3 LANE H.L BRIDGE OVER RIVER GANDAK WITH APPROACHED AT BANGRAGHAT, BIHAR
Sr. Total Balance
Type of Work unit Completed Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20
No. Scope work
Structures
15 Crash Barrier Casting RM 3010 - 3010 56 56 56 170 170 170 112 56 56 56 172 172 172 172 112 112 112 112 56 172 172 172 172 172
Road Works
3 Earthwork in Embankment Km 18.5 11.536 6.96 0.50 0.50 0.50 0.50 0.49 0.49 0.35 0.35 0.55 0.35 0.35 0.35 0.35 0.42 0.46 0.46
4 Grannular Sub Base Km 18.5 5.58 12.92 0.65 0.90 1.00 1.00 1.00 1.00 1.29 0.90 0.90 0.77 0.75 0.75 1.00 1.00
5 Wet Mix Macadam Km 18.5 - 18.50 1.40 1.20 1.00 1.20 1.40 1.00 1.00 1.00 1.00 1.20 1.10 1.00 1.00 1.00 1.00 1.00 1.00
6 Dense Bituminous Macadam Km 18.5 - 18.50 2.00 2.00 2.00 2.00 1.00 1.50 2.00 2.00 2.00 2.00
7 Bituminous Concrete Km 18.5 - 18.50 1.00 1.00 1.50 3.50 3.50 3.50 3.50 1.00
Guide Bund
1 Eartwork Filling in Guide Bund RM 2250 - 2250 150.00 150.00 250.00 300.00 250.00 250.00 300.00 300.00 300.00
2 Boulder Pitching in Apron RM 2250 - 2250 150.00 350.00 300.00 300.00 150.00 300.00 350.00 350.00
3 Boulder Pitching in Slope RM 2250 - 2250 100.00 150.00 200.00 150.00 150.00 200.00 200.00 200.00 200.00 150.00 150.00 200.00 200.00
4 WMM at Top of Guide Bund RM 2250 - 2250 180.00 270.00 405.00 450.00 450.00 337.50 112.50 45.00
5 Misc Item % 100% - 100% 10% 10% 2% 8% 12% 16% 10% 10% 15% 5% 2%