You are on page 1of 1

Quotation

Project: Geotechnical Investigation for Building


Client: ****************
Location: Amhara Region, Debre Birhan, Industry Park

Your Ref. _______________________ Our Ref. __________________


Date: _______________________ Date __________________

Item Description Unit Quantity Unit Price Amount (Birr)

A. Field Work
Mobilization and Demobilization of one drilling rig with its
1 LS - - 58,920.00
accessories
2 Inter borehole movement and set up of drilling equipment No. 3 800.00 2,400.00
3 Core Drilling
a. Drilling in all formations from 0 up to 10 meters depth m 40 500.00 20,000.00
b. Drilling in all formations from 11 up to 20 meters depth m 0 550.00 -
4 Standard Penetration Tests (SPTs) No. 16 250.00 4,000.00
5 Undisturbed soil sampling from boreholes No. 4 100.00 400.00
Elevation and coordinate measurment of boreholes using hand-
6 No. 4 50.00 200.00
held GPS
7 Ground Water Level Measurement No. 4 50.00 200.00

8 Core boxes and photographing of cores in core boxes (coloured) No. 8 350.00 2,800.00

Sub Total A 88,920.00


B. Laboratory Tests
Soil sample
1 Grain size distribution No. 12 90.00 1,080.00
2 Atterberg Limit No. 12 90.00 1,080.00
3 Free swell No. 12 50.00 600.00
4 Specific Gravity No. 4 90.00 360.00
5 Moisture Content No. 4 50.00 200.00
6 Bulk Density No. 4 50.00 200.00
7 Unonfined Compressive Strength of soil No. 1 250.00 rate only
8 Direct Shear test No. 2 450.00 rate only
9 Triaxial Test, UU No. 1 1,500.00 rate only
10 Consolidation No. 1 850.00 rate only
11 Chemical Test(soil/water PH, Chloride, Sulphate content) No. 1 500.00 500.00
Rock
12 Uniaxial Compressive strength, if encountered No. 4 250.00 1,000.00
Sub Total B 5,020.00
C. Technical Report

Technical report including borehole logs, laboratory test results


1 LS - - 4,500.00
and foundation recommendation (two copies).

Sub Total C 4,500.00


Total A+B+C 98,440.00
15% VAT 14,766.00
Grand Total 113,206.00

Note:

- Four boreholes are to be drilled to a maximum depth of 10.00m in Each BHs.


- Quantities are tentative. Final payment shall be effected based on the actually executed and measured work.
- 40% advance to be paid on signature of contract. 30% shall be issued up on the submission of draft report. The remaining
30% shall be paid on submission of the final factual and interpretative report.
- Mobilization shall be within three days after advance payment.
- The client shall facilitate the provision of clean water for drilling and access to the borehole locations.
- Field work completion time shall be 8 calendar days. Laboratory completion time shall be 9 calendar days. Report completion
time shall be 4 Calendar Days. Total duration of work shall be 21 Calendar Days.
Sincerely yours,

____________________________________________________________________________________________________________________
P. O. Box 110246; Tel +251929906464/65; Fax:+251118603699; E-mail:ar-con@ethionet.et, Addis Ababa, Ethiopia