Professional Documents
Culture Documents
: 1
BIDDER : DATE :
INQUIRY No. : LPP-00-A12-RQ-210-R PROJECT : LOMBOK CFSPP FTP-2 (2x50MW)
WORK TITLE : HVAC WORK JOB No. : 18-1206
A FORM OF BID
Dear Sirs,
Having examined the Bid Documents for LOMBOK CFSPP FTP-2 (2 X 50 MW) PROJECT
we, the under signed bidder, offer to perform the Work at the Site and complete the whole of
the said work in conformity with said Bid Documents for the Lump Sum fixed Unit Price
of Nine Billion Nine Hundred and Seventeen Million Rupiah (Rp. 9.917.000.000).
If the proposal is accepted, we undertake to commence the work immediately on receipt of your
order to commence, and to complete the whole of the work in accordance with the Work
Schedule stated in the Bid Documets.
We agree to abide by this Bid for the period of ( 120 ) calenders days from closing time of
the Bid and it shall remain binding upon us and may be accepted at any time before the
expiration of the period.
If the proposal is accepted, we will furnish the required performance bond in the sum
of (Rp.10.119.388.000), ten percen (10%) of the Contract Price in a form satisfactory to the
REKAYASA, no later than fourteen ( 14 ) days from the date of Firm order.
Attached hereto and by this reference incorporated herein and made a part of this proposal is
the proposal data required by Para 15 of the Requisition.
COST SUMMARY
(WORK ITEM WISE)
B PERMANENT WORK
B.1 STEAM TURBINE BUILDING 6,021,991,400
B.2 WAREHOUSE, WORKSHOP & FIRE STATION 223,046,200
B.3 LABORATORY BUILDING 95,976,300
B.4 GUARD HOUSE 24,564,900
B.5 MOSQUE 58,717,200
B.6 ADMINISTRATION BUILDING 1,321,063,900
B.7 COAL HANDLING CONTROL BUILDING 136,393,800
B.8 COOLING WATER ELECTRICAL BUILDING 179,755,300
B.9 ELECTROSTATIC PRECIPITATOR CONTROL BUILDING 244,120,400
B.10 PLANT WATER BUILDING (WTP-WWTP ELECTRICAL BUILDING) 179,514,900
B.11 TOXIC & HAZARDOUS WASTE STORAGE BUILDING 6,855,700
B.12 ELEVATED GUARD HOUSE -
B.13 ACID & ALKALI STORAGE SHED -
B.14 FIRE FIGHTING PUMP STATION -
B.15 CEMS HOUSE -
COST BREAKDOWN
(WORK ITEM WISE)
COST BREAKDOWN
(WORK ITEM WISE)
Supply, fabrication and installation include setting, testing, commissioning and balancing c/w support, hanger, painting -
B.1.5.4.1 Supply Air Diffuser Lot 1.0 31,326,200 - 10,953,200 5,477,000 47,756,400 47,756,400
B.1.5.4.2 Return Air Grille Lot 1.0 15,334,500 - 548,300 33,642,600 49,525,400 49,525,400
B.1.5.4.3 Non-return damper Lot 1.0 15,334,500 - 5,477,000 3,912,900 24,724,400 24,724,400
B.1.5.4.4 Manual Volume damper Lot 1.0 10,953,200 - 548,300 2,347,900 13,849,400 13,849,400
B.1.5.4.5 Motorized Volume Control Damper (MCD) c/w actuator, controlling & monitoring devices Lot 1.0 19,715,700 - 1,643,200 3,130,900 24,489,800 24,489,800
B.1.5.4.6 Motorized Shut Off Damper (SOD) c/w actuator, controlling & monitoring devices Lot 1.0 8,215,100 - 548,300 1,565,900 10,329,300 10,329,300
B.1.5.4.7 Rain hood & insect screen for fresh air intake duct Lot 1.0 383,500 - 274,600 235,500 893,600 893,600
B.1.5.5 Ducting & Accessories for Exhaust Air System -
Supply, fabrication and installation include setting, testing, commissioning and balancing c/w support, hanger, painting -
B.1.5.5.1 Ducting non-insulation for Exhaust Fan Male & Female Toilet Lot 1.0 822,000 - 657,200 7,512,200 8,991,400 8,991,400
B.1.5.5.2 Non-return damper / gravity damper Lot 1.0 657,200 - 54,900 235,500 947,600 947,600
B.1.5.5.3 Exhaust Air Grille Lot 1.0 1,095,700 - 109,800 940,300 2,145,800 2,145,800
B.1.5.5.4 Manual Volume damper Lot 1.0 1,643,200 - 54,900 470,100 2,168,200 2,168,200
B.1.5.6 All other material undetected : support, hanger, and consummable material for Ducting Installation Lot 1.0 10,953,200 - 2,190,600 3,912,900 17,056,700 17,056,700
SUB TOTAL DUCTING INSTALLATION WORK 0 1,658,594,900
B.1.6 ELECTRICAL & INSTRUMENT INSTALLATION WORK 0
B.1.6.1 HVAC Panel 0
Supply, fabrication and installation include terminating, setting, connecting, testing, and commissioning c/w supporting, painting and
0
accessories
B.1.6.1.1 HVAC Power Distribution Panel (HDP) for : Lot 1.0 246,441,200 - 2,190,600 7,824,100 256,455,900 256,455,900
Indoor Unit (AHU), Outdoor Units (CDU), Electric Duct Heater, Exhaust Fans & -
Control System ( Manufactured Std ) -
B.1.6.1.2 HVAC Control Panel (HCP/ PLC & HMI) for : Lot 1.0 109,530,200 - 21,906,400 6,260,000 137,696,600 137,696,600
Indoor Unit (AHU), Outdoor Units (CDU), Electric Duct Heater, Motor Dampers & -
Instrument Devices -
B.1.6.2 HVAC Instrument Devices 0
Supply, fabrication and installation include terminating, setting, connecting, testing, and commissioning c/w supporting, painting and
0
accessories
B.1.6.2.1 Temperature Transmitter (TT) for controlling room air temperature Lot 2.0 109,800 - 54,900 1,565,900 1,730,600 3,461,200
B.1.6.2.2 Humidity Transmitter (HT) for controlling room air humidity Lot 2.0 8,762,500 - 548,300 2,347,900 11,658,700 23,317,400
B.1.6.2.3 Pressure Differential Transmitter (PDT) for controlling room air differential pressure Lot 2.0 356,500 - 109,800 783,900 1,250,200 2,500,400
B.1.6.2.4 Duct mounted Air Flow Switch (AFS) Lot 4.0 1,095,700 - 11,100 157,300 1,264,100 5,056,400
B.1.6.2.5 Duct mounted High Temperature Limit Switch (HLS) Lot 2.0 985,900 - 54,900 157,300 1,198,100 2,396,200
B.1.6.3 Power Cables 0
Supply, fabrication and installation include terminating, setting, connecting, testing, and commissioning c/w supporting, painting and
0
accessories
B.1.6.3.1 Power Cable from HDP to AHU-01 Lot 1.0 1,643,200 - 274,600 470,100 2,387,900 2,387,900
B.1.6.3.2 Power Cable from HDP to AHU-02 Lot 1.0 1,643,200 - 274,600 470,100 2,387,900 2,387,900
B.1.6.3.3 Power Cable from HDP to AHU-03 Lot 1.0 822,000 - 219,700 235,500 1,277,200 1,277,200
B.1.6.3.4 Power Cable from HDP to AHU-04 Lot 1.0 822,000 - 219,700 235,500 1,277,200 1,277,200
B.1.6.3.5 Power Cable from HDP to CDU-01 Lot 1.0 26,287,700 - 5,477,000 6,845,600 38,610,300 38,610,300
B.1.6.3.6 Power Cable from HDP to CDU-02 Lot 1.0 27,382,500 - 5,477,000 7,198,400 40,057,900 40,057,900
B.1.6.3.7 Power Cable from HDP to CDU-03 Lot 1.0 10,350,800 - 2,739,000 2,817,200 15,907,000 15,907,000
B.1.6.3.8 Power Cable from HDP to CDU-04 Lot 1.0 10,942,000 - 2,739,000 2,895,400 16,576,400 16,576,400
B.1.6.3.9 Power Cable from HDP to EXF-01 (Roof Fan) Lot 1.0 4,381,200 - 877,000 1,174,900 6,433,100 6,433,100
B.1.6.3.10 Power Cable from HDP to EXF-02 (Roof Fan) Lot 1.0 4,381,200 - 877,000 1,174,900 6,433,100 6,433,100
B.1.6.3.11 Power Cable from HDP to EXF-03 (Roof Fan) Lot 1.0 4,381,200 - 877,000 1,174,900 6,433,100 6,433,100
B.1.6.3.12 Power Cable from HDP to EXF-04 (Roof Fan) Lot 1.0 4,929,600 - 877,000 1,174,900 6,981,500 6,981,500
B.1.6.3.13 Power Cable from HDP to EXF-05 (Roof Fan) Lot 1.0 4,929,600 - 877,000 1,174,900 6,981,500 6,981,500
B.1.6.3.14 Power Cable from HDP to EXF-06 (Roof Fan) Lot 1.0 5,914,600 - 877,000 1,174,900 7,966,500 7,966,500
B.1.6.3.15 Power Cable from HDP to EXF-07 (Roof Fan) Lot 1.0 5,914,600 - 877,000 1,174,900 7,966,500 7,966,500
B.1.6.3.16 Power Cable from HDP to EXF-08 (Roof Fan) Lot 1.0 6,571,900 - 877,000 1,174,900 8,623,800 8,623,800
B.1.6.3.17 Power Cable from HDP to EXF-09A (Battery Room) Lot 1.0 6,571,900 - 877,000 1,174,900 8,623,800 8,623,800
B.1.6.3.18 Power Cable from HDP to EXF-09B (Battery Room) Lot 1.0 657,200 - 219,700 392,800 1,269,700 1,269,700
B.1.6.3.19 Power Cable from HDP to EXF-10A (GCB Room) Lot 1.0 657,200 - 219,700 392,800 1,269,700 1,269,700
B.1.6.3.20 Power Cable from HDP to EXF-10B (GCB Room) Lot 1.0 1,095,700 - 219,700 392,800 1,708,200 1,708,200
B.1.6.3.21 Power Cable from HDP to EXF-11A (GCB Room) Lot 1.0 1,095,700 - 219,700 392,800 1,708,200 1,708,200
B.1.6.3.22 Power Cable from HDP to EXF-11B (GCB Room) Lot 1.0 1,095,700 - 219,700 392,800 1,708,200 1,708,200
B.1.6.3.23 Power Cable from HDP to EXF-12 (Toilet 2nd Floor) Lot 1.0 1,095,700 - 219,700 392,800 1,708,200 1,708,200
B.1.6.3.24 Power Cable from HDP to EXF-13 (Pantry 2nd Floor) Lot 1.0 1,095,700 - 219,700 392,800 1,708,200 1,708,200
B.1.6.3.25 Power Cable from HDP to EDH-01 Lot 1.0 1,095,700 - 219,700 392,800 1,708,200 1,708,200
B.1.6.3.26 Power Cable from HDP to EDH-02 Lot 1.0 1,095,700 - 219,700 392,800 1,708,200 1,708,200
B.1.6.3.27 Power Cable from HDP to HCP/ PLC Lot 1.0 1,095,700 - 219,700 392,800 1,708,200 1,708,200
REQUISITION No. : LPP-00-A12-MR-210-R - FORM No. : 2B
BIDDER : PT MITRA HUTAMA ENGINEERING DATE : Tuesday, March 05, 2019
INQUIRY No. : LPP-00-A12-RQ-210-R - PROJECT : LOMBOK CFSPP FTP-2 (2x50MW)
WORK TITLE : HVAC WORK JOB No. : 18-1206
COST BREAKDOWN
(WORK ITEM WISE)
COST BREAKDOWN
(WORK ITEM WISE)
COST BREAKDOWN
(WORK ITEM WISE)
COST BREAKDOWN
(WORK ITEM WISE)
B.5 MOSQUE
B.5.1 MAIN EQUIPMENT
B.5.1.1 Air Cooled DX - Wall Mounted, Refrigerant with R407C or R134A or Non CFC Unit 1.0 164,700 6,330,800 109,800 940,300 7,545,600 7,545,600
Supply and installation c/w supportting, setting, testing and commissioning. -
- Room : Office -
- Type : Wall Mounted -
- Total Cooling Capacity = 12.624,40 Btu/h (3,70 kW) CS/CU-PN18SKP (18000btuh) -
- Air Volume : 1.105,20 CMH (307 L/S) -
- Power Consumption : TBA -
- External Static Pressure : Manufacture Standard -
- Electrical spec : 220-230V/ 50Hz/ 1 Phase -
- Blue Fin, Black Fin, Gold Fin or equal -
B.5.1.2 Air Cooled DX - Wall Mounted, Refrigerant with R407C or R134A or Non CFC Unit 1.0 219,700 6,330,800 109,800 1,017,500 7,677,800 7,677,800
Supply and installation c/w supportting, setting, testing and commissioning.
- Room : Library
- Type : Wall Mounted
- Total Cooling Capacity = 14.671,60 Btu/h (4,30 kW) CS/CU-PN18SKP (18000btuh)
- Air Volume : 1.281,60 CMH (356 L/S)
- Power Consumption : TBA
- External Static Pressure : Manufacture Standard
- Electrical spec : 220-230V/ 50Hz/ 1 Phase
- Blue Fin, Black Fin, Gold Fin or equal
B.5.1.3 Exhaust Fan for Male Toilet DWA 200 Unit 1.0 109,800 1,293,100 39,100 313,700 1,755,700 1,755,700
Supply and installation c/w supportting, setting, testing and commissioning. -
- Type : Propeller Wall Mounted Fan -
- Air Volume : 75,00 CMH (20,83 L/S) -
- Power Consumption : VTA -
- Total External Static Pressure : 38 Pa -
- Electrical spec : 220-230V/ 50Hz/ 1 Phase -
- c/w electrical switch/ receptackle, rain hood, gravity damper & insect screen -
B.5.1.4 Exhaust Fan for Female Toilet DWA 200 Unit 1.0 109,800 1,293,100 39,100 313,700 1,755,700 1,755,700
Supply and installation c/w supportting, setting, testing and commissioning. -
- Type : Propeller Wall Mounted Fan -
- Air Volume : 75,00 CMH (20,83 L/S) -
- Power Consumption : VTA -
- Total External Static Pressure : 38 Pa -
- Electrical spec : 220-230V/ 50Hz/ 1 Phase -
- c/w electrical switch/ receptackle, rain hood, gravity damper & insect screen -
REQUISITION No. : LPP-00-A12-MR-210-R - FORM No. : 2B
BIDDER : PT MITRA HUTAMA ENGINEERING DATE : Tuesday, March 05, 2019
INQUIRY No. : LPP-00-A12-RQ-210-R - PROJECT : LOMBOK CFSPP FTP-2 (2x50MW)
WORK TITLE : HVAC WORK JOB No. : 18-1206
COST BREAKDOWN
(WORK ITEM WISE)
COST BREAKDOWN
(WORK ITEM WISE)
Supply, fabrication and installation include setting, testing, commissioning and balancing c/w support, hanger, painting -
B.6.4.4.1 Supply Air Diffuser Lot 1.0 17,306,300 - 1,095,700 5,258,200 23,660,200 23,660,200
B.6.4.4.2 Return Air Grille Lot 1.0 13,362,600 - 1,095,700 3,912,900 18,371,200 18,371,200
B.6.4.4.3 Non-return damper Lot 1.0 2,739,000 - 274,600 548,300 3,561,900 3,561,900
B.6.4.4.4 Manual Volume damper Lot 1.0 2,739,000 - 274,600 548,300 3,561,900 3,561,900
B.6.4.4.5 Rain hood & insect screen for fresh air intake duct Lot 1.0 1,643,200 - 109,800 657,200 2,410,200 2,410,200
B.6.4.5 Ducting & Accessories for Exhaust Air System -
Supply, fabrication and installation include setting, testing, commissioning and balancing c/w support, hanger, painting -
B.6.4.5.1 Ducting non-insulation for Exhaust Fan Pantry Ground Floor Lot 1.0 2,410,300 - 109,800 2,347,900 4,868,000 4,868,000
B.6.4.5.2 Ducting non-insulation for Exhaust Fan Male & Female Toilet Ground Floor Lot 1.0 6,353,100 - 274,600 5,398,800 12,026,500 12,026,500
B.6.4.5.3 Ducting non-insulation for Exhaust Fan Male & Female Toilet Second Floor Lot 1.0 4,601,000 - 27,900 3,990,200 8,619,100 8,619,100
B.6.4.5.4 Non-return damper / gravity damper Lot 1.0 1,095,700 - 54,900 392,800 1,543,400 1,543,400
B.6.4.5.5 Exhaust Air Grille Lot 1.0 3,176,500 - 109,800 157,300 3,443,600 3,443,600
B.6.4.5.6 Manual Volume damper Lot 1.0 657,200 - 109,800 392,800 1,159,800 1,159,800
B.6.4.6 All other material undetected : support, hanger, and consummable material for Ducting Installation Lot 1.0 548,300 - 109,800 313,700 971,800 971,800
SUB TOTAL DUCTING INSTALLATION WORK 0 687,083,900
B.6.5 ELECTRICAL & INSTRUMENT INSTALLATION WORK 0
B.6.5.1 VAC Power Distribution Panel (HDP) for : Lot 1.0 38,335,700 - 1,095,700 40,000 39,471,400 39,471,400
Indoor Unit (AHU), Outdoor Units (CDU), Exhaust Fans & Internal -
Control System ( Manufactured Std ) -
Supply, fabrication and installation include terminating, setting, connecting, testing, and commissioning c/w supporting, painting and
0
accessories
B.6.5.2 Power Cables 0
Supply, fabrication and installation include terminating, setting, connecting, testing, and commissioning c/w supporting, painting and
0
accessories
B.6.5.2.1 Power Cable from HDP to AHU-01 Lot 1.0 657,200 - 54,900 235,500 947,600 947,600
B.6.5.2.2 Power Cable from HDP to AHU-02 Lot 1.0 1,314,500 - 109,800 470,100 1,894,400 1,894,400
B.6.5.2.3 Power Cable from HDP to CDU-01 Lot 1.0 1,095,700 - 548,300 3,130,900 4,774,900 4,774,900
B.6.5.2.4 Power Cable from HDP to CDU-02 Lot 1.0 5,477,000 - 274,600 1,565,900 7,317,500 7,317,500
B.6.5.2.5 Power Cable from HDP to EXF-ADM-01 (Pantry) Lot 1.0 548,300 - 54,900 235,500 838,700 838,700
B.6.5.2.6 Power Cable from HDP to EXF-ADM-02 (Toilet) Lot 1.0 657,200 - 54,900 235,500 947,600 947,600
B.6.5.2.7 Power Cable from HDP to EXF-ADM-03 (Toilet) Lot 1.0 877,000 - 66,100 313,700 1,256,800 1,256,800
B.6.5.2.8 Power Cable from HDP to EXF-ADM-04 (Pantry) Lot 1.0 877,000 - 66,100 313,700 1,256,800 1,256,800
B.6.5.2.9 Steel conduit/EMT Cable Tray ,Cable gland , c/w Accessories Lot 1.0 10,953,200 - 1,095,700 313,700 12,362,600 12,362,600
B.6.5.3 Grounding cable Lot 1.0 5,477,000 - 328,600 1,252,100 7,057,700 7,057,700
B.6.5.4 AHU - CDU Control Cables 0
Supply, fabrication and installation include terminating, setting, connecting, testing, and commissioning c/w supporting, painting and
0
accessories
B.6.5.4.1 Control Cable from AHU-01 to CDU-01 Lot 1.0 2,739,000 - 109,800 783,900 3,632,700 3,632,700
B.6.5.4.2 Control Cable from AHU-02 to CDU-02 Lot 1.0 1,369,500 - 54,900 392,800 1,817,200 1,817,200
B.6.5.4.3 Steel conduit/EMT Cable Tray ,Cable gland , c/w Accessories Lot 1.0 8,215,100 - 548,300 2,347,900 11,111,300 11,111,300
B.6.5.5 All other material undetected : support, hanger, and consummable material for Electrical Installation Lot 1.0 5,477,000 - 548,300 1,565,900 7,591,200 7,591,200
SUB TOTAL ELECTRICAL INSTALLATION WORK 0 102,278,400
B.6.6 TESTING COMMISSIONING 0
Pre-Commissioning, Testing & Commissioning & other test required Lot 1.0 - - - 5,477,000 5,477,000 5,477,000
TOTAL ADMINISTRATION BUILDING 1,321,063,900
COST BREAKDOWN
(WORK ITEM WISE)
COST BREAKDOWN
(WORK ITEM WISE)
COST SUMMARY
(COST ITEM WISE)
1 Direct cost
1.1 Direct material 2,805,132,200
1.2 Direct labor (ongkos buruh lapangan) 1,470,376,500
1.3 Direct construction equipment (biaya peralatan kerja) 3,957,717,200
2 Indirect c
2.1 Home office cost (biaya kantoran) 110,000,000
2.2 Mobilization and demobilization 125,000,000
2.3 Temporary facilities (kantor lapangan, listrik, air, dll) 58,774,100
2.4 Salaries, wages, allowance 150,000,000
2.5 Field expenses (biaya operasional lapangan yang lain) 200,000,000
2.6 Maintenance cost for equipment 90,000,000
2.7 Small construction supplies (material consumable) 50,000,000
2.8 Transportation cost 200,000,000
2.9 Insurance 275,000,000
2.10 Direct labor service cost (makan, transportasi dll utk buruh) 325,000,000
2.11 Pre financing cost (biaya mengawali proyek berjalan) 100,000,000
ROUNDED (Pembulatan)
REQUISITION No. : LPP-00-A12-MR-210-R FORM No. : 3B
BIDDER : PT MITRA HUTAMA ENGINEERING DATE : Tuesday, March 05, 2019
INQUIRY No. : LPP-00-A12-RQ-210-R PROJECT : LOMBOK CFSPP FTP-2 (2x50MW)
WORK TITLE : HVAC WORK JOB No. : 18-1206
COST BREAKDOWN
(COST ITEM WISE)
1 Direct cost
1.1 Direct material LS 1 2,805,132,200 2,805,132,200
1.2 Direct labor LS 1 1,470,376,500 1,470,376,500
1.3 Direct construction equipment LS 1 3,957,717,200 3,957,717,200
2 Indirect cost
2.1 Home office cost LS 1 110,000,000 110,000,000
2.2 Mobilization and demobilization
2.2.1 Field personnel LS 1 75,000,000 75,000,000
2.2.2 Equipment, tools, etc. LS 1 50,000,000 50,000,000
Sub Total 2.2
2.3 Temporary facilities (cost, supply and demolition)
2.3.1 Temporary building facilities and accessories LS 1 25,000,000 25,000,000
2.3.2 Camp or housing LS 1 15,000,000 15,000,000
2.3.3 Temporary electrical LS 1 5,000,000 5,000,000
2.3.4 Temporary water distribution LS 1 3,774,100 3,774,100
2.3.5 Temporary road and drainage, if necessary LS 1 5,000,000 5,000,000
2.3.6 Temporary civil work LS 1 5,000,000 5,000,000
Sub Total 2.3
2.4 Salaries, wages, allowance
2.4.1 Expatriate, supervising staff LS 1 50,000,000 50,000,000
2.4.2 Indirect worker for field operation LS 1 100,000,000 100,000,000
Sub Total 2.4.
2.5 Field expenses
2.5.1 Traveling
Jakarta - Location of Project Trip 1 75,000,000 75,000,000
Others Trip 1 25,000,000 25,000,000
2.5.2 Print and stationeries LS 1 5,000,000 5,000,000
2.5.3 Communication expense LS 1 5,000,000 5,000,000
2.5.4 Welfare expense LS 1 20,000,000 20,000,000
2.5.5 Third parties inspection LS 1 50,000,000 50,000,000
2.5.6 Other expenses LS 1 20,000,000 20,000,000
Sub Total 2.5
2.6 Maintenance cost for equipment
2.6.1 Maintenance cost Lot 1 60,000,000 60,000,000
2.6.2 Spare parts Lot 1 30,000,000 30,000,000
Sub Total 2.6
2.7 Small construction supplies
2.7.1 Consumables LS 1 15,000,000 15,000,000
2.7.2 Gases LS 1 4,000,000 4,000,000
2.7.3 Fuels and lubrications LS 1 7,500,000 7,500,000
2.7.4 Hand tool LS 1 10,000,000 10,000,000
2.7.5 Drinking water LS 1 3,000,000 3,000,000
2.7.6 Others LS 1 10,500,000 10,500,000
Sub Total 2.7
2.8 Transportation cost
2.8.1 Transportation for direct equipment and materia Lot 1 175,000,000 175,000,000
2.8.2 Transportation for indirect equipment and mater Lot 1 25,000,000 25,000,000
Sub Total 2.8
2.9 Insurance
2.9.1 Workmen's compensation, employer's liability
Lot 1 175,000,000 175,000,000
and social insurance
2.9.2 Automobile liability insurance Lot 1 25,000,000 25,000,000
2.9.3 Marine/cargo insurance Lot 1 60,000,000 60,000,000
2.9.4 Other insurance Lot 1 15,000,000 15,000,000
Sub Total 2.9
2.10 Direct labor service cost
2.10.1 Traveling and transportation LS 1 100,000,000 100,000,000
2.10.2 Welfare expense LS 1 75,000,000 75,000,000
2.10.3 Recruiting expense LS 1 25,000,000 25,000,000
2.10.4 Training expense LS 1 50,000,000 50,000,000
2.10.5 Lunch service cost M/D 1 50,000,000 50,000,000
2.10.6 Other expenses LS 1 25,000,000 25,000,000
Sub Total 2.10
REQUISITION No. : LPP-00-A12-MR-210-R FORM No. : 3B
BIDDER : PT MITRA HUTAMA ENGINEERING DATE : Tuesday, March 05, 2019
INQUIRY No. : LPP-00-A12-RQ-210-R PROJECT : LOMBOK CFSPP FTP-2 (2x50MW)
WORK TITLE : HVAC WORK JOB No. : 18-1206
COST BREAKDOWN
(COST ITEM WISE)
GRAND TOTAL
REQUISITION No. : LPP-00-A12-MR-210-R FORM No. :
BIDDER : 0 DATE :
INQUIRY No. : LPP-00-A12-RQ-210-R PROJECT :
WORK TITLE : HVAC WORK JOB No. :
B Direct Manpower
1 Foreman 280,000 56,000
2 Skill Worker 280,000 56,000
3 Heavy Equipment Operator 120,000 24,000
4 Surveyor 160,000 32,000
5 Assistance Surveyor 130,000 26,000
6 General Worker 120,000 24,000
Remark :
Normal working hour = 10 hours per day
4
Tuesday, March 05, 2019
LOMBOK CFSPP FTP-2 (2x50MW)
18-1206
OVERTIME RATE/HOUR
HOLIDAY/SUNDAY
(Rp)
150000
100000
40000
40000
80000
100000
40000
37500
70000
37500
70000
70000
30000
40000
32500
30000
REQUISITION No. : LPP-00-A12-MR-210-R FORM No. : 5
BIDDER : PT MITRA HUTAMA ENGINEERING DATE : Tuesday, March 05, 2019
INQUIRY No. : LPP-00-A12-RQ-210-R PROJECT : LOMBOK CFSPP FTP-2 (2x50MW)
WORK TITLE : HVAC WORK JOB No. : 18-1206
Month
NO. DESCRIPTION MAN-MONTH REMARK
1 2 3 4 5 6 7 8 9 10 11 12
1 Foreman
2 Skill worker carpenter
3 Skill worker concrete
4 Skill worker rebar
5 Welder
6 Heavy equipment operator
7 Surveyor
8 Assistance Surveyor
9 General Worker
TOTAL MANMONTHS
LEGEND :
Remark:
Normal working hour = 10 hours per day
REQUISITION No. : LPP-00-A12-MR-210-R FORM No. : 6
BIDDER : PT MITRA HUTAMA ENGINEERING DATE : Tuesday, March 05, 2019
INQUIRY No. : LPP-00-A12-RQ-210-R PROJECT : LOMBOK CFSPP FTP-2 (2x50MW)
WORK TITLE : HVAC WORK JOB No. : 18-1206
MAN Month
NO. DESCRIPTION REMARK
-MONTH 1 2 3 4 5 6 7 8 9 10 11 12
1 Site Manager
2 Superintendent
3 QA/QC
4 Engineering
5 Supervisor
6 Material Controller
7 Safety Officer
8 Administrator
9 Electrician/Mechanic
10 Security
TOTAL MANMONTHS
LEGEND :
Remark:
Normal working hour = 10 hours per day
REQUISITION No. : LPP-00-A12-MR-210-R FORM No. :
BIDDER : PT MITRA HUTAMA ENGINEERING DATE :
INQUIRY No. : LPP-00-A12-RQ-210-R PROJECT :
WORK TITLE : HVAC WORK JOB No. :
SUBCONTRACTOR
PROJECT KEY PERSONNEL RESUMES
A resume of each key person to be assigned to the work containing at least the following information.
a. Nationality
b. Position
c. Name
d. Age
e. Education
f. Relevant Experiences
g. Employment History
h. Language Spoken
Resume of key personnel shall be with the organization chart for the Work
REQUISITION No. : LPP-00-A12-MR-210-R FORM No. : 9
BIDDER : PT MITRA HUTAMA ENGINEERING DATE : Tuesday, March 05, 2019
INQUIRY No. : LPP-00-A12-RQ-210-R PROJECT : LOMBOK CFSPP FTP-2 (2x50MW)
WORK TITLE : HVAC WORK JOB No. : 18-1206
If the contractor awarded, the bidder shall propose to employ the following subcontractors who will perform or labor or render service to the work by
subcontractor or joint operation in or about the work.
A. National subcontractor
B. Local subcontractor
Remark :
Normal working hour = 10 hours per day
REQUISITION No. : LPP-00-A12-MR-210-R FORM No. : 10
BIDDER : PT MITRA HUTAMA ENGINEERING DATE : Tuesday, March 05, 2019
INQUIRY No. : LPP-00-A12-RQ-210-R PROJECT : LOMBOK CFSPP FTP-2 (2x50MW)
WORK TITLE : HVAC WORK JOB No. : 18-1206
TOTAL 52,400,000
REQUISITION No. : LPP-00-A12-MR-210-R FORM No. : 11
BIDDER : PT MITRA HUTAMA ENGINEERING DATE : Tuesday, March 05, 2019
INQUIRY No. : LPP-00-A12-RQ-210-R PROJECT : LOMBOK CFSPP FTP-2 (2x50MW)
WORK TITLE : HVAC WORK JOB No. : 18-1206
1 Split Duct Unit - Clima 1 lot 2,217,000 China 2-3 Months 3 x container 40HQ
Qty : 8 Unit
TOTAL 2,217,000
NOTE : (*) Total price shall include import txes and duties, the Bidder shall provide in this list the amount of tax and duties required for imported materials
REQUISITION No. : LPP-00-A12-MR-210-R FORM No. : 12
BIDDER : PT MITRA HUTAMA ENGINEERING DATE : Tuesday, March 05, 2019
INQUIRY No. : LPP-00-A12-RQ-210-R PROJECT : LOMBOK CFSPP FTP-2 (2x50MW)
WORK TITLE : HVAC WORK JOB No. : 18-1206
Month
NO. DESCRIPTION TOTAL REMARK
1 2 3 4 5 6 7 8 9 10 11 12
1 WATER
a. Raw water Liter 3000 3000 3000 3000 3000 3000 3000 3000 3000 3000 3000 3000
b. Potable water Liter 600 600 600 600 600 600 600 600 600 600 600 600
2 ELECTRIC POWER KWH 900 900 900 900 900 900 900 900 900 900 900 900
3 FUEL Liter 375 375 375 375 375 375 375 375 375 375 375 375
LEGEND :
REQUISITION No. : LPP-00-A12-MR-210-R FORM No. : 13
BIDDER : PT MITRA HUTAMA ENGINEERING DATE : Tuesday, March 05, 2019
INQUIRY No. : LPP-00-A12-RQ-210-R PROJECT : LOMBOK CFSPP FTP-2 (2x50MW)
WORK TITLE : HVAC WORK JOB No. : 18-1206
TOTAL MANMONTHS
LEGEND :
Remark:
Normal working hour = 10 hours per day
REQUISITION No. : LPP-00-A12-MR-210-R FORM No. : 13A
BIDDER : PT MITRA HUTAMA ENGINEERING DATE : Tuesday, March 05, 2019
INQUIRY No. : LPP-00-A12-RQ-210-R PROJECT : LOMBOK CFSPP FTP-2 (2x50MW)
WORK TITLE : HVAC WORK JOB No. : 18-1206
TOTAL 18,600,000
NOTE : Equipment rate shall include operator cost, fuel cost and maintenance cost
Remark:
Normal working hour = 10 hours per day
REQUISITION No. : LPP-00-A12-MR-210-R FORM No. : 14
BIDDER : PT MITRA HUTAMA ENGINEERING DATE : Tuesday, March 05, 2019
INQUIRY No. : LPP-00-A12-RQ-210-R PROJECT : LOMBOK CFSPP FTP-2 (2x50MW)
WORK TITLE : HVAC WORK JOB No. : 18-1206
LEGEND :
page 1
CONSTRUCTION METHOD
(DISKRIPSI & GAMBAR METODE KONSTRUKSI UNTUK MASING-MASING PEKERJAAN)
REQUISITION No. : LPP-00-A12-MR-210-R FORM No. : 15
BIDDER : PT MITRA HUTAMA ENGINEERING DATE : ###
INQUIRY No. : LPP-00-A12-RQ-210-R PROJECT : LOMBOK CFSPP FTP-2 (2x50MW)
WORK TITLE : HVAC WORK JOB No. : 18-1206
page 2
CONSTRUCTION METHOD
(DISKRIPSI & GAMBAR METODE KONSTRUKSI UNTUK MASING-MASING PEKERJAAN)
REQUISITION No. : LPP-00-A12-MR-210-R FORM No. : 15
BIDDER : PT MITRA HUTAMA ENGINEERING DATE : ###
INQUIRY No. : LPP-00-A12-RQ-210-R PROJECT : LOMBOK CFSPP FTP-2 (2x50MW)
WORK TITLE : HVAC WORK JOB No. : 18-1206
page 3
CONSTRUCTION METHOD
(DISKRIPSI & GAMBAR METODE KONSTRUKSI UNTUK MASING-MASING PEKERJAAN)
REQUISITION No. : LPP-00-A12-MR-210-R FORM No. : 16
BIDDER : PT MITRA HUTAMA ENGINEERING DATE : Tuesday, March 05, 2019
INQUIRY No. : LPP-00-A12-RQ-210-R PROJECT : LOMBOK CFSPP FTP-2 (2x50MW)
WORK TITLE : HVAC WORK JOB No. : 18-1206
PERSONNEL TO BE CONTACTED
REGARDING THIS INQUIRY
(PERWAKILAN ORANG YANG BISA DIHUBUNGI BERKAITAN DENGAN TENDER INI)
REQUISITION No. : LPP-00-A12-MR-210-R FORM No. : 17
BIDDER : PT MITRA HUTAMA ENGINEERING DATE : Tuesday, March 05, 2019
INQUIRY No. : LPP-00-A12-RQ-210-R PROJECT : LOMBOK CFSPP FTP-2 (2x50MW)
WORK TITLE : HVAC WORK JOB No. : 18-1206
PROVISION OF BID
(KETENTUAN YANG DIAJUKAN UNTUK PENAWARAN)
(MISAL: KONDISI EQUIPMET, TOOLS, MANPOWER, KEUNGGULAN DLL)
REQUISITION No. : LPP-00-A12-MR-210-R FORM No. : 18
BIDDER : PT MITRA HUTAMA ENGINEERING DATE : ###
INQUIRY No. : LPP-00-A12-RQ-210-R PROJECT : LOMBOK CFSPP FTP-2 (2x50MW)
WORK TITLE : HVAC WORK JOB No. : 18-1206
EXPERIENCE STATEMENT
(PERNYATAAN PENGALAMAN KERJA)
The bidder shall submit, as a part of its proposal the following statements as to its experience qualification. The bidder
certifies that all statements and information set forth below are true and accurate.
a. The bidder has been engaged in the contracting business under its present business name for 8 years.
Experiences in work of a nature similar in type and magnitude to that set forth in the Invitation To Bidder extends over a period of
b.
sixth.
The bidder, as contractor or subcontractor, has satisfactorily completed all contracts awarded to bidder, except as follow
c.
(name any and all exceptions and reasons, therefore bidder should attach and designate additional pages if necessary).
The following contracts covering work similar in type and magnitude to that forth in the Invitation To Bidder have been
d.
satisfactorily completed within the last their years for the following owners (person, firm or authority).
NOTE :
1. Bidder should attach and designate additional pages if necessary.
2. If Bidder is a jointventure or partnership formed within the Past.
REQUISITION No. : LPP-00-A12-MR-210-R FORM No. : 19
BIDDER : PT MITRA HUTAMA ENGINEERING DATE : Tuesday, March 05, 2019
INQUIRY No. : LPP-00-A12-RQ-210-R PROJECT : LOMBOK CFSPP FTP-2 (2x50MW)
WORK TITLE : HVAC WORK JOB No. : 18-1206
BANK REFERENCE
(REFERENSI & GARANSI BANK)
REQUISITION No. : LPP-00-A12-MR-210-R FORM No. : 23
BIDDER : PT MITRA HUTAMA ENGINEERING DATE : Tuesday, March 05, 2019
INQUIRY No. : LPP-00-A12-RQ-210-R PROJECT : LOMBOK CFSPP FTP-2 (2x50MW)
WORK TITLE : HVAC WORK JOB No. : 18-1206
DESCRIPTION OF AMOUNT OF
No. YEAR PROJECT
CLAIM LITIGATION CLAIM LITIGATION
- - - - -
REQUISITION No. : LPP-00-A12-MR-210-R FORM No. : 24
BIDDER : PT MITRA HUTAMA ENGINEERING DATE : Tuesday, March 05, 2019
INQUIRY No. : LPP-00-A12-RQ-210-R PROJECT : LOMBOK CFSPP FTP-2 (2x50MW)
WORK TITLE : HVAC WORK JOB No. : 18-1206
PAYMENT SCHEDULE
(SKEMA PEMBAYARAN YANG DIAJUKAN OLEH SUBKONTRAKTOR)
(DP = 30%, Penagihan tiap bulan/per-progress = 10% , Retention =5%)