NOMINAL CANDIDATE FORM

Date:19/05/2015

Name: Nutek

1 SITE IDENTIFICATION:
Site no. Site name: Area name and phas
Mikundi Mchinji
1 SITE TYPE
X Coverage Improvement TERMINAL
Tri-Sectored [3] Bi - Sectored [2] Omni [1]
Celtel Site Sharing MW repeater

1 SITE LOCATION
Reference map:
X Y
WGS - 84 Co-ord :
-13.70634 33.13631
Site objective: To Improve Coverage

Search Area.
1 RADIO REQUIREMENTS
Theoretical Engineering Sector 1 Sector 2
Tower Height 40m
GSM ABH (Radio Proposal): 36m 36m
WCDMA ABH (Radio Proposal): 36m 36m
GSM Azimuths: 50 120
WCDMA Azimuths: 50 120
GSM Mechanical Tilt: 0 0
GSM Electrical Tilt 2 2
GSM Antennae Type: DBXLH-6565B-VTM DBXLH-6565B-
WCDMA Mechanical Tilt: 0 VTM
0
WCDMA Electrical Tilt 2 2
WCDMA Antennae Type: AGISSON-A19451801 AGISSON-
TMA (DUAL) No A19451801
No
Feeder System: Feederless Feederless
Number of TWIN TRX: 2 2
Space Diversity: No No
, TECHNICAL VISIT REQUIREMENT (RADIO) YES
, TRANSMISSION REQUIREMENTS Diani_Center
Trans system: FE Lat
FE Long
Leased line
LMDS
Microwave
Theoretical Engineering VSAT
Vendor
l No. of antennae:
l Diameters:
l Azimuths NE:
l Azimuths FE:
Link parameters : l Minimum height NE :
l Minimum height FE:
l Link config :
l LOS Status:
l MW Frequncy Band
, TECHNICAL VISIT REQUIREMENT (TRANSMISSION) YES

, SITE DOCUMENTS
Location Map Radio Simulation Map Terrain profile

, SITE VALIDATION/NP&O MANAGER


Signature
Validated
Release:V1

Area name and phase:


Mchinji

NODAL
MSC
BSC

Elevation
1109m

Sector 3

36m
36m
300
300
0
2
DBXLH-6565B-
VTM
0
2
AGISSON-
A19451801
No
Feederless
2
No
NO
Kwale_Ukunda

NO

Link budget

NOT Validated
2G & 3G Technical Site Survey Report

Project Name: Airtel Site Number: MW0398

Date of Survey 25-Nov-14 Surveyed By : Andrew&Tendai Site Name: Bwaila Hosptal

Site Information = picture requested

A. General information

Address: Area_2, Lilongwe Longtitude: 33.77501°


Town: Lilongwe Lattitude: -13.99039°

Tower Owner (if applicable) Airtel Malawi Height info sea level: 3459ft

Typology: Co-location Existing Tower Rooftop

Site location: ✘ Town Suburban Rural

Tower Tower Height


Monopole Lattice Pylon Guyed Pylon

Rooftop Type Building Height 15


✘ Pitched Roof Flat Roof

B. Travelling information

Reference Distance Time

Travel from: Airtel Office, City Centre 5km 15mins

(city center, hotel, airport,…)

C. Access

Length Width Kind:


Access road: Existing 100m 8m Boulder asphalt Murram ✘ Concrete
To create

Access possible for truck/crane? ✘ Yes No

Access possible through lift/ elevator? Yes ✘ No

Key details Located in middle of densily populated nieghborhood

Page 5 of 66
2G & 3G Technical Site Survey Report

Project Name: Airtel Site Number: MW0398

Date of Survey 25-Nov-14 Surveyed By : Andrew&Tendai Site Name: Bwaila Hosptal

D. Site Environment

Site location free of trees, debris,...? Yes ✘ No

Strong wind area?


Yes ✘ No
Danger of flooding? Yes ✘ No

Presence of airport, air traffic? Yes ✘ No Distance

E. New Tower Yes No

Expected tower height at this location: m

Width Length

Available space for foundation:

Kind of underground: Hard rock Normal Sandy Other, describe

Site location free of trees, debris,… Yes No


If no, description of works:

F. Existing Greenfield Tower ✘ Yes No

i. General info Height

Nature of support: Lattice Pylon Guyed Pylon Monopole m

Owner of support: Constructor of support:

Page 6 of 66
2G & 3G Technical Site Survey Report

Project Name: Airtel Site Number: MW0398

Date of Survey 25-Nov-14 Surveyed By : Andrew&Tendai Site Name: Bwaila Hosptal

ii. Tower Condition

Visible corrosion Yes No

Tower painted Yes No

Missing tower members/bolts Yes No

General condition of tower Good Fair Bad

Additional Remarks

iii. Safety

Existing anti-fall protection? Yes No

Existing Beaconing? Yes No

Existing Lightning protection Yes No

Additional Remarks

G. Existing Rooftop ✘ Yes No Height

Number of floors: 3 15m

i. General info

Type of building: Commercial

Nature of roof: Flat roof ✘ Pitched

Nature of wall structure: ✘ Concrete wall Brick wall Metal structure

Nature of support: Stub Tower ✘ Wall mount Ballast Mount Height 2 m

Page 7 of 66
2G & 3G Technical Site Survey Report

Project Name: Airtel Site Number: MW0398

Date of Survey 25-Nov-14 Surveyed By : Andrew&Tendai Site Name: Bwaila Hosptal

ii. Safety

Existing anti-fall protection (cage, anchor points)? Yes ✘ No

Existing Beaconing? Yes ✘ No

Existing Lightning protection ✘ Yes No

Existing installation on roof


✘ Yes No

Additional Remarks

iii. Building Condition

Cracks corrosion Yes ✘ No

Signs of recent repairs ✘ Yes No

General condition of building ✘ Good Fair Bad

Additional Remarks

Page 8 of 66
2G & 3G Technical Site Survey Report

Project Name: Airtel Site Number: MW0398

Date of Survey 25-Nov-14 Surveyed By : Andrew&Tendai Site Name: Bwaila Hosptal

H. BTS Information

Current BTS is Indoor(NOTE: BTS will be installed on pole outdoor) ✘ Yes No

Space outdoor to do (1m*1m) Slab for System Module Pole Mount ✘ Yes ✘ No

Air con sufficient after new installation? Yes ✘ No


Comments:

Current BTS is Outdoor(NOTE: BTS will be installed on pole outdoor) Yes No

Space outdoor to do (1m*1m) Slab for System Module Pole Mount Yes No
Type of BTS Swap proposed
Hot Swap Cold Swap
Comments:

Equipment Mounting for System Module )


RF Module will be planned on the top of tower ( Wherever
possible )

Wall mounted

Floor stacked

✘ Pole Mounted

Equipment Mounting (RF Module)

Pole for Mounting the RF Module


present ✘ Yes ✘
No

Space present for the new Pole


required for RF module on the ✘ Yes No
tower
Page 9 of 66
2G & 3G Technical Site Survey Report

Project Name: Airtel Site Number: MW0398

Date of Survey 25-Nov-14 Surveyed By : Andrew&Tendai Site Name: Bwaila Hosptal

Dual Mount Required?

Yes ✘ No

Additional Pole required? (Incase no Dual Mount)

Yes ✘ No

I. Transmission Information

New DDF required Transmission capacity on site


✘ Yes No
Number of free E1 4 Transmission protection type 1+0
Number of free LAN/Ethernet Port 1
Length of E1 cable required to outdoor location of MR 5m m PCM Ohm 120
Length of LAN cable required to oudooor location of MR 5m m

Does serving IDU have IP Capability? ✘ Yes No


Serving MW IDU Location In indoor TRS Rack In Indoor BTS In Outdoor BTS

Mounted on Wall ✘ In Outdoor TRS Rack


If Serving IDU Rack is Indoor is it possible to shift Outdoor? Yes ✘ No
If Serving IDU Rack is in Ericsson BTS Rack is there Space on MW Rack to move it? Yes No

J. AC Power

Mains power available Available voltage on site


✘ Yes No ✘ 1 x 230 V 3 x 230 V

Page 10 of 66
2G & 3G Technical Site Survey Report

Project Name: Airtel Site Number: MW0398

Date of Survey 25-Nov-14 Surveyed By : Andrew&Tendai Site Name: Bwaila Hosptal

✘ Yes No ✘ 1 x 230 V 3 x 230 V


Existing Generator Generator Rating 10KVA
✘ Yes N/A
Free breakers available in PDB Space for new breakers available No
Yes ✘ No Yes ✘

Number of new breakers to install Rating of of new breakers to install

Comments:

K. DC Power

Rectifier type Battery Technology Number of installed modules 4

Total Output 4.8 KW Number of new rectifier moduels to install

Number of batteries in rectifier 24 Rating of batteries in the recifier 600Ah

Free breakers available in rectifier ✘ Yes No Number of free breakers available 2*63A + 2*32A

Space for new breakers available Yes


✘ No N/A
Number of new breakers to install Rating of of new breakers to install

Free breakers available in rack PDU Number of free breakers available


Yes No
Space for new breakers available
Yes No N/A
Number of new breakers to install Rating of of new breakers to install
Power cable to install from rectifier to proposed flexi position Length (m) 8
Section (mm2) 16
Existing equipment busbar ? Yes No
Required Cable length
25 sq mm MCMK RF module 40 m
16 sq mm Blue/Black System module 8m m

16 sq mm Grounding cable to System Module Length 4 m

16 sq mm Grounding cable to RF module Length 4 m

L. Detailed Antenna System Information

Equipment Location on Rooftop Facade ✘ Wall Mount


Ballast Mount Sub Tower

Page 11 of 66
2G & 3G Technical Site Survey Report

Project Name: Airtel Site Number: MW0398

Date of Survey 25-Nov-14 Surveyed By : Andrew&Tendai Site Name: Bwaila Hosptal

Existing Radio equipment on tower


Centre Height of antenna (m) Azimuth MHA/TMA Mechanical tilt RET UMTS/GSM
900 cell 1 17 90° N/A 0° N/A Dual GSM
900 cell 2 17 220° N/A 0° N/A Dual GSM
900 cell 3 17 290° N/A 2° N/A Dual GSM
1800 cell 1
1800 cell 2
1800 cell 3
Dual cell 1
Dual cell 2
Dual cell 3
2100 cell 1 17 90° N/A 0° N/A UMTS
2100 cell 2 17 240° N/A 0° N/A UMTS
2100 cell 3 17 340° N/A 0° N/A UMTS

Comments:

New feeder and jumper installation required? If yes, attach sketch


Hatch frame Required for 900/1800/3G Yes ✘ No If yes Height & number
Existing feeder and jumper installation re-routing required? If yes, attach sketch
Yes ✘ No
THE NEW
CABLE
Feeder installation modification required? If yes, give description and attach sketch
TRAY TO BE Yes ✘ No
INSTALLED
WILL
REROUTE
THE
EXISTING
CABLE
TRAY

Extra grounding of feeder installation required? If yes, give description


Yes ✘ No

Feeder details
Type (Fibre/Coax) Coax Size Length

Sector 1 FIBRE FIBRE 100M


Sector 2
Sector 3

Page 12 of 66
2G & 3G Technical Site Survey Report

Project Name: Airtel Site Number: MW0398

Date of Survey 25-Nov-14 Surveyed By : Andrew&Tendai Site Name: Bwaila Hosptal

Jumper detail

Top Bottom

Cell 1
Cell 2
Cell 3
Cell 4
Cell 5
Cell 6

M. Cable Management System Type of Roxtec module required

New ROXTEC required? Yes Number of new modules required N/A


✘ No
Adequate space on existing cable management system
Yes ✘ No

Length & size of New Cable tray Width mm Depth mm Length

Existing cable tray re-routing required? Yes ✘ No If yes, give description and attach sketch
Cable tray cover required Yes ✘ No Width mm Length

N. External Alarm Cable


From the current termination point is the length enough to reach proposed MR position
outdoor?
✘ Yes No

If no then propose length of Extension CAT 5/6 upto the new MR position Length m

Page 13 of 66
MW0398

Bwaila Hosptal

Time

15mins

Page 14 of 66
MW0398

Bwaila Hosptal

Page 15 of 66
MW0398

Bwaila Hosptal

Page 16 of 66
MW0398

Bwaila Hosptal

Page 17 of 66
MW0398

Bwaila Hosptal

3 x 400 V + N

N/A

Page 18 of 66
MW0398

Bwaila Hosptal

Page 19 of 66
Sector-1 Leg

2G and 3G antenna
proposed position at
36m

Sector-3 Leg

2G and 3G antenna
proposed position at
36m
Sector-2 Leg

2G and 3G antenna
proposed position at
36m
Sector-1

Sector-3
Sector-2
Coverage Overview Plot
DETAILED SKETCH OF SHELTER FLOOR PLAN SHOWING THE FOLLOWING DETAILS:
1. Existing position and dimensions of BTS , Microwave rack , Rectifier and Batteries , Aircons etc.
DETAILED SKETCH OF SHELTER FLOOR PLAN SHOWING THE FOLLOWING DETAILS:
1. Existing position and dimensions of BTS , Microwave rack , Rectifier and Batteries , Aircons etc.
2. Proposed position and dimensions of both 2G & 3G BTS . Minimun footprint of Flexi BTS required is 600 x 600
Note : The proposed flexi position should be preferably as close as possible to the feeder termination point ( position of surge arrestors)

SHOWING THE PROPOSED POSITION FOR SYSTEM MODULE AND RF MODULE ON TOWER
1. Space for Slab for Ssyetme Module pole Mount photo (both 2G and 3G)
2. Space on tower for RF position photo (both 2G and 3G)
Inside IP55 rack for rectifier
and Battery bank
DETAILED NEW CABLE MANAGEMENT SYSTEM LAYOUT
LAYOUT
PHOTO OF EXISTING 2G EQUIPMENT
PHOTO OF EXISTING MICROWAVE / TRANSMISSION EQUIPMENT
PHOTOS OF EXISTING CABLE MANAGEMENT SYSTEM
Note : Photos of the cable management system showing the following details :
1. The feeder cable tray / cable ladder installed in shelter
2. The feeder cable tray / cable ladder installed outdoor
3. The feeder cable management system on the tower
PHOTO OF EXISITING ROXTEC AND PROPOSED NEW ROXTEC
PHOTO OF EXISTING PDB AND POWER SUPPLY
PHOTO OF EXISTING RECTIFIER EQUIPMENT
0 Deg 30 Deg

90 Deg 120 Deg

180 Deg 210 Deg


270 Deg 300 Deg
60 Deg

150 Deg

240 Deg
330 Deg
PHOTO OF EXISTING COMMERCIAL POWER SOURCE
GENERAL SITE PHOTOS SHOWING THE FOLLOWING DETAILS:
1. Shelter
2.Tower
3. Panoramic view of existing antenna system for each sectors
4. Genset room
5. Site compound
Materialisation

Project
Name:
#REF!
Site
Number #REF! Site Name: #REF! Report Version : #REF!
:

BACK TO STARTPAGE

Coaxial works
FEEDERS

S1 S2 S3 S4 S5 S6
Feeder type #REF! #REF! #REF! #REF! #REF! #REF!
Feeder length #REF! #REF! #REF! #REF! #REF! #REF!
Feeder amount #REF! #REF! #REF! #REF! #REF! #REF!
Total length per sector #REF! #REF! #REF! #REF! #REF! #REF!

Length
TOTAL PER FEEDER TYPE 1/2" 0m
5/8" 0m
7/8" 0m
1 1/4" 0m
1 5/8" 0m
2 1/4" 0m
2 1/2" 0m
Amount
TOTAL BOTTOM JUMPER HF Fem-Male Right angle 1 meter 0
HF Fem-Male Right angle 2 meter 0
HF Fem-Male Right angle 3 meter 0

Amount
TOTAL TOP JUMPER HF Female-Male 1 meter 0
HF Female-Male 2 meter 0
HF Female-Male 3 meter 0

TOTAL CABLE CLAMPS S1 S2 S3 S4 S5 S6


#REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF!

TOTAL GROUNDING KITS S1 S2 S3 S4 S5 S6


#REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF!

CABLE MANAGEMENT

CABLE TRAYS Type Material Cover Width Height Length


#REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF!
#REF! #REF! #REF! #REF! #REF! #REF!
Pole required for RF

Cable tray required


from IP55 Rack to th
tower
MCBs Available
Pole required for RF module

Cable tray required


from IP55 Rack to the
tower
MCBs Available

Existing Single Band


Antenna
Used Bands= 900
1.Site Ambohiby

2. Site Environment
3. Exiting BTS

4. Rectifier System

5. Transmission IDU & E1 DDF


6. Antifall protection

7. GSM Photo
9. Proposed Location
10. Battery Bank