The following items are required in the design package due before 4 pm on Sunday, December
24, 2017
1 An equipment schedule showing all processing equipment in the section and their equipment
designations consistent with the PFDs.
2 For each piece of major equipment state:
basis of equipment selection and brief description
basis for the shortcut design such as residence time, heat load, throughput, product
quality, operating P and T, etc.
3 Shortcut equipment designs to obtain sizing of equipment. Present as a calculation sheet for
each item with any references to charts, monographs or simplified equations. Can be done
neatly on numbered calculation sheets. ( no duplication for identical items).
4 A simple outline sketch of the equipment, showing location of any key features such as
nozzles, hatches, instrument connections etc. This shows plan, elevation and side elevation.
Show overall dimensions of the item.
5 Preliminary detailed equipment design