout has been
correctly installed and free fall cannot be inadvertently activated.
Guidelines for Relaxation of Policy
The use of the free fall function on a mobile crane should be extremely rare and only be permitted where
a documented safe work method statement has shown there is no other reasonable alternative. A
documented risk assessment is to be prepared for this situation and submitted to the relevant Executive
/General Manager with a request for a waiver of the policy.
COMMERCIAL-IN-CONFIDENCE PAGE 44 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
Beaufort Scale Ave. Ave. Ave. Effects of wind speed Effects of wind speed over Operating
Wind Wind Wind over land water Information
Speed Speed Speed
(knots) (km/h) (m/s)
0 Calm Less Less 0 - 0.2 Calm, smoke rises Sea like mirror Normal Lifting
than 1 than 1 vertically. Zone for most
cranes:
1 Light Air 1-3 1-5 0.3 – Direction of wind shown Ripples with the appearance of
Confirmation of
1.5 by smoke drift, but not scales are formed, but without
operating
by wind vanes. foam crests
parameters
should be
2 Light 4-6 6-11 1.6 – Wind felt on face; Small wavelets, still short, but sought from the
Breeze 3.3 leaves rustle; ordinary more pronounced; crests have crane operations
wind vane moved by a glassy appearance and do not manual and
wind. break reviewed by the
crane operator.
3 Gentle 7-10 12-19 3.4 - Leaves and small twigs Large wavelets; crests begin to
Breeze 5.4 in constant motion; wind break; foam of glassy
extends light flag. appearance; perhaps scattered
white horses
4 Moderate 11-16 20-28 5.5 – Raises dust and loose Small waves, becoming longer;
Breeze 7.9 paper; small branches fairly frequent white horses
moved.
5 Fresh 17-21 29-38 8.0 – Small trees in leaf begin Moderate waves, taking a more
Breeze 10.7 to sway; crested pronounced long form; many
wavelets form on inland white horses are formed
waters. (chance of some spray)
6 Strong 22-27 39-49 10.8 – Large branches in Large waves begin to form; the Review and
Breeze 13.8 motion; whistling heard white foam crests are more Assess Zone:
in telegraph wires; extensive everywhere (probably
Review crane
umbrellas used with some spray)
operation limits
difficulty.
and effects on
loads lifted.
7 Near Gale 28-33 50-61 13.9 – Whole trees in motion; Sea heaps up and white foam
17.1 inconvenience felt when from breaking waves begins to Agreement to
walking against the be blown in streaks along the continue with
wind. direction of the wind entire crane
crew and person
in charge of
lifting
operations.
8 Gale 34-40 62-74 17.2 – Breaks twigs off trees; Moderately high waves of No Lifting
20.7 generally impedes greater length; edges of crests Zone:
progress. begin to break into the spindrift;
the foam is blown in well-
COMMERCIAL-IN-CONFIDENCE PAGE 45 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
Beaufort Scale Ave. Ave. Ave. Effects of wind speed Effects of wind speed over Operating
Wind Wind Wind over land water Information
Speed Speed Speed
(knots) (km/h) (m/s)
9 Strong 41-47 75-88 20.8 – Slight structural damage High waves; dense streaks of
Gale 24.4 occurs (chimney pots foam along the direction of the
and slates removed). wind; crests of waves begin to
topple, tumble and roll over;
spray may affect visibility
10 Storm 48-55 89-102 24.5 – Seldom experienced Very high waves with long
28.4 inland; trees uprooted; overhanging crests; the
considerable structural resulting foam, in great patches,
damage occurs. is blown in dense white streaks
along the direction of the wind;
on the whole, the surface of the
sea takes a white appearance;
the tumbling of the sea
becomes heavy and shock-like;
visibility affected
11 Violent 56-63 103- 28.5 – Very rarely Exceptionally high waves (small
Storm 117 32.6 experienced; and medium sized ships might
accompanied by be for a time lost to view behind
widespread damage. the waves); the sea is
completely covered with long
white patches of foam lying
along the direction of the wind;
everywhere the edges of the
wave crests are blown into
froth; visibility affected
12 Hurricane 64 and 118 32.7 – Severe and extensive The air is filled with foam and
over and 36.9 damage. spray; sea completely white
over with driving spray; visibility very
seriously affected
COMMERCIAL-IN-CONFIDENCE PAGE 46 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
Cranes
Jib Boom / Mast The main section of the crane used for lifting. It has 3 or 4 chords and
lattice sections.
Headache Ball Used above the hook to weight down and steady the hoist line.
(Auxiliary Hook)
Main Block A sheave block above the main hook used to take multiple parts of the
hoist rope.
Rooster Usually the part at the top or tip of the boom that holds the auxiliary line
or whip hoist rope.
Whip / Auxiliary Line The secondary line for doing smaller or lighter lifts.
Tip The working end of the boom holds the rooster and the main hoist rope
sheaves.
Bridle Holds the pendant ropes and is connected to the luffing ropes allowing
the boom to move up and down.
Pendant/ Pendant The main supports holding the boom or jib in place.
Ropes
Rams Horn Usually on the main block. This is a double hook used partly to balance
the load but it is made to put multiple slings on it for big or awkward
lifts and spread weight out more evenly.
Butt The bottom section of the boom. This is the part that is connected to the
crane that has pins to pivot up or down the crane.
Carbody This is the part that holds the engine winches and boom of the crane as
well as the cab and counterweights
Base / Chassis This frame supports the car body through the slew ring and the tracks
are also fixed to the base
Counter Weights These provide the balance that the crane requires to lift objects.
COMMERCIAL-IN-CONFIDENCE PAGE 47 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
Belly Weights This provides extra weight to the crane to perform larger lifting capacity.
Mobile-hydraulic / As the name implies it can be setup quickly to move around a site(s).
Oilcan Not for pick and carry these cares usually have some of the attributes of
a crawler crane however the boom is telescopic and retracts; it has
outriggers for stability and usually has rubber tyres.
Rough Terrain / These usually are similar to mobile cranes however they usually have a
Roughie pick and carry capability. They are sometimes very quick to set up.
Franna This is proprietary name however they usually have a pick and carry
capability.
Tom Thumb A small hydraulic crane used to set up in very tight or small areas
however they cannot pick up large amounts of weight or sizes.
Tower Cranes These are fixed on top of a frame or tower and are self climbing using
extra pieces on the tower. There are usually two types.
Luffing Boom
Meaning the luffing boom can either move up or down on a pivot point
on the main boom
Saddle Jib or Hammer Head
Meaning the jib is in a horizontal position and a trolley or saddle moves
in and out along the boom carrying the hoisting rope with hook below.
Shark Hook A hook sometimes connected to the tagline. They alleviate the need to
tie the rope to the item being lifted.
Sheep Shank A rope hitch used to shorten the rope and can be also used to give you
purchase when tying a load down.
COMMERCIAL-IN-CONFIDENCE PAGE 48 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
Wire ropes
Snotter Is a sling with an eye either hand or machine spliced at each end.
Sheave This is a grooved wheel used to run a wire over. Usually used on cranes,
however can be used for rigging applications.
Grommet Is formed into a circle and is either hand spliced or machine spliced.
These types of wire rope slings can be used for stingers. However they
are generally used to increase capacity without increasing the size of the
wire rope.
FC Fibre core.
Bulldog Grip For temporarily joining two ropes together or making an eye.
Thimble A piece of formed or cast metal formed into an eye to help support the
way rope sits and stops deformation of the rope.
Ferrule Is a piece of metal to clamp two pieces of rope (called a swage) together
to form an eye grommet.
Superflex Is a woven wire rope generally used where a tight bend cannot be
overcome or on painted items reducing paint damage.
Flemish Eye Is a type of splice to form an eye. It is used when steel ferrules are used
in making FSWR slings. These should never be used for lifting without
being swaged and tested first.
Swage Is the term used for a ferrule compressed to form an eye in a wire rope.
Hambone / Wedge Is a fitting generally used on the hook of a crane by wrapping the rope
Socket around a wedge and welding the rope into a socket.
COMMERCIAL-IN-CONFIDENCE PAGE 49 OF 50
MCCONNELL DOWELL
CRANE AND LIFTING OPERATIONS
MMS # 020-T001-100
REVISION 5
OCTOBER 2015
Spelter Socket Is a socket that a rope terminates in. It is usually used in conjunction
with either hot metal or two pack epoxy type compound these have an
efficiency rating of 100%, based on the catalogue strength of wire ropes.
Chains
Latch Lock Hook Is a hook attached usually to chains. It is a hook with a positive latch
closing mechanism.
Multi Large oblong with two smaller ones permanently fitted to it.
Shackles
Tirfor / Creeper Winch Used in communication with wire rope for guy wires or temporary stays.
COMMERCIAL-IN-CONFIDENCE PAGE 50 OF 50
MCCONNELL DOWELL