Professional Documents
Culture Documents
ABSTRACT: Stage construction of embankment is often obstructed by low bearing capacity of soil because
of that critical height of embankment is smaller than final height of embankment design. Height of embankment
construction will always be greater than final height requirement because of the settlement of soil. Due to the
problems mentioned above, it is conducted the installation of PVD for accelerate consolidation settlement to
reach the final height of the embankment with stable condition. The shear strength will be increased if the
settlement consolidation completed so that the soil bearing capacity will also be increased.
This study aims to analyze how much shear strength increase if settlement consolidation completed. By case
study in Teluk Lamong, Indonesia where the soil is normally consolidated will look how much increase shear
strength that occurs by using the Mohr method coulombs, Ardana & Mochtar (1999) and changes in volume
method. Expected outcomes of this research are obtain a) new shear strength value on various condition of stage
construction of embankment, b) Provide the method that are suitable for looking for increasing shear strength.
1
Lecturer,Sepuluh Nopember Institute of Technology, yudhi.lastiasih@gmail.com, Indonesia
2
Lecturer, Sepuluh Nopember Institute of Technology, tantrigeoteknik@gmail.com, Indonesia
1
Lamong and degree of consolidation that is
used as the analysis is 95%. If consolidation settlement occurs in soft
soil due to working loads, such as
REVIEW STUDY embankment, will reduce the excess pore
From previous observation and research water pressure and the void ratio on soft
result can be seen the relationship between soil so that the density and effective
un-drained shear strength (=Cu) with vertical stress would increase. As a result,
vertical effective soil stress (=σp') working undrained shear strength and safety factor
on the clay. would increase. Increased soil shear
Some studies that have been done for the strength is a function of the degree of
normally consolidated clays (NC-Soil) to consolidation, as shown in Equation 9.
increase the value of Cu are as follows: Therefore the speed of embankment must
a. Based on Jamiolkowski et al. (1985) be controlled so that sufficient
C consolidation occurs, with the result that
u 0.23 0.04 (1) the shear strength can be achieved. This
'
p method should be considered when height
b. Based on Mesri (1975) & of embankment design exceeds the critical
Balasubramaniam (1991) height that can be safely supported by the
C subgrade.
u 0.22 (2)
' Change in magnitude of soil strength can
p
be taken approximately the same with
c. Based on Skempton dan Henkel (1953)
embankment load. For normally
C
u 0.11 0.0037PI (3) consolidated clay a factor are ranging from
' 0.20 to 0.40. The full increase shear
p
d. Based on Ardana dan Mochtar (1999) strength will only occur just below the
highest embankment area and down to the
- For Plasticity Index PI < 120 %. toe of embankment.
Cu (kg/cm2) = 0,0737 + (0,1899 - 0,0016 An estimate shown in Figure 1 is sufficient
PI) σp' (4) for the purposes of stability analysis.
- For Plasticity Index PI > 120 %
Cu (kg/cm2) = 0,0737 + (0,0454 - 0,00004
PI) σp' (5)
Where:
σp': Vertical Effective Stress of Soil
(kg/cm2). Figure 1. Increase Shear Strength Due to
IP: Plasticity Index Consolidation
The value of vertical effective stress (σp ')
changes with time during consolidation. Increased shear strength on soft soil take
Vertical Effective Stress of Soil (σp ') can place gradually in line with the process of
be searched with the following formulation consolidation of soft soil. As for the soil
consolidation can be calculated using
U
p' ' Equation 7
p ' o p . po ' (6)
p 'o
2
TH
2 using Table 2 and then new Cohesion un-
t v dr (7) drained (Cu) can be obtained.
Cv
where
Table1. Soil Parameter Correlation (Biarez,
U
2
3
Table 3. Soil layer parameters for the
calculation of data input
Depth mLWS 0 s/d 6 6 s/d 25 25 s/d 62 Uavg= 95% Tv= 1.13, Hdr = 22 m, t =
Thickness m 6 19 37
NSPT 4 12 23 6 month, so
Jenis Tanah
Tv H dr
Silt & Clay Silt & Clay Silt & Clay 2
sat t/m3 1.6 1.733 1.91 Cv
cu t/m2 1 2.5 8.22
t
0
3 11 21 1.13 2200 2
Cv
e0 1.85 1.34 0.87 6 30 24 3600
cm2/s
Cv 0.0004 0.000657 0.00095
Cv 3.51 10 3 cm 2 / s
w % 68.55 49.56 32
Cc 0.50 0.33 0.17 With the increasing soil density, the shear
E t/m2 138 250 1500 strength parameters (Cu) will be increased
n 0.2 0.2 0.2
as shown in Table 4. Increased shear
From soil parameter on Table 3, strength parameters in Table 4 is based on
embankment with slope 1:1.5 only H = 3 m the stages construction of embankment as
can be reached as seen in Figure 2, so we high as 3 m at each stage with a waiting
must soil improvement. In this cases, soil time of 8 weeks.
improvement is used PVD. PVD is Table4. Increasing Shear Strength
construction with spacing 1.4 m, and length Parameter (Cu)
(L) = 25 m
Stage 1
New Cu after consolidation (t/m2 )
After the stage construction of embankment Table 5. Safety Factor For Initial Condition
about 3 m and then installed PVD. and Increasing Shear Strength
Installation of PVD in the zone Container
Yard can resolve the consolidation (Uavarage
Initial Ardana Mohr Volume
= 95%) which occurs in this zone within 6 Method
SF
Condition
1.29
Jamiolskwi
1.39
Mesri
1.39
Skempton
1.05
Mochtar
1.52
Coulomb
1.48
Change
2.12
4
construction stage method can’t be
Chart 1
Sum-Msf
1.4
construction stage.
1
0.95 0.96 0.97 0.98 0.99 1
Sum-Marea
At this stage with increasing cu condition as Figure5. Safety Factor on First Stage
shown in Table 4 and in implementing the Construction of Embankment
Plaxis, actually to Mohr coulomb theory with Mesri
with waiting time of 8 weeks is still not
enough to increase the height of Sum-Msf
Chart 1
1.06
0.98
1.3
Chart 1
1.2
Sum-Msf
1.3
1.1
1.25
1.2 1
0.95 0.96 0.97 0.98 0.99 1
1.15
Sum-Marea
1.1
1.05
Figure7. Safety Factor on First Stange
1
0.95 0.96 0.97 0.98 0.99 1
Construction of Embankment
Sum-Marea
Chart 1
Sum-Msf 1.3
1.4
1.2
1.3
1.2 1.1
1.1 1
0.95 0.96 0.97 0.98 0.99 1
Sum-Marea
1
0.95 0.96 0.97 0.98 0.99 1
Sum-Marea
5
For the Ardana & Mochtar and Mohr settlement plate. Because from the
Coulomb method was not able to proceed to settlement plate result shown after the first
next stage construction of embankment and stage construction of embankment in height
thus require a longer time to continue the equal 3m can be continued to the next stage
next stage. after 87 day 12 weeks, so Mohr Coulomb
method is closely with field result.
Chart 1
Sum-Msf
2.4
2.1
1.8 CONCLUSION
1.5 Based on comparative analysis carried out
1.2 by using Plaxis and the results of field
0.9
0.95 0.96 0.97 0.98 0.99 1
observations in this case study can be
Sum-Marea
summarized as follows:
Figure9. Safety Factor on First and Second 1. That the Mohr Coulomb method is
Stage Construction of the most closely method with the
Embankment with Volume condition of the field with SF = 1.48
Change Method 2. Of the six methods of looking for an
increase in the value of Cu after the
Figure 9 shows safety factor for stages consolidation, which gives the
construction of embankment after waiting smallest value increase is the method
for the first stage with the volume change mohr coulomb.
method. From Figure 9, third stage
construction of embankment has been Reference
unable to proceed because it is failure. Ardana, Made Dodiek dan Indrasurya B.
Mochtar (1999), Pengaruh Tegangan
Chart 1
Sum-Msf
2.8
Overburden Efektif dan Plastisitas Tanah
2.4
terhadap Kekuatan Geser Undrained Tanah
2
Lempung berkonsistensi sangat lunak
1.6
sampai kaku yang terkonsolidasi normal,
Thesis S-2 di Jurusan Teknik Sipil FTSP –
1.2
ITS.
0.8
0.95 0.96 0.97 0.98 0.99 1
Sum-Marea
6
Mesri, G. (1975). Discussion: new design
procedure for the stability of soft clays.
ASCE J. Geotech. Engng 101, No. 4,
409–412.