You are on page 1of 1

SP SINGLA CONSTRUCTIONS PVT.

LTD
3 LANE H.L BRIDGE OVER RIVER GANDAK WITH APPROACHED AT BANGRAGHAT, BIHAR
Sr. Total Balance
Type of Work unit Completed Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18 Dec-18 Jan-19 Feb-19 Mar-19 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 Jul-20 Aug-20
No. Scope work
Structures

1 Fabrication of Cutting Edge Nos 36 36 - Completed

2 Well Curb Nos 36 36 - Completed

3 Well Steining Casting RM 1500 1325 175 10 10 10 10 10 10 10 10 10 10 5 10 10 10 10 10 10 10

4 Sinking RM 1730 1492 238 15 15 15 15 15 15 15 15 10 10 10 10 10 10 10 10 10 10 10 8

5 Bottom Plug Nos 36 17 19 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

6 Sand Filling Nos 36 16 20 1 1 1 1 1 1 1 1 1 1 1 1 1 2 1 1 1 1 1

7 Intermediate Plug Nos 36 16 20 1 1 1 1 1 1 1 1 1 1 1 1 1 2 1 1 1 1 1

8 Well Cap Nos 36 15 21 1 1 1 1 1 1 1 2 1 1 1 1 1 1 1 1 1 1 1 1

9 Pier Shaft Nos 36 14 22 1 1 1 1 1 1 1 1 1 1 1 1 1 2 2 1 1 1 1 1

10 Pier Cap Nos 36 7 29 1 1 1 2 2 1 2 1 1 2 2 2 2 2 1 1 1 1 1 1 1

11 Launching Girder Erection Nos 1 1 - Completed

12 PSC I-Girder Casting Nos 175 45 130 3 7 10 10 10 10 10 10 10 10 10 10 10 10

13 Erection of Beams Nos 175 - 175 5 5 5 5 5 10 10 10 10 10 5 5 10 10 10 5 5 5 10 5 5 5 5 5 5 5

13 Bearing Fixing Span 35 - 35 1 1 1 1 1 2 2 2 2 2 1 1 2 2 2 1 1 1 2 1 1 1 1 1 1 1

14 Deck Slab Casting Span 35 - 35 1 1 1 1 2 2 2 2 2 1 1 1 2 2 2 1 1 1 1 2 1 1 2 1 1

15 Crash Barrier Casting RM 3010 - 3010 56 56 56 170 170 170 112 56 56 56 172 172 172 172 112 112 112 112 56 172 172 172 172 172

16 Expansion Joint Fixing Nos 36 - 36 1 1 1 1 1 1 1 1 1 1 1 1 1 2 3 3 3 2 2 2 2 2 2

17 Other Miscellaneous Items % 100% - 100% 5% 5% 10% 10% 5% 5% 5% 5% 5% 5% 10% 10% 5% 5% 5% 5%

Road Works

1 Pipe Culvert & Box Culverts Nos 57 36 21 1 2 4 5 5 3 1

2 Underpass Nos 1 1 - Completed

3 Earthwork in Embankment Km 18.5 11.536 6.96 0.50 0.50 0.50 0.50 0.49 0.49 0.35 0.35 0.55 0.35 0.35 0.35 0.35 0.42 0.46 0.46

4 Grannular Sub Base Km 18.5 5.58 12.92 0.65 0.90 1.00 1.00 1.00 1.00 1.29 0.90 0.90 0.77 0.75 0.75 1.00 1.00

5 Wet Mix Macadam Km 18.5 - 18.50 1.40 1.20 1.00 1.20 1.40 1.00 1.00 1.00 1.00 1.20 1.10 1.00 1.00 1.00 1.00 1.00 1.00

6 Dense Bituminous Macadam Km 18.5 - 18.50 2.00 2.00 2.00 2.00 1.00 1.50 2.00 2.00 2.00 2.00

7 Bituminous Concrete Km 18.5 - 18.50 1.00 1.00 1.50 3.50 3.50 3.50 3.50 1.00

Guide Bund

1 Eartwork Filling in Guide Bund RM 2250 - 2250 150.00 150.00 250.00 300.00 250.00 250.00 300.00 300.00 300.00

2 Boulder Pitching in Apron RM 2250 - 2250 150.00 350.00 300.00 300.00 150.00 300.00 350.00 350.00

3 Boulder Pitching in Slope RM 2250 - 2250 100.00 150.00 200.00 150.00 150.00 200.00 200.00 200.00 200.00 150.00 150.00 200.00 200.00

4 WMM at Top of Guide Bund RM 2250 - 2250 180.00 270.00 405.00 450.00 450.00 337.50 112.50 45.00

5 Misc Item % 100% - 100% 10% 10% 2% 8% 12% 16% 10% 10% 15% 5% 2%

1 Land Will be provided by the Deptt.


2 Land for Bund Will be Acquired by Deptt.
3 Drawings & Design for Guide Bund shall be Provided to us
4 The Programme does not include Anti Social Elements or villagers hampering the Works
5 Girder Casting & launching will be allowed in July'17 by Deptt.

You might also like