Professional Documents
Culture Documents
There is no definite and fixed classification of mathematical algorithms. Here, we are not
going to discuss them in details. Instead, we are going to introduce some topics which are
of more interest in this book and may be applicable to power system planning issues.1
Some topics, such as game theory, which are of more interest for other power system
issues (such as market analysis of power ystems), are not addressed here.
2. What are the constraints observed during optimization process of power system
expansion planning?
Optimization Techniques:
In everyday life, all of us are confronted with some decision makings. Normally, we try to decide
or the best. If someone is to buy a commodity, he or she tries to buy the best quality, yet with the
east cost. These types of decision makings are categorized as optimization problems in which the
aim is to find the optimum solutions; where the optimum may be either the least or the most.
Most of the operational and planning problems consist of the following three major steps
• Definition
• Modeling
• Solution algorithm
Decision variables are the independent variables; the decision maker has to determine their
optimum values and based on those, other variables (dependent) can be determined. For instance,
in an optimum generation scheduling problem, the active power generations of power plants may
be the decision variables. The dependent variables can be the total fuel consumption, system
losses, etc. which can be calculated upon determining the decision variables. In a capacitor
allocation problem, the locations and the sizing of the capacitor banks are the decision variables,
whereas the dependent variables may be bus voltages, system losses, etc. Mathematical
Algorithms.
The latter methods require the evaluations of the first and possibly, the higher order derivatives
of the objective function. As a result, these methods are generally more efficient than the direct
methods. All the unconstrained optimization methods are iterative in nature and start from an
initial trial solution; moving stepwise in a sequential manner towards the optimum solution. The
gradient methods have received more attention in power system literature. For instance, in the so
called steepest descent method; widely used in power system literature, the gradient vector is
used to calculate the optimum step length along the search direction so that the algorithm
efficiency is maximized.
Let us come back to the constrained case. Two types of methods, namely, direct and indirect
methods apply. In the former methods, the constraints are handled in an explicit manner, while in
most of the latter methods; the constrained problem is converted into a sequence of
unconstrained problems and solved through available algorithms. As an example of the direct
methods, in the so called constraint approximation method, the objective function and the
constraints are linearized about some point. The resulting approximated LP problem is solved
using LP techniques. The resulting solution is then used to construct a new LP problem. The
process is continued until a convergence criterion is satisfied. As an example of the indirect
methods, the so called penalty function method, works on the principle of converting the
problem into an unconstrained type. It is, in turn, classified as interior and exterior penalty
function methods. In the former, the sequence of unconstrained minima lie in the feasible region
while in the latter, they lie in the infeasible region. In both, they move towards the desired.
A failure does not need to be fault, but a fault usually leads to a failure.
Outages occur when permanent faults take place in the direct path
feeding the customer.
Dips and swells occur during faults on the system that are not in the
direct path supplying the load.
Faults are of a stochastic nature and so are the dips caused by these
faults.
Several random factors are involved in the analysis of voltage dips.
An extensive list is
• Fault type. Three phase faults are more severe than single-phase
faults, but the later are much more frequent.
The list of random factors is not complete but is enough to illustrate the
stochastic nature of voltage dips, Frequency and Duration of Long &
Short Interruption.
INTER-CONNECTED SYSTEM
Power system is an interconnected system in which various electrical components such as
generators, transformers, transmission lines, distributors, loads etc are connected in the form of a
network.
*Increased effective capacity of power system: The load curves of different interconnected
stations are likely to differ the result is that the maximum demand on the system is much reduced
as compared to the sum of individual maximum demands on various power stations. In other
words, the diversity factor of the whole system is improved, thereby increasing the effective
capacity of the whole system.
*Economical operation: Interconnection between hydroelectric power station and thermal power
station makes their operation economical.
*Use of older plants: The interconnected system makes it possible to employ the older and less
efficient plants to carry peak loads of short durations.
*Exchange of peak loads: The main advantage of this system is that the peak load of the power
stations can be exchanged.
*The major disadvantages of interconnected power system is that fault level of the system
increases as more and more power sources are connected . In case of any fault at any point ,
heavy fault current will flow which are fed from the sources , causing heavy voltage dip in the
system . Thus the ratings of the electrical equipment, cables etc have to be upgraded as per the
increased fault level, which is huge cost. Long length transmission lines and tie lines are required
which results increased cost of transmission. Since it is a large system , the analysis of the system
will be very complicated.
*Stability problem
*Cascaded failures
• Adequacy:
A measure of the ability of the power system to supply the aggregate electric
power and energy requirements of the customers within components ratings and
voltage limits, taking into account planned and unplanned outages of system
components. Adequacy measures the capability of the power system to supply the
load in all the steady states in which the power system may exist considering
standards conditions.
Analysis involving level 3 are not generally done due to enormity of the problem.
Most of the probabilistic techniques for reliability assessment are with respect to
adequacy assessment.
Reliability of a system
• A system composed of large number of components connected in series and
parallel.
• AENS = Average Energy Not Supplied = (kwh/y. Cust.) = Total energy not
supplied / Total number of customers served
• LOLP = Loss of Load Probability =The probability that the total production in
system cannot meet the load demand
• Security:
• A measure of power system ability to withstand sudden disturbances
such as electric short circuits or unanticipated losses of system components
or load conditions together with operating constraints. Another aspect of
security is system integrity, which is the ability to maintain interconnected
operation. Integrity relates to the preservation of interconnected system
operation, or avoidance of uncontrolled separation, in the presence of
specified severe disturbances.
Power system reliability refer to the ability of a power system to provide adequate stable, reliable
power to a given distribution as the name clearly suggests 'Reliability' means the quality of being
'trust worthy'.
Electrical systems are not exception to their destination lesser of number of system outages of
the Power supply, more reliable the system ideally.
Electricity should be available to every customer all the time, no exception. But the scenario is
different in the real world.
So we tend to measure number of times the outage occurs which is inversely proportional to
reliability.
The basic function of an electric power system is to satisfy the system load requirements as
economically as possible and with a reasonable assurance of continuity and quantity.
In order to achieve the required degree of reliability, planners and operators have utilised a wide
range of criteria in their respective areas of activity.
RELIABLITY PLANNING:
Proper planning prevents the poor performance cutting out the roof to extract a critical motor with
the helicopter is not the definition of proper planning.
Significant through into maintenance considerations and the failure made and effects analysis
should be a part of new project planning and facility with proper maintenance and reliability
planning etc.
A better chance of maximising the throughout and availability, making them more competitive in
market place.
EVALUATION OF TECHNIQUES
1. MARKOV MODEL
2. RECURESIVE TECHNIQUE
MARKOV’S MODEL:
There are four common markov’s models used in different situations depending on whether
every sequential state is observable or not and whether the system is to be adjusted on the basis of
observations made:
Markov analysis is a method used to forecast the value of a variable whose future value is
influenced only by its current position or state, not by any prior activity that led the variable to its
current position or state.
RECURSIVE MODEL:
An electric utility much concerns you to plan, design, operate and maintain its power supply to
provide an acceptable level of reliability to its user. Reliability index, loss of load probability
(LOLP) of any power system is evaluated using recursive algorithm and considering no derated
state of generators.
Our important objective is generate and transmit power to meet the load demand at
minimum cost by optimal mix of different types of plants.
Therefore the study of the optimal scheduling for power generation at different plants in a
power system is of high importance.
SCHEDULING:
The operating cost of thermal plant is very high , though their initial cost is low.
On the other hand the operating cost is low in case of hydroelectric generation
Due the low operating cost in case of hydel plants so we can operate it in conjuction with
thermal plants which will lead to save fuel
So Hydrothermal scheduling is a power system optimization problem which gives us idea
how to manage the hydel and thermal plant combinely.
a)Long range Problem : This type of scheduling having the scheduling interval of a month
or a year.
b)Short range Problem : This type of scheduling having the scheduling interval of a day or
a week.
In load flow analysis we know that every bus associated with four operational variables
like P,Q,|V| and δ.Out of these four,two are specified variable and other two are not given.
According to these two specified variables we have three types bus that are PQ bus(Load
bus),PV bus(Generator Bus),Slack bus.
If the specified variables are varied within their constraints that cause an infinite number of
load flow solution.
Each value of load flow solution related to one set of specified variables.
The optimal choice is that values of specified variable for which gives best load flow
solution.