Date:19/05/2015
Name: Nutek
1 SITE IDENTIFICATION:
Site no. Site name: Area name and phas
Mikundi Mchinji
1 SITE TYPE
X Coverage Improvement TERMINAL
Tri-Sectored [3] Bi - Sectored [2] Omni [1]
Celtel Site Sharing MW repeater
1 SITE LOCATION
Reference map:
X Y
WGS - 84 Co-ord :
-13.70634 33.13631
Site objective: To Improve Coverage
Search Area.
1 RADIO REQUIREMENTS
Theoretical Engineering Sector 1 Sector 2
Tower Height 40m
GSM ABH (Radio Proposal): 36m 36m
WCDMA ABH (Radio Proposal): 36m 36m
GSM Azimuths: 50 120
WCDMA Azimuths: 50 120
GSM Mechanical Tilt: 0 0
GSM Electrical Tilt 2 2
GSM Antennae Type: DBXLH-6565B-VTM DBXLH-6565B-
WCDMA Mechanical Tilt: 0 VTM
0
WCDMA Electrical Tilt 2 2
WCDMA Antennae Type: AGISSON-A19451801 AGISSON-
TMA (DUAL) No A19451801
No
Feeder System: Feederless Feederless
Number of TWIN TRX: 2 2
Space Diversity: No No
, TECHNICAL VISIT REQUIREMENT (RADIO) YES
, TRANSMISSION REQUIREMENTS Diani_Center
Trans system: FE Lat
FE Long
Leased line
LMDS
Microwave
Theoretical Engineering VSAT
Vendor
l No. of antennae:
l Diameters:
l Azimuths NE:
l Azimuths FE:
Link parameters : l Minimum height NE :
l Minimum height FE:
l Link config :
l LOS Status:
l MW Frequncy Band
, TECHNICAL VISIT REQUIREMENT (TRANSMISSION) YES
, SITE DOCUMENTS
Location Map Radio Simulation Map Terrain profile
NODAL
MSC
BSC
Elevation
1109m
Sector 3
36m
36m
300
300
0
2
DBXLH-6565B-
VTM
0
2
AGISSON-
A19451801
No
Feederless
2
No
NO
Kwale_Ukunda
NO
Link budget
NOT Validated
2G & 3G Technical Site Survey Report
A. General information
Tower Owner (if applicable) Airtel Malawi Height info sea level: 3459ft
B. Travelling information
C. Access
Page 5 of 66
2G & 3G Technical Site Survey Report
D. Site Environment
Width Length
Page 6 of 66
2G & 3G Technical Site Survey Report
Additional Remarks
iii. Safety
Additional Remarks
i. General info
Page 7 of 66
2G & 3G Technical Site Survey Report
ii. Safety
Additional Remarks
Additional Remarks
Page 8 of 66
2G & 3G Technical Site Survey Report
H. BTS Information
Space outdoor to do (1m*1m) Slab for System Module Pole Mount ✘ Yes ✘ No
Space outdoor to do (1m*1m) Slab for System Module Pole Mount Yes No
Type of BTS Swap proposed
Hot Swap Cold Swap
Comments:
Wall mounted
Floor stacked
✘ Pole Mounted
Yes ✘ No
Yes ✘ No
I. Transmission Information
J. AC Power
Page 10 of 66
2G & 3G Technical Site Survey Report
Comments:
K. DC Power
Free breakers available in rectifier ✘ Yes No Number of free breakers available 2*63A + 2*32A
Page 11 of 66
2G & 3G Technical Site Survey Report
Comments:
Feeder details
Type (Fibre/Coax) Coax Size Length
Page 12 of 66
2G & 3G Technical Site Survey Report
Jumper detail
Top Bottom
Cell 1
Cell 2
Cell 3
Cell 4
Cell 5
Cell 6
Existing cable tray re-routing required? Yes ✘ No If yes, give description and attach sketch
Cable tray cover required Yes ✘ No Width mm Length
If no then propose length of Extension CAT 5/6 upto the new MR position Length m
Page 13 of 66
MW0398
Bwaila Hosptal
Time
15mins
Page 14 of 66
MW0398
Bwaila Hosptal
Page 15 of 66
MW0398
Bwaila Hosptal
Page 16 of 66
MW0398
Bwaila Hosptal
Page 17 of 66
MW0398
Bwaila Hosptal
3 x 400 V + N
N/A
Page 18 of 66
MW0398
Bwaila Hosptal
Page 19 of 66
Sector-1 Leg
2G and 3G antenna
proposed position at
36m
Sector-3 Leg
2G and 3G antenna
proposed position at
36m
Sector-2 Leg
2G and 3G antenna
proposed position at
36m
Sector-1
Sector-3
Sector-2
Coverage Overview Plot
DETAILED SKETCH OF SHELTER FLOOR PLAN SHOWING THE FOLLOWING DETAILS:
1. Existing position and dimensions of BTS , Microwave rack , Rectifier and Batteries , Aircons etc.
DETAILED SKETCH OF SHELTER FLOOR PLAN SHOWING THE FOLLOWING DETAILS:
1. Existing position and dimensions of BTS , Microwave rack , Rectifier and Batteries , Aircons etc.
2. Proposed position and dimensions of both 2G & 3G BTS . Minimun footprint of Flexi BTS required is 600 x 600
Note : The proposed flexi position should be preferably as close as possible to the feeder termination point ( position of surge arrestors)
SHOWING THE PROPOSED POSITION FOR SYSTEM MODULE AND RF MODULE ON TOWER
1. Space for Slab for Ssyetme Module pole Mount photo (both 2G and 3G)
2. Space on tower for RF position photo (both 2G and 3G)
Inside IP55 rack for rectifier
and Battery bank
DETAILED NEW CABLE MANAGEMENT SYSTEM LAYOUT
LAYOUT
PHOTO OF EXISTING 2G EQUIPMENT
PHOTO OF EXISTING MICROWAVE / TRANSMISSION EQUIPMENT
PHOTOS OF EXISTING CABLE MANAGEMENT SYSTEM
Note : Photos of the cable management system showing the following details :
1. The feeder cable tray / cable ladder installed in shelter
2. The feeder cable tray / cable ladder installed outdoor
3. The feeder cable management system on the tower
PHOTO OF EXISITING ROXTEC AND PROPOSED NEW ROXTEC
PHOTO OF EXISTING PDB AND POWER SUPPLY
PHOTO OF EXISTING RECTIFIER EQUIPMENT
0 Deg 30 Deg
150 Deg
240 Deg
330 Deg
PHOTO OF EXISTING COMMERCIAL POWER SOURCE
GENERAL SITE PHOTOS SHOWING THE FOLLOWING DETAILS:
1. Shelter
2.Tower
3. Panoramic view of existing antenna system for each sectors
4. Genset room
5. Site compound
Materialisation
Project
Name:
#REF!
Site
Number #REF! Site Name: #REF! Report Version : #REF!
:
BACK TO STARTPAGE
Coaxial works
FEEDERS
S1 S2 S3 S4 S5 S6
Feeder type #REF! #REF! #REF! #REF! #REF! #REF!
Feeder length #REF! #REF! #REF! #REF! #REF! #REF!
Feeder amount #REF! #REF! #REF! #REF! #REF! #REF!
Total length per sector #REF! #REF! #REF! #REF! #REF! #REF!
Length
TOTAL PER FEEDER TYPE 1/2" 0m
5/8" 0m
7/8" 0m
1 1/4" 0m
1 5/8" 0m
2 1/4" 0m
2 1/2" 0m
Amount
TOTAL BOTTOM JUMPER HF Fem-Male Right angle 1 meter 0
HF Fem-Male Right angle 2 meter 0
HF Fem-Male Right angle 3 meter 0
Amount
TOTAL TOP JUMPER HF Female-Male 1 meter 0
HF Female-Male 2 meter 0
HF Female-Male 3 meter 0
CABLE MANAGEMENT
2. Site Environment
3. Exiting BTS
4. Rectifier System
7. GSM Photo
9. Proposed Location
10. Battery Bank