You are on page 1of 140

Thesis

on
THE APPLICATION OF RISK MANAGEMENT IN
BUILDINGS PROJECTS IN LIBYA
Submitted for partial fulfillment for award of degree of

Ph.D
in
Civil Engineering(Construction Engineering & Management)
by
HASSAN MOHAMED ABUDULNABI
(ID NO. : 13PHCVE101)

Under the Supervision of

Dr. V.C. AGARWAL


Prof.& HOD (Civil Engg.)
Department of Civil Engineering
Shepherd Institute of Engineering & Technology,
SAM HIGGINBOTTOM UNIVERSITY OF AGRICULTURE,
TECHNOLOGY&SCIENCES
ALLAHABAD-211007, (U.P), INDIA

2018
IN MEMEORY

To My Father: Mr. Mohamed

To My Mother: Mrs. Najma

To My Wife: Mrs. Hanan

To My Kids: Mohamed, Ahmed, Najma, Mansour

To My Best Friend: Mr. Bright

To My College and My Country


SELF ATTESTATION

This is to certify that I have personally worked on the research work entitled “The
Application of risk Management in Buildings Projects in Libya” The data mentioned in
the thesis have been generated during the investigation and are genuine. Data/information
obtained from agencies have been duly acknowledged. None of the findings /informations
pertaining to the work results embodied in the thesis have been submitted to any other
university or Institute for the award of any degree or diploma.

Place:-Allahabad Hassan Mohamed Abdulnabi Ahmed

Date: - I.D.13PHCV101
ABSTRACT
Risk has a great impact on the performance of residential projects in Libya in terms of cost,

time and quality. It has increased the size and complexity of the projects and has become the

ability to manage risk in all phases of the construction process a central element to prevent

unwanted consequences. The risk management process between the actors in the project is

governed to a large extent to know the importance of risk management as well as documents

related to the content of the contract. Therefore, the experience in the risk management of the

project is the main issue for the actors of the project. This research aims to deepen

understanding of risk management and its application during the construction period in Libya

and know the reasons that led to the delay in the completion schedule and as well as finding

suitable solutions. The study includes ten projects including (27,571) housing units recently

carried out in Libya. This includes the questionnaire and a series of interviews with clients,

contractors, and consultants involved in these construction projects.It has been prepared in a

form to determine and identify the risks facing the housing projects in Libya and then

distributed to a number of companies that implement these projects. After it has identified

risks that these projects faced by questionnaire and interviews form with engineers and

project managers, these data were analyzed qualitatively, and then a checklist of the risks one

may be facing in the projects in Libya was prepared.

This research aims to let everyone understand the risks management in Libya ,and a deep

study on the procedure of risks management in the projects. Especially, since the prime

minister of the Libyan government, issued a decision in 2005 to build 200, 000 thousand

housing units and should be delivered to citizens in 2011, but most of these projects are

delayed. The study involved will take ten large projects all over Libya .

The results of this study present the effect of common and major risks on construction period.

Keywords: Risk management, construction, projects, implementation, housing.

I
ACKNOWLEDGEMENT

This thesis is a representation of the combined efforts and invaluable contributions of a large
number of individuals and it is my great pleasure to acknowledge them with due obligations.

First of all, I would thank the Allah Almighty who has always blessed me by granting His
kindness to complete the task.

I acknowledge my sincere thanks to Rt. Professor (Dr.) R. B. Lal, Hon’ble Vice Chancellor,
Sam Higginbottom University of Agriculture, Technology and Sciences, Allahabad for
granting me the opportunity to obtain my doctorate degree for the betterment of my academic
career.

I am heartily Grateful to, Prof. (Dr.) Mohd Imtiyaz, Shepherd Institute of Engineering and
Technology, Sam Higginbottom University of Agriculture, Technology and Sciences,
Allahabad.

I would like to express my special appreciation and thanks to my advisor Prof (Dr).V.C.
AGARWAL Head of the Dept. of Civil Engineering, Shepherd institute of Engineering and
Technology, Sam Higginbottom University of Agriculture, Technology and Sciences,
Allahabad. You have been a tremendous mentor for me. I would like to thank you for
encouraging my research and for allowing me to grow as a research scientist. Your advice on
both research as well as on my career have been priceless.

I would like to thank all for acting as members of my thesis committee and giving me
excellent suggestions.

A special thanks to my family. Words cannot express how grateful I am to, my mother,
father, brothers and sisters for all the sacrifices that they’ve made on my behalf. Their
blessing and moral support to achieve this goal. I would also like to thank my country
LIBYA for continuously supporting me even in these difficult times, and incented me to
strive towards my goal. At the end I would like express appreciation to the patience and the
generous sacrifices of my better half my Wife and my lovely children Mohamed, Ahmed and
Najma who often missed my presence and affection at home and when at home allowed me
to work continuously with the smile on their faces. I offer my regards and blessings to all of
those who supported me in any respect during the completion of the project.

Hassan Mohamed Abdulnabi Ahmed.

II
TABLE OF CONTENTS

Title page No.


Abstract i

Acknowledgement ii

Table of Contents iii

List of Figures VIII

Chapter I: Introduction 1

1.1. Risk Management Process 4

1.1.1. Identification 4

1.1.2. Assessment 6

1.1.3. Potential Risk Treatments 7

1.2. Limitation 10

1.3. Project Management 11

1.4. Objectives 12

1.4.1Research Questions 12

1.5. Statement Of The Problem 13

1.6. Significance Of The Study 13

1.7. Scope Of The Study 13

Chapter II: Literature Review 14

2.1 .Preliminary Remarks 14

III
Chapter III: 33

3.0 Material & Methodology 33

3.1. Case Study 36

3.1.1. Construction of (1612) housing units in Wadi AlshaticityBrak "LIBYA” 37

3.1.2. Construction of (128) housing units in Akhlafe Ubari city "LIBYA” 40

3.1.3. Construction of (140) housing units in El Houamed city "LIBYA” 43

3.1.4. Construction of (341) housing units in Elmahrougha "LIBYA" 46

3.1.5. Construction of (2000) housing units in Ghadames city "LIBYA” 49

3.1.6. Construction of (3050) housing units in Sabha city "LIBYA ". 52

3.1. 7.Construction of (130) housing units in Wanzureik "LIBYA" 56

3.1.8. Construction of (60) housing units in Tamzawh "LIBYA” 59

3.1.9. The construction of twenty thousand housing units in Benghazi city “LIBYA” 62

3.1.10. The construction of 110 housing units in Almansoura city"LIBYA” 65

3.2. Libyan Audit Bureau and Construction projects. 68

3.3. Project managers response to the real reasons for delays in the housing Projects 69

Chapter IV: Results and Discussion 71

4. Questionnaire survey 71

4.1 Questionnaire distribution and respondents profile 71

4.2 Questionnaire response & abstention 73

4.3 years of experience in the line of work 73

4.4 Executive situation for the project 74

4.5 Studding risk management and project management courses 75

4.6 Knowledge of Risk Management 76

IV
4.6.1. Evaluating the project implementation in terms of Time, cost and Functionality 77

4.6.2 The participating in project phases 78

4.6.3 The risk management processes that are carried out systematically in the projects 79

4.6.4The phases of the project where the risk management processes performed 80

4.6.5The participation in risk management . 82

4.6. 6Construction Risks that face the projects in Libya 83

4.6.7 The Influence of project actors on risk management. 84

4.6.8 The collaboration between the actors in the project 85

4.6.9 Delay in payment of the work invoices and the increase delay and the cost of the
project. 86

4.6.10 Option time extension and Impact on risk management. 87

4.6.11 Impact decisions of Change Orders in contract on risk management . 88

4.7 The risks in construction projects in Libya 89

4.8 Identifying and assessing the risks before and during construction period 90

4.9 Control of risks during construction period 91

4.10 Risk management and construction companies’ management systems in Libya. 92

4.11 Impact time extensions option in contracts on risk management 92

4.12 Impact of the decisions of Change Orders in contract on risk management 93

4.13 Effects of the project risk 93

4.14 Risk management 94

Chapter V: Recommendations, future scope and project work 98

Conclusion 99

V
References 103

Questionnaire survey 107

List of publications 114

VI
LIST OF FIGURES
Figure No Title Page

Figure3.1.Construction of (1612) housing units in Wadi Alshati city Brak 39

Figure 3.2.Construction of (128) housing units in Akhlafe Ubari city 42

Figure 3.3.Construction of (140) housing units in El Houamed city 45

Figure 3.4.Construction of (341) housing units in Elmahrougha 48

Figure 3.5.Construction of (2000) housing units in Ghadames city 51

Figure 3.6.Construction of (3050) housing units in Sabha city 55

Figure 3.7.Construction of (130) housing units in Wanzureik 58

Figure 3.8.Construction of (60) housing units in Tamzawh 61

Figure 3.9. The construction of 20 thousand housing units in Benghazi city 64

Figure 3.10.The construction of 110 housing units inAlmansoura city 67

Figure. 4.1. Questionnaire distribution and respondents profile figure 72

Figure. 4.1. Questionnaire (response & abstention) 73

Figure. 4.2. Years of experience in the line of work 73

Figure. 4.3.the executive situation for the project 74

Figure. 4.4. Studding risk management and project management courses 75

Figure.4.5. Values versus project, contractor and consultant 76

Figure.4.6. Values versus fuctionality, cost and time 77

Figure 4.7.The participating in project phases 78

Figure 4.8. Values versus identification, assessment and response 79

Figure. 4.9. Values versus risk identification, assessment and response 81

Figure 4.10.Values versus risk management 82

VII
Figure 4.11.Construction Risks that face the projects in Libya 83

Figure. 4.12. Frequency versus project actors 84

Figure.4.13 Frequency versus collaboration between actors in the project 85

Figure.4.14. Delay in paying work invoices versus frequency 86

Figure. 4.15. Values versus impact on risk management 87

Figure 4.16.Frequency versus impact decision 88

VIII
LIST OF TABLE
Table No Title Page

Table. 4.1.Questionnaire distribution and respondents profile figure 72

Table. 4.2 Study risk management or project management courses 75

Table. 4.3 Values versus project Manager, contractor and consultant 76

Table. 4.4 Values Versus Functionality, Cost and Time 77

Table. 4.5 The participating in phases of the project 78

Table. 4.6 The risk management processes that carried out 79

Table. 4.7 The phasses where the risk management processes performed 80

Table. 4.8 The participation in risk management. 82

Table. 4.9 Construction Risks that face the projects in Libya 83

Table. 4.10 The Influence of project actors on risk management.

Table. 4.11 The collaboration between the actors in the project 85

Table. 4.12 Delay in payment of the work invoices and the increase in the cost

of the project 86

Table. 4.13 Option time extension and Impact on risk management. 87

Table. 4.14 Impact decisions of Change Orders in contract on risk management. 88

IX
CHAPTER I

Introduction

Today, economic growth has led to the demand for infrastructure facilities, residential and

commercial buildings, and parks. This has given rise to a high volume of development

activities and as the most frequent and typical project types have several characteristics such

as time limit, financial constraints and monetary requirements, personal organizational and

legal conditions, complexity and methodical characteristics, so each investment project itself

is sophisticated system, there are many risk facets and complicated relations, which will

affect it.

Risk management is the identification, assessment, and prioritization of risks followed by

coordinated and economical application of resources to minimize, monitor, and control the

probability and impact of unfortunate events or to maximize the realization of opportunities.

Risk management’s objective is to assure that uncertainty does not deflect the endeavour

from the business goals.

Risks can come from various sources including uncertainty in financial markets, threats from

project failures at any phase in design, development, production, or sustainment life-cycles,

legal liabilities, credit risk, accidents, natural causes and disasters, deliberate attack from an

adversary, or events of uncertain or unpredictable root-cause. There are two types of events:

negative events can be classified as risks while positive events are classified as opportunities.

Several risk management standards have been developed including the Project Management

Institute, the National Institute of Standards and Technology, actuarial societies, and ISO

standards. Methods, definitions and goals vary widely according to whether the risk

management method is in the context of project management, security, engineering, industrial

1
processes, financial portfolios, actuarial assessments, or public health and safety. Risk

management is also defined in ISO 31000 as ‘the effect of uncertainty on objectives’.

Risk sources are identified and located in human factor variables, mental states and decision

making as well as infrastructural or technological assets and tangible variables. The

interaction between human factors and tangible aspects of risk highlights the need to focus

closely on human factors as one of the main drivers for risk management, a "change driver"

that comes first of all from the need to know how humans perform in challenging

environments and in face of risks (Trevisani, 2007).

It is an extremely hard task to be able to apply an objective and systematic self-observation,

and to make a clear and decisive step from the level of the mere sensation that something is

going wrong, to the clear understanding of how, when and where to act. The truth of a

problem or risk is often obfuscated by wrong or incomplete analyses, fake targets, perceptual

illusions, unclear focusing, altered mental states, and lack of good communication and

confrontation of risk management solutions with reliable partners. This makes the Human

Factor aspect of Risk Management sometimes heavier than its tangible and technological

counterpart.

Strategies to manage threats (uncertainties with negative consequences) typically include

avoiding the threat, reducing the negative effect or probability of the threat, transferring all or

part of the threat to another party, and even retaining some or all of the potential or actual

consequences of a particular threat, and the opposites for opportunities; that is uncertain

future states with benefits).

Certain aspects of many of the risk management standards have come under criticism for

having no measurable improvement on risk; whereas the confidence in estimates and

decisions seem to increase.

2
In ideal risk management, a prioritization process is followed whereby the risks with the

greatest loss (or impact) and the greatest probability of occurring are handled first, and risks

with lower probability of occurrence and lower loss are handled in descending order. In

practice the process of assessing overall risk can be difficult, and balancing resources used to

mitigate between risks with a high probability of occurrence but lower loss versus a risk with

high loss but lower probability of occurrence can often be mishandled.

Intangible risk management identifies a new type of a risk that has a 100% probability of

occurring but is ignored by the organization due to a lack of identification ability. For

example, when deficient knowledge is applied to a situation, a knowledge risk materializes.

Relationship risk appears when ineffective collaboration occurs. Process-engagement risk

may be an issue when ineffective operational procedures are applied. These risks directly

reduce the productivity of knowledge workers, decrease cost-effectiveness, profitability,

service, quality, reputation, brand value, and earnings quality. Intangible risk management

allows risk management to create immediate value from the identification and reduction of

risks that reduce productivity.

Risk management also faces difficulties in allocating resources. This is the idea

of opportunity cost. Resources spent on risk management could have been spent on more

profitable activities. Again, ideal risk management minimizes spending (or manpower or

other resources) and also minimizes the negative effects of risks.

According to the definition of the risk, the risk is the possibility that an event will occur and

adversely affect the achievement of an objective. Therefore, risk itself has the uncertainty.

Risk management can help managers to have a good control for their risk. Each company

may have different internal control components, which leads to different outcomes.

3
1.1 RISK MANAGEMENT PROCESS

According to the standard ISO 31000 Risk management Principles and guidelines on

implementation, the process of risk management consists of several steps as follows:

1.1.1 Identification

After establishing the context, the next step in the process of managing risk is to identify

potential risks. Risks are about events that, when triggered, cause problems or benefits.

Hence, risk identification can start with the source of our problems and those of our

competitors (benefit), or with the problem itself.

Source analysis: Risk sources may be internal or external to the system that is the target of

risk management (use mitigation instead of management since by its own definition risk deals

with factors of decision-making that cannot be managed).

Examples of risk sources are: stakeholders of a project, employees of a company or the

weather over an airport.

Problem analysis: Risks are related to identified threats. For example: the threat of losing

money, the threat of abuse of confidential information or the threat of human errors, accidents

and casualties. The threats may exist with various entities, most important with shareholders,

customers and legislative bodies such as the government.

When either source or problem is known, the events that a source may trigger or the events

that can lead to a problem can be investigated. For example: stakeholders withdrawing during

a project may endanger funding of the project; confidential information may be stolen by

employees even within a closed network; lightning striking an aircraft during takeoff may

make all people on board immediate casualties.

4
The chosen method of identifying risks may depend on culture, industry practice and

compliance. The identification methods are formed by templates or the development of

templates for identifying source, problem or event. Common risk identification methods are:

Objectives-based risk identification: Organizations and project teams have objectives. Any

event that may endanger achieving an objective partly or completely is identified as risk.

Scenario-based risk identification: In scenario analysis different scenarios are created. The

scenarios may be the alternative ways to achieve an objective, or an analysis of the

interaction of forces in, for example, a market or battle. Any event that triggers an undesired

scenario alternative is identified as risk – see Futures Studies for methodology used

by Futurists.

Taxonomy-based risk identification : The taxonomy in taxonomy-based risk identification is a

breakdown of possible risk sources. Based on the taxonomy and knowledge of best practices,

a questionnaire is compiled. The answers to the questions reveal risks.

Common-risk checking: In several industries, lists with known risks are available. Each risk

in the list can be checked for application to a particular situation

Risk charting :This method combines the above approaches by listing resources at risk,

threats to those resources, modifying factors which may increase or decrease the risk and

consequences it is wished to avoid. Creating a matrix under these headings enables a variety

of approaches. One can begin with resources and consider the threats they are exposed to and

the consequences of each. Alternatively one can start with the threats and examine which

resources they would affect, or one can begin with the consequences and determine which

combination of threats and resources would be involved to bring them about.

5
1.1.2 Assessment

Once risks have been identified, they must then be assessed as to their potential severity of

impact (generally a negative impact, such as damage or loss) and to the probability of

occurrence. These quantities can be either simple to measure, in the case of the value of a lost

building, or impossible to know for sure in the case of an unlikely event, the probability of

occurrence of which is unknown. Therefore, in the assessment process it is critical to make

the best educated decisions in order to properly prioritize the implementation of the risk

management plan.

Even a short-term positive improvement can have long-term negative impacts. Take the

"turnpike" example. A highway is widened to allow more traffic. More traffic capacity leads

to greater development in the areas surrounding the improved traffic capacity. Over time,

traffic thereby increases to fill available capacity. Turnpikes thereby need to be expanded in a

seemingly endless cycles. There are many other engineering examples where expanded

capacity (to do any function) is soon filled by increased demand. Since expansion comes at a

cost, the resulting growth could become unsustainable without forecasting and management.

The fundamental difficulty in risk assessment is determining the rate of occurrence since

statistical information is not available on all kinds of past incidents and is particularly scanty

in the case of catastrophic events, simply because of their infrequency. Furthermore,

evaluating the severity of the consequences (impact) is often quite difficult for intangible

assets. Asset valuation is another question that needs to be addressed. Thus, best educated

opinions and available statistics are the primary sources of information. Nevertheless, risk

assessment should produce such information for senior executives of the organization that the

primary risks are easy to understand and that the risk management decisions may be

prioritized within overall company goals. Thus, there have been several theories and attempts

to quantify risks.

6
Likewise, the impact of the risk is not easy to estimate since it is often difficult to estimate

the potential loss in the event of risk occurrence.

Further, both the above factors can change in magnitude depending on the adequacy of risk

avoidance and prevention measures taken and due to changes in the external business

environment. Hence it is absolutely necessary to periodically re-assess risks and

intensify/relax mitigation measures, or as necessary. Changes in procedures, technology,

schedules, budgets, market conditions, political environment, or other factors typically

require re-assessment of risks.

1.1.3 Potential risk treatments

Once risks have been identified and assessed, all techniques to manage the risk fall into one

or more of these four major categories:

 Avoidance (eliminate, withdraw from or not become involved)

 Reduction (optimize – mitigate)

 Sharing (transfer – outsource or insure)

 Retention (accept and budget)

1.1.3.1 Risk avoidance

This includes not performing an activity that could carry risk. An example would be not

buying a property or business in order to not take on the legal liability that comes with it.

Another would be not flying in order not to take the risk that the airplane were to be hijacked.

Avoidance may seem the answer to all risks, but avoiding risks also means losing out on the

potential gain that accepting (retaining) the risk may have allowed. Not entering a business to

7
avoid the risk of loss also avoids the possibility of earning profits. Increasing risk regulation

in hospitals has led to avoidance of treating higher risk conditions, in favor of patients

presenting with lower risk.

Hazard prevention refers to the prevention of risks in an emergency. The first and most

effective stage of hazard prevention is the elimination of hazards. If this takes too long, is too

costly, or is otherwise impractical, the second stage is mitigation.

1.1.3.2 Risk reduction

Risk reduction or "optimization" involves reducing the severity of the loss or the likelihood

of the loss from occurring. Acknowledging that risks can be positive or negative, optimizing

risks means finding a balance between negative risk and the benefit of the operation or

activity; and between risk reduction and effort applied. By an offshore drilling contractor

effectively applying Health, Safety and the Environment Management in its organization, it

can optimize risk to achieve levels of residual risk that are tolerable.

Modern software development methodologies reduce risk by developing and delivering

software incrementally. Early methodologies suffered from the fact that they only delivered

software in the final phase of development; any problems encountered in earlier phases meant

costly rework and often jeopardized the whole project. By developing in iterations, software

projects can limit effort wasted to a single iteration.

Outsourcing could be an example of risk reduction if the outsourcer can demonstrate higher

capability at managing or reducing risks. A company may outsource only its software

development, the manufacturing of hard goods, or customer support needs to another

company, while handling the business management itself. This way, the company can

concentrate more on business development without having to worry as much about the

8
manufacturing process, managing the development team, or finding a physical location for a

call centre.

1.1.3.3 Risk sharing

Briefly defined as "sharing with another party the burden of loss or the benefit of gain, from a

risk, and the measures to reduce a risk."

The term of 'risk transfer' is often used in place of risk sharing in the mistaken belief that you

can transfer a risk to a third party through insurance or outsourcing. In practice if the

insurance company or contractor go bankrupt or end up in court, the original risk is likely to

still revert to the first party. As such in the terminology of practitioners and scholars alike, the

purchase of an insurance contract is often described as a "transfer of risk."

. Risk retention pools are technically retaining the risk for the group, but spreading it over the

whole group involves transfer among individual members of the group. This is different from

traditional insurance, in that no premium is exchanged between members of the group up

front, but instead losses are assessed to all members of the group.

1.1.3.4 Risk retention

Risk retention involves accepting the loss, or benefit of gain, from a risk when it occurs. Risk

retention is a viable strategy for small risks where the cost of insuring against the risk would

be greater over time than the total losses sustained. All risks that are not avoided or

transferred are retained by default. This includes risks that are so large or catastrophic that

they either cannot be insured against or the premiums would be infeasible.

9
Risk management planning selects appropriate controls or counter measures to measure each

risk. Risk mitigation needs to be approved by the appropriate level of management. For

instance, a risk concerning the image of the organization should have top management

decision behind it whereas IT management would have the authority to decide on computer

virus risks.

The risk management plan should propose applicable and effective security controls for

managing the risks. For example, an observed high risk of computer viruses could be

mitigated by acquiring and implementing antivirus software. A good risk management plan

should contain a schedule for control implementation and responsible persons for those

actions.

1.2 Limitation

Prioritizing the risk management processes too highly could keep an organization from ever

completing a project or even getting started. This is especially true if other work is suspended

until the risk management process is considered complete.

It is also important to keep in mind the distinction between risk and uncertainty. Risk can be

measured by impacts and probability.

If risks are improperly assessed and prioritized, time can be wasted in dealing with risk of

losses that are not likely to occur. Spending too much time assessing and managing unlikely

risks can divert resources that could be used more profitably. Unlikely events do occur but if

the risk is unlikely enough to occur it may be better to simply retain the risk and deal with the

result if the loss does in fact occur. Qualitative risk assessment is subjective and lacks

consistency. The primary justification for a formal risk assessment process is legal and

bureaucratic.

10
1.3PROJECT MANAGEMENT

Project risk management must be considered at the different phases of acquisition. In the

beginning of a project, the advancement of technical developments or the response to threats

presented by a competitors projects, may cause a risk or threat assessment and subsequent

evaluation of alternatives. Selection of a response presented by technology options, or

competitor threats are important applications of risk management. Once a decision is made,

and the project begun, more familiar project management applications can be used

Planning how risk will be managed in the particular project. Plans should include risk

management tasks, responsibilities, activities and budget.

 Assigning a risk officer – a team member other than a project manager who is responsible

for foreseeing potential project problems. Typical characteristic of risk officer is a

healthy scepticism.

 Maintaining live project risk database. Each risk should have the following attributes:

opening date, title, short description, probability and importance. Optionally a risk may

have an assigned person responsible for its resolution and a date by which the risk must

be resolved.

 Creating anonymous risk reporting channel. Each team member should have the

possibility to report risks that he/she foresees in the project.

 Preparing mitigation plans for risks that are chosen to be mitigated. The purpose of the

mitigation plan is to describe how this particular risk will be handled – what, when, by

whom and how will it be done to avoid it or minimize consequences if it becomes a

liability.

11
1.4 OBJECTIVES:

The objectives of this study are as follows:

 To study the impact of risk factors on the projects in Libya .

 To identify risk and study their management in construction in Libya.

 To formulate strategies for optimizing risk management in Libya .

1.4.1 RESEARCH QUESTIONS

To realise these aims, the following research questions have been formulated.

1. What is the process of risk management?

2. How to apply risk management in construction projects?

3. What risks are there in construction projects in LIBYA?

4. How can the risks be identified and assessed before and during construction period ?

5. How risks can be controlled during construction period?

6- What kind of risk management is applied in the construction companies’ management

systems in Libya?

7- What impact does the chosen time extensions option have on risk management?

8- What impact does the decisions of quantities adjustment in contract on risk management?

12
1.5 STATEMENT OF THE PROBLEM

Risk has a great impact on the performance of residential projects in Libya in terms of cost,

time and quality has increased the size and complexity of the projects and has become the

ability to manage risk in all phases of the construction process a central element to prevent

unwanted consequences. Since the prime minister of the Libyan government, issued a

decision in 2005 to build 200, 000 housing units to be delivered to citizens in 2011, most of

these projects have delayed and have not been delivered in Libya, after several years ).

1.6 SIGNIFICANCE OF THE STUDY

This research aims to let everyone understand the risks management in Libya , through a

deep study procedure on the application of risks management in building projects in Libya,

especially since the prime minister of the Libyan government, issued the decision in 2005.

Moreover,

 This study will enable the researcher to discuss some of the risk factors affecting

building projects.

 It also aims at bringing into clear focus the benefits and importance of applying

risk management processes to achieve best results in Libyan projects.

1.7 SCOPE OF THE STUDY

The scope of this study basically focuses on risk assessment of building projects in Libya for

both clients and contractors. Thus the study includes ten projects which will comprises of

about (27,571) housing units having been carried out in Libya, since the prime minister of

the Libyan government, issued a decision in 2005 to build 200, 000 thousand housing units

to be delivered to citizens by the year 2011.

13
CHAPTER II

LITERATURE REVIEW

2.1 Preliminary Remarks

The following researchers have carried out study on the delay of construction projects:

Ali (2006), carried out a field study of the main reasons for delay in construction projects in

Saudi Arabia and the results of the study, indicated 56 reasons for the delay. The main

reasons are listed below: -

1- Authentication of maps.

2- Delays in certificates of payment during the implementation period.

3- Change in engineering designs.

4- Conflicts due to the Schedule for the subcontract.

5- The slowing in decision Making

6- Mistakes in designs

7- Lack of expertise

Jaser (2006), analysed 44 project risks factors in Palestine, and found that the most

dangerous factors from the point of view of construction companies are: Contractor failed

financially, and the vicinity of the project from dangerous areas, the blockade, the wrong

design, and delayed payments. But the most dangerous factors from the point of view of

owner were: the wrong design, accidents at work, and access to the site, and the lack of real

quantities.

14
The results showed that there are a large number of risk factors in the construction companies

and project owners cannot identify these risks. Also, the contractions companies still rely on

direct assessment based on experience and have neglected the modern methods of risk

analysis and estimate the time needed for the project and cost.

Kajsa (2006) found that, small projects in Sweden lack systematic risk management. In a

business where the core value is to handle continuously arising uncertainties, the small

projects rely on the experience and personal judgments of individuals to do their risk

management continuously throughout the project life cycle. Timetables, quality surveillance,

and detailed work plans are common methods used. Tools are either checklists or blank

pieces of paper. This way of controlling risks and uncertainties are not to be regarded as

systematic risk management.

Mohamed (2006), observed that, the construction projects in Egypt cause many difficulties

during the implementation and unexpected problems at the design stage. In some cases, these

problems are the result of the same design. In most cases, the consulting engineer or

supervisor resort to diligence in solving these problems through the instructions issued to the

contractor by a simple change orders. In both cases these problems concern the engineer.

And usually it leads to the claims of the contractor which finally lead to an increase in

unforeseen cost of the project and its duration. The purpose of research is to study the types

of claims and sources that occur in construction projects mainly as a result of design.

Samir (2006), aimed to apply critical path method (CPM) and technology of Earned Value

Management System (EVT) to avoid delays in construction projects. The researcher found

through his studies that the most important reason for delays in construction projects is the

technique applied i.e., critical path method (CPM).

15
The primary objective of this (EVT) is the conclusion of any negative deviation from the plan

as early as possible and carry out corrective actions. The timeline for the project network

schedule is basically to do comparisons with the actual performance of the project. (GANTT)

charts can be used to represent this scheme graphically on a time axis, and especially when

the results are shown to senior management in the organization.

Hindawi (2007), designed a questionnaire including (78) causes of project delays. It was

classified into four items (categories) and offered to form in multiple courses with the method

of the Delphi ( Delphi method). Variance was used to check the sample answers. ANOVA

was also used to calculate the arithmetic averages for each of the occurrence and importance

of the causes then determine the number of points within the moral scale score. The use of

regression analysis (regression) was done to investigate the relationship between the number

of years of experience and the rate of ratio of the delay by the respondents.

It was concluded that the most common reasons for delay in projects occurring and strongly

influential are:-

1. Delay in laboratory tests of materials

2. Business transfers

3. Inefficient financial Contractor

4. Abnormal rise in the prices of materials

5. Miscalculation by the contractor at the time of implementation of the project.

16
Maher (2007), This study carried out in Lebanon showed that most of the causes of delay in

construction projects in Lebanon are: Factors relating to financial problems, contractual

relationships and project management.

Mohamed (2007), disclosed in Tunisia that the main aim from definition of risks, is to

identify appropriate strategies to confront them or avoid them at least to reduce the severity

or transfer to the other. The most important conclusions are the following:

1-Studying the risk in the project seriously and not to start the implemention of the project

until there is a management or specialized risk management working team .

2- The risk management team will continue its work on the project and do not stop until the

end of the project because the risks may appear at different stages of the project life cycle.

3- Develop the capacity of a team of risk management in the project, whenever skill required

was high, results were more accurate and therefore can overcome the risk or reduce the

severity at least.

Salih (2007), carried out in Syria addressed the fundamental problem faced by all projects in

any of the phases where the risk leads to additional costs or require the allotment of

additional resources such as time and labor as these are all additional costs. What explains the

importance of the subject is the large number of projects that fail either in construction or in

the development of information systems and new solutions. The study indicated that only

30% of organizations conduct a risk analysis in information technology projects.

Seung (2007), carried out this study in Indonesia and revealed that, methods relating to

decisions in the international construction markets include all cases of anxiety and

uncertainty in the local construction projects in addition to the risks of international

transactions. A comprehensive approach to take decisions about international projects was

17
developed by using the method of analysis of the impact - the intersection (Cross - Impact

Analysis) in order to predict future events through activities between variables.

Yarab (2007), In this research conducted in Jordan, there has been the development of risk

matrix and the expected yield which can be identified on the organization's position in the

environment in which it operates and identify what are the most important factors which

could occur in the performance of the organization and get an ongoing assessment of the risks

and how those risks affect performance in general through the study of joint relationship

between risk and yield.

Adnan (2008),Concluded in Palestine that, the supervision of subordinates in order to

minimize faulty work and good coordination with subcontractors are considered to be the

most effective risk reduction method used in the construction industry. It is recommended

that bids should be awarded to true estimated cost bidder and not necessarily to the lowest

bidder. Exchange rate fluctuations should be considered as a risk factor for owners and

donors and they should offer a compensation mechanism if there was any damage due to this

risk. The process of design is the most important phase in the construction steps. Design

products should be the highest level of quality and should have more focus by owners.

Almwmany (2008), The researcher studied more than 130 projects records in Jordan and

tried to design a mathematical form of the relationship between the schedule and

implementation. The study results showed that the designer is the first reason, climate and the

different work site conditions are the second reasons. He designed a mathematical form

(linear simple) of the relationship between the expected time to finish the work and real time

project by a degree of 99 % .

Enshassi (2008),The researcher found in Palestine that, the most important legal risks are

legal disputes during the construction between the parties of the project. According to him,

18
they are of medium importance of risk because the probability of occurrence average are

close to low, because they understand the importance of solving problems between the parties

before it reaches the judiciary. The consequences of their arrival at the judiciary have

redundant costs and takes time to be resolved judicially.

Political risks that cannot be controlled such as bribery and corruption are at the forefront of

political risk. But it is important medium, and the results showed that the probability of

occurrence of these risks are medium and has a medium impact. Therefore, it is necessary to

address them and not to be neglected. The rest of the political risks are the risks of low

importance such as the political risk all of which have a low probability of occurrence due to

the stability of the country's politics and security .

Hafez (2008),Identified in Iraqthat,the risks of fluctuating supply and demand of materials,

equipments or labour and changes in government policy are more prominent than the risks of

qualitative assessment hand and risks of changes in government policy. Fluctuations of

demand on the material and internal factors are more prominent from the terms of relative

importance. A management system could be adopted in the qualitative assessment of the risks

and the simulation of this evaluation using a technique for quantitative assessment. In order

to benefit from the advantages of software program it can also adopt administrative principles

to design the proposal system.

Namara (2008),Revealed in a study conducted in Malaysia found that, risk management is

an attempt to identify potential threats to the project and the probability of risk occurrence

must take appropriate actions to address these threats and verify the probability of their

occurrence. This must include risk management process definition and identify risks, mitigate

and reduce risks, and follow-up risk.

19
Amal (2009),Results of the study conducted in Syria found a set of recommendations

including:

- Raising awareness of the role of strategic factors in project management performance,

especially private ones.

- Adopting the entrance of "total quality management" standards as a strategy, based on a

deeper awareness of the role and importance of quality.

- Dealing with the case study can be applied to any project planned strategically as it needs to

improve the effectiveness of the Calendar action through comprehensive and competitive

quality standards.

Mustafa (2009 ),This study in Libya aimed to teach the owner, consultant and construction

companies in the public and private sectors of the importance of apply methodology

(Understanding the Time Delay in Libyan's Construction Projects using Lean Six Sigma

DMAIC Methodology) , known as ( DMAIC) to avoid delays across projects construction in

Libya.

The researcher found that most of the problems are concentrated in the definition

methodology ( DMAIC) stage, known as phase planning project by 28%, then assess phase

at 20%, then the analysis phase by 19%, then the control and surveillance of 18% stage, and

finally found that the delay problems due to lack of follow-up improvement operations of

15%.

The results also showed that the most important factors of the delay are:

1- Bad planning of the project

2- Schedule and financial problems of the contractor.

3- The project cost estimate, poor site and supervision management.

20
4- The work team is not qualified for the project.

5- Lack of equipment, labor and construction materials.

6- Miscalculation timeline for the project.

7- Difficulties in monthly payments.

8- Change in the workplace.

9- Sub-contractors are not eligible.

Oday (2009), Identified reasons for the delay of project construction in Jordan. Seven main

groups were related to the owner and each group included the following reasons such as late

payment certificates, intervention of the owner in the work, slow in adoption of decision,

wrong estimate for implementation of the project, factors related to contractor in the

management of the work site, construction methods , planning unsuitable for the project and

the mistakes in the implementation period, lack of experience of the contractor, and included

factors related to consultant quality control, and the time of waiting for the results of

materials tests.

Samira (2009),This study recommended reasons for delay in construction projects in Libya

to the necessity and cooperation in the study phase and design phase to avoid problems

before they occur and to improve the performance of projects in Libya.

The researcher found that the problem of delayed bank credit and non-payment of payment

certificates are the most important reasons for the delay in critical Path Method. , where at a

value of 90.6% , the responsibility of these problems occur on the owner as he determines

the degree of influence. The reasons of delay of the main objectives of projects are duration,

cost, and quality while the most common reasons are the duration of the project due to central

administration and instability in administration.

21
Suad (2009),Studied in Saudi Arabia that the cost and risk assessment during the

implementation phase of the project is a key factor for success and control of cash flows

through that stage.

The things affecting increased cost of risks are the impact the creation of designs, drawings

and methods of contracting and other factors and their impact for the formulation of cash

flows and avoid disputes that often occur due to lack of understanding or confusion

regarding cash flows or Payment certificates. The research showed that there are a lot of

factors that have an impact in increasing the cost of risk. Design requirements is one of the

most important factors that influence (80%) the cost overrun of the project, followed by other

factors with less impact.

Adel (2010),Observed in Iraq that, project risk management process helps project owners and

project teams make decisions regarding alternative plans to achieve their objectives and the

risk involved in each item. In order to increase the likelihood of success of meeting the most

important objectives is the time. Sometimes at the expense of other objectives , risk

management encourages the project team to take appropriate measures to reduce adverse

effects to the project such as cost, schedule, and quality to maximize opportunities to improve

the project’s goals with lower cost, shorter schedules, enhanced scope and higher quality and

minimize management crisis.

El-Sayegh (2010),This study carried out in Kuwait identified that designers generate risks

such as defective design, deficiency in drawings, changes in design and documents not issued

on time. Design risk arises when there are design errors and omissions as well as design

change. This source of risk includes defective or incomplete design documents,

inconsistencies, and flaws among the plans and specifications. Design errors could be due to

defective design, and unavailable or inappropriate design detail. These happen due to:

22
incomplete design scope; incomplete or erroneous geological and geotechnical exploration;

and inadequate interaction of design with methods of construction.

Nasser (2010),This study identified the reasons of delay in construction projects in the city of

Benghazi, Libya. The necessity to solve the problem of delays in the implementation of

projects and taking tough administrative steps to reduce this phenomenon through suitable

planning and good control to the activities of design and construction works. The study

recommended the necessity to follow the planning phase , and coordination and work on the

reorganization of oversight of government enterprises .

One of the main reasons for delay in construction projects in Libya delays are: -

1- .Mistakes in the estimate of the project in terms of money and time

2- Lack of good study projects.

3- Instability of Administration.

Salem (2010), Identified cash flow and financial difficulties and transfer to lower bidding

work form the most important reasons for the delayin construction projects in Iraq. The

contractor is primarily responsible for the delay, followed by the owner and consultant.

Compensation claims resulting from causing delay, change orders and additional work are the

most important causes of conflicts.

Zakria (2010), Study carried out by him in Libyarevealed that the Audit Bureau report on the

supervisory and operational performance assessment in the municipality for the low

percentage of cash flow on projects extending implementation for several years during the

year 2009/2008 was 3.9% only.

23
The report criticized the delay in the termination of some building-operation transfer and

dates of projects, due to the slow pace of the proceedings and delay in the handing of

locations of the companies executed.

The report included the lack of proper planning of the labor force in the municipality and the

lack of clarity of the functions assigned to the heads of branches of the municipal sectors and

the lack of standard rates for employee performance by each administration.

Fouzi (2011), found that valuation of companies in Libya is a key factor for the success of

the project by making sure the financial, technical and administrative ability and its expertise

in the construction. The field study created a form to test construction companies before

contracting with them. The aim of this form is to ensure the ability of financial, technical and

administrative capacity of companies. Companies that don’t possess the conditions in the

form cannot be contracted.

Herroelen (2011),Observed in Ireland that, risk management is generally a part of other

management systems such as quality, environmental or work environmental management

systems. Some of the core values are environmental management systems, the pledge of all

employees, customer concentration, management commitment, focus, continuous

improvement, and fact-based decisions. These basic values are closely connected and could

easily be found in the theoretical framework of risk management.

Sajida (2011),This study conducted in Palestine aimed to evaluate the applications of

projects management pursued by different departments in the public sector in Palestine,

particularly in the Ministry of Public Works and Housing, as well as aiming to explore

effective techniques in project management within the public sector as well as to understand

the main factors that prevent the achievement of goals of the project.

24
In order to achieve the objectives of this study, a survey was conducted on a questionnaire

between the general managers, department heads, and project managers from various

departments in the Ministry of Public Works and Housing. Results of the study demonstrated,

that there was lack of efficiency in the application of the project management in the public

sector in Palestine, compared with the recommended international practices. Project

management in the Ministry of Public Works and Housing practices was seen as a medium

compared to global standards, poor follow-up and not to disseminate the lessons learnt from

previous projects. There was lack of effective communication between the project team, and

lack of intensive planning, the failure to adopt a clear methodology was such major factors

that impeded the achievement of project objectives.

Waji (2011),Identified how to face the crisis in construction projects in Malaysia: -

1 - Adoption of early warning systems and good planning to contain any crisis before they

happen to develop scenarios and solutions appropriate to each what is expected of crises

before they occur and the training of workers, and to provide data of all the information

necessary to manage the crisis and prevent or get out with minimal losses base.

2. Readiness and speed of dealing with the crisis: Time is a factor of great importance for

both individuals and institutions, the more the individual or institution is ready and and has

the ability to deal with the event with all the needed things possible to control the crisis and

contain it and get out with minimal losses.

3 - An important factor to deal directly from reassured factors and a reflection of confidence

in the ability to deal with the crisis, and helps to know the magnitude of the crisis.

4 - Transparency in dealing with the crisis play an important role in dealing with the crisis

both for the states or organizations or individuals must put the full truth in a timely manner so

25
that the concerned authorities understand the crisis and provide a helping hand to solve or

reduce their impact.

Faisal (2012), revealed that projects in Saudi Arabia require a feasibility study to be carried

out by the Project Management Office and documented before presenting the project based

on the following steps:

1. Identify the need to work and show the actual need for a new project

2. Conduct a study of the need to work in coordination with the relevant departments and

estimate the cost and then submit to the Dean of Information Technology for approval.

3-If approved, the project idea is based on the Project Management Office to prepare the bid

requirements and specifications of the project externally.

4- Procedures are followed in competition law within the Kingdom of Saudi Arabia in order

to launch a new project.

5- The Office of Project Management share the study of the technical offers for the selection

of the contractor depending on technical standards prepared for the project.

6- If awarded the project, the contractor is assigned an engineer supervisor of the Project

Management Office or one of the relevant departments for follow-up with the contractor at

the beginning of the project.

Karim (2012),Observed in Iraq that more awareness is required about risk management with

respect to insurance, organizational policy planning and implementation, project management

and general management skills , finance, economics, law, and accounting. Construction

organizations need to define well-organized responsibilities and authorities for all

26
stakeholders, by which risk management processes can be established for senior engineers

working in construction projects.

Mohammed (2012), Identified that in Syria, people must know the degree of risk before the

start of any project to achieve goals. The project manager must know what will happen and

what should be done in the event of any change to find support for the project plans such as

transferring resources from inside the project.

He must know the likelihood of changes because he must continue the project without delay

and have justification for that. Other costs or extra time or slow performance would weaken

the project and these are exposed to costs He should develop a plan for the unexpected and

speculate time and budget.

Mona (2012), carried out a study in Syria found that the risk of inflation and price

fluctuations and differences between actual and contractual quantities are one of the most

important risks.

Assaf (2013),Observed that there are fifty-six reasons for the delay of projects in Palestine

and puts it in nine items and found an agreement between the owner and the contractor

consultant in arranging importance of the reasons. Financial matters ranked first between the

items.

Defrawy (2013),The researcher studied in Egypt thatdelay in projects can be grouped into

two main reasons as justified and unjustified reasons:

First justifiable reasons:

-Emergence of risks during the project implementation as subjected to weather conditions

such as floods and damage part leads to the contract extension, sudden loss of material

27
associated with implementation of the project by force majeure as close factory ... leading to

the contract extension, and restoration and maintenance of projects because of the uncertainty

of some of the items hidden .

Second unjustified reasons:-

-Reasons related to the source of the study, lack of investigation, errors in the design of

various specializations, errors in the estimation of quantities, and errors in the book of

conditions and technical specifications, such as lack or multiple possibilities of interpretation.

Haitham (2013), According to him, the main challenges facing management are to estimate

the level of risk by the position holder, to estimate whether management is aware of the risk

and are implying their knowledge in avoiding risks. Top management should investigate

various types of risks facing the business , and how to manage the risk via education or past

experience and other sources.

Hussein (2013),This study in Libya found construction projects with risk and uncertainty of a

special nature because of length of the implementation period that lead to changed

circumstances making it contain multiple risks. The most important risk facing projects is that

companies are unable to implement projects in time with the required quality and budget and

specifications agreed upon.

The assessment of companies is a key factor in the success of projects by ensuring financial

and technical capacity and managerial experience in the previous risk management.

Jaser (2013), Reported that the contractors and owners still depend on traditional approaches

to managing risk factors and their consequences in Kuwait.

28
The use of direct judgment to control risk factors was the most applied method used to

control risk events and these results assure the need to develop the used methods for

managing risk factors.

Use of quantitative methods, computer systems or sensitivity analyses were not practiced by

respondents, they also depend on direct judgment and comparing analysis to analyze risk

consequences .

Sameh (2013), Concluded that the construction sector is facing two main reasons relating to

production, and information infrastructure and that the construction sector in Dubai, is one of

the basic employment and income growth in the emirates. The sector faces five major

challenges which need immediate attention to help the construction sector to face the

economic crisis and recession. The study revealed that the first of those risks, i.e the supply

of inputs and inflate costs, which impacts on the profitability levels, as the lack of

infrastructure to provide that information leads to the risks, due to a significant imbalance

between supply and demand. The global financial crisis has caused a slowdown in the

construction sector, but a correction that has occurred in this sector succeeded compared to

the economies of other countries with large contracting sectors.

Ali (2014),Observed in Tunisia that contractors want owners to accept and share more risks

with them. This can be attributed to two factors; first, owners have some control over some of

the risks, for example, the payment on contract, changes in work, and scope limitations and

work definition.

Second, because the high competition in the market has slowed the economy in recent years,

the surveyed risks have the highest impact on the schedule of a project while the same risks

affect the safety of the project. Most of the risk categories affect schedule and budget more

than other project parameters.

29
Aouda (2014),Carried out in Iraq, the study identified the preliminary study for the

implementation of projects of great importance in estimating costs and provide financial

surplus after running the project and invest in direct need of infrastructure projects and the

employment of local labor, training and exploitation of income in raising individual and

household level.

This is able to reduce unemployment and optimization of staff (technical, administrative) and

dispensing import of many products as long as it can be produced locally.

Heba (2014), This recent study in the Emirates, Dubai, showed that a lot of insurance

companies in the Arab region and the Arab Gulf face some challenges when they are

submitted to insurance services associated with some major projects in the world. This has

spread dramatically recently, and has become so much representing distinctive landmarks in

the cities and the Gulfian states.

The study included a survey of the views of officials in the local insurance industry to know

if the local insurance companies suffer from these challenges, and whether they are capable

and qualified as required to insure this type of project as well as various mega big financial

value in state projects. Most insurance companies at the moment do not have the

qualifications and no possibilities to deal with this major development projects, and to be able

to do so, it must combine the efforts of local insurance companies to work together with each

other as joint coordination will increase the financial capacity and the exchange of

experiences and competencies through work joint committees between these companies. In

addition to bringing in expertise from abroad to assist in the work on such projects.

30
Muhammad(2014),Observedin Algeriathat, in order to minimize the chances of failure or

under performance of a partnering, risk management techniques must be introduced into the

construction industry. Critical risk factors must be identified before making any meaningful

Partnering agreement. The critical risk factors can be systematically studied based on

internal, project-specific, and external risk groups.

Shenila (2014),This study revealed that 90% of companies in Saudi Arabia do not use

enterprise management system while companies that do not use the administrative and

financial resources planning system are more than 60%. Project delays due to many reasons,

including the financial, technical and administrative reasons.

Competencies in civil engineering and planning are available and the numbers are good but

there are shortfalls in specialized competencies in the fields and administrative micro-projects

such as risk management, scheduling, and quality management. Government agencies lack

the understanding of the obligations of the contracts because the multiplicity officials

responsible for the contract are transferred to work on others. More importantly, some of

them lack experience in the subject of the contract.

Alexander ( 2015),This study carried out in Egypt revealed that,risk management is a

complicated process that interrelates with many other processes in the construction industry.

Investigating project risks includes studying potential events that may affect the scope, cost,

time, or performance of the project's objectives. Investigating potential risks requires the

collaboration of all disciplines contributing to the project. Technical, managerial, financial,

and administrative departments of the participating firms. Organization’s risk management

policy should set out its approach to risk management. The policy should also set out

responsibilities for risk management throughout the organization.

31
Eriksson (2015),In Sweden, the construction sector at some time suffered from poor

performance and lack of control in most steps of the execution process due to the sector’s

problems with many faults and increasing buildings costs.

The government initiated and assigned a commission whose assignment was to concentrate

on where are the problems and how to increase the effectiveness instead of the costs. They

found amongst other things the cost and the construction faults, risks and other uncertainties

can cause losses leading to increased costs, delay in construction period and lack of quality

during the implementation of the projects.

Falqi (2015),The researcher did not find any similarity in the reasons for the delay between

the two countries and that the factors related to contractors emerged first, and then the special

factors that is, the owner, and that there is an agreement between the project team members

in Saudi Arabia. He tried to find mathematical relationship between the causes of delays in

various stages of the project but did not receive any important correlation between them.

Gunhan (2015),Observed that in the Philippines, international projects are generally more

difficult to manage due to conditions such as multiple ownership, elaborate financial

provisions, and different political ideologies.

32
CHAPTER III

MATERIAL & METHODOLOGY

Research Design

This study was a descriptive study for collecting information about risk factors associated

with building projects in Libya.

Study area

The study was conducted in the major cities and towns in Libya where housing projects for

Libyan citizens were being constructed.

Study Population

The study includes ten projects for a total of (27,571) housing units been carried out in

Libya, a decision by prime minister of the Libyan government, issued in 2005 to build two

hundred thousand housing units to be delivered to citizens by 2011 but most locations with

the lack of sufficient labor and funds have led to delayed delivery in Libya.

Sample size

The study considered ten large projects in the major cities in Libya. Data was collected from

10 sites visited to know the dangers and difficulties facing the implementation of housing

projects during the implementation period, which led to delay completion, and the risks faced

by them.

33
Sampling procedure

The main sampling technique employed in this research are the simple random sampling

Simple random sampling was used to select the various project managers and staff at the site.

It gives each respondent an equal opportunity of being selected.

Tools and Technique for data collection

 There was interview schedule prepared for the project managers and contractors.

 All the respondents were questioned about the main factors causing the delay of the

 project at the various sites and locations in Libya.

Methods of data collection:

Data was collected through Questionnaire and face to face interview with the respondents at

their convenient times.

Management and Analysis of data

Data collected was analyzed using the SPSS(StatisticalPackage for the Social Sciences)

software version 20. Furthermore, the analysis and interpretation of data was done in

diagrammatic form, tables, and graphs using frequencies and percentage analysis.

34
Ethical Issue

1) Before the collection of data from the respondents, they were fully informed about the

overall aims and objectives of the study and verbal consent will be taken from them.

2) Project managers and site contractors’ privacy and confidentiality was maintained in the

process of the data collection.

3) Respondents were not forced to participate in the study without their interest.

4) Data was collected at the convenient times of the respondents when they are available for

best results.

35
3.1 Case Study :-

In order to get a more realistic data, the sites of projects in many cities were visited. In all, 10

sites containing 27,571 housing units where working projects have temporarily stopped

because of lack of sufficient labor and funds. The author met with the project managers at

various locations, talked to them at length about the dangers and difficulties facing the

implementation of housing projects during the implementation period, which led to delay in

completion.

Due to security disturbances in Libya since 2011, some the foreign companies that

implement thousands of housing projects were forced to evacuate staff from Libya. The

successive regional security unrest sparked fears in the foreign companies because of the

possibility of exposure of human and material assets to more vandalism and destruction

pushing some of them to stop all their activities and withdraw from Libya.

Moreover, the researcher also met with some of the Deans of Municipalities at locations

where work on housing units have stopped for some time to figure out the reasons.

The project risk associated with each housing unit and their details at various locations have

been classified below according to the answers provided by the project managers:

36
3.1.1. Construction of (1612) housing units in Wadi AlshaticityBrak
"LIBYA " Implementation By "Rawaws" company of Investment
Contracting and Real estate .

Background of the Project:-

The project area is located in the west of the city about 3 km from its centre. This area lacked

large residential projects which will bring with it a large number of the population of the

region, and cover the pressing demand for housing in the area and its environs. The 1612

housing units project in " Wadi Alshati" which was one of the projects that have been

selected. Each unit consists of three rooms , two bathrooms and kitchen.

Project name:- Construction of (1612) housing units in Wadi Alshaticity.

Contract number: - 571/2007.

Contractor: -" Rawaws" company of the Investment Contracting and real estate .

The contract value of the Libyan dinar :- 174,731,032.000 LYD

Site handing over date: - 26-10-2008

Period of implementation: - 30 months.

Duration of the extension of the contract to the contractor: - 22 months

Date of work on the project stopped: - 17-02-2011.

The date of the resumption of work on the project: - 14-07-2013

Percentage of execution: - 57%

37
Construction Related Risks

Meeting with the supervisor of this project engineer " Rashid Abdul Rahman" and

discussing with him about some of the most important risks that face the project, his response

included the following:

1- Legal risks:-

The project manager reported that legal risk is one of the significant risks faced by the project

before and during the construction period due to the lack or absence of a legal vision of the

requirements or possible modifications in the project in terms of legislation related to the

environment, urban planning, real estate purchase and compensation of owners and initiating

legal proceedings before the courts. All of these risks delayed the implementation of the

project for a long period of time.

2- Financial Risk:-

Financial risk is one of the most important risks that have affected the progress of work on

the project altering the prices of construction materials and non-payment of the work invoices

executing exchange in a timely, as well as the change in exchange rates all this led to the

delay in the project.

3-Technical risks:-

There are many technical errors encountered by the project and caused delays in its

implementation for a period of time including the lack of monitoring in terms of studies,

maps, architectural and construction, which made them resort to modifying designs by work-

site requirements and this requires additional work added to the original value of the contract

this needs the approval of the Housing Infrastructure Board and facilities additional works all

of which need a long time for approval of the amendments.

38
4-Security risks:-

Security risks in Libya have had a negative impact on the implementation of the project. Most

workers returned to their home countries because of the security situation in Libya since 2011

and we are facing a problem in convincing them back to work.

Figure3.1:Construction of (1612) housing units in Wadi AlshaticityBrak

39
3.1.2. Construction of (128) housing units in Akhlafe Ubari city "LIBYA "
Implementation By "Wadi Alfouz" company of Investment Contracting
and Real estate .

Background of the Project:-

This project is located in the municipality of Ubari "Okhalif" area and is one of the largest

housing projects, which will be dedicated to young people. The housing which is a ground

dwelling consists of a lounge and three bedrooms, two bathrooms, a kitchen and a room for

guests with an area of 220 m2. In addition to the many facilities attached to this project, is a

school and mosque compound, a hospital and the administration .

Project name:- Construction of (128) housing units in Ubari city "Akhlafe"

Contract number: - 208/2008

Contractor: - "Wadi Alfouz " company of Investment Contracting and Real estate .

The contract value of the Libyan dinar: - 15,027,200 LYD

Site handing over date: - 20-05-2009

Period of implementation: - 450 days

The date of signing of the contract: - 17-05-2008

Duration of the extension of the contract to the contractor: - 22 months

Date of work on the project stopped: - 24-07-2015

Percentage of execution: - 97%

40
Construction Related Risk:-
Meeting with the supervisor of this project engineer " Mohamed Ramadan " and asking

him about the most important risks that face the project, his answers were as follows: -

1-Legal Risks:-

Shortages or lack of legal vision requirements or potential adjustments where there are no

additional work on the project for taking a long time to be approved by the infrastructure of

the Housing Council and also there are legal proceedings for taking a long time in the Libyan

Audit Bureau when examining contracts. All this these have contributed to the project delay

and why it is not completed in time schedule.

2-Technical Risks:-

Special project new amendments are made during the implementation resulting in improper

estimation of the quantities necessary for the implementation of the project materials, as well

as having a lot of technical errors in the maps, architectural and construction of the project

causing the work to stop until it is corrected.

3- Financial Risks:-

Higher prices for materials used in the implementation of the project as well as the increase

of the daily cost of labor and the currency exchange rate changes, as well as non-debt

companies paid by the Libyan government.

4-Security risks:-

The security risks in Libya has a negative impact on the implementation of the project since

2011 and now face a big problem where people live in these housing units before completion

and still to this day in the apparent absence of the police, cannot intervene to get them out.

41
Figure 3.2:Construction of (128) housing units in Akhlafe Ubari city

42
3.1.3.Construction of (140) housing units in El Houamed city "LIBYA "
Implementation By" Almodrjat" company of Investment Contracting and
Real estate .
Background of the Project:-

This project is located in Aljabel Algarbi "El Houamed" area and is one of the largest housing

projects, which will be dedicated to young people, the housing is a ground dwelling

consisting of a lounge and three bedrooms, two bathrooms, a kitchen and a room for guests

with an area of 220 m2 .

Project name:-Construction of (140) housing units in "El Houamed" city

Contract number: - 59/2008

Contractor: - " Almodrjat " company of the Investment Contracting and real estate .

The contract value of the Libyan dinar: - 14,896,000 LYD

Site handing over date: - 01-01-2008

Period of implementation: - 30 month

Duration of the extension of the contract to the contractor: - 22 month

Date of work on the project stopped: - 24-02-2011

Percentage of execution: - 90%

43
Construction Related Risk:-
Meeting with the supervisor of this project engineer "Tariq Ahmed" and asking him about

the most important risks that face the project, his answers were as follows:-

1-Legal Risks:-

Delayed delivery of the project after the signing of the contract agreement leads to legal

action which may take a lot of time between the infrastructure of the Board of Housing and

the Office of the Libyan accounting, as well as having a lot of disputes over land and

compensation of ownership before the courts. This may cause delay of the implementation of

the project on time.

2-Technical Risks:-

Wrong estimate in calculating the amounts in the project, requires modified and the presence

of a lot of technical errors in the specifications agreed to the contract, which requires orders

to modify and increase the value of the contract and requires approvals from several entities

related to the project.

3. Financial risk: -

Delays in invoices of executed works, causes delays in the completion of works items in the

next stages of the project and this makes the contractor lose confidence in the owner of the

project and therefore will delay the work in site. In addition to the change in prices of

construction materials and the difficulty in obtaining them in Libya.

4-Security risks :- The security risks in Libya has a negative impact on the implementation

of the project since 2011 and now face a big problem where people live in these housing units

before completion and still to this day in the apparent absence of the police, cannot intervene

to get them out.

44
Figure 3.3:Construction of (140) housing units in El Houamed city

45
3.1.4. Construction of (341) housing units in Elmahrougha "LIBYA"

Implementation By "Fangah" company of Investment Contracting and

Real estate .

Background of the Project:-This project is located on the main road west of Barak city

about 30 km away from the city, which is a residential units with a ground floor area of each

225m2 contains three bedrooms, two bathrooms, a living room and an outdoor fence

surrounds the building, and there is in this project, a school garden and a hospital.

Project name:-Construction of (341) housing units in "Mahrougha "

Contract number: - 41/2008

Contractor: -"Fangah " company of the Investment Contracting and real estate .

The contract value of the Libyan dinar :-49,823,600,000 LYD

Site handing over date: - 09-11-2008

Period of implementation: - 18 months

Duration of the extension of the contract to the contractor: - 22 months

Date of work on the project stopped: - 17-02-2011

Percentage of execution: - 45%

46
Construction Related Risk:-
Meeting with the supervisor of this project engineer "Khamis Hassan" and asking him

about the most important risks that face the project, his answers were as follows: -

1-Legal Risks:-

Delay in the site handling of the company after the signing of the contract agreement may

take a lot of time before the legal proceedings between the infrastructure of the Council and

the Office of Housing Libyan accounting. Also, the period for taken decisions of quantity

adjustment in the contract getting approvals from several government offices takes a very

long time.

2-Technical Risks:-

The presence of lots of technical errors in the specifications and quantities agreed in the

contract, as well as technical reports recommends the removal of the surface layer of the soil

depth of 1 meter with the settlement area of the site in accordance with the level design.

Amendments require the contract is of financial worth of the value of the original contract for

the project and therefore will take a long time to be approved and thus delays the completion

of the project.

3. Financial risk: -

Rising prices of construction materials (such as wood, steel and cement) also the transport

prices and the costs of the maintenance and also the increase in fuel prices a result of

continued unrest, non-payment of work invoices executing exchange in a timely manner

leads to the stop of work at the site.

47
4-Security risks:-

The company now face a big problem in terms of these conditions which prevent workers

from continuing to work and cause frequent escape, as well as difficulty in bringing other

workers to the site because of the slowdown in the Foreigners Registration Office.

Figure 3.4: Construction of (341) housing units in Elmahrougha

48
3.1.5. Construction of (2000) housing units in Ghadames city "LIBYA " .

Background of the Project:-

The project is located in the city of Ghadames, western Libya away from the city centre about

5 km away. From the ground floor by and first floor, each of That room has two bathrooms,

and a kitchen. In addition, the ground floor has a fence, and designed to fit with the traditions

of the population city. The total area of the building is about500000m2 .

Project name:-Construction of (2000) housing units in "Ghadames "

Contract number: -502/2007

Contractor: -Chaabane and Co. company general enterprise for building and public works.

The contract value of the Libyan dinar: -277,356,800 LYD

Site handing over date :- 09-09-2007

Period of implementation: - 30 months

Duration of the extension of the contract to the contractor: -22 months

Date of work on the project stopped: - 17-02-2011

The date of the resumption of work on the project: -20-3-2012

Percentage of execution:-65%

49
Construction Related Risk:-
Meeting with officer of Housing Infrastructure Board Ghadames "Tawfiq " and asking him

about the most important risks that face the project, his answers were as follows: -

1- Political Risks:-

The collapse of the political system in Libya has resulted in the collapse of the security and

economic level and the absence of the rule of law making Libya unable to fulfil its

contractual obligations, as well as the failure to obtain approvals or allow to do some work

necessary at the appropriate time.

2-Financial Risks:-

Non-payment of work invoices executing exchange in a timely which would lead to stop the

work the site, as well as not to limitation the damage to the work of the project and the assets

and property of the company.

3-Technical Risks:-

Erroneous assessment of the required technology and methods of construction phases of the

project where there were amendments to the designs and construction methods and execution

during the implementation, in addition to the wrong estimate of amounts necessary to

implement the project materials.

4- Security risks: -

Security risks in Libya have a negative impact on the implementation of the project, the

company is now facing a big problem and cannot return to Libya because of security

conditions and the political instability in Libya prevented the company from returning and

completes its work on the project.

50
5-Legal Risks:-

There are always many legal risks facing the project especially between the company and the

Board of infrastructure for housing where the work stalled since the year 2011 to today and

there are many issues before the courts to seeking compensation for the losses suffered by the

company in Libya.

Figure 3.5: Construction of (2000) housing units in Ghadames city

51
3.1.6. Construction of (3050) housing units in Sabha city "LIBYA ".
Background of the Project:-

The project consists of a number of 3050 housing units full facilities of infrastructure,

services, roads, lighting and gardens all other needs of the project and the port of the project

so far gain of 40%, which is integrated in all its service facilities project, the project is located

on 456 hectares of land working with the company before 17-02-2011 toward 1400 workers,

technicians, engineers and administrative staff, as well as many of the Libyan workers and

employees.

Project name:-Construction of (3050) housing units in "Sabha " city .

Contract number: -132/2007

Contractor: - D. S. Construction Co. Pvt. Ltd

The contract value of the Libyan dinar: -719,965,465 LYD

Site handing over date: -02-09-2007

Period of implementation: - 24 month

Duration of the extension of the contract to the contractor: -15 month

Date of work on the project stopped: -17-02-2011

Percentage of execution: - 40 %

52
Construction Related Risk:-
By meeting with officer of Housing Infrastructure Board Sabha city "Mohamed Ali " and

asking him about the most important risks that face the project, his answers were as follows: -

1- Zoning Risks:-

The existence of obstructions to work in the place of execution columns of power lines and a

gas station as well as the existence of a building for the electricity company of all these

obstacles have delayed work on the completion of the housing units.

2- Political Risks:-

One of the main risks faced by the construction of this 3050 housing units in the city of

Sabha is political instability in Libya which has resulted in the collapse of the security and

economic level and the absence of the rule of law, making Libya unable to fulfil its

contractual obligations, as well as the failure to obtain approvals or allow to do some work

necessary at the appropriate time.

3- Financial Risks :-

Non-payment of work invoices executing exchange in a timely and the absence of cash flow

which would lead to stop the work the site, as well as assault and theft of equipment and

machinery assets and property of the company, estimated in the millions, and contractor

delay in the payment of workers' salaries .

4-Technical Risks:-

Erroneous assessment of the required technology and methods of construction phases of the

project where there amendments to the designs and construction methods and execution

53
during the implementation, for example Cancel kindergarten building model B29 and B30,

and also cancelled the gas network in the project, which caused a change of the project costs.

5- Security risks: -

Security risks in Libya have a negative impact on the implementation of the project, the

company left Libya since the start of the security unrest in Libya in 2011, in addition to the

entry of people into residential units before they are completed, and some of the buildings

exploited by armed military.

6-Organizational Risks:-

Shortage of technical staff and the number of workers on site caused a delay in bringing the

employment of finishing the project as well as the instability of the contractor in the work

plan.

7-Legal Risks:-

There are always many legal risks facing the project especially between the company and the

Board of infrastructure for housing where the work stalled since the year 2011 to today and

there are many issues before the courts to seek compensation for the losses suffered by the

company in Libya.

54
Figure 3.6:Construction of (3050) housing units in Sabha city

55
3.1.7.Construction of (130) housing units in Wanzureik "LIBYA" .
Background of the Project:-

This project is located in the Wanzureik city in south western Libya, which is a residential

unit designed according to the latest models and the largest space. There are three bedrooms,

a guest room, a kitchen and three bathrooms in addition to the front fence. The project also

contains several service facilities and infrastructure.

Project name:-Construction of (130) housing units in "Wanzureik " .

Contract number: -53/2008

Contractor: - "Joharat Al moden" company of the Investment Contracting and real estate .

The contract value of the Libyan dinar :-15028000 LYD

Cite handing over date: -16-08-2008

Period of implementation: - 18 month

Duration of the extension of the contract to the contractor :-48 month

Date of work on the project stopped: -17-02-2011

The date of the resumption of work on the project: -02-06-2013

Percentage of execution: -45%

56
Construction Related Risk:-

Meeting with the project engineer, "Tariq Mohammed " and asking him about some of the

most important risks that face the project, his answers were as follows: -

1- Financial Risks:-

Non-payment of work invoices and executing exchange in a timely manner has led to the

stop of work at the site, as well as the accumulation of debt on Housing Infrastructure Board

which undermines trust between the executing company and the state.

2-Technical Risks:-

Erroneous assessment of the required technology and methods of construction phases of the

project where there amendments to the designs and construction methods and execution

during the implementation, in addition to the wrong estimate of quantities necessary to

implement the project materials.

3- Security risks: -

Security risks in Libya have had a negative impact on the implementation of the project, the

company is now facing a big problem in terms of the inability to bring in workers from

abroad to work on the project, as well as security concerns as a result of the wars in Libya.

4-Legal Risks:-

There are always many legal risks facing the project between the company and the Board of

infrastructure for housing and foreigners registration office where there are legal and

administrative measures to prevent complicated bring laborers to Libya , the existence of

several legal problems about land ownership and the compensation caused a delay in

57
completing the project on schedule, in addition to the period you take decisions of quantities

adjustment in the contract and that need approvals from several government offices which

for take a long time.

Figure 3.7:Construction of (130) housing units in Wanzureik

58
3.1.8.Construction of (60) housing units in Tamzawh"LIBYA" .

Background of the Project:-

The project is located in a town in the south of the Libyan Tamzawh away from the city

centre and about 3 km away. The project is the creation of 60 residential units with an area of

230m2 model and includes the finishing of a three-bedroom and a living room, kitchen and

two bathrooms.

Project name:-Construction of (60) housing units in " Tamzawh " .

Contract number: - 229/2008

Contractor: - "Aljebal Alafrikia " company of Investment Contracting and Real estate

The contract value of the Libyan dinar: - 6,936,000.000 LYD

Site handing over date: -10-02-2009

Period of implementation:- 540 day

Duration of the extension of the contract to the contractor: -12 month

Date of work on the project stopped: -17-02-2011

The date of the resumption of work on the project: -14-11-2013

Percentage of execution:-79%

59
Construction Related Risk:-
Meeting with the project engineer "Massoud Ali " and asking him about the most important

risks that face the project his answers were as follows: -

1- Financial Risks:-

Non-payment of the work invoices has delayed executing exchange in a timely which has

also led to the slow progress of work at the site.

2-Zoning Risks:-

The inability to connect power supply to the project site since the handling of the site till

today has led to problems that still hamper the work site. The lack of a favourable

environment for the implementation of high temperatures up to 47 ° C as well as sandstorms

that last for a long period of time.

3-Technical Risks:-

Amendments to the designs and construction methods of execution during the

implementation, in addition to the wrong estimate for quantities necessary to implement the

project cause project delays.

4- Security risks: -

Security risks in Libya have a negative impact on the implementation of the project. The

company is now facing a big problem in terms of the inability to bring in workers from

abroad to work to the project, also exposure to the project site theft and vandalism has led to

the killing of two workers leading to the escape of a majority of workers out of Libya.

60
4-Legal Risks:-

There are always many legal risks facing the project from foreigners registration office where

legal and administrative measures prevent the bringing of laborers to Libya .

Figure 3.8:Construction of (60) housing units in Tamzawh

61
3.1.9The construction of 20 thousand housing units in Benghazi city

“LIBYA”.

Background of the Project:-

The project consists of 20 thousand housing units full facilities of infrastructure, mosques,

markets, schools, roads, lighting, parks. The project is divided across two major locations in

Benghazi. The first consists of 15 thousand housing units in the west of Benghazi " Qnfodh"

area, and the second city is made up of five thousand housing units in " Jardina", about 30 km

from Benghazi.

Project name:-The construction of 20 thousand housing units in the city of Benghazi.

Contract number:-120/2007

Contractor: - the National Company of China Construction Engineering Co., Ltd.

The contract value of the Libyan dinar: -Three billion Libyan dinars

Site handing over date: -15-4-2008

Period of implementation:- 36 month

Duration of the extension of the contract to the contractor: -24 month

Date of work on the project stopped: -17-02-2011

The date of the resumption of work on the project:12/5/2013

Percentage of execution: -40%

62
Construction Related Risk:-
Meeting with the municipality member of Benghazi, "Saad Saaiti" and asking him about

the most important risks that face the project, his response was as follows: -

The Chinese company, which implemented the project was forced to suspend its operations in

the city of Benghazi, eastern Libya, since 17.2.2011 due to security problems, where

thousands of Chinese laborers returned to their country to escape the fighting, which led to

theft the contents of the company's tools and & Heavy Equipments and machinery belonging

to the Chinese company.

Dated 12-5-2013 after two years as agreed to resume the project which is a 20,000 housing

units in the city of Benghazi after the municipality of Benghazi meeting with the Chinese

company and the Housing Minister, an interim government proposed a solutions for the

return of the Chinese company to resume work in the project .

The municipality member of Benghazi, "Saad Saaiti" said that the company has not been able

to work again because of the attacks on the headquarters of the company in addition to

repeated attacks on its staff and the takeover of citizens. Also, after the murder of the project

manager of Chinese company executing in Benghazi Mr. " Hoang Chi chang" dated

20/05/2014 , the project site turned into a battleground between armed militias in Benghazi

who destroyed the buildings .

Mr."Saad" said, summed the risk in the project to the security situation, compensation of

executed projects by the Chinese company and the increased prices of materials.

63
Figure 3.9:The construction of 20 thousand housing units in Benghazi city

64
3.1.10. The construction of 110 housing units in Almansoura city"LIBYA "
Background of the Project:-

This project is located in the Almasoura" city in Libya, which is a residential units designed

according to the latest models and the largest space. There are three bedrooms, a guest room,

a kitchen and three bathrooms in addition to the front fence. The project also contains

infrastructure.

Project name:- The construction of 110 housing units in "Almasoura" city

Contract number: -191/2008

Contractor: - "Aslween " company of Investment Contracting and real estate

The contract value of the Libyan dinar: -12,716,000.000LYD

Site handing over date: - 31-03-2009

Period of implementation: - .

Duration of the extension of the contract to the contractor: -26 month

Date of work on the project stopped: -17-02-2011

The date of the resumption of work on the project :-25-11-2013

Percentage of execution: -23%

65
Construction Related Risk:-
Meeting with the project engineer "Hossam Eddin" and discussing with him about the most

important risks that face the project, his answers were as follows: -

1- Financial Risks:-

Non-payment of the work invoices has led to slow progress of work at the site.

2-Technical Risks:-

Amendments to the designs and construction methods of execution during the

implementation, in addition to the wrong estimate for quantities necessary to implement the

project cause project delays.

3- Security risks: -

The security risk in Libya has a negative impact on the implementation of the project. Also,

the exposure of the project site to theft and vandalism because of insecurity in the country

since the year 2011 has cause a slow in work progress.

4-Legal Risks:-

There are always many legal risks facing the project from foreigners registration office where

legal and administrative measures prevent the bringing of foreign laborers to Libya .

66
Figure 3.10: The construction of 110 housing units in Almansoura city

67
3.2 Libyan Audit Bureau and Construction projects.
Lots of contractors and owners of projects believe that one of the reasons for delays in

projects construction in Libya is the Libyan Audit Bureau that audits and stops several

contracts and administrative procedures and finance for projects as well as the slowdown in

the ratification of the payment certificates.

The researcher held discussions with the Director of Contract Management in the Audit

Bureau of Libya on some of the reasons behinds their operations some of which contribute to

the delay of construction projects. According to him, the Audit Bureau reviews contracts

valued at 500,000 Libyan dinars or more and ensures accountability. Contracts worth 500,000

Libyan dinars are reviewed and the bureau is entitled to legally stop any financial or

administrative proceedings considered to be illegal as in the case of the following:-

1- Some of the contracts prior to submission to the Court of Audit show a violation of

the law No. 19 of 2013 on the organization of the Audit Bureau and amendment.

2- A Slowdown to provide the necessary documents for the purpose of study and review

contracts, and non-compliance of some parties to respond to the observations of the

Audit Bureau when studying for contracts, leading to delays.

3- Proceeding to enter into contracts with companies without specifying their legal

status and evidence of registration in the Commercial Register of the state.

4- Payment of the value of some payment certificates without the display on the Court

of Accounts on the basis of violation issued by the executive authority decisions.

5- Differences between vouchers and payment certificates for many of the payments

sent to the Audit Bureau .

6- Non-renewal of insurance policies and letters of guarantee for some of companies.

7- Payment certificates without Stamp of the Comptroller of the Housing Infrastructure

Board.
68
8- Refusal to submit executive maps of projects, and in which quantities are reviewed.

9- Time lag between the date of the adoption of some of the payment certificates, and

the date of preparation of payment authorization and the date of referral to review

the Audit Bureau.

10- Sending supplements of contracts, and change Orders proved to be unwarranted , as

the original contracts cover the work required in accordance with the original terms

of the contract, but the interpretation of the original contracts for the benefit of the

contractor or consultant, was not prepared.

11- Extension of the implementation period in the minutes of the activation of contracts,

and for a period beyond the original execution.

3.3 Project manager’s response to the real reasons for delays in the housing
Projects in Libya:-
According to the project manager, the most important reasons for delay in the housing

projects in Libya are due to financial, political, security, legal and technical reasons. These

issues are significant factors affecting clients, contractors and project owners.

Problems in projects risk management:-

1- Failure to prepare for a good contract before contracting quantities , designs, integrated

technical drawings and this calls for Change of Orders to correct the conditions of the

contracts when implemented.

2-Contracting with local and foreign companies who are unable to implement resulting in the

delays of many projects .

3-Delay of Housing Infrastructure Board in payment of the work invoices for the companies

executing for years.

69
4-Many projects broken by people but were not taking any measures against them so far.

5-Amendments to the designs and construction methods execution during the

implementation, in addition to the wrong estimate for quantities necessary to implement the

project .

6-Security risks in Libya have a negative impact on the implementation of the project.

7-Complicated legal and administrative measures which prevent bringing foreign laborers to

Libya .

70
CHAPTER IV

RESULTS AND DISCUSSION

4. Questionnaire survey
Survey is a good method of data collection for descriptive purposes. As one of the study’s

objectives was to analyse how risk management worked in the projects during construction, a

questionnaire survey was chosen as one of the methods of data collection.

There are four steps in the performance of the questionnaire:-

1-Obtain the views of the different actors in the projects.

2- Selected questions were formulated in a way where it could help to answer research

questions.

3- The survey sample comprised of projects manager, the contractors , the consultants and

the persons who worked with risk management in the project.

4- A Total of 52 questionnaires were sent to the contracting companies undertaking the

housing projects which include the 16287 housing units. The questionnaires were filled and

supported with personal interviews. Some difficulties that emerged in the course of the data

collection include the delivery of the questionnaire in hand andthe difficulty in having access

to the corporate managers and officials because of the limited time they have.

Table. 4.1 Questionnaire distribution and respondents profile.


The study sample included 32 persons holding qualifications such as graduate and

postgraduate programs. Table 4.1 summarizes the number of respondents, abstainers and

scientific expertise and qualifications.

71
Table. 4.1.Questionnaire distribution and respondents profile figure

project Contractor Consultant Total


manager

Number of questionnaires
sent 30 16 6 52

Number of usable
responses received 18 12 2 32

Response rate (%)


60 75 33 56

Experience in the work.


11.17 18.9 21 -

Education (number of
respondents)
University 10 5 2 17
High Institute 3 8 2 13
Vocational training 0 2 0 2

72
Fig. 4.1 Questionnaire (response & abstention)

Fig. 4.2 Years of experience in the line of work

73
4.4. Executive situation for the project
By checking the documentations for the project samples, it was revealed that the average

Completion percentage in the projects are (48.83%), and that the work in (43.75%) of the

projects are Continuously slow and (56.3) have stopped working.

Figure 4.3 summarizes the executive situation for the project

Fig. 4.3 the executive situation for the project

74
4.5. Studying risk management and project management courses
Considering respondents on their views on the study risk management or/ and project
management courses, their answers were: (75%) of them they didn’t study risk management
, and (25%) of them studied risk management . Figure 4.4 summarizes the answers of
respondents.

Table. 4.2 Study risk management or project management courses

Fig. 4.4 Studying risk management and project management courses

75
4.6 Knowledge of Risk Management
Figure 4.5 summarizes the respondent’s knowledge of Risk Management, who was project

managers.

Table. 4.3 Values versus project Manager, contractor and consultant

Fig. 4.5Values versus project Manager, contractor and consultant

76
4.6.1 Evaluating the project implementation in terms of the Time, cost and
the Functionality
Considering respondents on their views on evaluating the project implementation in terms of

the Time, cost and the Functionality, their answers were:

Table. 4.4 Values Versus Functionality, Cost and Time

Fig. 4.6: Values Versus Functionality, Cost and Time

77
4.6.2 The participating in project phases

Considering respondents on their views on the participating in project phases , their answers
were: production (46.9%) , procurement (28.1%), design (9.4%), programme (15.6%).
Figure 4.7 summarizes the answers of respondents.

Table. 4.5 The participating in phases of the project

Fig. 4.7: The participating in project phases

78
4.6.3 The risk management processes that are carried out systematically in
the projects
Considering respondents on their views on the risk management processes that carried out

systematically in the projects , their answers were: Risk Identification (22) yes ,(10) no , as

for Risk Assessment their answers were (17) yes and (15) no , while their answers for Risk

response (15) yes and (17) no . Figure 4.8 summarizes the answers of respondents.

Table. 4.6 The risk management processes that carried out

Fig. 4.8 Values versus identification, assessment and response

79
4.6.4The phases of the project where the risk management processes
performed

Considering respondents on their views on the phases of the project where the risk

management processes performed, their answers were: Risk Identification (7) for

programme ,(19) for design and (6) for procurement , also in risk assessment were their

answers (8) for design, (16) for procurement and ( 8 ) for production , while their answers

for risk response (15) for procurement and (17) for production , Figure 4.9 shows the

answers of respondents .

Table. 4.7 The phasses where the risk management processes performed

80
Figure 4.9 Values versus risk identification, assessment and response

81
4.6.5 The participation in risk management.
Considering respondents on their views on their participation in risk management, 21 of them

responded yes, and 11 of them responded no, and it can be considered a sign of their limited

awareness of risk management, Figure 4.10 summarizes the extent of their participation in

risk management in the project.

Table. 4.8 The participation in risk management.

Figure 4.10 Values versus risk management

82
4.6.6 Construction Risks that face the projects in Libya
Considering respondents on their views on the Construction Related Risks that face the
projects in Libya, their answers were: Legal risks (6.3%) , Financial Risk (21.9%),
Technical risks (18.8%), Security risks (34.4%), Political Risks (12.5%), as for
Organizational Risks and Zoning Risks (3.1%) . Figure 4.11 summarizes the answers of
respondents.

Table. 4.9 Construction Risks that face the projects in Libya

Figure 4.11: Construction Risks that face the projects in Libya

83
4.6.7 The Influence of project actors on risk management.

Considering respondents on their views on the Influence of project actors on risk

management, 31.3% of them responded that project manager has this Influence , the

contractor’s Influence of 53.1%, 16.5 % Influence of consultant , Figure 4.12 summarizes

Influence of project actors no risk management.

Table. 4.10 The Influence of project actors on risk management.

Figure 4.12 Frequency versus project actors

84
4.6.8 The collaboration between the actors in the project
Considering respondents on their views on the cooperation between the actors in the project,

15% of them responded that this is not important, 50% of them responded that the importance

is medium, 34% responded that it is very important, and it can be considered as a sign of their

limited awareness of the importance of cooperation between the actors in the project, Figure

4.13 shows the extent of their knowledge of the importance of cooperation between the actors

in the project.

Table. 4.11 The collaboration between the actors in the project

Table. 4.11 The collaboration between the actors in the project

Figure 4.13: Frequency versus collaboration between actors in the project

85
4.6.9 Delay in payment of the work invoices and the increase delay and the
cost of the project.
Considering respondents on their views on the delay in payment of the work invoices and the

increase delay and the cost of the project, 78% of them said that this Always cause the

increase in delay and the cost of the project while 21% of them supported that it increases

delay Often. Figure 4.14 summarizes the extent of knowledge on the impact of the delay.

Table. 4.12 Delay in payment of the work invoices and the increase in the cost of the project

Figure 4.14 Delay in paying work invoices versus frequency

86
4.6.10 Option time extension and Impact on risk management.
Considering respondents on their views on the option time extension and its impact on risk

management and increase delay and the cost of the project, (31.3%) of them said that it has

limited impact on risk management , (68.8%) of them said that it’s a large impact.

Figure 4.15 shows the extent of option time extension and its impact.

Table. 4.13 Option time extension and Impact on risk management.

Figure 4.15: Values versus impact on risk management

87
4.6.11 Impact decisions of Change Orders in contract on risk management.
Considering respondents on their views on the impact decisions of Change Orders in contract

on risk management and increase delay and the cost of the project, (25%) of them said that it

has a limited impact on risk management while (75%) of them said that it has a large impact.

Figure 4.16 shows the extent of impact decisions of Change Orders in contract.

Table. 4.14Impact decisions of Change Orders in contract on risk management.

Figure 4.16 Frequency versus impact decision

88
4.7 The risks in construction projects in Libya
The projects include several risks such as financial, political, security, legal and technical.

These five facets together have an effect on the construction projects in LIBYA.

The following are the description of the major risks influencing the construction projects.

(1). The financial risk: Delay of Housing Infrastructure Board in payment of the work

invoices for the companies executing for years, results in rise of prices of construction

materials , the transport prices and the costs of the maintenance and also the increase in fuel

prices ,Libyan currency change against the dollar , so this the risk plays an important role on

the construction period .

(2). The risk of politics is one of the main risks faced by the construction of housing units

because the political instability in Libya has resulted in the collapse of the security and

economic level and the absence of the rule of law. Libya is unable to fulfil its contractual

obligations. The failure to obtain approvals or allow to do some work necessary at the

appropriate time, so this is the risk which played an important role on the construction period.

(3).The risk of security in Libya have a negative impact on the implementation of the

projects. The companies are now facing a big problem in terms of the inability to bring in

workers from abroad to work for the project. Also exposure to the projects sites, theft and

vandalism and also occurrence of murders of director of Chinese company in the city of

Benghazi and some Laborers. This led to the escape of a majority of workers out of Libya.

Also many of the projects turned to a military barracks of the armed forces and some

subjected to breaking in from the citizens.

(4). The legal risk facing the projects between the companies and the Board of infrastructure

for housing and foreigners registration office where there are legal and administrative

89
measures to prevent complications to bring laborers to Libya. The existence of several legal

problems about land ownership and the compensation caused a delay in completing the

projects on schedule. In addition to the period you take decisions of quantities adjustment in

the contracts and that need approvals from several government offices which take a long

time.

(5). Technical risks are the risks which are caused due to amendments to the designs and

construction methods, execution during the implementation, in addition to the wrong estimate

for quantities necessary to implement the projects.

(6) Zoning Risks:-

The existences of obstructions and obstacles at work place of execution have delayed work

on the completion of the housing.

4.8. Identifying and assessing the risks before and during construction

period

Most of the risk occur in the construction phase and the main contractor bear its results and

he must manage it . Usually the owner "Housing Infrastructure Board " bear the risks on the

responsibilities of Contractor. Risks have been identified based on a rating reference and

study, and interviews were conducted with experts in the field of construction industry in

Libya.

Risk identification requires knowledge of project situation i.e legal, financial, political, and in

addition strategic objectives, Process of identifying risks continues and must be initiated

before starting the implementation of the project. There is need to involve the project team to

define the risks and must feel everyone responsible for their risk identification and inform the

project manager.

90
There are many statistical methods which can assess the degree of risk, but the simplest and

most effective is to describe the degree of danger as very high, high, medium, low, very low.

The degree of risks depends on the impact of the risk and the likelihood of occurrence of the

risk .

4.9 Control of risks during construction period

The process of risk control begins to specify a list of risk and assess the probability of impact

of each risk. Then identify the control tools and how to implement each one.

There are four types of risk control:

(1). Acceptance of risk: The contractors and project owners can choose to accept some risk.

And in this case the damage risk is not large or strongly influential. This does not mean that

in case of their occurrence that is not addressed, but are dealt with afterwards, because the

cost of dealing with it is less than the cost of the investigation and pre-planning.

(2). Mitigate risk: Where to take action to reduce risk to an acceptable limit.

)3(. Risk removal: For reducing the risk to zero, for example, sell a project which contains a

proportion of risk which will wipe out this menace on them.

(4). Risk transfer: Risks can be transferred to another organization or even to one of the

individuals, for example insurance against fires transfers the risk of losses resulting from the

fire to the insurance company.

91
4.10 Risk management and construction companies’ management

systems in Libya.

In Libya, most companies do not apply Risk Management. Also they have to know the

appropriate software’s or models to use in this field, and they have to understand

Occupational Safety and Risk Management. Some large companies use risk management in

projects program such as Project Management Professional (PMP) .

4.11 Impact time extensions option in contracts on risk management

Extension of the extra time for projects in Libya happened for reasons beyond the will of the

parties to the contract. A contractor and the Housing Infrastructure Board who gets

contractors on duration to extend the contracts according to the recommendations of engineer

of the Housing Infrastructure Board sometimes up to 33 months without reducing the risks in

the project, such as the employment and salaries, cost of materials, machinery and equipment

costs, health insurance, the costs of extra time. The extension of the project period is a

positive thing for the contractor and the owner, but it does not mitigate or eliminate the risks

resulting from this extension, but increase it.

4.12 Impact of the decisions of Change Orders in contract on risk

management

There are many complex and interlocking problems that cause obstruction of the

implementation of Housing projects, including the overlap between the executive agencies

and the lack of efficiency. The preparation of technical specifications, and the growing

phenomenon of decisions of quantities adjustment, and the change is due to the desire to

92
modify some of the Items in addition or deletion, modification or replacement of some of the

design elements of the project, leading to an increase in the amounts or change in the nature

of the work that often changes. Whether direct or indirect, it has side risks on the rest of the

project work and these risks both in the cost of works or delay of implementation , labor

productivity and efficiency it , but exploited in order to raise assessments for project fund.

4.13 Effects of the project risk:

1- Often the housing units that execute work are stopped and some of them work go

slowly. This result of the political and economical situation in Libya due to Events in

2011 has effect on the construction field in the last few years.

2- The executed projects linked with high level of risk was found to have a direct

correlation between the probability of occurrence of most of the risks, and that the

occurrence of some of the risks cause other risks, because the length of the

implementation period that lead to changed circumstances making it contain multiple

risk .

3- Search Results showed that "decisions of change orders, inflation, price fluctuations"

and "the difference between actual and contractual quantities," is one of the most

important risks.

4- The low percentage of completion of projects in spite of giving companies extra time

of extensions several times.

93
5- Leave most foreign companies from project sites in Libya due to security concerns.

6- Contractors and owners in Libya still depend on traditional approaches to manage risk

factors and their consequences; the use of direct judgment to control risk factors.

4.14 Risk Management:


1-Legal risk management:- Legal risk management refers to the process of evaluating

alternative regulatory and non-regulatory responses to risk and selecting among them. Even

with the legal realm, this process requires knowledge of the legal, economic and social

factors, as well as knowledge of the business world in which legal teams operate.

In an organizational setting, risk management refers to the process by which an organization

sets the risk tolerance, identifies potential risks and prioritizes the tolerance for risk based on

the organization’s business objectives, and manages and mitigates risks throughout the

organization.

Legal risk covers all areas of business where regulation and the law impact on operations and

decisions. From risks arising from contract drafting and management, through to regulators'

new focus on conduct, as well as compliance, regulatory and dispute risks, the effective

management of legal risk is key for organizations that want to maximise value while

minimizing cost and exposure to legal losses. The Legal Risk Management Handbook is a

practical guide to making sure your business is legal, protected and making the most of its

opportunities.

2-Financial risk: - Financial risk and construction goes hand-in-hand, and the further away a

company is from the project developer, the more risk it shoulders. The scope of financial risk

94
on a construction project is a huge topic contemplating under-funded or underbid projects,

contractor default problems, misappropriation of project funds and more.

Financial risks to consider when planning a large construction project is the fluctuation

of the currency, especially in the case of international projects. Recently in many countries

the construction of privately financed infrastructures has been based on foreign capital,

thus running the risk of devaluation of local currency. International lenders rarely take that

risk, preferring to have their payments in foreign currency. In the past, public companies

or governments have accepted the currency risk, but now, with the growing demand

for private financing, the risk of depreciation of the currency often lies in the promoter of the

project and, ultimately, on he financial risks almost always result in lose of money. The risks

in this sector depend heavily on countries or regions in which the projects are to be

built, and it is totally different to implement those projects in areas of political stability

such as Europe that performing them in countries where political conflicts are usual.

Therefore, when establishing which are the most important risks in a certain project it should

be taken into account in the first place where they intend to build. From there, the risk

analysis must be performed.

3- Technical risk management:-Working through the potential project and technical risks

can be rewarding process; the end result will open the project teams' eyes and prepare

everyone for the potential pitfalls ahead.

Types technical risk management

- Design process

1- Owner involvement in design

2- Inadequate and incomplete design

95
3- Change in seismic criteria

4- Errors in completion of structural / geotechnical / foundation

5- Wrong selection of materials

6- Take off data (traffic demand, water consumption demand, etc.)

7- Need for design exceptions

-Construction risks

1- Inaccurate contract time estimates

2- Construction procedures

3- Construction occupational safety

4- Work permissions

5-Utilities

6- Late surveys, incomplete or wrong

7-Delayed deliveries and disruptions

8- Worker and site safety

9- Innovative projects

10- Unsuitable equipment and materials

11- Environmental risks (such as projects close to a river, floodplain, coastal zone, high

habitat sensitivity, and so on)

-Environmental factors

96
1-Environmental analysis incomplete or wrong

2- Offsite and onsite wetlands

3- Hazardous waste, preliminary site investigation wrong

4- Lack of specialised staff (biology, anthropology archaeology, etc)

-Inaccurate assumptions on technical issues in the planning stage

- Fact sheet requirements (exception to standards)

4-Security risk management:-

Risk management is the identification, assessment and prioritisation of risks followed by

coordinated and economical application of resources to minimise, monitor, and control the

probability and/or impact of unforeseen events.

Security risk management is the specific culture, processes and structures that are directed

towards maximising the benefits of security in support of business objectives.

Adopting a risk based approach allows agencies to prioritise activities based on the likelihood

and consequence of a risk being realised, to maximise business outcomes while minimising

the occurrence or effects of events that may negatively affect outcomes.

97
CHAPTER V.

Recommendations , future scope and project work

1- Establish training courses on risk management, or teach within the curriculum, and

attention be given to the formation of a team of risk management in the company, and the

allocation of a budget for risk management. And follow the project team training sessions,

each according to its competence, and the application of codes of safety in companies and

projects strictly.

2-Study the types of contracts and contractual vocabulary accurately to identify risks assumed

by each party in the project in accordance with the selected nodes, and to turn the risks to the

party best able to manage.

3- Inventory of the damage to the work projects with the inventory of machinery and

equipment located at the projects sites before the 17th of February through supervision reports

Housing Infrastructure Board and identify the remaining ones and damaged even shorten the

time granted to those companies for the implementation of the projects, which will accelerate

to resume work immediately.

4- Should be reconsidered in the contracted projects through the formation of committees in

particular and rescheduling according to the economic and political interests of Libya.

5- Must form a transparent legal framework for the catalyst to foreign companies through the

knowledge of what their rights and obligations through the participation contracts are agreed

upon in advance.

6-Must guarantee the rights of foreign companies and therefore their sense of the presence of

justice, contributing to their return directly to their business.

98
7- Must compensate for foreign and domestic companies for damages suffered during the

War of 2011.

8- Providing attractive offers advantages such as giving tax cuts and other benefits, which in

turn contribute to the return of companies.

9- Facilitate administrative procedures and accelerate financial dues to the stages of

implementation of the projects first , in order to ensure the flow of work and not stop it.

10- The formation of committees legal, financial and technical to study of contracting

procedures, prices and foundations identified and negotiated with contractors to re-

contracting in accordance with the most suitable prices of market prices.

11- Use of the offices of foreign experience of audit firms and then to re-evaluate samples of

those contracts financially and technically in accordance with the international prices and the

expansion of the sample if it is to achieve results positive about alleviating the burdens

resulting from those contracts.

12- The need to achieve political and economic stability as well as the formation of

committees the task of revision of the stalled projects and that has not been initiated and

evaluated.

12- Assigned to guard facilities team to ensure the provision of reassuring foreign partner

and the domestic business environment.

99
CONCLUSION

The following conclusions are drawn from the present study:

1- That, the contractors and the owners suffer from lack of innovative methods to

prevent or mitigate risks and also that risk management education and training is low,

almost non-existent, in the projects in Libya .

2- That, Contractors and owners in many projects do not utilize risk analysis techniques

but depend widely on direct judgment in estimating time and cost , Causing the

negative effects on the projects regarding the schedule and the cost .

3- The contractors and owners of the projects do not find reasonable solutions and

provide practical suggestions and recommendations toward upgrading the risk

management process in construction and improve the performance of contracting

companies and owners in this field.

4- The results of the study provide useful guidelines for forming and operating effective

and efficient projects in Libya and other unstable countries.

5- Some of the companies are not able to implement projects on time and according to

the contract agreed upon in the budget.

6- Risk “of inflation and price fluctuations” plays a major role between the quantities

required and actual quantities to be used. This is one of the most important risks.

7- The risks reported by various companies are:

Financial,political, security, legal and technical. These issues are significant factors affecting

clients, contractors and project owners.

100
The following are the problems in projects risk management:-

Firstly, in general, there was no employee or a dedicated team of risk management by the

contractors. Contractors also do not have the appropriate software or models to be used in this

field and their knowledge of risk management was low.

Secondly, the failure to prepare good for contract before contracting from where of quantities

, designs ,integrated Technical drawings and this caused in issue decisions of Change Orders

to correct the conditions of the contracts when the implementation and preparation of random

Technical estimates for some items and inaccuracies in the prepare correctly as a result of

lack of experience.

Thirdly, lack of coordination with the Urban Planning Department to choose some

appropriate projects sites causing legal problems between the companies and entities which

owns the land sites.

Fourthly, contracting with local and foreign companies are unable to implementation

resulting in stalled many projects. Also, decline in the percentage of completion of projects

and most of them are stopped and resume work in 2013 in a very limited number.

Again, the extension of the implementation periods of the contracts and for a periods Exceed

the period on the original implementation in contract despite the fact that these projects have

expired duration of implementation before the scheduled 17-02-2011.

Moreover, the non assessment of the damages in the companies and projects for

compensation even after the projects resume.

Furthermore, the delay of Housing Infrastructure Board in payment of the payment

certificates for years. Many projects broken by people have seen no taking of measures

against them so far.

101
Lastly, the Libyan Audit Bureau stops a lot of contracts and the payment certificates due to

legal and administrative steps that did not comply with the implementing projects

102
REFERENCES:-

Adnan, Anshassi (2008). Risk management in building projects: owners’ perspective, The

Islamic University Journal,Vol.16, No. 1, pp25-123.

Alexander, Niel( 2015). Quantitative Risk Management: Concepts, Techniques, and Tools:

Concepts, Techniques, and Tools, Princeton University Press, 2010.

Al-salman, Ali (2005). Assessment of Risks Management Perception and Practices of

Construction Contractors in Saudi Arabia ,Journal of King Saud University - Engineering

Sciences,Vol 25,pp9-125-134.

Antunes, Ricardo; Gonzalez, Vicente (2015). "A Production Model for Construction: A

Theoretical Framework". Buildings. 5 (1): 209–228.

Craig Taylor; Erik VanMarcke, eds. (2002). Acceptable Risk Processes: Lifelines and

Natural Hazards. Reston, VA: ASCE, TCLEE. ISBN 9780784406236.

Crockford, Neil (1986). An Introduction to Risk Management (2 ed.). Cambridge, UK:

Woodhead-Faulkner. p. 18. ISBN 0-85941-332-2.

Dorfman, Mark S. (2007). Introduction to Risk Management and Insurance (9 ed.).

Englewood Cliffs, N.J: Prentice Hall. ISBN 0-13-224227-3.

El-Sayegh,S (2010). Risk Management in Construction Projects: A Knowledge-base

Approach, Procedia - Social and Behavioral Sciences Vol 119 March 2010, Pages 653-662.

Falqi,Ibrahin (2015).Assessment the Risk Management in the Project According to

International Standard, , International Journal of Construction Management Vol. (2) - No. (4)

2015.

103
Flyvbjerg, Bent &Budzier, Alexander (2011). "Why Your IT Project May Be Riskier Than

You Think". Harvard Business Review. 89 (9): 601–603.

Fouzi,Ahmed (2013).project cost risk assessment in Libya ,Carl. Journal of Civil

Engineering and Architecture,Vol 7, No. 5,pp 591-600.

Gunhan, Arditi (2015). Risk Management Principles and Governance , looming the modus

operandi among construction contractors in Malaysia, International Journal of Construction

Management Vol. (3) - No. (5) 2015.

Haitham, Alshibly (2013).The impact of risk management on construction projects

successfrom the employees perspective, interdisciplinary journal of contemporary research in

business,vol 5, no 4,pp12-42.

Haviz, Ibrahim (2008).development of risk management system in construction projects

using simulation, Iraqi civilian Journal,Vol.10,pp15-40.

Heba, Ehab (2014). Risk Management Practices and Financial Performance in Jordan,

Business Administration, Economics and Political Science, The British University in Egypt, Cairo,

Egypt.

Hindawi, Hamza (2007). Implementation of Risk Management in Malaysian Construction

Industry: Case Studies, Journal of Construction Engineering Vol. 2015 (2015), Article

ID 192742, 6 pages.

Hubbard, Douglas (2009). The Failure of Risk Management: Why It's Broken and How to

Fix It. John Wiley & Sons. p. 46.

104
ISO/DIS 31000 (2009). Risk management — Principles and guidelines on

implementation. International Organization for Standardization. Retrieved on 2012-04-17.

Jaser, Abu Mousa (2005).Risk Management in Construction Projects from Contractors and

Owners" perspectives, The Islamic University of Gaza – Palestine, pp9-17.

Kajsa, Simu (2006). Risk management in small construction projects, IOSR Journal of

Mechanical and Civil Engineering (IOSR-JMCE) ISSN: 2278-1684, PP: 59-65.

Karim, El-dash (2008). construction risk management: application and education,

International Congress on Project Engineering, Zaragoza .

Lev Virine and Michael Trumper. (2007).Project Decisions: The Art and Science.

Management Concepts. Vienna. VA. ISBN 978-1-56726-217-9

Maher, Khader (2007). A Stochastic Risk Management System for Construction Projects in

Gaza Strip, Islamic University of Gaza.pp7-30 .

Mohd, Nifa (2014). Management of construction phase risks for construction projects in

Syria, Damascus University Journal of Engineering Sciences, Vol. (28) - No. (1) 2014.

Mohamed, Othman (2006). looming the modus operandi among construction contractors in

Malaysia, International Journal of Construction Management Vol. (4) - No. (6) 2006.

Mohammad, Nayfeh (2012).Risk management of the construction stage for the construction

projects in Syria, Damascus University Journal Vol. (28) - No. (1) 2012.

Muhammad, Jamaluddin (2014).Risk analysis in construction projects: a Practical selection

methodology, american journal of applied sciences, vol no11,pp74-84

Muna, Hamadeh (2012).Risk management of the construction stage for the construction

projects in Syria, Damascus University Journal, Vol. (28) - No. (1) 2012,pp1-3.

105
Peter Simon and David Hillson, (2012). Practical Risk Management: The ATOM

Methodology Management Concepts. Vienna, VA. ISBN 978-1567263664

Roehrig, P (2006). "Bet On Governance To Manage Outsourcing Risk". Business Trends

Quarterly. Wideman RM (1992). Project and Program Risk Management (Newtown Square,

PA: Project Management Institute) ISBN 978-1-880410-06-6.

Sameer Mohamed (2007). Risk management in building projects in Palestine:

Contractors’ perspective, Emirates Journal for Engineering Research, 13 (1), 29-44 (2008).

Samir, Dany (2006). Scenario planning in supply chain risk management, IOSR Journal of

Mechanical and Civil Engineering (IOSR-JMCE) ISSN: 2278-1684, PP: 30-35.

Suad,Ahmed (2009).Risk Management Mediates the Influence of Good Corporate

Governance, Managerial Shareholder, and Leverage on Firm Value, IOSR Journal of

Business and Management (IOSR-JBM) e-ISSN: 2278-487X, p-ISSN: 2319-7668. Volume

18, Issue 11. Ver. VI (November. 2009), PP 62-70.

Shenila, Makhani (2010 ). Project Management Risk Sensitivity Analysis, Journal of

Information & Communication Technology,Vol. 4, No. 1,pp 38-48 .

Trevisani, Daniele (2007). Regie di Cambiamento (Translated Title: The Directions of

Change), Franco Angeli Publisher, Milan, ISBN 9788846483775

106
Questionnaire survey

107
108
109
110
111
112
113
Publications papers

1- International Journal of Engineering and Techniques - Volume 2 Issue 6, Nov – Dec


2016, Analysis of Risk Management for Construction Projects ,ER. Hassan Mohamed
Abdulnabi, Prof. (Dr.) V. C. Agarwal

2- International Journal of Civil Engineering and Technology (IJCIET), Volume 7, Issue


6, Nov-Dec 2016,Claims in construction projects “design errors and change orders”
ER. Hassan Mohamed Abdulnabi, Prof. (Dr.) V. C. Agarwal

114
International Journal of Civil Engineering and Technology (IJCIET)
Volume 7, Issue 6, November-December 2016, pp. 123–130, Article ID: IJCIET_07_06_014
Available online at http://www.iaeme.com/IJCIET/issues.asp?JType=IJCIET&VType=7&IType=6
ISSN Print: 0976-6308 and ISSN Online: 0976-6316
© IAEME Publication

CLAIMS IN CONSTRUCTION PROJECTS “DESIGN


ERRORS AND CHANGE ORDERS”
ER. Hassan Mohamed Abdulnabi
Student PhD, Department of Civil Engineering, Faculty of Engineering and Technology,
SHIATS University, Allahabad, India

Dr. V. C. Agarwal
Head of Department of Civil Engineering, Faculty of Engineering and Technology,
SHIATS University, Allahabad, India

ABSTRACT
In the implementation of a construction project, there are many difficulties and unexpected
problems in the design phase. In some cases these problems are caused by design and sometimes
consulting engineer or supervisor depends on diligence in solving these problems by changing the
orders issued to the Contractor simple limited or large comprehensive.
In both cases, these problems date back to the engineer or related with him and usually it leads
to the claims of contractor's, material or time, or both , in turn, leads to an increase in the cost of
the project and its duration for the owner of the project. This study aims to know the types of
claims that occur in construction projects because of mis-design that goes back to the General
Engineer.
This study is based on a sample statistic, random, for projects implemented in Libya during the
last ten years and it has been the monitoring of claims and their impact on the project, which
resulted mainly from design errors and change orders that were later during implementation,
define this search the causes of claims and types which are generally related to engineer, through a
sample of these projects, and then concludes that a number the results can be taken to avoid
occurrence of such claims in the future.
Key words: claims, change orders, risk management, construction projects.
Cite this Article: ER. Hassan Mohamed Abdulnabi and Dr. V. C. Agarwal, Claims in Construction
Projects "Design Errors and Change Orders". International Journal of Civil Engineering and
Technology, 7(6), 2016, pp.123 – 130.
http://www.iaeme.com/IJCIET/issues.asp?JType=IJCIET&VType=7&IType=6

1. INTRODUCTION
It's hard to imagine that engineering project, implemented without any difficulties and unexpected
problems. No matter how small or large size of the project, no matter the type of project, there are
expected problems, and therefore its difficult to imagine also that the contractor whether large or small, has
performed a certain project without any various claims, there are problems and difficulties present always
in engineering projects, and there are risks in the nature of these projects, and it is difficult in some cases.
Lack of prognosis or prediction of these problems before starting the implementation of the project or

http://www.iaeme.com/IJCIET/index.asp 123 editor@iaeme.com


Claims in Construction Projects "Design Errors and Change Orders"

during the study design, results in these problems. In most cases, different claims pertain to all parties to
the contract or the project, some of these problems are resolved amicably and some of find their way to the
court because of the containment of design defects or errors relating to the design, and the change orders
that even are given to the contractor during the execution and orders from the supervisor engineer. Even if
these orders are to avoid design errors, or at the behest of the owner in order to improve the function of the
project and as a result this increases the cost and duration of projects implemented which will reflect
negatively on the project owner.
According to the International Federation of Consulting Engineers, FIDIC defines claims and "there is
no construction project without the occurrence of difficulties and problems or disputes, because of the
nature of the construction and risks, especially if the project continues for a long period of time to
implement it. Because of the nature of the construction and risks, especially if the project continues for a
long period of time to implement it, found during the execution conditions were not taken into account
during the development of the tender documents or the contract, or disputes occurring during the
interpretation of the items of the contract. It is permissible then to the contractor in accordance with these
conditions to make claims against the owner in the contract, such claims because of the termination of the
contract or cancel it. As the owner may submit claims in some cases under a contract FIDIC.

1.1. Claim Definition


FIDIC knows Claim in construction contracts as an injured party request for appropriate compensation for
damages incurred based on the terms of the contract or because of violation of one of the Parties to the
contract or the law of the contract.
The claim may be by the contractor or the owner of the project and requires FIDIC filing the claim
(period or compensation) to the supervisor or consultant engineer. If the party did not accept the claims
according to the opinion of the engineer or his estimates and refuse it, he must write claims. We can say
that any breach of one of the terms of the contract by the parties will lead to the occurrence of claims and
then in most cases of differences.
Typically the construction contracts contain provisions which provide for the method of evaluation of
claims, and then how to resolve the differences between the parties to the contract. The global and
international laws for contracts focus on the role of the consulting engineer to assess the claim, where the
claim is evaluated
It is then submitted to the engineer in two phases: -
• Is there a reason to claim a contractual or legal agreement?
• Then comes the calculation of the compensation or cost or extension phase.

1.2. The Objective of Study


The research aims to detect the size of claims, types, and sources in the engineering studies for
construction projects executed in Libya, which contributes to increasing the duration and cost of these
projects and lead to the loss of the national economy. The research also aims to develop an effective
strategy in order to avoid the occurrence of these claims or minimise the effects of these disputes between
the parties to the contract. This strategy is summed up in a system for the management of these claims or
disputes in construction projects before they occur.

2. MATERIALS & METHODOLOGY


The basic material of this research was the available data on the implementation of housing projects in
Libya. And the data was studied analysed n study and analysed to extract conclusions and data about these
projects regarding the types of claims and their causes.
The focus was on the errors in the design and claims caused by the design engineer, supervisor
engineer, the financial value of these claims and the length of time also. The methodology used in this

http://www.iaeme.com/IJCIET/index.asp 124 editor@iaeme.com


ER. Hassan Mohamed Abdulnabi and Dr. V. C. Agarwal

study was based on statistical sampling randomness, the sample volume in this study is 8 projects selected
randomly. Information was from the establishments and departments owners, which are in many cases the
authority supervising Also, through the projects documents completed and under implementation.

2.1. Questionnaire Survey


This questionnaire is an important part of data collection in the project, the questionnaire consists of five
sections with a total of 34 questions.
The value of these claims differs from one project to another project, depending on the amount of fault,
according to the project volume and type. In some projects, the proportion of claims up to a large value of
the cost of the project creates real financial difficulties to the owner of the project, while some projects
have been stopped for a long period of time as a result of these claims, and have failed.
Table (1) shows a list of some projects that contain orders for change as a result of design errors and
change orders, the table also shows a comparison between data and information relating to (the duration
and cost) for Change Order and the duration and cost of the original contract.
Table 1

N principal contract the value of change Order

Value LYD Duration/month Value LYD Percentage Time Duration


extensions Percentage

1- 49,823,600.000 18 1,246,198.367 2.5% 16 88%

2- 15,028,000.000 18 1,325,164.383 8.81% 9 50%

3- 14,896,000.000 18 2,846,263.000 19.1% 9 50%

4- 11,704,000.000 18 392,608.040 3.35% 6 33%

5- 18,620,000.000 18 886,330.000 4.76% 10 55%

6- 31,920,000.000 18 1,542,071.000 4.83% 14 77%

7- 14,896,000.000 18 302,176.680 2.02% 9 50%

8- 26,600,000.000 18 701,917.129 2.63% 12 66%

Analysing the data given in table (1), we find the following- :


The supervising engineer and the owner together issued the change orders to avoid design flaws and
lack of supervision in the early stages of the project, and therefore, we find that the additional cost value
ratio of between 2.02% in the project No. 7 and 19.1% in the project No. 3 and we find that the value of
the additional period of between 33% in the project No. 4 and 88% in the project No. 1

2.2. The most important differences and claims that occur between the contractor and the
owner
Differences occur in engineering contracts as a result of divergent views in understanding some of the
issues between the parties to the contract, and can be classified as engineering differences on the basis of
the following sources, see Figure (2):
A-Design engineer (or Contract Documents / project file)
B-Supervising engineer: or quality control of the project and project management contract

http://www.iaeme.com/IJCIET/index.asp 125 editor@iaeme.com


Claims in Construction Projects "Design Errors and Change Orders"

C- Management (owner)
D- Contractor
E- Contract
F- Other problems.

Claims in
engineering
contracts

During the
The selection Selection of Other
contract contract
of Eng. the contractor problems
execution

Designer
supervisor Rising prices
Conditions of Cash flow
Financial and Contract Force Majeure
administrative Settlement of Climate
Quantities the claim in a
capacity Currency value
Specifications timely
Labor

Figure 2

The design engineer is responsible for the preparation of the study and documentation of the project
before the implementation phase and the supervising engineer who is overseeing the project since the
beginning of implementation.
The situation will be examined in two phases, the first phase will discuss claims belonging to the stage
study of the project, and in the next phase, we will discuss the engineering claims belonging to the
supervising
ervising engineer on the implementation of the project.
The study or engineering design for the project and drawings and contract documents are the first cause
of claims and disputes between the contractor and the owner, especially with regard to the specifications
spec
and the pricing method or estimate the price.
Figures (3,4,5) shows the parties to the claims and parties that cause them and the share of each party ,
as contained in the sample of the projects studied.

Figure 3 Parties to the claims

http://www.iaeme.com/IJCIET/index.asp 126 editor@iaeme.com


ER. Hassan Mohamed Abdulnabi and Dr. V. C. Agarwal

Figure 4 Parties causing claims

Figure 5 The main reasons for claims and the share of each of them

2.3. Claims caused by the contract documents and other problems


As shown in Figure (5) the contract documents had substantiated claims of 60% of the total claims, and
other problems such as (Rising prices, Force Majeure, Climate, Currency value, Labour) had substantiated
claims of 40%.
Claims are caused by the design engineer when Conducting a study of the project including documents
and drawings and specifications, where it is possible that the engineer commits unintended errors due to
lack of awareness or weakness of experience in the design work as a result of Insufficient time, which,
these errors can cause disagreements between the parties of the project resulting in financial and time
claims of both the contractor and the owner, and an increase in the quantity and volume of these errors
increases the volume of the project. These errors are called Design error.
According to Building Research Establishment -BRE estimates that 60% of the studied projects in
Britain contain design errors, and this error ranges from simple and functional error to a large structural
fault.

http://www.iaeme.com/IJCIET/index.asp 127 editor@iaeme.com


Claims in Construction Projects "Design Errors and Change Orders"

Through this study of the causes of claims, these claims can be classified into:

2.3.1. Technical Documents Claims


It is possible to make mistakes during the preparation of the technical documentation for the project (tender
documents of the project), causing many claims and these claims are divided into the following:
A - Claims of technical specifications.
B - Claims because of errors estimate prices.
C - Claims of quantities tables.
D - Contract claims.

Claims of technical specifications: These claims come due to errors in the writing and preparation of this
specification. It was the volume of the claims relating to the specifications in the studied sample of 10%
(see Figure 6).

Claims of quantities tables: Result from the wrong estimate of the quantities of the project by more than
the contractual ratio, and the volume of the claims relating to erroneously estimate quantities in the studied
sample 20 % (Figure 5), a large proportion. This is due to the speed in the calculation of quantities by the
engineer and not on detailed plans.

Contract claims: These claims relate to documents contract (the original contract) with the contractor,
such as the difference between the contract items and conditions and the general conditions of legal,
technical documents. In most documents contracts for these projects are of major differences, which give
many possibilities of interpretation leading to various financial claims of the parties to the contract, In the
sample studied was the percentage of the claims relating to the contract was 10 %.
The figure shows (6) common claims in the sample of projects as a result of errors in the design or
project documents

Figure 6 Claims ratios in construction projects and its causes

2.3.2. Drawings Claims


Causing mistakes in the preparation of project drawings have several claims, including:
1- Claims because of architectural errors with a percentage of 20 %.
2- Claims because of geotechnical studies and reports of soil and this is one of the most common claims
and with a percentage of 40 %.

http://www.iaeme.com/IJCIET/index.asp 128 editor@iaeme.com


ER. Hassan Mohamed Abdulnabi and Dr. V. C. Agarwal

3-Claims due to errors in the measurement of the project area in hectares and again per square meter.

3. RESULTS
By studying the claims and analysis in the sample projects, we conclude the following:
1. One of the main reasons for claims in construction projects is the engineering design for the project
errors.
2. There is the need to develop a methodology for the selection of the design engineer and supervising
engineer for the project well.
3. Application to achieve the quality of the Engineering Design System.
4. The composition of an expert team to the project owner to control the design stage in accordance with
the requirements of the standards and codes design.
5. Reducing change orders version of the supervising engineer consultant, especially those undocumented
entrepreneurs of the administration, it leads to financial and time claims of the contractor.
6. The need to develop a system for the management of claims in each project.

4. CONCLUSION
This study determines the defining qualities of construction claims which could impact on the
implementation of the engineering project. The finding of this study shed some light on the construction
claims; it was found that engineering design and geotechnical are a potential error for engineering projects
in Libya.
This study will help the industry personal gather the appropriate information about construction claims
for this study is recommended regarding construction claims ., construction claims, which could be faced
during the implementation of engineering projects and induced consulting engineer either designed or
supervisor of the implementation through a sample of the executed projects in Libya projects study. It was
found that more potential errors are in the engineering design of the project as well as the geotechnical
studies the reports of the soil will lead to claims.

REFERENCE

[1] Akpan, E. O. P., and Igwe, O. (2001). “A methodology for determining price variation in project
execution.” J. Constr. Eng. Manage. , 127(5), 367–373.

[2] Asem, M., Abdul-Malak, U., El-Saadi, M. M. H., and Abou-Zeid, M. G. (2002). “Process model for
administrating construction claims.” J. Manage. Eng., 18(2), 84–94.

[3] Brunies, R., and Eng, Z. E. (2003). “Calculating loss of productivity due to overtime using published
charts-Fact or fiction.” Technical Rep., Revay and Associates Limited, Montréal.

[4] Ibbs, C. W., and Allen, W. E. (1995). “Quantitative impacts of project change.” Source Document 108,
Construction Industry Institute, Univ. of Texas at Austin, Austin, Tex.

[5] Leonard, C., Moselhi, O., and Fazio, P. (1991). “Impact of change orders on construction productivity.”
Can. J. Civ. Eng., 18, 484 492.

[6] Thomas, H. R., and Napolitan, C. L. (1995). “Quantitative effects of construction changes on labour
productivity.” J. Constr. Eng. Manage. , 121(3), 290–296.

http://www.iaeme.com/IJCIET/index.asp 129 editor@iaeme.com


Claims in Construction Projects "Design Errors and Change Orders"

[7] U.S. Army Corps of Engineers (1979). “Modification impact evaluation guide.” Technical Rep. EP 415-
1-3, Washington, D.C.

[8] Jamal M. Assbeihat, Factors Affecting Delays on Private Construction Projects, International Journal of
Civil Engineering and Technology (IJCIET) , 7 (2), 2016, pp. 22-33.

[9] Sayali shet and Prof. Raju Narwade, An Empirical Case Study of Material Management in Construction
of Industrial Building by using Various Techniques. International Journal of Civil Engineering and
Technology (IJCIET), 7(5), 2016, pp.393 –400.

http://www.iaeme.com/IJCIET/index.asp 130 editor@iaeme.com


International Journal of Engineering and Techniques - Volume 2 Issue 6, Nov – Dec 2016
RESEARCH ARTICLE OPEN ACCESS

Analysis of Risk Management for Construction Projects


ER. Hassan Mohamed Abdulnabi 1 Prof. (Dr.) V. C. Agarwal 2

PhD student, Department of Civil Engineering Faculty of Engineering and Technology


SHIATS University, Allahabad, India 1
Professor Dr, Head of Department of Civil Engineering Faculty of Engineering and
Technology SHIATS University, Allahabad, India 2

Abstract:
The length of the implementation period in the construction of projects may lead to a change in
circumstances which expose them to many risks because of the length of the implementation period and multiple
stages, beginning with the start-up phase and even phase of the project, and this leads to increased circumstances of
uncertainty and increasing the probability of the occurrence of risks, and this is reflected negatively on the
construction contracting and construction economy.In this research questionnaire was developed to identify the
risks encountered in construction. Projects have been distributed to some local and foreign construction companies
in Libya, having been identified the risks that may face the projects. Through questionnaires and interviews with
engineers and project managers of companies, and making risk analysis qualitatively, there was a need to prepare a
checklist of the risks facing projects in Libya, and know the benefit of the contractor and the owner based on the
results. This paper examines the most important risks faced by construction projects in Libya, which is difficult and
how they are able to implement these projects and housing companies, the research explains a formulated model to
evaluate companies before being contracted to know the financial and technical capabilities.

Keywords — Risk management, construction of projects, evaluating the risks, risk analysis

INTRODUCTION I. PROJECT RISK CONCEPT


The sector of construction is one of the key
economic sectors and is the main force the Risks can be defined in any of the projects an
Libyan economy, in the last has event is uncertain which results from the
witnessed in noticeable expansion occurrence or negative impact positively on the
activities. This has resulted in the recovery of the goal of the project (PMBOK, 2002, P127). Every
construction profession and subsidiary industries, risk of reason leads to a result, for example, the
therefore, the construction sector has taken the reason may be the qualified labour force limited
foremost position among the other, mainly in the for the project and that the result clear will appear
attraction of investments and creation of new in the additional cost or imbalance in scheduling
jobs. The management of risks is very important work and the length of the implementation period
in the planning and management of the projects, or the quality of implementation. There are some
construction industry is subject to more risks and known risks that have been identified, analysed
uncertainty than several other industries. The take and can now be planned. On the contrary the
off process of project from initial investment unknown Risks cannot be managed, although the
assessment to completion and into use is a managers of the project can deal with it by
difficult process. The construction industry in applying General Contingency Plans based on
Libya Strip is suffering from the past experience gained during the implementation
misunderstanding of risk management including of previous projects. A risk is anything that
risk identification, analysis and assessment. threatens the success of the project but accepted

ISSN: 2395-1303 http://www.ijetjournal.org Page 153


International Journal of Engineering and Techniques - Volume 2 Issue 6, Nov – Dec 2016

when undergoing budget in return which will threaten its goals, and this requires methods to
result. identify risks such as questionnaire, interviews
with project managers or officials in companies,
checklists, brainstorming, or Delphi Technique.
II. THE RISK MANAGEMENT Risk identification can depend on goals, any risk
PROCESS impedes the achievement of project goals
considered risk.
Overall risk management is the process of
identifying and evaluating the risks and 2. QUALITATIVE RISK ANALYSIS
Qualitative analysis of risks is most common in
developing strategies to manage it. These
the risk analysis process. On part, uses qualitative
strategies include the transfer of risks to other
risk analysis to prioritize risks that affect the
parties and to avoid and minimize the negative
goals of the project, and must be done on
effects and to accept some or all of its
qualitative analysis of the risks at the beginning
consequences. Traditional risk management
of the project and reviewed during the
focuses on the risks arising from physical or legal
implementation to keep pace with changes in the
reasons (example: natural disasters, fires,
level of risk.
accidents, death and lawsuits) on the other hand,
The ranking of risks:
financial risk management focus on those risks
Each project has different risks associated with
that can be managed using financial barter.
its processes, risk implementation, all of which
Regardless of the type of risk management, all
affect the activities of the project. A technique
the big companies and small businesses have a
used in risk arrangement is Probability Impact
dedicated team of risk management.
Risk Rating Matrix( ward،1999) as shown in
The risk management process should include the
Table (1), which expresses the value of all the
definition of risk identification, risk analysis, risk
risk in numbers 1,5,10 to signal risk arrangement
mitigation, monitoring and control of risk as
(low, Medium, High). Risk = Possibility x
show in Figure (1)
impact.

Table (1), Probability Impact Risk Rating Matrix(ward،1999).

3. RISK MITIGATION
The goal of this strategy is to mitigate the
consequences of the risk to an acceptable level.
Taking some of the actions that mitigate the risks
for the best to take action to address the
Figure (1). The Risk Management Process consequences of that risk. Examples of actions
taken before the start of implementation of the
1. RISK IDENTIFICATION projects during implementation, or the
The aim of this phase is to identify all the engineering or seismic tests or the selection of
potential risks that may face the project and suitable suppliers, These procedures may include

ISSN: 2395-1303 http://www.ijetjournal.org Page 154


International Journal of Engineering and Techniques - Volume 2 Issue 6, Nov – Dec 2016

changing the conditions to mitigate the potential 3-Political factors.


for danger, such as adding resources or time to 4-Lack of security and stability.
the activities of the project. 5- Design errors.
6-Errors in the calculation of quantities.
4. RISK MONITORING AND FOLLOW UP 7- Obtaining permits and approvals.
It is monitor and follow up of the effectiveness of
the actions taken or any other deviations can
occur in the project.

III. CHECK LIST


Questionnaire was developed to identify the risks
faced by projects in Libya. Financial and
economic impact of projects on the distribution
of the questionnaire section for 32 the company
implemented housing projects in Libya to get to
know some of the risks faced by projects in Libya
with an estimate of the probability of occurrence
and the resulting impact.
Table 2 shows the checklist risks that could have Figure (2). The risks very high probability of occurrence.
faced the owner or contractor in the construction Lack of companies ability to implement:-
projects. The list of these risks that have been Lack of companies able to implement projects
identified from the companies in the study due to three reasons must be considered when
sample had a negative impact on the project in contracting and these reasons are: -
terms of (time, cost and quality). 1- Organizational ability
N The risk
2- Financial ability
1 Lack of companies ability to implement
2 Delays in the payment of payment certificates
3- Financial and technical ability and experience
3 Political factors. in the implementation of projects.
4 Lack of security and stability. Delays in the payment of payment certificates:
5 Design errors. Delays in the payment of payment certificates for
6 Errors in the calculation of quantities. the executed works, and can reduce these risks
7 Obtaining permits and approvals. through the following actions: -
8 The lack of experience of supervising engineers.
9 The inexperience of the offices of the National
1- Must submit payment certificates timely.
Advisory. 2- Must prepare preparation payment certificates
10 Centralised decision-making. before submission it to owner.
11 Technical specifications change during the Political factors:
execution of the project.
The worry of foreign financiers and domestic
12 Lack of experience and financial and technical
capacity of the contractor companies from the collapse of the political
13 Lack of labor experience. regime in the country where the result in the
14 Lack of materials. collapse of the security and economic level and
Table ( 2) the checklist risks the lack of the rule of law. In this case, one of the
Most of the participating companies in the study main parties in the contract is unable to fulfil its
questionnaire reported that the risks from 1 to 7 contractual obligations.
have very high probability of occurrence .All of Lack of security and stability:
these risks are described in Figure 2 and impact The risks security have a negative impact on the
are as follows: - projects. The companies face a big problem in
1-Lack of companies ability to implement terms of the inability to bring in workers from
2-Delays in the payment of payment certificates

ISSN: 2395-1303 http://www.ijetjournal.org Page 155


International Journal of Engineering and Techniques - Volume 2 Issue 6, Nov – Dec 2016

abroad to work to the project. Also many of the aim is to identify the main criteria that should be
projects turned to a military barracks of the used in the assessment of the construction
armed militias, and some subjected to breaking in companies.
from the citizens. 2. The criteria that must be provided in the
Design errors and Errors in the calculation of proposed form
quantities:- A- Financial situation: This includes aspects
There are technical risks amendments to the related to the financial status of the company and
designs and construction methods of execution the documents to be submitted and knowledge of
during the implementation, in addition to the monetary flowability and financial ability.
wrong estimate for quantities necessary to B- Material resources file: A file that includes
implement the projects in contracts. all the machinery and equipment available to the
Obtaining permits and approvals:- company to implement the project.
The difficulty in obtaining permits and approvals C- Years of experience of the company: The
before and during the implementation of projects company's experience in the implementation of
is one of the most important risks that affect the projects as well as the professional reputation of
project duration as these procedures may take the company.
months before the completion of its cycle of D- Technical File: A file that includes all the
administrative between the owner and the technical possibilities available to the company.
contractor. E- Human Resource file: A file that includes all
Rehabilitation of construction companies administrative and technical cadres available to
before contracting with them the company to implement the project.
One of the most important risks facing F- Planning and Follow-up: Is the company's
construction projects in Libya is the ability of ability to management, planning and control
companies implementing projects on time and at work on the project.
cost and specifications agreed upon. So it was a G- Safety and Insurance: Includes the industrial
study for the rehabilitation of these companies safety of the project and the safety of labourers
before contracting with them and suggests forms and insurance on the project.
for the rehabilitation of these companies so as to 3. The questionnaire results in the proposed
know the financial, technical and managerial its form
potential before being contracted. And It created a form for evaluating companies and
classification of companies should be in write all the basic criteria format questions with
accordance with the several criteria such as the the use of economic laws in Libya and that define
share capital and years of experience as well as and assess the activities of construction
volume of technical manpower and the cadres of companies. With included questionnaire on 7
administrative and equipment and machinery. basic criteria, each of which contains several
1. Suggested form for evaluating construction secondary standards were the result of many
companies. questions to illustrate different aspects and to
After seeing the economic laws in Libya, which evaluate construction companies before
identifies and assesses companies activities and contracting with them, were distributed to the
most recently the Council of Ministers project managers and contractors and consultants,
Resolution No. (171) of 2006, Issuing the and the table 3 major shows the results of the
executive regulations of Law No. (21) Of 2001 questionnaire ratios basic standards.
concerning the practice of economic activities in the basic criteria Secondary criteria
Libya. It has been proposed as a form for Having current accounts in banks
Financial situation Cash flow of the company
evaluating construction companies, through a 28.1%
questionnaire which was distributed to 32 of the Owning machines and equipment
companies that implement projects in Libya. The Material resources file required for the work

ISSN: 2395-1303 http://www.ijetjournal.org Page 156


International Journal of Engineering and Techniques - Volume 2 Issue 6, Nov – Dec 2016

15.6% Owning construction materials


required for the work
The lack of previously unsuccessful
Years of experience of projects
the company 15.6% The absence of a lawsuits against the
company
A number of similar projects for the
current project
Quality certificates in the
implementation of previous projects.
Technical File 12.5% Providing cadre trained in project
implementation
Having integrated engineering
Human Resource file specialities for the project wanted
12.5% implement
Having the entire organisational
structure of the company
Planning and Follow-up Having research and development
9.4% department
Having of control system and follow-
up work carried out in the project
Safety and Insurance Having certificates of insurance Figur (4). Files used in suggested form.
6.3% project Depending on the obtained results of the
The existence of previous incidents of questionnaire, the companies were ranked
death for workers
according to their potential and capabilities, and
Provide a cadre of industrial security
company so the candidate is notified for the tender, while
Provide training programs for the the companies that did not get the required grades
prevention of accidents are excluded. That the reality of companies in
Provide protection from natural Libya indicates the presence of a large deviation
disasters system
Table (3) the basic criteria and Secondary files in the proposed form in the success of these projects and the reason for
Results from the survey shows that the financial the deviation is due to many factors, including
situation of the companies is the most important those related to Implementing the company or the
factor in the proposed model for the evaluation of royal institution. The evaluation of companies is
construction companies. Where the percentage a key factor in the success of the project by
rate of 28.1% of the companies participating in making sure their potential financial and
the survey, and then followed by materials technical capabilities and administrative and its
resources file and years of experience of the previous experience in the projects implemented.
company by percentage rate of 15.6% , and then VI. CONCLUSION
comes to the files in the order as follows:- Construction projects are always associated with
Technical File 12.5% risk and uncertainty because of the length of the
Human Resource file 12.5% implementation period that change the conditions
Planning and Follow-up 9.4% making it contain multiple risks. The most
Safety and Insurance 6.3% important risk facing the projects in Libya are the
Figure 4 shows the proportions of these files in presence of companies not able to implement
suggested form. projects on time and in the required quality and
the approved budget and specifications agreed
upon. Valuation of companies is a key factor in
the success of the project by making sure the
financial, technical and administrative
capabilities and expertise in the implementation
of previous projects. Therefore this field study
was to determine suggested form for the

ISSN: 2395-1303 http://www.ijetjournal.org Page 157


International Journal of Engineering and Techniques - Volume 2 Issue 6, Nov – Dec 2016

rehabilitation of the construction companies 8. Kevin, J. Implementing A Design / Build.


before contracting with them, and the purpose of Prequalification System, Journal of Management
in Engineering, vol11 (3), 31-37, USA, (1995).
this model is to ensure the ability of companies
financial, technical and administrative 9. McNamara, C., Authenticity Consulting, LLC
capabilities and expertise in the implementation Copyright 2008, (2008).
of projects The definition of criteria that must be
available in these companies in the suggested
10. Rodger, C, and Jason P , Uncertainty and Risk
form to be invited to the auction. These Analysis, price water house ,U.K, (1999).
companies in the project and these standards are
(financial situation, material resources file, years 11. Samuel G S, Estimation of the Financial Risk Public
of experience of the company, technical file, Enterprises Construction in Egypt, Cairo-University,
human resource file, planning and Follow-up, Egypt, (1996).
safety and Insurance). using this suggested form
to evaluate companies before contracting with 12. Sonmez, M. H., Graham, G., Applying Evidential
them is recommended. The preparation checklist Reasoning to Prequalifying Construction
contains the risk of the projects to be a reference Contractors, Journal of Management in Engineering,
point for any owner or implementer of projects to 18(3), 116-118, USA, (2002).
be taken into account when hiring or
implementation of projects. These risks have the 13. WARD, S. C., Assessing and Managing Important
Risks, International Journal of Project Management,
greatest impact on the time, cost and quality. 17(6), 331-336, (1999).
REFERENCES
1. Carter, B., Hancock, T., Morin, J.M., and Robins, N.,
Introducing RI methodology, the Stationery Office,
London. (1996).

2. Dave H and David H , Universal Risk Project, Risk


Management Institute , UK , (2002).

3. Fouzi, hossen, Analyse and manage the risks faced by


construction projects, Faculty of Engineering,
University of Omar Mukhtar, Libya, (2012).

4. Gillett, J. E., Hazard Study and Risk Assessment in


the Pharmaceutical Industry, Interpharm Press,Inc,
USA, (1997).

5. Hossen Fouzi A. Planning Risk Assessment in the


Manufacture of Complex Capital Goods, PhD Thesis,
Newcastle University, UK, (2006).

6. Hulettvice ,D T , Project Risk Management, Risk


Management Institute, U.K, (2001).

7. Raftery, J.,Risk Analysis in Project Management,


Suffolk: St Ed Bury Press Limited, Bury St Edmunds,
(1994).

ISSN: 2395-1303 http://www.ijetjournal.org Page 158

You might also like