JOINT OPERATION BODY PERTAMINA MEDCOE
& P TOMORI SULAWESI
JOINT OPERATING BODY
PLN GAS RECEIVING &
Document No.
METERING STATION
Page 3 of 11
SNO-P-CC-001
RECORD OF REVISION
Rev. Implemented
Section Page CLIENT’s Comment Explanation
Code (Y/N)
JOINT OPERATION BODY PERTAMINA MEDCOE
& P TOMORI SULAWESI
JOINT OPERATING BODY
PLN GAS RECEIVING &
Document No.
METERING STATION
Page 4 of 11
SNO-P-CC-001
TABLE OF CONTENTS
1 INTRODUCTION
The Operating Body Pertamina – Medco E&P Tomori Sulawesi (JOB PMTS) is planning to
deliver sales gas to PLN Luwuk. The gas will be supplied from 30” sales gas pipeline, tapped
from KM 6+700, close to PEP Matindok tie in point. In order to achieve delivered gas minimum
specification, JOB PMTS will Instal receiving facility downstream of the pipeline tie in point.
Scope.
1.2 Scope
This document is intended to verify the calculation of wall-thickness requirement for the line
pipe to be used for the gas pipeline & piping from KM 6+700, close to PEP Matindok tie in
point. Wall thickness has been designed to meet minimum requirements Pressure containment
(Hoop Stress Check) in accordance with ASME B. 31.3.
No.300.K/38/M.PE/1997 : Decree of the Minister of Mines and Energy Regarding Oil and
Gas Pipeline Occupational Safety
5 FORMULA
a. Piping systems are designed based on ASME B31.3. The following formula is used for the
calculation of steel pipe wall thickness:
t= P.D
2(S.E.W + P.Y)
JOINT OPERATION BODY PERTAMINA MEDCOE
& P TOMORI SULAWESI
JOINT OPERATING BODY
PLN GAS RECEIVING &
Document No.
METERING STATION
Page 7 of 11
SNO-P-CC-001
Where ;
Y= Coeff. From table 304.1.1, valid for t< D/6 and for materials shown. The value of Y
maybe interpolated for intermediate temperatures. For t ≥ D/ 6.
t nom = t + CA
Where, CA : Corrosion Allowance 3 mm
7 ATTACHMENT
Piping Wall Thickness Calculation as per ASME B31.3
JOINT OPERATION BODY PERTAMINA MEDCOE
& P TOMORI SULAWESI
JOINT OPERATING BODY
PLN GAS RECEIVING &
Document No.
METERING STATION
Page 11 of 11
SNO-P-CC-001
Attachment
Piping Wall Thickness Calculation