Professional Documents
Culture Documents
1. Work required to be done: Modify existing WRQA feeder to establish WRSN-CHNA Circuit.
Briefly write the SCOPE of work against the respective system which ever is applicable in the following table.
Page 2
of 18
Template for Method Statement for Protection Modification Work
Contract No: CE/448D/07 Substation Name: WRSN
Contractor: DANWAY Bay Reference: C1160
Bay Name: WRQA Feeder
1.1 Prerequisites
Reference Documents (Copy shall be attached)
1.1.1. Reference details of Drawings
CE/448D/CHINA/E/12/228
1.1.2. Reference details of relay setting approvals
TPD/PCS/PSA/0320/2010 (M1 relay approval)
TPD/PCS/PSA/0233/2011 (M2 relay approval)
FR Signal List
SCMS Signal list
Page 3
of 18
Template for Method Statement for Protection Modification Work
Contract No: CE/448D/07 Substation Name: WRSN
Contractor: DANWAY Bay Reference: C1160
Bay Name: WRQA Feeder
22
Page 4
of 18
Template for Method Statement for Protection Modification Work
Contract No: CE/448D/07 Substation Name: WRSN
Contractor: DANWAY Bay Reference: C1160
Bay Name: WRQA Feeder
After completing necessary barricading of panels, identify and isolate the Trip links as per the below table.
Provide masking tape on the removed link base to avoid false insertion. Back trip wiring shall be isolated in
relay panel under modification and while isolating back trip wiring , precaution shall be taken to retain
supervision of back trip wiring (If available).
Sr. Panel Links Ferrule Purpose Isolation CONTR. DEWA
No / ref done at ENGR. ENGR.
Termi Date Time SIGN SIGN
nal Ref
1 132 KV LK94.2 K205, CB Fail-1
BUSBAR 5.1/LK K206
PROTN.P 94.25.2 Initiation from
ANEL 132 kV M1BZP
+R14
2 132 KV LK94.2 K111,
BUSBAR 5TC1.1 K112 CB Trip1 from
PROTN.P /LK94. M1BZP
ANEL 25TC1.
+R14 2
3 132 KV LK94.2 K115,
BUSBAR 5TC2.1 K116 CB Trip2 from
PROTN.P /LK94. M1BZP
ANEL 25TC2.
+R14 2
4 132 KV LK94.2 K207, CB Fail-2
BUSBAR 5.3/LK K208
PROTN.P 94.25.4 Initiation from
ANEL M1BZP
+R14
Breaker Fail
5 E25+R1 1,2,5 P3,P51
Trip (+ve) TC1
Page 5
of 18
Template for Method Statement for Protection Modification Work
Contract No: CE/448D/07 Substation Name: WRSN
Contractor: DANWAY Bay Reference: C1160
Bay Name: WRQA Feeder
Heater, Indication
+F110 H01 door switch,
1 E25+R1 Cubicle lamp &
-A.C H02
Socket switch
Isolation link
8 E25+R1 LK201 K102T Protection & 132
kV TC-2
Page 6
of 18
Template for Method Statement for Protection Modification Work
Contract No: CE/448D/07 Substation Name: WRSN
Contractor: DANWAY Bay Reference: C1160
Bay Name: WRQA Feeder
After completion of trip links and AC/DC isolation, the CT and VT circuit shall be isolated and masked as per
the requirement. The following table shall be filled for isolation and masking of VT and CT circuits.
3
CT E25 + S1 XDZ- 1, 2, 3, 4,
LCC 5, 6, 7, 8, 9, 10, BBP Disc
11, 12, 13, 14 Zone to be
masked
10
Page 7
of 18
Template for Method Statement for Protection Modification Work
Contract No: CE/448D/07 Substation Name: WRSN
Contractor: DANWAY Bay Reference: C1160
Bay Name: WRQA Feeder
Once all the isolation as mentioned above is done then list down the components which are to be
dismantled as a part of this modification scope. Removed components shall be properly packed with
details of the component on the packing and handed over to DEWA. Accordingly following table shall be
filled.
Sr.No Area Component Make/Type Details Purpose Remarks
1 400kV Not
RP applicable
2 400kV Not
CP applicable
3 400kV Not
LCC applicable
4 400kV Not
M1BZP applicable
5 400kV Not
M2BZP applicable
6 400kV Not
CCP applicable
7 132kV Main- Areva/Mi Diff
RP 1 comP543 Diff
Main- Siemens/ DOC
2 7SD62 DEF
DOC Areva/Mi
DEF com P127
Areva/Mi
com P127
8 132kV Not
CP applicable
9 132kV Not
LCC applicable
10 132kV Not
M1BZP applicable
11 132kV Not
M2BZP applicable
12 132kV Not
CCP applicable
Page 8
of 18
Template for Method Statement for Protection Modification Work
Contract No: CE/448D/07 Substation Name: WRSN
Contractor: DANWAY Bay Reference: C1160
Bay Name: WRQA Feeder
13 11kV Not
SWGR applicable
14 11kV Not
BZP applicable
15 DC Not
system applicable
16 Fault Not
Recorde applicable
r
17 ITU Inter Trip ABB/NSD Inter
Unit 570 trip
18 FDP Not
applicable
19 SCMS Not
applicable
20 AVR Not
panel applicable
21 400v Not
LVAC applicable
Before starting the dismantling, the contractor must confirm the existing cable schedule for correctness.
Necessary precautions shall be taken as not to disturb other live cables. The contractor to has to provide
the dismantling of the wiring schedule in the following table or attached a separate annexure
Page 9
of 18
Template for Method Statement for Protection Modification Work
Contract No: CE/448D/07 Substation Name: WRSN
Contractor: DANWAY Bay Reference: C1160
Bay Name: WRQA Feeder
After completion of dismantling work, list down the new components which are to be installed as part of this
modification scope. The components to be installed shall be mentioned in the below table.
2 400kV Not
CP applicable
3 400kV Not
LCC applicable
4 400kV Not
M1BZP applicable
5 400kV Not
M2BZP applicable
6 400kV Not
CCP applicable
9 132kV Not
LCC applicable
10 132kV Not
M1BZP applicable
11 132kV Not
M2BZP applicable
Page 10
of 18
Template for Method Statement for Protection Modification Work
Contract No: CE/448D/07 Substation Name: WRSN
Contractor: DANWAY Bay Reference: C1160
Bay Name: WRQA Feeder
13 11kV Not
SWGR applicable
14 11kV Not
BZP applicable
15 DC Not
system applicable
16 Fault Not
Recorder applicable
17 ITU Not
applicable
18 FDP Not
applicable
19 SCMS Not
applicable
20 AVR Not
panel applicable
21 400v Not
LVAC applicable
22
23
Once all the components are installed then wiring shall be started. The contractor has to provide the detailed
wiring schedules involved in the modification work for each panel as per the following table or attached
separate – Annexure
Page 11
of 18
Template for Method Statement for Protection Modification Work
Contract No: CE/448D/07 Substation Name: WRSN
Contractor: DANWAY Bay Reference: C1160
Bay Name: WRQA Feeder
The contractor has to provide the detailed wiring schedules involved in the modification work for interfacing
panel as per following table or attached separate - Annexure
Sr. No. Ferrule From To
Number TB No. Location TB. No Location
1 A11 XA.1.1-1 LCC XXA1-1 RP
2 A31 XA.1.1-6 LCC XA1-2 RP
3 A51 XA.1.1-11 LCC XA1-3 RP
4 A70 XA.1.1-17 LCC XA1-4 RP
5 E112 XE-1 LCC XE-1 RP
6 E132 XE-2 LCC XE-2 RP
7
8
After completion of all the wiring, ferrules verification and the preliminary checks, the panel shall be powered
up with temporary AC/DC supply to ensure the healthiness of the wiring. After confirmation of wiring the
temporary supplies shall be removed and the permanent panel AC and DC supplies shall be restored as per the
below format:
Sr.No Panel Fuse / Ferrule Purpose Restoration CONTR DEWA
Links ref done at ENGR. ENGR.
SIGN SIGN
Ref
Date Time
Heater, Indicat.
+F110 H01 door switch,
1 E25+R1 Cubicle lamp &
-A.C H02
Socket socket
Page 12
of 18
Template for Method Statement for Protection Modification Work
Contract No: CE/448D/07 Substation Name: WRSN
Contractor: DANWAY Bay Reference: C1160
Bay Name: WRQA Feeder
Isolation link
4 E25+R1 LK100 KL102
for Main-1
Isolation link
6 E25+R1 LK200 KL202
for Main-2
6. Testing Activities
Once the panel is powered up with the AC and DC supplies, identify and perform the testing activities as
part of this protection modification scope from the below table. All applicable testing shall be performed as
per relevant QPs as mentioned below
Page 13
of 18
Template for Method Statement for Protection Modification Work
Contract No: CE/448D/07 Substation Name: WRSN
Contractor: DANWAY Bay Reference: C1160
Bay Name: WRQA Feeder
2
LK94.25 K111, CB Trip1 from
132 KV BUSBAR TC1.1/L K112
PROTN. PANEL K94.25T M1BZP
+R1 C1.2
Page 14
of 18
Template for Method Statement for Protection Modification Work
Contract No: CE/448D/07 Substation Name: WRSN
Contractor: DANWAY Bay Reference: C1160
Bay Name: WRQA Feeder
Page 15
of 18
Template for Method Statement for Protection Modification Work
Contract No: CE/448D/07 Substation Name: WRSN
Contractor: DANWAY Bay Reference: C1160
Bay Name: WRQA Feeder
E25 + S1 CBF CT
7 CT LCC XC- Circuit to be
1,2,3,4,5,6,7,8,9 kept shorted
in NPP.
8. PRI Integration
The contractor has to check the PRI integration work at the remote end. If PRI is applicable then
the approved solution has to be provided by the contractor as per below format.
9. Load Test
After energization of the circuit, the load test has to be carried. The load test shall be carried as
per following QP. Please attach the necessary details if required.
Page 16
of 18
Template for Method Statement for Protection Modification Work
Contract No: CE/448D/07 Substation Name: WRSN
Contractor: DANWAY Bay Reference: C1160
Bay Name: WRQA Feeder
6 Separate file with all signed test report to be kept at record room.
Page 17
of 18
Template for Method Statement for Protection Modification Work
Contract No: CE/448D/07 Substation Name: WRSN
Contractor: DANWAY Bay Reference: C1160
Bay Name: WRQA Feeder
8 Ensure that all excess materials and tools have been demobilized
from the site.
Page 18
of 18