A Review Paper on Voided Slab:U-Boot Beton

Article · February 2019

CITATIONS READS
0 358

3 authors, including:

Cs Aslam Basha Balamurugan P C


Gojan School of Business and Technology Gojan School of Business and Technology
2 PUBLICATIONS   0 CITATIONS    1 PUBLICATION   0 CITATIONS   

SEE PROFILE SEE PROFILE

Some of the authors of this publication are also working on these related projects:

A Review Paper on Voided Slab:U-Boot Beton View project

U-boot Beton View project

All content following this page was uploaded by Balamurugan P C on 14 February 2019.

The user has requested enhancement of the downloaded file.


Editor
Ms. B. Sangeethavani

CENTRE FOR RURAL TECHNOLOGY


THE GANDHIGRAM RURAL INSTITUTE
(Deemed to be University)
Ministry of Human Resource Development (MHRD),
Government of India
Accredited by NAAC with 'A' Grade (3rd Cycle)
Gandhigram – 624302, Dindigul District, Tamil Nadu, India

Sponsored by
Recent Innovations and Technological Development in Civil Engineering ISBN: 978-0-6482502-2-7

A Review Paper on Voided Slab:U-Boot Beton


R.Arvind1, P.C.Balamurugan2, R.Aravind2, C.S.Aslam Basha2
1
Assistant Professor & Head of Civil Department,2 UG Students
Gojan school of business and technology,Redhills,Chennai-52.
arvindrajabather@gmail.compcbalu21@gmail.com

that was designed to create two-way voided


Abstract: Avoided slabs in which voids are developed slabs and rafts. It is used to create slabs with
to reduce the amount of concrete. This paper deals
with voided slabs using U-boot beton technology made
large span or that are able to support large loads
byrecycled polypropylene, The technology is designs without beams. A lightweight, concrete made
forlightweightslabsin RCC. It is solution to build slabs by unhardened mixture of concrete by generate
oflarge spans with more bearing capacity. It is like an the gases within that mixture. Thus the structure
shape of formwork like a pyramid and generallysize is able to two-directionally transmit loads in
measurement 52 X 52 centimetres. It is an simple to
use. Initial, a plain surface has been prepared with
direct by using U-boot structures is obtained
deck of wooden or other similar equipments. Then, capable of distribute the stresses in all direction
steel reinforcement has to be posed in the two transferring them directly to make the concept
involving right angles or perpendiculars directions, as simple. we imagine a series of an two teams of
designed in the project. Thus, steel dip into casting of alongside the other and arranged as a premise
the concrete. A grids of orthogonal beams, nearly
closed by slabs of various heights.U-Boot its
all stresses will be concentrated close to pillars
lightweight, stability, modularity, can be used to make where the suitable entire section gets left in that
structures without mechanical helps of equipmentand way floor slabs
its also foundation rafters can be created with a low
amount of concrete withbig thickness. By using U-boot II. MATERIAL REQUIRED
beton, it is easy to build raft foundations with a low Spacerjoint
quantity of concrete.It is used in high rise buildings to Thus spacerjoint isan effectivelyfixed
reduce the weight of the structure. It reduces the
construction time and also requires less labours. It has
spacer joint with graduated scale with the
high fire resistance and it’s economical. Higher desired width of the beams is fastly
number of floors can be built. determined.At the top of the formwork inside
Keywords: U-Boot beton,Voided slabs, Energy notches housing the fixing elements where the
efficiency, Structural solutions, Low cost material, joint fits .
Fire resistance.
It is fixed interconnection and ensures
perfect geometric compliance with the design
I. INTRODUCTION
Voided slabs are concrete slabs in which with the bearing capacity of the formworks,
reduce the requirement of amount of concrete. when casting under the pressure of the concrete,
The idea was developed by hollowbiaxial slab the weight of the operators and equipment.
with the equal capacity as normal solid slab, but The specific type of superimposing two
the reducing weight due to the removal of or more base elements allows the
excess concrete. implementation of load releasing elements of
In most of constructions, the slab is a various heights according to the plan things out
major part of structural element for making a the floor slack also the chronicle elevator feet
spaces. And the slab is one of the high placed at the four corners can be of different
requirement of consuming concrete.These are heights determining a different distance from
the reasons for innovative developments of an the casting deck plate and as a result the
idea of reinforced concrete have reducing the different thickness of the internals slapping the
weight and providing larger span. remarkable versatility and flexibility.The U-
U-boot is used for structural elements of boot beton construction system can satisfy any
different types such as slabs or foundation. It design.
grants solution preformation considerable Connection Bridge
designing, technical and economic. U-Boot A connection bridge is type of member to
Beton is a recycled polypropylene formwork joint two u-boot.The reinforcement pose is to be
completed by disposing the upper bending steel

33
Recent Innovations and Technological Development in Civil Engineering ISBN: 978-0-6482502-2-7

bars
✁ ✂✄☎ ✆ ✝✞✟✂ ☎✁✠ ✡✂☛✞ ✠ hear and punching Antiseismic
reinforcement,where needed.Due to the floating Reduced seismic mass,less dimensional
pressure exerted on u-boots, the concrete should limitations of elements,double inferior and
be cast in two different phases: the first casting superior slab.
has to fill a thicknessequal to the feet height. O pen Space
 More spacious rooms
 Bigger architectural freedom
 E asier change of use
E conomic
Concrete cost is lowwith an equal
thickness. Steel cost also low. Savings in useful
Closing Plate height on each level as there are no emerging
The reinforcement pose is to be completed beams. Possibility to gain floors at the same
by disposing the upper bending steel bars in two building height and building volume. Q uick and
directions, the shear and punching easy to implement. and also indicated for the
reinforcement, where necessary. Due to the top-down technique. It has possibility of large
floating pressure exerted on U-boots, the span at equal load or high load bearing capacity
concrete should be cast in two different phases: at an equal span. E conomical and easy to
the first casting has to fill a thickness equal to transport, handle, store and also outdoors. The
the feet height soffit has a plane surface that is ready to finish
The final phase has to be done when the and does not require a false ceiling for aesthetic
first concrete layer starts to settle and becomes purposes. If a false ceiling is required, it can be
semi-solid.Casting proceeds each time from the created fast.
previous starting point. W hile the casting Shear Strength
proceeds, the concrete sets.The U-boot system Shear strength of slab mainly depend on
execution time will be speedup by using new effective mass of concrete, as the special
deck technologies which permit to disassemble geometry shaped by the ellipsoidal voids acts
within 2-4 days, or using the carpet like the famous roman arch. Hence, making all
reinforcement system in order to reduce the concrete to be effective. This is only valid,
steel bars posing time up to 4 -6 times. when the U-boot technology is considered. The
shear resistance of U-boot greatly reduces in
comparison of solid slabsdue to the use of
plastic materials.
O utside the column z ones, the shear
stresses rapidly removed from the columns. It
has been demonstrated by testing, calculation
Advantages
and longitudinal shear stresses are within the
F lexible:
capacity of the voided slab system. N ear the
Span up to 20 m. N o beams between
columns, U-boot are left out. so in these
pillars. Reduction in the number of pillars. Can
situation, a voided slab is designed exactly the
be usedtogether with prefabs. Handling and
same way like the solid slab.
hoisting equipment doesnot needed. Thanks to
Punching Shear
the bridge accessory forPossibility of single
Punching shear capacity of voided slab
direction structures.
may causes major problem. Because of its
L ight - Thin – Bidirectional
reducing the weight, strengthened slabs have
Decrease of weight up to 4 0 % . Reduced
higher punching capacity compared to
deformations ( maximum loss of stiffness- 15% ) .
controlled voided slab. The average punching
Reduction of the foundation load and columns
shear is calculated as 9 1% when compared to
section or their number
solid slab. F irst, analyz e whether the applied
shear is lesser or greater than the shear capacity
of voided slab.Shear reinforcement is required,

34
Recent Innovations and Technological Development in Civil Engineering ISBN: 978-0-6482502-2-7

if the shear resistance of solid concrete portion foot. Casting will be continued for till initial
is lesser than applied shear. portion of the slab or the RC concrete starts to
Bending Strength settle and become partially fluid.
In this research study, the design moment Once preferable set, the casting can be
was derived by considering the span of voided reinitiated from the orgin point, completely
slab of U-boot 5m x 5m panel of interior, while burying the U-Boot Beton.
load applied on the voided flat plate slabs was 5 The levelled and smoothed of concrete in a
KN/m2 Live load and 1 KN/m2 floor finish load. olden basis. the structure gets hardenedof
self-weight of the slab was also considered. The concrete, the formwork can be removed.
grade of concrete is taken as 25 N/mm2.
Deflection
The test of deflection which specimens
was measured at their mid-span the lower face
of the tested slabs. When the slab reaches
advanced stage of loading, smaller
graduallyload applied until failure. Where the
load indicator is stopped recordsthe data’s and
the deflections increased very fast without any
increase in applied load.
The depth of span ratio calculations for u-boots slabs does not require beams
deflections are very accurately and are not between the pillars, edge beam is enough.The
suitable in flat slabs of irregular layout except both grid of beams transfers all stresses directly
the simple or non-essential cases. Fixed to the pillars,which is thick as the slab and
Endmodelling, including non-linear cracked variable in function of shear stresses.
section analysis is used for calculate the
deflection using normal structural concrete with IV. CONCLUSION
a Young’s Modulus , multiplied by 0.9 and the After the analysis, We conclude that the u-
tensile strength, fctm multiplied by 0.8 boot beton is so economical, efficient, Fire
resistance, and Eco friendly.Thus the result
III. INSTALLATION gives a clear view of u-boot beton that is very
Initiall the totalsurface of slab to be cast useful for construction purpose.
on site is shuttered with wood decks, then the
bottomreinforcement concrete are kept in two REFERENCES
[1] Daliform Group, Disposable formwork for lightened structures
mutually perpendicular directions as per the in reinforced concrete cast on site,
designs and the grid for the top RCC is [2] 2.Ashish Kumar, Voided Slab Design: Review Paper Vol 4-
issue 1.
arranged. [3] 3.B.Vaignam,Dr.B.S.R.K Prasad Analysis of voided deck slab
The Beton formworks are kept on the & cellular deckslab using Midias Civil.
[4] 4. Yogesh Tambe,PrashantKulkarni, Parametric study of solid
sideway directions spacers joints to place at the slab and voided slab.
specified centre distance that enhance to
determine the beam width. The elevator foot,
which the U-Boot formworks will be lifted from
the surface, making it is also possible for the
lower slab to be formed.
The pointing of the RCconcretes is
completed by placing above the U-Boot
formworks. The top bars in the two directions
as well as the reinforcement
forpunchingandshear based on the design.
The casting of concrete must be performs
in two position to prevent the floating of the
formworks. An starting layer will be cast to
filling a thickness, it is equal to the height of the

35