You are on page 1of 3

# Description Scale Manhours

Sheet: A00 Cover Page Rate Hours Amount


Drawing # 1 Perspective NTS PHP 400.00 10 PHP 4,000.00
2 Location Map NTS PHP 100.00 1 PHP 100.00
3 Vicinity Map NTS PHP 100.00 1 PHP 100.00
4 General Notes n/a PHP 100.00 0.5 PHP 50.00
5 Table of Contents n/a PHP 100.00 0.25 PHP 25.00
Total 12.75 PHP 4,275.00

# Description Scale Manhours


Sheet: A01 Architectural Plans Rate Hours Amount
Drawing # 1 Site Development Plan 1:100 PHP 120.00 2 PHP 240.00
2 Ground Floor Plan 1:101 PHP 120.00 3 PHP 360.00
2 Second Floor Plan 1: 100 PHP 120.00 3 PHP 360.00
3 Roof Deck 1: 100 PHP 120.00 1 PHP 120.00
4 Ground Floor Reflected Ceiling Plan 1:100 PHP 120.00 2 PHP 240.00
5 2nd Floor Reflected Ceiling Plan 1:100 PHP 120.00 2 PHP 240.00
6 Ground Floor Pattern 1:100 PHP 120.00 1 PHP 120.00
5 2nd Floor Pattern 1:100 PHP 120.00 1 PHP 120.00
Total 15 PHP 1,800.00

# Description Scale Manhours


Sheet: A02 Section & Elevation Rate Hours Amount
Drawing # 1 Cross Section 1:100 PHP 120.00 3 PHP 360.00
2 Longitudinal Section 1: 100 PHP 120.00 3 PHP 360.00
3 Front Elevation 1: 100 PHP 120.00 2 PHP 240.00
4 Left Side Elevation 1:100 PHP 120.00 2 PHP 240.00
5 Right Side Elevation 1:100 PHP 120.00 2 PHP 240.00
6 Rear Elevation 1:100 PHP 120.00 2 PHP 240.00
Total 14 PHP 1,680.00

# Description Scale Manhours


Sheet: A03 Room Detail - 01 Rate Hours Amount
Drawing # 1 Living Area - Wall Section - A 1:50 PHP 120.00 1.25 PHP 150.00
2 Living Area - Wall Section - B 1:50 PHP 120.00 1.25 PHP 150.00
3 Living Area - Wall Section - C 1:50 PHP 120.00 1.25 PHP 150.00
4 Living Area - Wall Section - D 1:50 PHP 120.00 1.25 PHP 150.00
5 Dinning Room - Wall Section - A 1:50 PHP 120.00 1.25 PHP 150.00
6 Dinning Room - Wall Section - B 1:50 PHP 120.00 1.25 PHP 150.00
7 Dinning Room - Wall Section - C 1:50 PHP 120.00 1.25 PHP 150.00
8 Dinning Room - Wall Section - D 1:50 PHP 120.00 1.25 PHP 150.00
5 Kitchen Area - Wall Section - A 1:50 PHP 120.00 1.25 PHP 150.00
6 Kitchen Area - Wall Section - B 1:50 PHP 120.00 1.25 PHP 150.00
7 Kitchen Area - Wall Section - C 1:50 PHP 120.00 1.25 PHP 150.00
8 Kitchen Area - Wall Section - D 1:50 PHP 120.00 1.25 PHP 150.00
Total 15 PHP 1,800.00
# Description Scale Manhours
Sheet: A04 Room Detail - 02 Rate Hours Amount
Drawing # 1 Master BR - Wall Section - A 1:50 PHP 120.00 1.25 PHP 150.00
2 Master BR - Wall Section - B 1:50 PHP 120.00 1.25 PHP 150.00
3 Master BR - Wall Section - C 1:50 PHP 120.00 1.25 PHP 150.00
4 Master BR - Wall Section - D 1:50 PHP 120.00 1.25 PHP 150.00
5 BEDROOM 01 - Wall Section - A 1:50 PHP 120.00 1.25 PHP 150.00
6 BEDROOM 01 - Wall Section - B 1:50 PHP 120.00 1.25 PHP 150.00
7 BEDROOM 01 - Wall Section - C 1:50 PHP 120.00 1.25 PHP 150.00
8 BEDROOM 01 - Wall Section - D 1:50 PHP 120.00 1.25 PHP 150.00
5 BEDROOM 02 - Wall Section - A 1:50 PHP 120.00 1.25 PHP 150.00
6 BEDROOM 02 - Wall Section - B 1:50 PHP 120.00 1.25 PHP 150.00
7 BEDROOM 02 - Wall Section - C 1:50 PHP 120.00 1.25 PHP 150.00
8 BEDROOM 02 - Wall Section - D 1:50 PHP 120.00 1.25 PHP 150.00
Total 15 PHP 1,800.00

# Description Scale Manhours


Sheet: A05 T & B Detail Rate Hours Amount
Drawing # 1 T & B 01 - Wall Section - A 1:50 PHP 120.00 1.25 PHP 150.00
2 T & B 01 - Wall Section - B 1:50 PHP 120.00 1.25 PHP 150.00
3 T & B 01 - Wall Section - C 1:50 PHP 120.00 1.25 PHP 150.00
4 T & B 01 - Wall Section - D 1:50 PHP 120.00 1.25 PHP 150.00
5 T & B 02 - Wall Section - A 1:50 PHP 120.00 1.25 PHP 150.00
6 T & B 02 - Wall Section - B 1:50 PHP 120.00 1.25 PHP 150.00
7 T & B 02 - Wall Section - C 1:50 PHP 120.00 1.25 PHP 150.00
8 T & B 02 - Wall Section - D 1:50 PHP 120.00 1.25 PHP 150.00
5 Laundry - Wall Section - A 1:50 PHP 120.00 1.25 PHP 150.00
6 Laundry - Wall Section - B 1:50 PHP 120.00 1.25 PHP 150.00
7 Laundry - Wall Section - C 1:50 PHP 120.00 1.25 PHP 150.00
8 Laundry - Wall Section - D 1:50 PHP 120.00 1.25 PHP 150.00
Total 15 PHP 1,800.00

# Description Scale Manhours


Sheet: A06 Windows & Door Schedule Rate Hours Amount
Drawing # 1 Door 1 (Elevation / Plan / Detail) 1:20 PHP 120.00 0.75 PHP 90.00
2 Door 2(Elevation / Plan / Detail) 1:20 PHP 120.00 0.75 PHP 90.00
3 Door 3 (Elevation / Plan / Detail) 1:20 PHP 120.00 0.75 PHP 90.00
4 Door 4 (Elevation / Plan / Detail) 1:20 PHP 120.00 0.75 PHP 90.00
5 Door 5 (Elevation / Plan / Detail) 1:20 PHP 120.00 0.75 PHP 90.00
6 Door 6 (Elevation / Plan / Detail) 1:20 PHP 120.00 0.75 PHP 90.00
7 Door 7 (Elevation / Plan / Detail) 1:20 PHP 120.00 0.75 PHP 90.00
8 Window 1 (Elevation / Plan / Detail) 1:20 PHP 120.00 0.75 PHP 90.00
5 Window 2 (Elevation / Plan / Detail) 1:20 PHP 120.00 0.75 PHP 90.00
6 Window 3 (Elevation / Plan / Detail) 1:20 PHP 120.00 0.75 PHP 90.00
7 Window 4 (Elevation / Plan / Detail) 1:20 PHP 120.00 0.75 PHP 90.00
8 Window 5 (Elevation / Plan / Detail) 1:20 PHP 120.00 0.75 PHP 90.00
9 Window 6 (Elevation / Plan / Detail) 1:20 PHP 120.00 0.75 PHP 90.00
10 Window 7 (Elevation / Plan / Detail) 1:20 PHP 120.00 0.75 PHP 90.00
11 Window 8 (Elevation / Plan / Detail) 1:20 PHP 120.00 0.75 PHP 90.00
12 Window 9 (Elevation / Plan / Detail) 1:20 PHP 120.00 0.75 PHP 90.00
13 Window 10 (Elevation / Plan / Detail) 1:20 PHP 120.00 0.75 PHP 90.00
14 Window 11 (Elevation / Plan / Detail) 1:20 PHP 120.00 0.75 PHP 90.00
15 Window 12 (Elevation / Plan / Detail) 1:20 PHP 120.00 0.75 PHP 90.00
16 Window 13 (Elevation / Plan / Detail) 1:20 PHP 120.00 0.75 PHP 90.00
17 Window 14 (Elevation / Plan / Detail) 1:20 PHP 120.00 0.75 PHP 90.00
14 Window 15 (Elevation / Plan / Detail) 1:20 PHP 120.00 0.75 PHP 90.00
Total 16.5 PHP 1,980.00

# Description Scale Manhours


Sheet: A07 Stair Detail & Water Tank Detail Rate Hours Amount
Drawing # 1 Stair Plan 1: 20 PHP 120.00 1 PHP 120.00
2 Stair Section 1:20 PHP 120.00 2 PHP 240.00
3 Stail Blow-up Detail (1-2-3-4) 1:10 PHP 120.00 2 PHP 240.00
4 Water Tank Plan 1:20 PHP 120.00 1 PHP 120.00
Water Tank Section 1:20 PHP 120.00 2 PHP 240.00
5 Stail Blow-up Detail (1-2-3-4) 1:10 PHP 120.00 2 PHP 240.00
Total 10 PHP 1,200.00

Grand Total 113.25 PHP 16,335.00


--------------
8 hours / day 14.15625
or
Note: Tracing Printing / Blueprint is not included… Turnover: 14Days
Additional - Php 150 per sheet Tracing Printing Early Turover: 10 Days
Additonal - Php 12 per Blueprint Copy Discount: PHP 16,000.00